0% found this document useful (0 votes)
19 views

Billing - SOP

The document outlines the billing process for construction projects, detailing the steps from receipt of the Bill of Quantities (BOQ) and drawings to invoicing and payment governance. It covers various project types, including lump sum and item rate contracts, and includes procedures for variation preparation, ordering, and vendor billing. Additionally, it highlights roles and responsibilities of different teams involved in the billing process to ensure accuracy and compliance.

Uploaded by

rishika.jolly
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
19 views

Billing - SOP

The document outlines the billing process for construction projects, detailing the steps from receipt of the Bill of Quantities (BOQ) and drawings to invoicing and payment governance. It covers various project types, including lump sum and item rate contracts, and includes procedures for variation preparation, ordering, and vendor billing. Additionally, it highlights roles and responsibilities of different teams involved in the billing process to ensure accuracy and compliance.

Uploaded by

rishika.jolly
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 12

Billing Process

Section 1: Receipt of BOQ and Drawings

1.1 Receipt of BOQ

● The BOQ (Bill of Quantities) is shared by the Business Development (BD), Finance, or Design
team.

● The format is typically an Excel sheet.

● It is shared with the Billing team via email for reference and initial documentation.

1.2 Receipt of Drawings

● The Design team submits AutoCAD drawings through a shared drive/email.

● These drawings are the base documents for quantity surveying and further billing processes.

● The Design team is accountable for the upkeep and version control of all project-related drawings
without exception. Any superseded drawings must be clearly marked, and revised versions should
be issued promptly to avoid discrepancies.
● To enhance coordination and traceability, a project management tool should be adopted to log
revisions, track updates, and highlight major design changes effectively.

Section 2: Variation Preparation Process

Managed by the Planning Department

2.1 Quantity Surveying

● Detailed measurements are extracted from CAD drawings.

● A Measurement Book (MB) is prepared with complete item-wise quantity take-off.

2.2 Time Estimation for Quantity Take-off


● Once drawings are reviewed and deemed final:

○ The Civil & Interior (C&I) team takes 3 working days.

○ The Mechanical, Electrical, and Plumbing (MEP) team takes 3 working days.

● Both teams work simultaneously to complete the task within the same timeframe.

2.3 Variation Extraction

● Any difference between BOQ quantities and actual measured quantities is recorded as variation.

● Variations are tagged as additions or deletions.

● These are documented and supported by MB and drawing snapshots for client discussion.

2.4 Updating the BOQ

● Actual site quantities are inserted against each BOQ item.

● The revised BOQ reflects the impact of variations, used for re-billing and scope adjustments.

Section 3: Bill of Material (BOM) Preparation


● Identify the raw materials for every line item.
● Set the multiplier/ coefficients for every raw material based on design, wastage etc.
● Extract the order quantities & share with procurement.

Section 4: Ordering Process

4.1 Indent Generation by Site Team

● The site execution team raises a material indent using a pre-defined template.
● The indent includes:

○ BOQ reference item

○ Required quantity

○ Justification or site remarks

4.2 Quantity Verification by QS Team

● QS (Quantity Surveying) team verifies the indent for accuracy.

● Suggestions or corrections (if any) are added to maintain consistency with MB.

● Approved indent is submitted to Procurement.

4.3 Procurement Process

● The procurement team places orders based on approved quantities.

● Purchase Order (PO) is generated and shared with vendors.

● PO is cross-verified against the indent to avoid mismatch.

4.4 Material Receipt at Site

● Site acknowledges receipt of material with GRN (Goods Receipt Note).

● Material is checked for quantity and quality upon delivery.

Section 5: Billing Process – Project Type Based

5.1 Lump Sum Projects

5.1.1 Characteristics

● The total billing value is pre-defined in the Work Order or Agreement.

● Payments are linked to pre-approved milestones.


5.1.2 Invoicing Steps

● Project Manager (PM) monitors milestone completion.

● PM raises Performa Invoice (PI) upon achieving a milestone.

● Client approves the PI, post which:

○ PM coordinates with Accounts Receivable (AR) team to generate Tax Invoice.

○ Tax Invoice is submitted to the client via email, portal or hard copy.

5.1.3 Additional Work or Variation

● Any deviation from the freezed layout & 3D at the time of commercial closure, will be
considered as additional work.
● Any excess work or quantity is evaluated and documented as a variation.
● The billing team adds cost implications to the original value.
● Rate analysis of such items shall be prepared along with at least three vendor quotations for
client approval.
● Procurement & execution of such items will only be incorporated once approved from the client.

5.2 Item Rate Contract Projects

5.2.1 Characteristics

● Billing is done as per actual executed quantity at site.

● Payments are made based on certified measurements.

5.2.2 Measurement & Billing Cycle

● Billing personnel visit the site on a scheduled frequency (weekly/bi-weekly).

● Measurements are recorded in the Measurement Book and signed off by PMC/Client.

● Bill is prepared based on measured quantities and applicable item rates.

5.2.3 Invoicing Steps

● The prepared bill is reviewed and approved by the internal senior authority.

● Once approved, Tax Invoice is raised and submitted to the client.


● The billing person follows up with the client for timely payment.

Section 6: Additional Addendum / Non Tendered Items / Extra Work Items

● Additional Addendum

A formal document issued post-tender to modify, clarify, or add to the original scope, specifications, or
contract terms.

● Non-Tendered Items

Items or works not originally included in the BOQ or tender documents but required during execution.

● Extra Work Items

Tasks or materials that arise during execution due to site conditions or client instructions, beyond the
agreed scope and requiring separate approval and costing.

6.1 Identification & Documentation

● Non-BOQ/Extra items (NT Items) are identified by PM or Billing personnel.

● Shared with Billing team with:

○ Description

○ Measured quantity

○ Rate analysis along with technical specs

6.2 Rate Analysis Process

● Billing team coordinates with Procurement team to obtain vendor quotations.

● Billing team prepares Rate Analysis Sheet.

● Rate is submitted to Client/PMC for approval.


● Check profit margin as per tender/ contract (i.e 15% or 20% etc)
6.3 Procurement Initiation

● Upon client approval of rate, PM/site team raises an indent.

● The procurement process follows as per standard procedure.

Section 7: Billing Reconciliation

7.1 Purpose & Scope

● Reconciliation ensures alignment between:

○ BOQ quantities v/s Measured quantities v/s Procured quantities

7.2 Process

● Conducted by the Billing/Planning team in parallel with project execution.

● Every line item is compared and verified.

● Variations in procurement vs. measured quantity are flagged if deviation is found.

7.3 Outcomes

● Identifies wastage, pilferage, and excess consumption.

● Financial implications such as loss/profit are reported.

● Final reconciliation submitted during project closure.

Section 8: Vendor Billing Process (Common to All Projects)

8.1 Bill Submission

● Vendors submit invoices through email or physical copy.


● Format must include:

○ PO reference

○ Item description as per PO

○ Quantity supplied/ installed or executed against each line item of PO

○ Tax breakup

8.2 Vendor bills categories:

1. Running Account (RA) Bill

● Raised during the project’s execution phase.

● Reflects ongoing work progress.

● The Project Manager or Billing Manager is responsible for verifying progress and validating
the RA Bill.

● Once verified, the vendor collects the signed copy from the Billing Manager.

● The signed RA bill is then submitted by the vendor to the Head Office for further processing.

2. Final Bill

● Raised post project virtual handover.

● Represents the final billing for the entire scope of work completed.

● Verified and approved by the Billing Manager.

● Vendor collects the signed final bill from the Billing Manager.

● The final bill is submitted to the Head Office by the vendor for final closure.

7.3 Verification

● Billing team checks bill against:

○ Purchase Order

○ Delivery notes/GRN
○ Site confirmation

7.4 Approval and Processing

● Bills are approved internally.

● GM – Quality and Planning are kept in the loop for material verification and certification.

● Verified bills are sent to the Accounts Department for payment release subjected to clearance
from the client on quality parameters.

Section 8: Contract and Payment Governance

8.1 Contract and Payment Terms

● Clear contracts define scope, milestones, and payment terms (progress/final).

8.2 Progress Billing

● Payments tied to deliverables or completed work %.

8.3 Change Orders and Variations

● Scope changes documented via Change Orders.


● Impact on cost/timeline recorded.

8.4 Invoices

● Detailed, covering labor, materials, additional charges.

8.5 Payment Certification

● 3rd party/Consultant/PMC may certify progress for payments.

8.6 Final Account

● Prepared post-completion.
● Adjusts outstanding dues and variations.

8.7 Cost Control & Monitoring

● Ongoing tracking to control budget.

8.8 Dispute Resolution

● Standard mechanism in place for resolving billing disputes.

8.9 Invoice Management


● Efficient tracking, approval, and processing.

Section 9: Common Billing Methodologies


● Lump Sum Billing: Fixed contract value, paid by milestone.
● Time and Material: Billed based on actual labor hours and material cost.
● Cost Plus Percentage: Reimbursement of cost + agreed profit %.
● Guaranteed Maximum Price: Contractor guarantees not to exceed agreed price.
● Unit Price: Payment per defined units (e.g., sq.ft.).
● Retainer Billing: Initial retainer + periodic billing for ongoing work.

Roles & Responsibilities Overview

Role Key Responsibilities

Project Manager Raise invoice upon milestone completion; Share anti-items; Follow up for
(PM) payments.

Billing Team Prepare bills, rate analysis, reconciliation, invoice generation, client
submission.

QS Team Verify quantity from drawings/indents, validate MB, update BOQ.

Procurement Team Procure approved material, provide quotations, raise PO.

Design Team Share CAD drawings, resolve drawing-related queries.

Accounts Team Generate Tax Invoice, process vendor/client payments.

You might also like