2727
2727
ስራው ዋናው ውል
Project:-Bole community school G+2 Adim. Builiding main contract
ቦታው ተቀጽላ ውል
Location:- Wereda 12 SUPP AGREE.
አሰሪው መስሪያ ቤት ድምር
Owner:-Bole Sub City Design and Construction Office Total
ስራ ተቋራጭ ቫት
Contructor:-YEHIN CON STRUCTION Vat 15%
Rebate 9%
After rebate
Supp.work
Amount (birr)
የገንዘቡ ልክ / ብር /
8,244,644.75
8,244,644.75
1,236,696.71
9,481,341.46
Amount (birr)
የገንዘቡ ልክ
/ ብር /
1,799,423.92
161,948.15
1,637,475.76
1,637,475.76
409,368.94
1,228,106.82
184,216.02
-
247,339.34
184,216.02
1,412,322.85
Approved by
Con.Cont.Administration Team Leader
Grand Summary
__________________________ __________________________
Contractor Consultant/Superviser
Summary of Statement-2
A.Sub structure
-
8,244,644.75 __________________________
__________________________ 9,481,341.47 Consultant/Superviser
Contractor
2
Total Amount
664,560.00
1,103.20
814,540.00
54,000.00
265,220.72
1,799,423.92
1,799,423.92
__________________________
Consultant/Superviser
WORE 12
PROJCET :- G+2 ADMIN.BUILDING
CLIENT:-BOLE SUB CITY CONSTRUCTION OFFICE
CONTRACTOR:-YEHIN CONSTRUCTION
CONSLUTANT C
LOCATION :- Woreda 13,Bole Sub City Description T D A
T D A Description
1 22.6 EGA 700 SHEET COVER
1 52.00 10.50
32cm wide 3cm thick best 32cm wide 3cm thick best
20 1.00 quality marble window sill 7 1.00 quality marble window sill
4.00 3.00
80.00 ML 21.00 M
101.00
101 ml total
WOREDA 13 BOLE COMMUNITY SEHCOOL G+2 ADMIN.BUILIDING
PROJCET :- G+2 ADMIN.BUILDING
CLIENT:-BOLE SUB CITY CONSTRUCTION OFFICE
CONTRACTOR:-YEHIN CONSTRUCTION
CONSLUTANT C Description
gypsum WORK for stair ditto but door sill
celling and wall 0
5.00 1
10.00 0.00 2.3 0 m2 total
0 1.20 0 ditto but door sill
6.00 0.00 edg part 1
1.2 0 m2 total
0 1.20 0 m2 total
2.90 0.00 column part
ELECTRICAL INSTALLATION
50 50 NO
0 0.80 edges for windows and doo 1 1 TV ( geniune legrand)
Privious
QTY Rate contrat agg Current TODATE Privious amount Current amount To date Amount
A. SUB-STRUCTURE - -
1. EXCAVATION AND EARTH WORK -
Bulk excavation in ordinary soil to a depth 750mm
1.1 from reduced level of tre leveling.
m3 88.24 100.00 8,824.00 - - -
supply and back fill under around foundation
masonry includeing paved way prograsively well
compacted, rolled and compressed, layer back fill
material should be the in-situ mosture content a
density saall be compared with labratory test results
of modified ASHTO T180 or equvalent performed on
samples of the seleceted material the miniumm
1.2 relative compaction to achived in the compacted
area shall be 95% maximum dry density and the
moisture content shall be with in the range of 95%
dry denisty. the moisture content of the fill material
shall be adjusted as necessary to achive the required
compaction. any material wich after repeated
compaction does not full fill the requirements shall
be removed & replaced. m3 81.00 100.00 8,100.00 - - -
cart away surplus excaveted material and disposite
1.3 at a distance not exeeding 15km from site as per the
engineers direction. m3 88.24 60.00 5,294.40 - - -
supply and fill 25kcm thick basaltic or equvalent
1.4 stone hardcore well rolled consolidated and nlinded
with crushed stone. m2 48.00 350.00 16,800.00 - - -
1.5
Total Carried Summary 39,018.40 - - -
1.6 2.CONCRETE WORK - - -
Supplay and cast reinforcment concret in class c-
25/30 withminemum cement content of 360kg/m3
filled in to form work and vibrete arround steel - - -
reinforcment
A) in 10cm ground floor slab price shuld include
10x1cm stayrofoam for expnsion joint
m2 48.00 300.00 14,400.00 - - -
B)diameter300mmconcret half dich around paved
way on base of 10cm sand bedding and comared
selected material ,price shall include 10x40xLcorb
ston arround half dich ml 82.00 500.00 41,000.00 - - -
9. PAINTING
- - -
supply & apply three coats of painting to internal
wall, edge of window & door and internal part of
beam and column surfces. Surfaces to up 1.50cm
height syntetic paint and above 1.50cm plastic
emulision paint. Price shall include all necessary
works to full fill the job N.B the color choice must be
approved by the recommendation of the architect.
m2 899.67 60.00 53,980.20 - - -
ditto but for beams, columns, stair sofit & edges for
1 windows and doors.
m 2
1,458.00 60.00 87,480.00 - - -
supply and apply one coat of primer & two coats of
quartz graffiti textured pointing to plastered external
surface parapet wall external part of beam and
column and surface strictly in accordance with
1.1 manufactures instruction color choico and sampla
paint shall be approved by the consultant prior to
work programs price shall include to pre & post clean
the working area.
m2 765.85 250.00 191,462.50 - - -
1.2 Total Carried Summary 332,922.70 - - -
1.2 Septic Tank - - -
1.3 1.Excavation Earth Work - - - -
Back Fill Around Masonry wall with borrowed
1.4 selected non-expansive soil well compacted from
outside of site rolled and compressed in layer not
exceeding 20cm. m3 13.40 100.00 1,340.00 - - - -
1.5
Total Carried Summary 1,340.00 - - -
1.6 3.Concrete Work. - - -
Supply and cast 5cm thick lean concrete quality in c-
1.7 25 with minimum cement content of 150kg/m3 under
masonry. m2 51.80 7.00 362.60 - - - -
Supply and fix reinforced concrete in c-25 with
minimum cement content of 360kg/m3 filled and
vibrated into form work and around reinforcement
bar .formwork and reinforcement bar measured bar
measured separately. - - -
In 15cm thickTop RC slab m3 2.90 3,000.00 8,700.00 2.80 2.80 8,400.00 8,400.00
2.1 In 12cm thick manhole cover m 3
0.49 400.00 196.00 0.47 0.47 188.00 188.00
In 30*20cm grade beam. m3 2.85 3,000.00 8,550.00 2.81 2.81 8,430.00 8,430.00
Supply and Fix in Position sawn zigba wood or
equivalent.Formwork. - - -
3.1 To 15cm thick top RC slab .Price Shall include props
for soffits of slab m 2
44.00 200.00 8,800.00 42.00 42.00 8,400.00 8,400.00
Ø 16mm deformed bar Kg 320.28 115.00 36,832.20 321.58 321.58 36,981.73 36,981.73
3.6
Total Carried Summary 228,958.69 - 227,260.72 227,260.72
3.7 4.Plastering - - - -
Supply and Apply two coat of plastering by cement
sand mix ratio 1:3 to internal side of the septic tank
stone masonry wall inorder to prevent leakage.Price
shall include any necessary materials and work. m2 96.00 150.00 14,400.00 - - - -
Supply and Fix Boding admixture Geo-textile and
cement 3 in 1as per the manufacturere's instruction
4.1 to internal side of the septic tank retaining plastered
stone masonry wall.The material sholud be approved
prior to Purchase. m2 96.00 400.00 38,400.00 94.90 94.90 37,960.00 37,960.00
4.2
Total Carried Summary 52,800.00 - 37,960.00 37,960.00
1.1
1. pc ACB of 63A 3-phase
2. pc ACB of 25A,
3-phase 3. pc
ACB of 16A, 1-phase
4. pc ACB of 10A, 1-phase NO 1.00 9,000.00 9,000.00 - - - -
flush mounting SDB-TYP complet with phase
metalic bar fixing
enclusure with
lockable door consisting phase bars of 50A nrultral
earth bar connection terminal of.
1. pc ACB of
1.2 25A, 3-phase
2. pc ACB of 10A 1-phase
3. pc ACB of 16A, 1-phase
reserve for 3 pc
ACB complete with phase bar fixing bar accessories NO 2.00 9,000.00 18,000.00 - - - -
2 Light point - - - - -
light point fed through PVC conductor of 2x2.5 sqmm
in thermoplastic conduit of 13mm under surface
2.1 including jonction boxes with covers and screw type
connectors with insulating caps. NO 50.00 1,000.00 50,000.00 - 50.00 50.00 50,000.00 50,000.00
Extra over liht points for switches type legrand décor
2.2
of equivalent approved with jonction box 31301 - - - - -
a) flush mounting double poleswith (lgniune legrand) NO 10.00 200.00 2,000.00 - - - -
b) flush mounting 2 way swith( geniune legrand) NO 2.00 200.00 400.00 - - - -
c) flush mounting single pole swith (geniune legrand) NO 10.00 200.00 2,000.00 - - - -
d) intermidate flush mounting switch (geniune
legrand) NO 1.00 200.00 200.00 - - - -
3 Socket outlet - - - - -
Flush mounting socket oultlet 16A/1p with grounding.
3.1
NO 80.00 300.00 24,000.00 - - - -
4 LIGHT FITTING AND LAMPS (OR equivalent) - - - - -
4.1 Philps TCS 314/236 c6 with 2xYL'D 36w fl lamp NO 65.00 4,000.00 260,000.00 - - - -
4.2 rzb 22145.002 with A60 60w lamp NO 16.00 3,500.00 56,000.00 - - - -
4.3 pilips TCS 314/218 with 2xTL'D 18w ft lamp NO 20.00 3,500.00 70,000.00 - - - -
5 TELEPHONE (geniune legrand) - - - - -
Telephone system only conduit of 50/32/20mm
5.1 diameter pulting wiro, axes, terminal all as shown on
the drawing. NO 11.00 1,000.00 11,000.00 - - - -
patch panel with the appropriate size for riser of
trle/data circuite in each floor. NO 3.00 10,000.00 30,000.00 - - - -
6 TV ( geniune legrand) - - - - -
tv system only conduit of 50/32/20mm diameter
6.1
pulling wire boxes, terminal all shown on the drawing NO 2.00 1,000.00 2,000.00 - 2.00 2.00 2,000.00 2,000.00
patch panel with the appropriate size for riser of tv
6.2
circuit in each floor. NO 2.00 1,000.00 2,000.00 - 2.00 2.00 2,000.00 2,000.00
7 power - - - - -
a) 5x16 sqmm in PVC of 76mm from EEPCO KWHM to
7.1
MUB actual length taken from site ml 25.00 50.00 1,250.00 - - - -
7.2 b) 5x6 sqmm in pvc of 32mm ml 30.00 50.00 1,500.00 - - - -
construct manhoe with double brick wall internally
7.3 piastered with removable renforced concrete cover
thickness 8cm size a) 70x70x70mm No 2.00 8,000.00 16,000.00 - - - -
supply and install earthing sustem with rod diam.
16mm length 240cm with a base slab of 8cm theck
7.4 and removable reinforced concrete cover 8cm thek
and with all the necessary accessories. No 1.00 8,000.00 8,000.00 - - - -
2 CONCRET WORK - - -
SPPLAY and cast non sippery reinforced concrete
qualitiy in c-25,360kg cement /m3 filled in form work
and vibreted around rod reinforced steel and form
work measured separetly - - -
A,15*40cm curve stone around terazo tile floor finish ml 102.33 400.00 40,932.00 - - -
B, for ramp slab m3 1.00 3,000.00 3,000.00 - - -
supplay and provide , cut, fix in position sawen zigiba
form work up of minimum 3mmthick sheet metal and
folded thickness of 50mm which ever is
approprated ;contractor submit form work design - - - -
A)15*40cm curve stone for greenery m2 43.93 200.00 8,786.00 - - -
B) for ramp slabe m2 1.04 200.00 208.00 - - -
supplay and lay in position steel reinforcment for use
in ramp concrete works with aminumem yild strength
fyk 300mpa, price including cut, bending, placing in
position and tying wires and spacers - - - -
C) under masonry
3 2.2 for footing F2 3 25 wall
2.2 14.52 m 2
0.5 37.5 m2
T D A Description T D A Description
B)in foundation
11 0.3 column
for C1 4 13.85 on axis 2,3,4 & 5
4 3.3 43.56 m2 0.5
1.7 47.09 m3
4 0.4 for C2
4 3.2 20.48 m2 2 10.2 on axis 1 & 6
0.5
4 0.4 for C3 1.8 18.36 m3
4 3.2 20.48 m2
1 5.25
3 0.3 for C4 0.5
4 3.3 11.88 m2 1.8 4.73 m3
3. MASONRY WORK
3.1 construct 50cm thick
trychastic or equivalent
stone masonry foundation
wall bedded in cement
sand martar ratio 1:3
A. BNGL & ANGL price
3 25 shall include pointing.
1 16.62 on axis A
0.5
1.8 14.96 m3
T D A Description T D A Description
B. SUPER- STRUCTURE
1.CONCRETE WORK
1.1 Supply and cast
reinforced concrete in
class c-25/30,
A) in elevation column
11 0.3 for C1
0.3
3 2.97 m3
4 0.4 for C2
0.4
3 1.92 m3
4 0.4 for C3
0.4
3 1.92 m3
3 0.3 for C4
0.3
3 0.81 m3
A) in elevation column
11 0.3 for C1
4 3.0 39.6 m2
4 0.4 for C2
4 3.0 19.2 m2
4 0.4 for C3
4 3.0 19.2 m2
3 0.3 for C4
4 3.0 10.8 m2
T D A Description T D A Description
Septic Tank 2 5.5
A.Sub Structure 1.1
1.Excavation Earth 2.9 35.09 m3
Work 110.69 total volume
1.1 Clear the Site to
remove soil to adepth of
1 14.85 20cm 3.Concrete Work.
3.1 Supply and cast 5cm
7.5 111.38 m2 thick lean concrete
1 11.85 quality
1.2 Bulk excavation 5.5 65.18 m2
2 6.5
0.5
2.9 18.85 m3 2 10.05 3.5 In 30*20cm grade beam.
0.25 Grade.B on axis 2,3
56.11 total volume 0.3 1.51 m3
2 3.25 soffit
0.25 1.63 m2
2 3.25 soffit
0.25 1.63 m2
2 9.25
0.25 4.63 m2
2 3.7
2.9 21.46 m2
A.Sub structure
Footing Pad
F1: 1 14 3.6 15 4 216.00
2 14 3.6 15 4 216.00
F2: 3 14 3.1 15 3 139.50
4 14 3.1 15 3 139.50
F3: 5 14 2.7 12 6 194.40
6 14 2.7 12 6 194.40
F4: 7 14 2.7 11 9 267.30
8 14 2.7 11 9 267.30
Foundation Columns
C1 16 5.34 8 11
C2 16 5.34 8 4
C3 16 5.34 8 4
C4 16 5.34 8 3
GFB-1
onaxis B,C& D
Top 14 7.70 2 3 46.20
14 11.70 2 3 70.20
14 7.57 2 3 45.42
negative bar 10 2.11 1 3 6.33
10 3.02 1 3 9.06
10 3.46 1 3 10.38
12 4.00 2 3 24.00
10 3.25 1 3 9.75
10 1.67 1 3 5.01
10 3.30 2 3 19.80
10 3.10 2 3 18.60
10 4.20 2 3 25.20
10 4.20 2 3 25.20
10 2.60 2 3 15.60
Bottom 14 9.89 2 3 59.34
14 6.53 2 3 39.18
14 10.53 2 3 63.18
Stirup at c/c190mm 8 1.40 132 3 554.40
GFB-2
On Axis 2,3,4,5
Top 14 6.90 2 4 55.20
14 8.20 2 4 65.60
negative bar 10 1.74 2 4 13.92
10 2.90 2 4 23.20
10 3.30 2 4 26.40
10 2.14 2 4 17.12
10 2.56 2 4 20.48
10 3.50 2 4 28.00
10 3.50 2 4 28.00
Bottom 14 9.37 2 4 74.96
14 5.72 2 4 45.76
Stirup at c/c190mm 8 1.40 125 4 700.00
GFB-2 onaxis A
top 14 9.59 2 1 19.18
14 9.49 2 1 18.98
negative bar 10 3.02 1 1 3.02
10 3.46 1 1 3.46
12 4.00 2 1 8.00
12 3.25 2 1 6.50
12 3.10 1 1 3.10
12 4.20 2 1 8.40
12 4.20 2 1 8.40
Bottom 14 6.54 2 1 13.08
14 6.53 2 1 13.06
14 6.80 2 1 13.60
Stirup at c/c190mm 8 1.40 102 1 142.80
floor Slab
B/n axis 1-2 & B-C,C-D 8 4.68 21 2 196.56
8 4.95 20 2 198.00
8 4.95 19 2 188.10
B/n axis 3-4,4-5 & B-C,C-D 8 5.97 21 4 501.48
8 4.95 25 4 495.00
8 4.95 16 2 158.40
8 3.65 25 2 181.62
8 3.65 19 1 67.60
Elevn. Column
14 4.64 8 11 408.32
C1
8 1.1 25 11 298.47
Stirup
16 4.64 8 4
C2
8 1.5 21 4 124.33
Stirup
16 4.64 8 4
C3
8 1.5 19 4 112.50
Stirup
14 4.64 8 3 111.36
C4
8 1.1 19 3 61.88
Stirup
TOTAL LENGTH 597.18 - - 519.68
UNIT WT/ml 0.395 0.617 0.888 1.209
SUB TOTAL WEIGHT 235.88 - - 628.29
No.of
Location Bar Bar dia. Bar Length bars Total No
shape (mm) of bars
ø8 ø10 ø12 ø14
SEPTIC TANK
BOTTOM SLAB
8 4.61 65 1 299.65
8 10.1 32 1 323.2
8 5.48 32 1 175.36
8 2.3 25 2 115
TEMPRETURE BAR
and kebeleto 8 9.05 4 2 72.4
16 2.166 2 2
16 2.166 2 2
16 1.333 2 2
botoom bar 16 10 4 2
Striup 8 1 65 2 130
14 4.15 2 2 16.6
14 1.265 2 2 5.06
14 1.265 2 2 5.06
16 3.65 3 2
Striup 8 1 26 2 52
14 4.15 2 2 16.6
14 1.265 2 2 5.06
14 1.265 2 2 5.06
16 3.65 3 2
Striup 8 1 26 2 52
TOP SLAB
10 4.65 32 1 148.8
10 6.31 43 1 271.33
10 2.2 38 2 167.2
10 3.73 29 1 108.17
10 2.16 38 1 82.08
10 5.76 6 1 34.56
10 7.9 36 1 284.4
10 6.31 43 1 271.33
10 5.95 7 1 41.65
10 9.8 4 2 78.4
TOTAL LENGTH 1,219.61 1,513.92 - 95.44
UNIT WT/ml 0.395 0.617 0.888 1.209
SUB TOTAL WEIGHT 481.75 934.52 - 115.39
ø16
469.92
170.88
170.88
128.16
939.84
1.579
1,483.69
ø16
148.48
148.48
296.96
1.58
469.27
ø16
5.332
8.664
8.664
5.332
80
21.9
21.9
151.79
1.58
239.87
T D A Description T D A
FORM WORK 2 16.05
for elevetion 0.45 28.89
11 0.3 column
for G+1 For C1
4 3.23 42.64 m2 4 12.27
0.45 44.17
4 0.4 for C2
4 3.23 20.67 m2 3 25
0.25 37.50
4 0.4 for C3
4 3.23 20.67 m2 1 17.97
0.25 8.99
3 0.3 for C4
4 3.23 11.63 m2 3 15.2
95.61 total area 0.25 22.80
For G+2
11 0.2 For C1 1 16.05
4 3.23 28.42 m2 0.25 8.03
1 16.05
2 17.97 FFB &SFB-2 onaxis A 0.4 12.84
0.45 32.35 m 2
2 12.27
6 15.2 FFB &SFB-2 onaxis 2,3,4 0.4 19.63
0.45 82.08 m 2
T D A Description T D A
Soffit of beam
3 25 on axis B,C,D 4 1.35
0.2 15.00 m 2
1.3 7.02
2 3.9
1.15 8.97 m2
2 3.9
1.37 10.69 m2
715.78 total area
water tanker seat slab
1 5.25
4.05 21.26 m2
stair case
2 2.68 for 1st flight
1.35 7.24 m2
T D A Description T D A
CONCRETE WORK
Elevetion column
at G+1 3 25
11 0.3 for C1 0.25
0.3 0.45 16.88
3.23 3.20 m3
1 17.97
4 0.3 for C2 0.25
0.3 0.45 4.04
3.23 1.16 m3
3 15.20
4 0.3 for C3 0.25
0.3 0.45 10.26
3.23 1.16 m3
1 16.05
3 0.3 for C4 0.25
0.3 0.45 3.61
3.23 0.87 m3
1 17.97
4 0.3 for C3 0.2
0.3 0.4 1.44
3.23 1.16 m3
3 15.20
3 0.25 for C4 0.2
0.25 0.4 3.65
3.23 0.61 m3
4.35 total volume 1 16.05
0.2
0.4 1.28
2 12.27
0.2
0.4 1.96
14.33
T D A Description T D A
stair case concrete
2 2.51 for 1st flight
1.35
0.15 1.02 m3 2 25
10.2 510.00
2 0.9 for 2nd flight
0.86 2 18.07
0.15 0.23 m3 5.15 186.12
2 3.9
4 1.35 1.37 10.69
1.3 715.78
0.15 1.05 m3
1 5.25
8 1.35 4.05 21.26
0.3
0.18 1.17 m3
3 0.86
0.3
0.18 0.28 m3
8 1.35
0.3
0.18 1.17 m3
stair beam
2 4.94
0.25
0.45 1.11 m3
2 1.24
3.76
0.15 1.40 m3
8.55 total volume
T D A Description T D A
BLOCK WORK
For G+0
Class B 20*20*40cm
HCB 1 10.02
On axis 1 3.23 32.36
1 10.02
3.0 30.06 m2 1 24.60
On axis D 3.23 79.46
1 18.75
3.0 56.25 m2
On axis 6 1 12.12
1 12.12 3.23 39.15
3.0 36.36 m2
1 22.04
On axis A 3.23 71.19
1 18.26
3.0 54.78 m2 1 9.60
3.23 31.01
On axis 5
1 1.93 1 11.80
3.0 5.79 m 2
3.23 38.11
183.24 total area 291.28
Class B 15*20*40cm
HCB 1 3.85
5 5.25 toilet area 3.23 12.44
3.0 78.75 m2
1 5.75 1 9.90
3.0 17.25 m 2
3.23 31.98
6 1.55 1 24.60
3.0 27.90 m 2
3.23 79.46
123.90 total area
1 12.12
3.23 39.15
1 22.04
3.23 71.19
T D A Description T D A
On axis 5
1 7.70 1 10.02
3.23 24.87 m2 3.23 32.36
b/n axis 1&2
1 7.75 1 24.60
3.23 25.03 m 2
3.23 79.46
271.68 total area
Class B 15*20*40cm
HCB 1 12.12
1 7.4 3.23 39.15
3.23 23.90 m2
Roofing 1 22.04
1 25.8 3.23 71.19
16.35 421.83 m 2
ceiling 2 9.60
1 25 3.23 62.02
15.2 380.00 m 2
G-28 gutter 2 11.80
4 42.6 3.23 76.23
170.4 ml 2 3.85
Internal Plastering 3.23 24.87
G+0
On axis 1 1 9.90
1 10.02 3.23 31.98
3.0 30.06 m 2
On axis D 1 24.60
1 18.75 3.23 79.46
3.0 56.25 m 2
On axis 6 1 12.12
1 12.12 3.23 39.15
3.0 36.36 m 2
On axis A 1 22.04
1 18.26 3.23 71.19
3.0 54.78 m 2
On axis 5 1 7.70
2 1.93 3.23 24.87
3.0 11.58 m 2
T D A Description T D A
Column,beam,soffit,stair
&edges 1 5.25
5.95 31.24
24 1.6
3.23 124.03 m2 10 1.1
3 33.00
42 0.5 2 1.2
3.23 67.83 m2
3 7.20
2 25 8 1.28
13.76 688.00 m2
3 30.72
9 25 2 1.15
0.6 135.00 m2 3 6.90
12 13.76 6 1.4
0.6 99.07 m2
3 25.20
1 5.2
6 10.02 3 15.60
0.6 36.07 m2
118.62
3 18.26
0.6 32.87 m2 1 21
14.87 312.27
4 2.51
1.35 13.55 m2 1 21
14.9 312.90
2 1.01
1.3 2.63 m2 1 3.65
3.29 12.01
4 1.35
1.3 7.02 m2 1 3.75
5.75 21.56
8 2.51
0.33 6.63 m2
1 21
1212.70 total area 14.9 312.90
1212.70 1 3.75
For beam,column,soffit,edge
refer 6.2 5.75 21.56
1005.21
T D A Description T D A
Internal Painting
G+0 1 9.90
On axis 1 3.23 31.98
1 10.02
3.0 30.06 m2 1 24.60
On axis D 3.23 79.46
1 18.75
3.0 56.25 m2 1 12.12
On axis 6 3.23 39.15
1 12.12
3.0 36.36 m2 1 22.04
On axis A 3.23 71.19
1 18.26
3.0 54.78 m2 1 7.70
On axis 5 3.23 24.87
2 1.93
3.0 11.58 m2 1 7.75
9 5.25 toilet area 3.23 25.03
3.0 141.75 m2 1 7.4
2 5.75 3.23 23.90
3.0 34.50 m2 1101.9317
12 1.55
3.0 55.80 m2
G+1
1 10.02 On axis 1
3.23 32.36 m2
On axis D
1 24.60
3.23 79.46 m2
On axis 6
1 12.12
3.23 39.15 m2
On axis A
1 22.04
3.23 71.19 m2
On axis 5
2 9.60
3.23 62.02 m2
b/n axis 1&2
2 11.80
3.23 76.23 m2
2 3.85
3.23 24.87 m2
T D A Description T D A
Column,beam,soffit,stair
&edges painting
24 1.6
3.23 124.03 m2
42 0.5
3.23 67.83 m2
2 25
13.76 688.00 m2
9 25
0.6 135.00 m2
12 13.76
0.6 99.07 m2
6 10.02
0.6 36.07 m2
3 18.26
0.6 32.87 m2
4 2.51
1.35 13.55 m2
2 1.01
1.3 2.63 m2
4 1.35
1.3 7.02 m2
8 2.51
0.33 6.63 m2
T D A Description T D A
External quartiz paint
G+0 1 7.75
On axis 1 3.23 25.03
1 10.02 1 7.4
3.0 30.06 m2 3.23 23.90
On axis D
1 18.75 8 25
3.0 56.25 m 2
0.45 90.00
On axis 6
1 12.12 8 15.15
3.0 36.36 m2 0.45 54.54
On axis A
1 18.26 42 0.3
3.0 54.78 m 2
3.23 40.70
G+1
1 10.02 On axis 1
3.23 32.36 m2 2 25.05
On axis D 1 50.10
1 24.60
3.23 79.46 m2 2 25.05
1 50.10
On axis 6
1 12.12 2 15.5
3.23 39.15 m2
1 31.00
On axis A
1 22.04 2 15.5
3.23 71.19 m2 1 31.00
For G+2
1 9.90 On axis 1 1042.62
3.23 31.98 m2
On axis D
1 24.60
3.23 79.46 m2
On axis 6
1 12.12
3.23 39.15 m2
On axis A
1 22.04
3.23 71.19 m2
On axis 5
1 7.70
3.23 24.87 m2
T D A Description T D A
Aluminum work
for ground floor 1 14.67
1 9.9 on axis 2 3.4 49.88
3.4 33.66 m2
1 18.91
1 6.93 on axis 3 3.4 64.29
3.4 23.56 m2
1 6.5
1 9.75 b/n axis 2 & 3 3.4 22.10
3.4 33.15 m2
1 5.0
1 4.95 on axis 4 3.4 17.00
3.4 16.83 m2
1 5.0
1 8.56 on axis C 3.4 17.00
3.4 29.10 m2
679.96
1 11.79 b/n axis B & C
3.4 40.09 m2
1 13.05 on axis B
3.4 44.37 m2
For window
12 1.4 for left section G+0 - G+2
2.05 34.44 m2
m2
m2
m2
m2
m2
total area
top tie beam
Roof level on axis B,C,D
m2
on axis A
m2
on axis 2,3,4
m2
on axis 5
m2
on axis 1&6
m2
Description
for landing
m2
for riser
m2
m2
m2
side formwork
m2
m2
m2
total area
for gutter
Description
for floor beam
For 1st & 2nd floor
FFB & SFB onaxis B,C,D
m3
m3
m3
m3
total volume
Top tie beam
Roof level onaxis B,C,D
m3
m3
m3
m3
m3
total volume
Description
CONCRETE WORK
for floor slab
for 1st & 2nd floor
m2
m2
m2
m2
total area
water tanker seat slab
m2
for gutter
Description
For G+1
m2
On axis 6
m2
On axis A
m2
On axis 5
m2
b/n axis 1&2
m2
total area
Class B 15*20*40cm HCB
m2
For G+2
Class B 20*20*40cm HCB
On axis 1
m2
On axis D
m2
On axis 6
m2
On axis A
m2
Description
G+1
On axis 1
m2
On axis D
m2
On axis 6
m2
On axis A
m2
On axis 5
m2
b/n axis 1&2
m2
m2
For G+2
On axis 1
m2
On axis D
m2
On axis 6
m2
On axis A
m2
On axis 5
m2
b/n axis 1&2
m2
m2
total area
Description
b/n axis 1&2
m2
m2
m2
m2
m2
parapet wall
front section
m2
rear section
m2
left section
m2
right section
m2
total area
Description
CERAMIC TILES
G+0
m2
CERAMIC WALL TILES
m2
m2
m2
m2
m2
m2
total area
Non slippery porcilen floor tiles
G+0
m2
G+1
m2
m2
m2
G+2
m2
m2
m2
total area
Description
For G+2
On axis 1
m2
On axis D
m2
On axis 6
m2
On axis A
m2
On axis 5
m2
b/n axis 1&2
m2
m2
total area
Description
Description
b/n axis 1&2
m2
m2
m2
m2
m2
parapet wall
front section
m2
rear section
m2
left section
m2
right section
m2
total area
Description
for first floor
on axis C
m2
on axis 2
m2
on axis 4
m2
total area
በአዲ ስ አበባ ከተ ማ አስተ ዳ ደር Addis Ababa city administration
የቦሌ ክፍ ለ ከተ ማ አስተ ዳ ደር Bole Sub City Administration
ስራው ዋናው ውል
ተፈረመበት ቀን ፡02/09/2014
ው የተሰራበት ቀን ፡-26/09/2014
e of issued payed
Amount (birr)
የገንዘቡ ልክ / ብር /
8,244,644.75
1,236,696.71
9,481,341.46
Amount (birr)
የገንዘቡ ልክ
/ ብር /
1,799,423.92
161,948.15
1,637,475.76
1,097,648.589
232,125.69
67,478.40
164,647.29
1,262,295.88
0 ሳንቲም) ቫትን ጨምሮ ሲሆን ይህንኑ ብር ለስራ
Approved by
Con.cont Administration Team Leader