Billing - SOP
Billing - SOP
● The BOQ (Bill of Quantities) is shared by the Business Development (BD), Finance, or Design
team.
● It is shared with the Billing team via email for reference and initial documentation.
● These drawings are the base documents for quantity surveying and further billing processes.
● The Design team is accountable for the upkeep and version control of all project-related drawings
without exception. Any superseded drawings must be clearly marked, and revised versions should
be issued promptly to avoid discrepancies.
● To enhance coordination and traceability, a project management tool should be adopted to log
revisions, track updates, and highlight major design changes effectively.
○ The Mechanical, Electrical, and Plumbing (MEP) team takes 3 working days.
● Both teams work simultaneously to complete the task within the same timeframe.
● Any difference between BOQ quantities and actual measured quantities is recorded as variation.
● These are documented and supported by MB and drawing snapshots for client discussion.
● The revised BOQ reflects the impact of variations, used for re-billing and scope adjustments.
● The site execution team raises a material indent using a pre-defined template.
● The indent includes:
○ Required quantity
● Suggestions or corrections (if any) are added to maintain consistency with MB.
5.1.1 Characteristics
○ Tax Invoice is submitted to the client via email, portal or hard copy.
● Any deviation from the freezed layout & 3D at the time of commercial closure, will be
considered as additional work.
● Any excess work or quantity is evaluated and documented as a variation.
● The billing team adds cost implications to the original value.
● Rate analysis of such items shall be prepared along with at least three vendor quotations for
client approval.
● Procurement & execution of such items will only be incorporated once approved from the client.
5.2.1 Characteristics
● Measurements are recorded in the Measurement Book and signed off by PMC/Client.
● The prepared bill is reviewed and approved by the internal senior authority.
● Additional Addendum
A formal document issued post-tender to modify, clarify, or add to the original scope, specifications, or
contract terms.
● Non-Tendered Items
Items or works not originally included in the BOQ or tender documents but required during execution.
Tasks or materials that arise during execution due to site conditions or client instructions, beyond the
agreed scope and requiring separate approval and costing.
○ Description
○ Measured quantity
7.2 Process
7.3 Outcomes
○ PO reference
○ Tax breakup
● The Project Manager or Billing Manager is responsible for verifying progress and validating
the RA Bill.
● Once verified, the vendor collects the signed copy from the Billing Manager.
● The signed RA bill is then submitted by the vendor to the Head Office for further processing.
2. Final Bill
● Represents the final billing for the entire scope of work completed.
● Vendor collects the signed final bill from the Billing Manager.
● The final bill is submitted to the Head Office by the vendor for final closure.
7.3 Verification
○ Purchase Order
○ Delivery notes/GRN
○ Site confirmation
● GM – Quality and Planning are kept in the loop for material verification and certification.
● Verified bills are sent to the Accounts Department for payment release subjected to clearance
from the client on quality parameters.
8.4 Invoices
● Prepared post-completion.
● Adjusts outstanding dues and variations.
Project Manager Raise invoice upon milestone completion; Share anti-items; Follow up for
(PM) payments.
Billing Team Prepare bills, rate analysis, reconciliation, invoice generation, client
submission.