Shutdown Work Methodology
Shutdown Work Methodology
Coordinate with PED, Safety and OM thru Sir Allan Esperon for the
RELOCATION
2 After disconnection, an M-PRO personnel will pull the wiring up, removing
it from the FACP.
After removing the wiring from the FACP, place a resistor (c/o Ma'am
3 Lorraine) on the terminals where the wires are removed and splice the
removed wire to the prepared wire of M-PRO.
5 Only after the steps above will the next disconnection of wiring be
RELOCATION OF performed. Repeat steps 1-4
FACP AT BLDG. G
6 Cut the power supply of the FACP and splice the power supply to the
prepared wirinf of FACP Power Supply of M-PRO.
Check the status of the FCAP Panel if same as before activity, normal, or
7 with new trouble. If status has new troubles, coordinate with PED for next
steps.
8 If status is OK with PED, remove the plus from its outl.et and remove FACP
and transfer to its new location
9 After fixing thew FACP to its new location, terminate each removed wire at
its corresponding zone.
10 Terminate the power supply to the outlet of the FACP. Check its volatge
reading after. Plug the FACP if the voltage reading is acceptable.
trouble emerges.
M-PRO/PED PED
M-PRO/PED BLDG. G
OWNER : INTEGRATED MICROELECTRONICS INC.
PROJECT : INSTALLATION OF KILOWATTHOUR METER
LOCATION : MAIN SUBSTATION/ GENSET ROOM # 1
SUBJECT : TRACING & TERMINATION OF NEWLY INSTALLED KILOWATTHOUR METER SHUTDOWN METHODOLOGY
DATE : SEPTEMBER 15, 2022
SHUTDOWN SCHEDULE: TO BE DETRMINED
1 Check if there are other panels affected other than the predefined panels
cy
PREPARED BY:
RAMON ALISEN
PROJECT-IN CHARGE
MPRO INDUSTRIAL CONSTRUCTION CORP.
TDOWN METHODOLOGY
M-PRO Procject in
Charge
BEFORE
M-PRO SHUTDOWN
ACTIVITY
CDO Engineering (EMD)
M-PRO/CDO Engineering
M-PRO/CDO Engineering
Ground Floor Electrical Room, BLDG C
Plan
M-PRO/CDO Engineering Substation
Actual
Plan
M-PRO/CDO Engineering Substation
Actual
Plan
M-PRO/CDO Engineering Substation
Actual
Plan
M-PRO Substation
Actual
Plan
M-PRO Substation
Actual
Plan
M-PRO Substation
Actual
Plan
CDO Engineering Substation
Actual
Plan
M-PRO Substation
Actual
Plan
M-PRO Substation
Actual
Tentative Shutdown Schedule
8:30 8:40 8:50 9:00 9:10 9:20 9:30 9:40 9:50 10:00
11:00
OWNER: INTEGRATED MICROELECTRONICS INC.
PROJECT: PABLO FACILITATION PROJECT
LOCATION : LTI BIÑAN, LAGUNA
SUBJECT: SHUTDOWN TOOLS, EQUIPMENTS & MATERIALS
DATE: DECEMBER 25, 2020
Prepared by:
Ramon Alisen
Project-in Charge
MPRO Industrial Construction Corp