Schedule 4267
Schedule 4267
Name of work :- Work of geotechnical investigation for proposed 1 x 660 MW super critical
unit at STPS Sarni.
Sl. Particular of Item Unit Qty Rate Amount
No. (in Rs.) (in Rs.)
1 2 3 4 5 6
1 a) Making 150mm nominal diameter bore hole up to a M 700
maximum depth of 25m below ground level at various
locations in all types of soil including laterite using
suitable approved method of boring including
chiselling, cleaning, providing casing pipes as
required or as directed: performing standard
penetration test at every 3m interval, at change of
strata and at depths wherever undisturbed soil
samples could not be collected: collection of
undisturbed soil samples at every 3m interval and at
change of strata; collection of disturbed soil samples
and water samples, sealing and packing of samples,
observation such as ground water table etc;
transportation of all the collectd samples to the
laboratory and back filling of boreholes, with sand on
completion of the same etc all complete as per
specification and as directed by the Engineer-in-
charge
b) In water body (river/nala/canal etc) upto water M 100
depth
of 7m using staged/fixed platform. from bed level to
20m depth
2 a) Core drilling (Nx-size) in rock using hydraulic feed M 1000
rotary drill and double tube core barrel with diamond
bit including collection of core samples, performing
SPT at location, where core recovery is less than
20% maintaining continuous record of core recovery
and RQD, keeping the cores in wooden core boxes,
transporting the cores to laboratory, back filling the
holes with 1 part of cement 3 part of sand grout on
completion of the same etc all
complete as per specification, drawing and as
directed by the Engineer in charge.
b) In water body (river/naIa/canal etc.) upto water M 50
depth
of 7m using staged/fixed platform
3 Excavating trial pit of size 3mx3m at various locations Cum 400
up to 4m depth below ground level in all types of soil
and weathered rock which can be excavated with pick
axe/crow bar etc including sheeting or shorting like
sides of the purpose of stability, dewatering and
maintaining the pit dry at all times, collecting
disturbed/undisturbed samples at 1m interval and at
final depth and transporting all the collecting samples
to the laboratory, backfilling of the pit with excavated
material etc all complete as per specification and as
directed by the Engineering-in-charge
4 Conducting plate load test in various location at Each 6
specified depth complete as per specification,
drawings and as directed by the Engineer in charge
payment for making the pit of suitable size, maintaning
it dry and backfilling etc shall be separately as per item
no. 3
5 Conducting cyclic plate load test in various location at Each 6
specified depth complete as per specification,
drawings and as directed by the Engineer in charge
payment for making the pit of suitable size,
maintaining it dry and backfilling etc shall be separate
as per item no. 3
6 Performing dynamic cone penetration test at various Each 7
location using 65mm cone with circulation of bentonite
slurry etc all complete as per specification, drawings
and as directed by the Engineer-in-charge,
7 Conducting electrical resistivity test at various Each 40
locations
complete as per specification drawings and as
directed by the Engineer in charge
8 Conducting field CBR test in various locations at Each 5
specified depth complete as per specification.
drawings and as directed by the Engineer-in-charge
9 a) Conducting pump in type field permeability test by Each 6
constant head or falling head method (suitability of
type of test shall be as per site conditions) in various
boreholes at specified depth including providing
packers as required etc all complete as per
specification, drawings and as directed by the
Engines-in-charge. Cost of the borehole and
backfilling etc shall be paid separately as per item no.2
bI Pump out test in bore hole. Each 6
c) Conducting field Permeability test in rock in Drill Each 6
holes at various depths all complete as per
specification and directions of the Engineer.
10 Conducting seismic refraction test at various M 1000
locations
complete as per specification, drawings and as
directed by the Engineer-in-cahrge
11 Conducting laboratory test on soil samples at an
approved laboratory including prepration of soil
samples to determine the following properties etc all
complete as per specification.
IS: 10060 Code of practice for subsurface investigation for power house sites
IS: 10074 Specification for compaction mould assembly for light and heavy
compaction
IS: 10108 Code of practice for sampling by thin wall sampler with stationary piston
IS: 10589 Equipment for determination of subsurface sounding of soils
IS: 10837 Specifications of moulds for determination of relative density and its
accessories
IS: 11229 Specifications for shear box testing of soils
IS: 11315 Description of discontinuities in rock mass – Core Part-II recovery and
rock quality
IS: 12070 Code of practice for design and construction of shallow foundations on
rocks
IS:13372 Seismic testing of rock mass – Code of practice (Part I & II)
b) All bore holes shall extend up to the depths shown on the construction drawings or as
directed by the engineer-in-charge. If the strata with standard penetration test (SPT) ‘N’
value greater than 100 with characteristics of rock is met with earlier, the bore hole shall
be advanced further by chiselling. Chiselling shall be continued for a maximum depth of
20cm or upto 2 hours whichever is earlier. During chiselling rock fragments/rock cores
shall be collected. Identification of rock strata shall be on the basis of visual examination
of SPT sample and rock fragments. After it is established that rock is met with, the
borehole shall be advanced further by drilling in rock as specified in Clause-7.0 and cores
shall be collected. When the bore hole is terminated in soil strata, an additional standard
penetration test shall be carried out at the termination depth.
c) Casing pipe shall be used in the borehole to support its sides when side fall is
suspected to occur inside the borehole. When casing pipe is used, it shall be ensured
that its bottom end is at all times 15 cm above the bottom of the bore hole. In case of
cohesionless soils the advancement of the casing pipe shall be such that it does not
disturb the soil to be tested or sampled. The casing shall be advanced by slowly turning
the casing pipe and not by driving.
d) In-situ tests and collection of undisturbed samples (UDS) shall be carried out at regular
intervals and at change of strata or as decided by the engineer-in-charge. Representative
disturbed and undisturbed samples shall be preserved for conducting various tests in the
laboratory. Water table in the borehole shall be carefully recorded and reported. No
water/drilling mud shall be added while boring above ground water table. For
cohesionless soil below water table, the water level in the borehole shall all times be
maintained at slightly above the water table.
e) The bore hole shall be cleaned using suitable tools up to the depth of testing or
sampling ensuring that there is minimum disturbance of soil at the bottom of the bore
hole. The process of jetting through an open tube sampler shall not be permitted. In
cohesive soils, the borehole may be cleaned using a bailer with a flap valve. Gentle
circulation of drilling fluid shall be done when rotary mud circulation boring is adopted.
f) On completion of the borehole, the portion drilled in soil shall be backfilled with sand
unless otherwise specified and as directed by the engineer-in-charge.
g) Wash boring shall not be adopted.
6.1 .2 Auger Boring
Auger boring can be adopted in soft to stiff cohesive soils above water table. Augers shall
be of helical or post hole type which may be manually or power operated. While boring
care shall be taken to minimise the disturbance to the deposits below the bottom of the
borehole. The cuttings brought up by the auger shall be carefully examined in the field
and the description of all the strata shall be duly recorded in the field borelog as per
IS:1498. No water shall be used while auger boring.
6.1.3 Shell and Auger Boring
Shell and Auger boring can be used in all types of soil free from boulders. For
cohesionless soil below ground water table, the water level in the bore hole shall always
be maintained at or above the ground water level. The use of chisel bit shall be permitted
in hard strata with SPT ‘N’ value greater than 100. Chisel bits may also be used to extend
the borehole through local obstruction such as old construction, boulders, rocky
formations etc. All other requirements in clause 6.1.2 shall apply for this type of boring
also.
6.1.4 Percussion Drilling
This method can be adopted in soil with gravel and boulders when the boring has to be
done at a faster rate. This method consists of breaking of the strata by repeated blows
from a chisel or drilling bit and bailing out the debris at intervals by adding water into the
bore hole. This method is not suitable for careful and very reliable sampling operation
because of the disturbance caused during boring.
This method shall not be adopted unless otherwise specified or permitted by the engineer-
in-charge.
6.1.5 Rotary Mud Circulation Drilling
This method can be used in all types of soil below water table. In this method boring shall
be done by rotating the bit fixed at the bottom of the drill rod. Proper care shall be taken
to keep a firm contact between the bit and the bottom of the borehole. Bentonite or mud
laden fluids shall be used as the drilling fluid to serve as the protective surface inside the
borehole.
6.2 Standard Penetration Test (SPT)
This test shall be conducted in all types of soil deposits met within the bore hole to find
the variation in the soil stratification by correlating with the number of blows required for
unit penetration of a standard penetrometer. This test shall be conducted at every 1m
interval alternate to collection of UDS upto 10m depth below ground level and at every
1.5m interval alternate to collection of UDS beyond 10m depth, at every change of strata,
at depths wherever undisturbed soil samples could not be collected and as per the
directions of the engineer-in-charge. The starting depth of performing SPT shall be 1m
below ground level unless otherwise specified. The depth interval between the top level
of standard penetration test and to that of (next) undisturbed sampling shall not be less
than 1m. The specification for equipments and other accessories, procedure for
conducting the test, presentation of test results and collection of disturbed soil samples
etc shall conform to IS: 2131.
This test shall be carried out by driving a standard split spoon sampler in the borehole by
means of a 63.5 kg hammer having a free fall of 0.75m. The sampler shall be driven using
the hammer for 450 mm penetration. While driving, the number of blows for every 150
mm penetration and the penetration for every 50 blows shall be recorded.
The number of blows for the last 300 mm drive shall be reported as ‘N’ value. This test
shall be discontinued when the blow count is equal to 100 and the penetration shall be
recorded. Refusal shall be considered to be met with when the blow count is equal to 100.
At the location where the test is discontinued, the penetration and the corresponding
number of blows shall be reported. Sufficient quantity of disturbed soil samples shall be
collected from the split spoon sampler for identification and laboratory testing. The
samples shall be visually classified & recorded at the site and shall be properly preserved
and labelled for future identification & testing.
6.3 Sampling
6.3.1 General
a) Sufficient number of soil samples shall be collected for reliable estimation of soil
properties. The samples collected shall be either disturbed or undisturbed. Disturbed soil
samples shall be collected for field identification and conducting laboratory tests such as
sieve analysis, index properties, specific gravity, chemical analysis etc.
Undisturbed samples shall be collected to estimate physical, strength and settlement
properties of the soil.
b) All the accessories required for sampling and the method of sampling shall conform to
IS:2132. All disturbed and undisturbed samples collected in the field shall be classified at
site as per IS: 1498.
c) All the samples shall be identified with date, bore hole or trial pit number, depth of
sampling etc. It is also essential to mark an arrow pointing towards the top surface of the
undisturbed sample as the soil was in-situ. Care shall be taken to keep the undisturbed
soil samples and box samples vertically with the arrow directing upwards. The tube
samples shall be properly trimmed at both ends and suitably sealed with molten paraffin
wax at both ends immediately after extracting the samples from the bore hole/trial pit and
suitably capped on both sides.
d) When the contractor fails to collect undisturbed soil sample at a specified depth,
the borehole shall be advanced by 0.50m and shall be performed with a standard
penetration test. The reason for not obtaining the undisturbed soil sample shall be
indicated in the borelog.
e) Precaution shall be taken to ensure that there shall not be any change in moisture
content and disturbance of the soil samples and they shall be placed in a temporary store
at the end of the day's work.
All the samples shall be kept over a bed of sand, jute bags, saw dust etc and covered
over the top with similar material. The bed and top cover shall be kept moist till they are
properly packed in wooden boxes. The contractor shall be responsible for packing and
transporting of all the samples from site to the laboratory within seven days after sampling
with proper protection against loss and damage.
f) All the samples shall be suitably packed in wooden boxes using sand, saw dust etc all
around the samples before transporting to the laboratory for testing.
6.3.2 Disturbed Samples
a) Disturbed soil samples shall be collected from cuttings and from split spoon sampler in
boreholes at regular intervals to provide complete description of soil profile and its
variation. The samples shall be immediately stored in airtight jars or polythene bags and
labelled with borehole/trial pit number and depth.
b) In elevated areas, if superficial material is available in plenty, then bulk samples from
a depth of about 0.5m below ground level shall be
collected to establish all required properties to use it as a fill material. Disturbed samples
weighing about 250N shall be collected at shallow depths and immediately stored in
polythene bags as per IS: 1892. The bags shall be sealed properly and shall be kept in
wooden boxes.
6.3.3 Undisturbed Samples
In each borehole UDS shall be collected at regular interval of 1m alternate to conducting
SPT upto 10m depth below ground level and at every 1.5m interval alternate to conducting
SPT beyond 10m depth and as directed by the engineer-in-charge. The starting depth of
collecting UDS shall be 2m below ground level unless otherwise specified and as directed
by the engineer-in-charge. Undisturbed samples shall be of 100mm diameter and 450mm
length. Samples shall be collected in such a manner that the structure of soil and its
moisture content do not get altered. The specification for the accessories required for
sampling and the sampling procedure shall conform to IS:1892 and IS:2132. Undisturbed
sampling in sand shall be done using compressed air technique as mentioned in IS:8763.
Thin walled sampler shall be used to collect undisturbed samples by pushing the tube
into the soil. The sampling tube shall have a smooth finish on both surfaces and minimum
effective length of 450mm.
The area ratio of sampling tubes shall be less than 12.5%. However in case of very stiff
soils area ratio upto 20% shall be permitted.
a) Undisturbed Sampling in Cohesive Soil
Undisturbed samples in soft to stiff cohesive soils shall be obtained using a thin walled
sampler. In order to reduce wall friction, suitable precautions such as oiling the surfaces
shall be taken. The bore hole shall be cleaned and the depth of sampling below ground
level shall be noted. The sampler shall then be attached to the bottom of boring rods and
lowered into the borehole. The sampler shall be pushed into the clay layer by hand or by
jacking and soil sample of specified length shall be collected without disturbing the soil.
The distance by which the sampler penetrates into the soil strata shall be checked.
Care shall be taken to ensure that the sampler is not driven too far as this will compress
the soil. The sampler shall be rotated to break the core at bottom of the sampler and then
steadily drawn up.
b) Undisturbed Sampling using Piston Sampler
Undisturbed samples in very loose saturated sandy & silty soils and very soft clays shall
be obtained by using a piston sampler consisting of a sampling cylinder and piston
system. In soft clays and silty clays with water standing in the casing pipe, piston sampler
shall be used to collect undisturbed samples. During this method of sampling expert
supervision is called for.
The interior surface of the sampler shall be smooth, clean and corrosion resistant. Its
cutting edge and the ring seals shall be inspected for wear and rejected if worn. Check
shall be done to ensure that the moving parts of the sampler function freely before the
sampler is lowered into the borehole. While pushing the system into the soil and till the
beginning of the sampling operations, the bottom of the piston shall be flushed with the
cutting edge of the sampler. At the depth of sampling, the piston should be fixed relative
to the ground and the sampler cylinder shall be independently pressed down smoothly
and continuously into the ground. If an obstruction is met, the sampler shall be withdrawn
and another sample be taken after the obstruction is removed.
Accurate measurements of the depth of sampling, height of sampler, stroke and length of
sample recovery shall be noted and recorded.
After the sampler is pushed to the required depth, both the sampler cylinder and the piston
system shall be drawn up together ensuring that there shall not be any disturbance to the
sample which shall then be protected from changes in moisture content.
c) Undisturbed Sampling in Cohesionless Soils
Undisturbed samples in cohesionless soils shall be obtained as per the procedure given
in IS:8763. Compressed air sampler shall be used to take the samples of cohesionless
soil below water table.
Precautions shall be taken to clean the borehole before sampling. Thin walled tube
samplers of 60mm internal diameter shall be used. The height and other dimensions of
the sampler shall be recorded before use. Proper care shall be taken to maintain the
water level in the bore hole slightly above the ground water table before and during
sampling operations. Immediately after the sample is obtained, the ends of the sample
shall be waxed and capped to avoid moisture content changes.
6.3.4 Relaxation During Sampling
a) The sampler shall be pushed into the soil and driving of sampler shall be resorted to
only when it cannot be pushed into the soil. This shall be done only with the permission
of the engineer-in-charge and all the details about the same shall be recorded in the bore
logs.
b) In clays when ‘N’ value is greater than 50, the undisturbed sampling may be replaced
by standard penetration test.
6.4 Ground Water
6.4.l One of the following methods shall be adopted for determining the ground water
table in bore holes as per IS:6935 and as per the instructions of the engineer-in-charge.
a) In permeable soils, the water level in borehole shall be allowed to stabilize after
lowering it adequately by bailing. When water level inside the borehole is found to be
stable, the depth of water level below ground level shall be measured. Stability of sides
and bottom of the borehole shall be ensured at all times.
b) For both permeable and impermeable soils, the following method shall be suitable. The
borehole shall be filled with water and then bailed out to various depths. Observation on
the rise or fall of water level shall be made at each depth. The level at which neither a fall
nor a rise is observed shall be considered as the water table elevation.
This shall be established by three successive readings of water level taken at an interval
of two hours.
6.4.2 In case any variation in the ground water level is observed in any specific boreholes
then the water level in these bore holes shall be recorded daily during the course of field
investigation. Levels in nearby wells, streams etc if any shall also be noted whenever
these readings are taken. If so called for, observation wells shall be drilled for the purpose
of long term studies on the fluctuation in ground water levels and pressure. Either stand
pipe or piezometer shall be installed at the specified depths in the selected previously
drilled bore holes or specially drilled bore holes for this purpose as per the specification
and instructions of the engineer-in-charge. Daily water level readings shall be recorded
immediately following the installation upto the time of leaving the site. At the end of field
work, these installations shall be handed over in satisfactory working condition to the
engineer-in-charge without disturbing their position so that the owner can continue further
observations.
6.4.3 Stand pipes and piezometers shall consist of 19mm internal diameter rigid
unplasticised (UPVC) tubing. All the joints in the tubing shall be made of coupling sleeves.
The top of UPVC tubing shall be enclosed in a 75mm diameter galvanised steel pipe of
1.5m length having a galvanised steel screw cap with well greased threads and the caps
shall be tightened such that it would be impossible to loosen by hand. The lower end of
the pipe shall have four legs of 6mm thick and 100mm long and welded to have projection
of 25mm. The pipe shall be sealed into the ground with cement grout so that it does not
rotate. The top end of the pipe shall project about 300mm above ground level unless
otherwise specified by the engineer-in-charge.
The perforated tubing for the porous element shall be surrounded by a response zone of
well graded sand from 500mm below to 150mm above the lower end of the stand pipe or
piezometer and the bore hole above the response zone shall be back filled with natural
soil or well graded sand.
a) Stand pipe
Stand pipes shall be installed to measure the water level in soils with high permeability
such as sand and gravel. The stand pipe shall consist of a perforated tubing attached to
the bottom of the UPVC tubing. The perforated tube shall be 150mm long having
perforations of diameter not greater than 1mm.
b) Piezometers
Piezometers shall be installed to measure the pore pressures in soil with medium to low
permeability. Piezometer shall consist of a porous filter attached to the bottom of the
UPVC tubing. The filter shall be 300mm in length and shall be placed in the bore hole and
sealed at top and bottom by grouting. Hydraulic piezometers with double line are to be
used to remove the air trapped in the system.
6.4.4 Sub-Soil Water Samples
a) Sub-soil water samples shall be collected for carrying out chemical analysis.
Representative samples of ground water shall be collected when it is first encountered in
boreholes before the addition of water to aid boring or drilling. Water samples shall not
be collected when bentonite slurry or mud has been used for drilling operations. If water
has been added for drilling purposes or if ground water has been diluted by surface rain
water then the bore hole shall be dewatered and water be allowed to rise from which the
sample may be taken.
b) The sampling apparatus shall be such that the water at the desired depth can be
collected directly without any disturbance and any change in concentration of constituents
like dissolved gases etc. Undue agitation shall be avoided. An ordinary suction pump with
its suction end inserted upto the required depth in the borehole shall be used for this
purpose.
c) The sample shall be collected in a clean vessel and allowed to settle so that the
supernatural liquid can be poured into a clean well rinsed glass or polythene bottle.
Sufficient quantity and number of samples shall be collected to carry out the chemical
analysis and sent to a laboratory in airtight bottles with proper labelling. Chemical analysis
of water samples shall include determination of pH value, turbidity, sulphate, carbonate,
nitrate & chloride contents, presence of organic matter and suspended solids etc.
d) In some cases constituents may be mixed and analysed later as specified in the
specific test methods. Chemical preservatives may be added to the sample for cases as
specified in the test method/IS codes. This shall only be done if analysis cannot be
conducted within an hour of collection and shall have the prior written permission and
approval of the engineer-in-charge.
6.5 In-situ Permeability Test
6.5.1 In-situ permeability test shall be conducted to determine the water percolation
capacity of overburden soil. This test shall be performed inside the bore hole/trial pit at
specified depths or in each layer or as per the directions of the engineer-in-charge. The
type of test shall be either pump-in or pump-out test depending on the subsoil and ground
water conditions. Pump-in test shall be conducted whether ground water in borehole
exists or not. Pump-out test shall be conducted to obtain data for dewatering purposes
when ground water is met in the borehole. The specification for equipments required for
the test and the procedure of testing shall be in accordance with IS: 5529, Part-1.
When it is required to carry out the permeability test for a particular section of the soil
strata above ground water table, bentonite slurry shall not be used while boring.
6.5.2 Pump-in-Test
Pump-in test shall be conducted in the bore hole/trial pit by allowing water to percolate
into the soil. Choice of the method of testing shall depend on the soil permeability and
prevailing ground water level. Only clear water shall be used for conducting the test.
Before conducting the test, the borehole shall be cleaned as specified in clause 6.1.1 (e).
Water shall be allowed to percolate through the test section for sufficient period of time to
saturate the soil before starting the observation.
a) Constant Head Method (In Bore Hole)
This test shall be conducted in boreholes where soil has a high permeability. Water shall
be allowed into the borehole through a metering system ensuring gravity flow at constant
head so as to maintain a steady water level in the borehole. A reference mark shall be
made at a convenient level which can be easily seen in the casing pipe to note down the
fluctuations of water level. The fluctuations shall be counteracted by varying the quantity
of water flowing into the borehole. The elevation of water shall be observed at every 5
minute interval. When three consecutive readings show constant value, the necessary
observations such as flow rate, elevation of water surface above test depth, diameter of
casing pipe etc shall be made and recorded as per the proforma recommended in IS:
5529, Part-1, Appendix-A.
b) Falling Head Method (In Bore Hole)
This method shall be adopted for soils of low permeability and which can stand without
casing. The test section shall be sealed at the bottom of the borehole and a packer at the
top of the test section. If the test has to be conducted at an intermediate section of a pre-
bored hole then double packers shall be used. Access to the test section through the
packer shall be by means of a pipe which shall extend above the ground level. Water
shall be filled into the pipe upto the level marked just below the top of the pipe and water
be allowed to drain into the test section. The water level in the pipe shall be recorded at
regular intervals as mentioned in IS: 5529, Part-1, Appendix-B. The test shall be repeated
till constant records of water level are achieved.
c) Percolation Test (In Trial Pit)
Percolation test shall be conducted in trial pit in areas where water/effluent is
stored/discharged in ground level tanks. The loss of water due to percolation into the soil
shall be estimated by the soil absorption capacity.
6.5.3 Pump-Out Test
This test shall be carried out at site to determine the co-efficient of permeability of soil
below water table. This test shall be conducted by continuous pumping out of water from
a well so as to maintain a steady water level at the desired depth in the well. The
fluctuations in the water level shall be counteracted by varying the quantity of water
pumped out of the well. The specification for the equipments & accessories required for
performing the test, the procedure of testing, field observations and reporting of results
shall conform to IS: 5529, Part-1. The well shall be of 400mm in diameter to be installed
with a 250mm diameter perforated GI/MS pipe. Observation pipes of 50mm diameter shall
be installed at regular intervals along three radial lines extending from the well at 120
degrees to each other. Length of these pipes shall depend upon the ground level,
estimated depth of lowering the ground water and the distance from the well. Sufficient
number of observation pipes shall be installed along each of the radial lines so as to
assess the zones of influence due to dewatering. Draw down depth in the well shall be
as specified in the drawing.
6.6 TRIAL PIT
6.6.1 Trial pits shall be of 3m x 3m size so as to permit easy access for visual examination
of walls of the pit and to facilitate sampling and in-situ testing operations. Pits shall be
excavated upto a maximum depth of 4m below ground level or as per the directions of
the engineer-in-charge. Precautions shall be taken to ensure the stability of pit walls
including provision of shoring if necessary as per IS: 4453. Precautions shall be taken to
prevent surface water draining into the pit. Arrangements shall be made for dewatering if
the pit is extended below water table. Trial pits shall be kept dry and a ladder shall be
provided for easy access to the bottom of the pit. ln-situ tests shall be conducted and
undisturbed samples shall be collected immediately on reaching the specified depth so
as to avoid substantial changes in moisture content of the subsoil. Arrangements shall be
made for barriers, protective measures and lighting necessary for the period the pits
remain open.
6.6.2 A note on the visual examination of soil strata shall be prepared. This should include
the nature, colour, consistency and visual classification of the soil, thickness of soil strata,
thickness of expansive soil & ground water table if any etc.
6.6.3 Undisturbed samples shall be collected at 1m, 2m, 3m depth and at the termination
depth in all the pits.
a) Chunk Samples
In cohesive soils, undisturbed samples of regular shapes shall be collected. The samples
shall be cut and trimmed to a size of 0.3m x 0.3m x 0.3m. A square area of 0.35m x 0.35m
shall be marked at the centre of the levelled surface at the bottom of the pit. Without
disturbing the soil inside the marked area, the soil around this marking shall be carefully
removed upto a depth of 0.35m. The four vertical faces of the soil block protruding at the
centre shall be trimmed slowly so that its size reduces to 0.3m x 0.3m. Wax paper cut to
suitable size shall be wrapped uniformly and covered with two layers of thin cloth over all
the five exposed surfaces of the soil block and sealed properly using molten wax. A firmly
constructed
box of size 0.35m x 0.35m x 0.35m (internal dimensions) with the top and bottom open
shall be placed around the soil block and held such that its top edge protrudes just above
the surface of the block. The space between the soil block and the box shall be filled
uniformly and tightly with moist saw dust. The top surface shall also be covered with saw
dust before nailing the wooden lid to cover the box firmly taking care that the soil block is
not disturbed. The area of contact between the bottom portion of the block and the ground
shall be reduced slowly by removing soil in small quantities using small rods so that the
block can be separated from the ground slowly without disturbance. After inverting the
wooden box along with the soil block, the bottom portion shall be trimmed and covered
with wax paper, cloth and to be sealed with molten wax. A wooden lid shall be nailed to
the box after providing proper saw dust cushion below it. An arrow mark shall be made
on the vertical face of the wooden box to indicate the top surface of the sample along with
the location, date and depth of sampling.
b) Tube Samples
Undisturbed tube samples may also be obtained by means of 100mm diameter sampling
tubes with a cutting edge. The sampler shall be slightly oiled or greased inside and outside
to reduce friction. The sampler shall be pushed into the soil and while doing so soil around
the tube shall be carefully removed. In case it is not possible to push the sampler it may
be driven by light blows from a "monkey".
6.6.4 In case it is not possible to collect undisturbed samples in the pit, insitu density of
soil shall be determined by sand replacement method.
The specification, equipments, accessories etc required for the test and the procedure of
testing shall be in accordance with IS: 2720, Part-XXVIII. No separate payment shall be
made for this test.
6.6.5 After the completion of the test, sampling and visual examination, the pit shall be
suitably backfilled as directed by the engineer-incharge. Unless otherwise specified
excavated soil shall be used for this purpose.
6.7 Vane Shear Test
Field vane shear test shall be performed inside the borehole to determine the shear
strength of cohesive soils, especially of soft and sensitive clays which are highly
susceptible to sampling disturbance.
This test shall be conducted by advancing a four winged vane of suitable size (75mm or
100mm diameter as per the soil condition) into the soil upto desired depth and measuring
the torque required to rotate the vane. The specification for equipments & accessories
required, the test procedure and field observations etc shall be as per IS: 4434. This test
may also be conducted by direct penetration from the ground surface. If the cuttings at
the test depth in the bore hole show any presence of gravel, sand, shells, decomposed
wood etc which are likely to influence the test results substantially, the test at that
particular depth may be omitted with the permission of the engineer-in-charge. However
the test shall be conducted at a depth where these obstructions cease to occur. On
completion of the test the results shall be reported in an approved proforma as specified
in IS: 4434, Appendix-A.
6.8 Static Cone Penetration Test
Static cone penetration test shall be conducted to know the soil stratification and to
estimate the various physical and engineering properties of soil. The cone penetrometer
shall be advanced by pushing and the static force required for unit penetration shall be
determined. The test shall be conducted using a 200kN capacity mechanically operated
equipment upto the specified depth or refusal whichever is earlier. For this test, 'refusal'
means meeting a very hard strata which cannot be penetrated at the rate of at least
0.3cm/sec even when the equipment is loaded to its full capacity.
The specification for the equipment and accessories required for performing the test, test
procedure, field observation and reporting of results shall conform to IS : 4968, Part-III.
At the ground level, preboring upto 0.5m depth shall be permitted if the overlying strata is
very hard. No extra payment shall be made on account of this preboring. Continuous
record of the penetration resistance shall be maintained.
6.9 Dynamic Cone Penetration Test
Dynamic cone penetration test shall be conducted using bentonite slurry by driving a
standard size cone attached to the bottom of a string of drill rods. The test shall be
conducted upto the specified depth or refusal whichever is earlier. Refusal shall be
considered when the blow count exceeds 150 for 300mm penetration. The specification
for the equipment and accessories required for performing the test, test procedure, field
observations and reporting of results shall conform to IS:4968, Part-II. The driving system
shall comprise of a 65 kg weight having a free fall of 0.75m. The cone shall be of 65mm
diameter provided with vents for continuous flow of bentonite slurry through the cone and
rods in order to avoid friction between the rods and soil. On completion of the test, the
results shall be presented as a continuous record of number of blows required for every
300mm penetration of the cone into the soil in a suitable chart supplemented by a
graphical plot.
6.10 Plate Load Test
6.10.1 Plate load test shall be conducted to determine the bearing capacity and
load/settlement characteristics of soil at shallow depth by loading a plane and levelled
steel plate kept at the desired depth and measuring the settlement under different loads
until a desired settlement takes place or failure occurs. The specification for equipment
and accessories required for conducting the test, the test procedure, field observations
and reporting of results etc shall conform to IS: 1888. The location and depth of the test
shall be as given in the drawing or as indicated by the engineer-in-charge.
Undisturbed tube samples as specified in clause 6.6.3 (b) shall be collected at 1m and
2.5m depths from the ground level for carrying out laboratory tests.
6.10.2 The size of pit shall not be less than five times the plate size and the depth shall
be as specified. All provisions regarding excavation and visual examination of pit under
clause 6.6.1 and 6.6.2 shall apply here also.
6.10.3 If the ground water table is at a depth higher than the specified test depth, the
ground water table shall be lowered and maintained at the test depth for the entire
duration of the test. Dewatering shall be at the cost of the contractor.
6.10.4 Unless otherwise specified the reaction method of loading shall be adopted.
Settlement shall be recorded from dial gauges placed at four diametrically opposite ends
of the test plate. The test plate shall be of 600mm x 600mm size and atleast 25mm thick.
The bottom of the pit shall be levelled before placing the plate in position for conducting
the test.
6.10.5 A seating load of 7kN/sqm shall be applied and after the dial gauge readings are
stabilized, the load shall be released and the initial readings of the dial gauges be
recorded after they indicate constant reading. The load shall be increased in stages.
These stages shall be 20, 40, 70, 100, 150, 200, 250, 300, 400, 500, 600 and 800kN per
sqm or as directed by the engineer-in-charge. Under each loading stage, record of ‘time
vs settlement’ shall be kept as specified in IS:1888.
6.10.6 In case of cohesive soils, each load increment shall be maintained until the
settlement is less than 0.02mm/minute or 6 hours whichever is later. Dial gauge readings
for settlement shall generally be taken at 1, 2.25, 4, 6.25, 9, 16, 25, 60, 90 and 120
minutes from the start of each stage of loading. Thereafter the readings shall be taken at
hourly interval upto a further 4 hours and at two hours interval thereafter for another 6
hours.
6.10.7 Other than cohesive soils ( for all other type of soils), each stage loading shall be
maintained for a minimum duration of one hour or till the settlement rate reduces to
0.02mm/minute whichever is later. No extrapolation of settlement rate from periods less
than one hour shall be permitted. The final loading shall be maintained for 24 hours.
During unloading, reading of dial gauge shall be recorded for each stage of unloading.
6.10.8 Loading shall be carried out in stages as specified above till one of the following
conditions occur.
a) Failure of soil under the plate i.e. the settlement of the plate at constant load becomes
progressive and reaches a value of 40 mm or more.
b) Load intensity of 800 kN/sqm is reached without failure of the soil.
6.10.9 Backfilling of the pit shall be carried out as per the directions of the engineer-in-
charge. Unless otherwise specified the excavated soil shall be used for this purpose.
6.11 Cyclic Plate Load Test
This test shall be carried out to determine the dynamic soil properties required for the
analysis of foundation subjected to dynamic loads. This test shall be conducted on similar
lines as the ordinary plate load test with an addition that unloading shall also be done
before each stage of loading. Test set up, load increment and maximum load intensity etc
shall be as per Clause- 6.10.
6.11.1 After each stage of loading, the load shall be removed in a minimum of two stages
and as directed by the engineer-in-charge. After each stage of reduction of load, dial
gauge readings and settlements shall be taken for atleast one hour until the readings
stabilize. Thereafter the next loading stage shall commence. Recording and analysis of
test data shall be as per IS: 5249.
6.12 Field California Bearing Ratio Test
This test shall be carried out to obtain the properties of soil required for the design of
roads. The equipments and accessories required for carrying out the test, test procedure,
recording of observations and presentation of results shall conform to IS: 2720 part XXXI.
The test locations and depth shall be as specified in the drawings or as directed by the
engineer-in-charge.
6.13 Electrical Resistivity Test
This test shall be conducted to determine the electrical resistivity of soil required for
designing safety grounding system for the entire power plant area. The specification for
the equipments and other accessories required for performing the test, test procedure
and reporting of field observations shall conform to IS:3043. The test shall be conducted
using Wenner's four electrode method as specified in IS:1892, Appendix-B2. Unless
otherwise specified, at each test location the test shall be conducted along two
perpendicular lines parallel to the co-ordinate axes. On each line, the spacing of
electrodes shall be kept at 1m, 2m, 5m and 10m. Testing shall be done during the driest
season prevalent in the area to the extent possible. In no circumstances shall the testing
be done during or immediately after the rainy season or persistent rains or in the vicinity
of any existing water body such as ponds, streams etc.
6.14 Seismic Refraction Test
6.14.1 This test shall be carried out to establish the rock and soil profiles of varying
density. The dynamic shear modulus of the soil shall also be obtained from the results of
this test. The specification for the equipments and other accessories, procedure for
carrying out the test, recording and analysis of results and their presentation shall conform
to IS: 1892.
6.14. 2 This test shall be carried out by inducing shock waves into the soil by striking a
plate placed on the ground surface with a hammer. The shock waves shall be picked up
through geophones placed on the ground surface at regular intervals in line with the plate
along a straight line. The time elapsed before the waves reach the geophones shall be
recorded to an accuracy of one millisecond or better.
6.14.3 The distance between the shock point and the geophones shall be increased to
cover a wider area. Alternatively, multiple geophones shall be used simultaneously using
multiple channel seismograph to record the arrival time and intensity of waves reaching
the geophones. The spacing of geophones shall be 5m. As the distance between
geophones and the shock producing point are increased, the time lapse for the waves
passing through different underlying strata and reaching the geophone shall be recorded.
The wave forms shall be recorded for each test using multiple channel seismograph.
6.14.4 The test shall be conducted along traverses in two orthogonal directions as
specified in the drawing or as directed by the engineer in- charge. During testing, proper
care shall be taken to avoid disturbance caused due to the movement of vehicles or other
working operations around the test location. The type of wave (compression or shear)
shall be analysed properly using the data recorded during the test.
6.15 Cross Hole Shear Test
This test shall be generally carried out in accordance with IS: 13372 to establish the
dynamic elastic properties of soil and rock. In this test, the seismic waves are to be picked
up in two adjacent receiver boreholes. The spacing of boreholes shall be determined so
as to obtain good results. The boreholes shall be uncased in the portion carrying the
geophones. However it should be kept filled with water or drilling mud in order to ensure
perfect contact between the borehole wall and the geophone. In case of cased hole
preferably a low velocity material such as a high impact PVC should be used for casing
and it is essential that it should be well grouted behind in order to make an intimate contact
with the soil. The charge shall be installed within the depth as specified and the waves
shall be picked up from the geophones installed at required depths in receiver boreholes.
Knowing the travel time from shot hole to receiver hole and corresponding distance, the
velocity of the waves is determined which enables to estimate dynamic elastic modulus,
shear modulus and Poisson’s ratio. In each receiver borehole multiple geophones shall
be provided at 2m interval (with starting depth as 3m below ground level) to cover the
depth and various strata as specified. Intensity of the waves shall be recorded by multiple
channel seismograph.
6.16 Pressuremeter Test
6.16.1 This test shall be conducted in bore holes at desired depth to obtain the in-situ
stress-strain characteristics and strength parameters of soil/rock layer by measuring the
deformation of the probe at different pressures of the volumemeter. The location and
depth of the test shall be as given in the drawing or as per the directions of the engineer-
in-charge.
6.16.2 All precautions shall be taken to ensure a smooth bore hole of required diameter
with minimum disturbance to the surrounding soil. In soft, loose and sensitive soils, the
bore hole shall be predrilled deeper than the testing depth for enough so that the cuttings
settling at the bottom of the bore hole shall not interfere with the test.
6.16.3 The equipment shall be calibrated for pressure losses (membrane correction/air
calibration) and volume or radius changes (line calibration/thick wall rigid steel cylinder
test) before starting of test and at regular intervals as per the manufacturer’s specification.
6.16.4 Maximum value of pressure correction shall not be more than 50% of limit
pressure. The total volume loses in the system shall not exceed 0.5% of the static probe
volume per 100kPa. Volume correction may he neglected in soil if it is less than 0.1% of
probe volume per 100 kPa.
6.16.5 The test shall be performed by expanding a cylindrical probe to obtain a pressure
vs volume or pressure vs radius curve as specified in IS:1892. The probe may be of Ax,
Bx or Nx size. However the size of the borehole shall be compatible to the size of
pressuremeter probe. Hose pipe connecting the probe with the surface unit shall be of
flexible tubing of single or coaxial type. The equipment should be able to reach a
maximum pressure of 5000kPa for testing in soil and 8000kPa for testing in rock. The
accuracy of measuring device shall be such that a change of 0.2% of static probe volume
or 0.1% of probe radius is measurable as specified in IS:1892.
6.16.6 The probe shall be lowered down to the required depth as soon as the boring is
completed so as to limit the expansion of soil due to release of stresses. The probe shall
be held by a clamping device ensuring that it is not located at the interface of two different
soil/rock layers.
6.16.7 The pressure shall be increased in atleast 20 equal stages as directed by the
engineer-in-charge. At each stage the pressure shall be
maintained for a period of atleast 60 seconds and volume reading shall be taken for 7 to
14 minutes. The volume of water sent into the probe during this period shall be measured
upto an accuracy of 0.01cum. In case the water level in the volumemeter drops rapidly, it
is necessary to close the volumemeter valve quickly so that the reservoir does not empty
and allow air or gas into the tubing.
6.16.8 The test shall be carried out in stages till one of the following conditions occur.
a) The volume of the probe is doubled
b) Ultimate failure of soil/rock occurs
c) Load intensity of 5000kPa for soil and 8000kPa for rock is reached without failure.
6.16.9 If the shape of uncorrected pressure vs volume curve drastically varies from the
ideal test curve, the test shall be repeated at no extra cost to the owner/MPPGCL at a
different depth as decided by the engineer-in-charge.
6.16.9 On completion of the test, all results mentioned in Clause- 9.2 shall be reported.
7.0 FIELD INVESTIGATION - ROCK
7.1 Rock Drilling
Drilling in rock shall be done at specified locations or as per the directions of the engineer-
in-charge. Before commencing drilling, it shall be proved that characteristics of rock has
been met with as mentioned in clause 6.1.1(b). The starting depth of drilling in rock as
mentioned in clause 6.1.1(b) shall be certified by the engineer-incharge. The portion
drilled in rock shall be backfilled with 1part of cement : 3 part of sand (1:3) grout unless
otherwise specified and as directed by the engineer-in-charge.
7.1.1 Equipment
a) Core drilling shall be done by rotary motion using diamond bit. The feed or thrust to the
drilling bit shall be actuated by hydraulic system. The rotary core drilling equipment and
procedure for drilling shall conform to IS: 6926. The equipment shall be provided with
necessary facilities to regulate the spindle speed, bit pressure and water pressure during
core drilling to get a good core recovery.
b) Drilling shall be carried out with Nx size diamond tipped drill bits or impregnated
diamond bits depending on the type of rock encountered. Double tube swivel core barrel
of Type B conforming to IS: 6926 shall be used to ensure a good core recovery and to
pick up cores from all layers of rock. Suitable core catchers shall be used to ensure
continuous and good core recovery.
7.1.2 Procedure
a) The drilling fluid shall be clean water. Circulation of drilling fluid shall be started before
the core barrel reaches the bottom of the hole to prevent cuttings or sludge from entering
the core barrel at the start of coring. Drilling fluid shall be circulated continuously down
the hollow rods and the sludge conveying the rock cuttings to the surface shall be
collected.
b) When drilling through soft/weathered/fractured rock, water circulation must be reduced
so as to avoid shattering/breaking of core.
c) The rotational speed of the bit (spindle speed), the amount of downward pressure
applied on the bit (bit pressure) and water pressure shall be suitably adjusted and properly
monitored so that the core is collected with least disturbance and to avoid shearing of the
core from its base. Bit speed, bit pressure, water pressure for the type of bit for various
rock types shall be as per Appendix A of IS:6926.
d) No drill run shall exceed 0.75m in length. This can be increased to 1.5m provided the
core recovery observed is more than 80% in two successive 0.75m drill runs and on
approval from the engineer-incharge. If the core recovery is less than 20% then SPT shall
be performed before commencing the next drill run as explained in Clause- 6.2.
e) If at any time blocking of the bit or grinding of the core is observed, the core barrel shall
be immediately withdrawn from the borehole regardless of the length of drill run
completed.
7.1.3 Observations
a) The colour of return water at regular intervals, the depth at which any change of colour
of return water is observed, the depth of occurrence and amount of flow of hot water if
encountered shall be recorded.
b) The depths through which a uniform rate of penetration was maintained, the depth at
which a marked change in rate of penetration or sudden fall of drill rod occurs, the depth
at which any blockage of drill bit causing core loss if any etc shall be recorded.
c) Any heavy vibration or torque noticed during drilling should be recorded together with
the depth of occurrence.
d) Special conditions like the depth at which grouting was done during drilling, presence
of artesian conditions, loss of drilling fluid, observation of gas discharge with return water
etc shall also be observed and recorded.
e) During drilling operation, observation on return water, rate of penetration etc shall be
recorded in a proforma as given in IS: 5313, Appendix-A.
7.1.4 Core Samples
a) Core samples shall be extracted by the application of a continuous pressure at one
end of the core with the barrel held horizontally without vibration. Friable cores shall be
extracted from the barrel directly into a suitable sized half round plastic channel section.
Care shall be taken to maintain the direction of extrusion of sample same as that while
coring to avoid stress reversal.
b) Immediately after withdrawal from the core barrel, the cores shall be placed in a tray
and transferred into boxes specially prepared for the purpose. The boxes shall be made
from seasoned timber or any other durable material and shall be indexed on top of the lid
as per IS:4078. The cores shall be numbered serially and arranged in the boxes in a
sequential order. The description of the core samples shall be recorded as per IS: 4464.
Where no core is recovered, it shall be recorded as specified in the continuous record of
core recovery and RQD in the corelog as per IS:11315, Part-II.
c) The basic information for the description of rocks shall cover i) degree of weathering ii)
discontinuity spacing iii) strength iv) colour v) grain size vi) structural condition, the
mineralogy of the grains and cementing material vii) rock name, special features like
major joint planes, features/laminations, faults etc.
7.2 Standard Penetration Test
The relevant hardness of rocks shall be tested in boreholes after every drill run of 0.75m
in rock if core recovery observed is less than 20% or as directed by the engineer-in-
charge. The testing equipment and arrangement shall be conforming to IS: 2131. The
number of blows for each 75mm penetration to a total penetration of 450mm shall be
recorded. Penetration for every 50 blows shall be recorded and the test shall be stopped
at a total of 100 blows.
7.3 Plate Load Test
The test shall be conducted as described under Clause- 6.10 for soil subject to the
following changes.
The test plate shall be of size 45cm x 45cm and at least 25mm thick. The maximum load
shall be 1500 kN/sqm to be applied in stages of 25, 50, 100,150,200, 300, 400, 600, 800,
1000, 1200, 1400 and 1500 kN per sqm. Under each load the time Vs settlement shall be
recorded and plotted.
7.4 Pressuremeter Test
This test shall be conducted as described under Clause- 6.16 for soil subject to the
following changes. The test shall be carried out till one of the following condition occurs.
a) The volume of the probe is doubled
b) Ultimate failure of rock
c) Load intensity of 8000 kN/sqm is reached without failure.
7.5 Cross Hole Shear Test
This test shall be conducted as described under Clause- 6.15 for soil.
DENS PARTICLE
STRENGT SWE
ITY CONSOLIDATI
H L COMPACTI
SIZE (%
ATTERBERG' ON TEST
(kN/C SOIL TEST
S LIMITS TEST TEST
um
WATER CONTENT (%)
PERMEABILITY (m/hr)
BORE HOLE/ TRIAL PIT
IS CLASSIFICATION
RELATIVE DENSITY
SPECIFIC GRAVITY
TYPE OF SAMPLE
DESCRIPTION
DEPTH (m)
REMARKS
GRAVEL
SAND
BULK
CLAY
TYPE
OMC
MDD
SILT
CBR
DRY
S.Pr
FSI
mv
PL
SL
Cc
Cv
Pc
LL
eo
Pi
Φ
C
p
For type of sample For others tests
DEPTH
MOISTURE CONTENT
SPECIFIC GRAVITY
HARDNESS
POROSITY
DRY DENSITY
SLAKE DURABILITY
POINT LOAD
STRENGTH INDEX
DEFORMABILITY
(DRY /SATURATED)
UNCONFINEDCOMPRESSIVE
STRENGTH ( INSITU/SATURATED)
CORE DESCRIPTION
REMARKS
.
ANNEXURE-C
MINIMUM STAFF TO BE DEPLOYED
S.No. Description No. of persons
1 Geotechnical Engineer
2 Engineering Geologist
3 Supervisor
4 Qualified Surveyor
5 Rig Operators
6 Mechanic
ANNEXURE-D
LIST OF EQUIPMENTS TO BE MOBILISED TO SITE (MINIMUM)
(Hydraulic feed)
Note:
Additional equipments shall be mobilized if required as per the directions of the engineer-
in-charge to match the work schedule.
AE P&W