Rate Analysis

The document provides a detailed analysis of rates for various construction materials and labor costs, emphasizing that rates vary by location. It outlines the components of rate analysis, including material costs, labor costs, transportation, and contractor's profit. Additionally, it includes examples of calculations for required materials and total costs for different types of work, such as cement concrete and excavation.

Uploaded by

ruwan81.cv
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views31 pages

Rate Analysis

The document provides a detailed analysis of rates for various construction materials and labor costs, emphasizing that rates vary by location. It outlines the components of rate analysis, including material costs, labor costs, transportation, and contractor's profit. Additionally, it includes examples of calculations for required materials and total costs for different types of work, such as cement concrete and excavation.

Uploaded by

ruwan81.cv
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 31

ANALYSIS OF RATES

• To determine the rate of a particular item


of work from a quantities of materials and
labours required and their costs
• The rates of materials and labour are
changing from place to place, therefore the
rates o different items of work also
changes from place to place
ANALYSIS OF RATES
• Every Estimate should be accompanied
by the analysis of rates of the items
provided in it .
• Analysis of rates comprises of
1. Cost of Material
2. Cost of Labour
3. T and P , and Sundries
4. Carriage
5. Contractor’s Profit
ANALYSIS OF RATES
• Tools and Plants ( T & P ) = 2.5 to 3 % of
the labour cost
• Transportation cost more than 8 km is
considered
• Water charges = 1.5 to 2 % 0f total cost
• Contractor ‘ s profit = 10 %
ANALYSIS OF RATES
• Rates of Materials and Labours :
• 1st class bricks = Rs 4500 per 1000 Nos.
• 2nd class bricks = Rs 4000 per 1000 Nos.
• Brick Ballast = Rs 800 per cum
• Coarse sand = Rs 800 per cum
• Cement 50 kg bag = Rs 270 per bag
• Twisted bars = Rs 5000 per Quintel
• Bitumen = Rs 10 per kg
ANALYSIS OF RATES
• Mason = Rs 450 per day
• Plaster = Rs 400 per day
• Carpenter = Rs 400 per day
• Bhishti = Rs 250 per day
• Mazdoor = Rs 250 per day
• Painter = Rs 300 per day
ANALYSIS OF RATES
• Earth work in excavation: Mazdoor = 33
(% cum) Mason = 1.5
• Earth work in Filling : Mazdoor = 18
(% cum) Mason = 0.5
• Cement concrete : Mazdoor = 15
in foundation Mason =1.5
Bhishti = 2
ANALYSIS OF RATES
• Cement concrete : Mazdoor = 15
Mason = 1
Bhishti = 2.5
• R. Cement concrete : Mazdoor = 40
(10 cum ) Mason = 2.5
Bhishti = 5
Blacksmith = 4
Carpenter = 4
ANALYSIS OF RATES

• DPC : Mazdoor = 2.5


(10 cum ) Mason = 1.5
Bhishti = 0.5
• 1st class brick work : Mazdoor = 15
Mason = 8
Bhishti = 2
ANALYSIS OF RATES

• Plastering work : Mazdoor = 10


( 100 sqm) Mason = 10
Bhishti = 2
• Distempering/painting/white washing :
Mazdoor = 5
( 100 sqm) Painter = 4
ANALYSIS OF RATES

Example 1. Find out dry materials required


for 1 cu m. C. concrete 1:4:8 in foundation.

Solution.
Ratio = 1:4:8 (cement,sand and aggregate)

Sum = 1+4+8=13
cont..
Total dry mortar for 1 cu m cement concrete
=1.54 cu m
Therefore the following materials are
required:

Cement = (1*1.54*28.8)/13
= 3.41 bags

Sand = (4*1.54)/13
= 0.47 cu m
cont..
Aggregate (Brick ballast) = (8*1.57)/13
= 0.94 cu m
so materials for 1 cu m cement concrete
1:4:8.

Cement 3.41 bags

Sand 0.47 cu m Ans.

Brick ballast 0.94 cu m


Example 2. Find out dry materials for 1
cu m lime concrete.

Solution:
Ratio = 1:2 (lime,surkhi)

Sum = 1+2
=3
Total dry mortar for 1 cu m lime concrete
= 0.40 (lime, surkhi mortar)
Therefore the following materials are
required.

Lime = (1*0.40)/3
= 0.13 cu m

Surkhi = (2*0.40)/3
= 0.27 cu m

Aggregate (brick ballast) = 1.00 cu m


Materials required for1 cu m lime cocrete 1:2

Lime 0.13 cu m

Surkhi 0.27 cu m Ans.

Brick ballast 1.00 cu m


ANALYSIS OF RATES OF
DIFFERENT ITEMS OF
WORK.
1. Excavation for foundation: payment
% cu m
(a)Materials at the site for % cu m nil
No material is required Rs. P.

(b)labour for % cu m
Mazdoor 33 nos.@ 250.00/day = 8250.00
Mason 1 no. @ 450.00 = 450.00
Sundries and Tand P 3%
on labour = 261.00
Total = 8961.00
(c)Add 10% contractor’s profit = 896.10
grand total =9857.10
say Rs. = 9857.00

Rate per % cu m = Rs. 9857.00


2.Earth filling under floors payment % cu m
(a)Materials at site for %cu m Rs.P.
No material is required nil
(b) Labour for % cu m
[email protected]/day =4500.00
Bhishti 1/[email protected]/day = 125.00
Sundries and Tand P3% on
labour 465.00 = 123.75
total = 4748.75
Add 10% contractor’s profit = 474.87
G.Total= 5223.62 say Rs.=5224.00
Rate per % cu m = Rs. 5224.00
3. Cement concrete 1:4:8 in foundations
(a) Materials at site for 1 cu m payment
per cu m
Cement 3.41 bags @270 bag = 929.70
Sand 0.47 cu m @800.00 per cu m=376.00
Brick ballast 0.94 cu m @ 800.00
= 752.00
Cost of labour for 10 cu m = 7520.00
(b)Labour for 10 cu m Rs. P
Mason 1@ 400.00/ day = 400.00
Mazdoors 15@ 250.00/ day = 3750.00
Bhishti 2@ 250.oo/ day = 500.00
Sundries and Tand P @ 3%
on labour = 139.50
• Cost of for 10 cu m = 12309.50
• Cost of for 1 cu m =12309.50/10
• =1230.95
• PROBLEM: Conglomerate floor 4 cm thick
of cement concrete 1:2:4 over 10 cm thick
cement concrete 1:6:18 over 10 cm sand
filling.
calculation of material for 10 sq m
(1) Wet mortar for cement concrete
1:2:4= 10 sq m*4cm
= 10*4/100
=0.40cu m
Dry mortar = 0.40*1.54=0.616+0.62 cu m

Ratio = 1:2:4 Sum =1+2+4=7

Cement = 1*0.62*28.8/7 =2.55 bags

Sand = 2*0.62/7 = 0.18 cu m


Crusher = 4*0.62/7=0.36 cu m

(2)Wet mortar for cement concrete 1:6:18

= 10 sq m*10 cm

=10*10/100

=1 cu m
Dry mortar 1*1.54 =1.54cu m

Ratio =1:6:18=1+6+18
= 25

Cement = 1*1.54*28.8/25
= 1.78 bags
Sand =6*1.54/25
= 0.37 cu m

Brick ballast = 18*1.54/2


= 1.11 cu m

(3) Sand for 10 sq m = 10 sq m* 10 cm


= 10*10/10
= 1 cu m

Total dry mortar for 10 sq m conglomerate


flooring.

Cement = 2.55+1.78

Sand = 0.18+0.37+1.00

Crusher = 0.46
(a) Materials at site for 10 sq m Rs.P

Cement 4.33 bags @ 270.00/bag = 1170.00

sand 1.55 cum@ 800.00 per cu m = 1240.00

Crusher 0.36 cu m @1200 /cu m = 432.00

Brick ballast 1.11 cu m@ 800 / cu m = 888.00


Cost of material for 10 sq m =3730.00

(b) Labour for 10 sq m Rs. P

Mason 2@ 400.00/ day = 900.00

Mazdoor 3@ 250.00/day = 750.00

Bhishti 1@ 250.00 / day = 250.00


Sundries T and P 3% on labour
= 57.00

Cost of labour for 10 sq m = 1957.00

Cost of material and labour for 10 sq m

=5687.00
Add 10% contractor’s profit =
568.70
and total = 6255.70
Rate for 10 sq m = Rs.6256.00

Rate per sq m = Rs.625.60