Shutdown Work Methodology

The document outlines the procedures for the relocation of a Fire Alarm Control Panel (FACP) and the installation of a kilowatt-hour meter at Integrated Microelectronics Inc. It details the necessary activities, methods of work, and shutdown schedules for both projects, emphasizing coordination with engineering teams and safety measures. Additionally, it lists the required tools, equipment, and materials needed for the shutdown operations.

Uploaded by

bmarclouise
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4 views9 pages

Shutdown Work Methodology

The document outlines the procedures for the relocation of a Fire Alarm Control Panel (FACP) and the installation of a kilowatt-hour meter at Integrated Microelectronics Inc. It details the necessary activities, methods of work, and shutdown schedules for both projects, emphasizing coordination with engineering teams and safety measures. Additionally, it lists the required tools, equipment, and materials needed for the shutdown operations.

Uploaded by

bmarclouise
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 9

OWNER : INTEGRATED MICROELECTRONICS INC.

PROJECT : ADDITIONAL WORKS FOR ISAHAYA RESTORATION


LOCATION :
SUBJECT : FACP RELOCATION
DATE : OCTOBER 10, 2024
SHUTDOWN SCHEDULE: OCTOBER 14, 2024

ACTIVITIES Item METHODS OF WORK


No.
BEFORE FACP

Coordinate with PED, Safety and OM thru Sir Allan Esperon for the
RELOCATION

1 silencing and start of activity of FACP Relocation.

2 Take picture of current FACP status and its terminations.

1 With a facilities representative beside, perform disconnection one


zone/bell supply.

2 After disconnection, an M-PRO personnel will pull the wiring up, removing
it from the FACP.

After removing the wiring from the FACP, place a resistor (c/o Ma'am
3 Lorraine) on the terminals where the wires are removed and splice the
removed wire to the prepared wire of M-PRO.

4 Afetr splicing, conduct continuity test at the new location of FACP to


ensure matching zone tagging.
DURING FACP RELOCATION

5 Only after the steps above will the next disconnection of wiring be
RELOCATION OF performed. Repeat steps 1-4
FACP AT BLDG. G

6 Cut the power supply of the FACP and splice the power supply to the
prepared wirinf of FACP Power Supply of M-PRO.

Check the status of the FCAP Panel if same as before activity, normal, or
7 with new trouble. If status has new troubles, coordinate with PED for next
steps.

8 If status is OK with PED, remove the plus from its outl.et and remove FACP
and transfer to its new location

9 After fixing thew FACP to its new location, terminate each removed wire at
its corresponding zone.

10 Terminate the power supply to the outlet of the FACP. Check its volatge
reading after. Plug the FACP if the voltage reading is acceptable.

1 Check the status of the FACP. Troubleshoot/coordinate with PED if new


AFTER FACP
RELCATION

trouble emerges.

2 If the status is OK, random check Bldg. G, if smoke detectors are


blinking/functioning.
PREPARED BY:
RAMON ALISEN
PROJECT-IN CHARGE
MPRO INDUSTRIAL CONSTRUCTION CORP.
RESPONSIBLE Location AREA

M-PRO/PED PED

M-PRO/PED ISAHAYA HALLWAY

M-PRO ISAHAYA HALLWAY

M-PRO ISAHAYA HALLWAY

M-PRO ISAHAYA HALLWAY


BLDG. G GROUND FLOOR AND SECOND FLOOR

M-PRO CORPORATE LOBBY

M-PRO ISAHAYA HALLWAY

M-PRO ISAHAYA HALLWAY

M-PRO/PED ISAHAYA HALLWAY

M-PRO ISAHAYA HALLWAY

M-PRO CORPORATE LOBBY

M-PRO CORPORATE LOBBY

M-PRO/PED CORPORATE LOBBY

M-PRO/PED BLDG. G
OWNER : INTEGRATED MICROELECTRONICS INC.
PROJECT : INSTALLATION OF KILOWATTHOUR METER
LOCATION : MAIN SUBSTATION/ GENSET ROOM # 1
SUBJECT : TRACING & TERMINATION OF NEWLY INSTALLED KILOWATTHOUR METER SHUTDOWN METHODOLOGY
DATE : SEPTEMBER 15, 2022
SHUTDOWN SCHEDULE: TO BE DETRMINED

ACTIVITIES Item METHODS OF WORK


No.
Checking of load of medium voltage switchgear to be Shutdown, located at
1 substation
Tracing existing
metering for
Pre-shutdown

incoming medium 2 Coordination to CDO Engineering


voltage to correct
the 15% 3 Prepare all the tools/materials needed
difference of
kilowatthour 4 Coordination -Go signal to proceed with the shutdown
reading of
BATELEC & CDO
5 Prior to shutdown of Lmedium Voltage Switchgear, check the existing for
data baseline
Emergen

1 Check if there are other panels affected other than the predefined panels
cy

1 Shutdown of Medium Voltage Switchgear Incoming Main VCB


During Shutdown of LVSG # 3 & LVSG # 4

2 Discharge stored voltage if any


Termination of
newly Install
kilowatthour 3 Provide Cluster Ground for protection of workers
meter for
medium Voltage
Incoming Tracing of existing metering connection. Correct the connection if any
4 mistake termination

5 Termination of newly installed Kilowatthour Meter to current transformer


& potential transformer

Visual checking of Medium Voltage Switchgear & cluster grounding


6 disconnection

6 Energization of Medium Voltage Switchgear Main VCB


Post shutdown

1 5S / Housekeeping at the area/ painting works of Pipes

2 Coordination:Go signal to BU for production use

PREPARED BY:
RAMON ALISEN
PROJECT-IN CHARGE
MPRO INDUSTRIAL CONSTRUCTION CORP.
TDOWN METHODOLOGY

RESPONSIBLE Location AREA 8:00 8:10 8:20

CDO Engineering (EMD)

M-PRO Procject in
Charge
BEFORE
M-PRO SHUTDOWN
ACTIVITY
CDO Engineering (EMD)

M-PRO/CDO Engineering

M-PRO/CDO Engineering
Ground Floor Electrical Room, BLDG C

Plan
M-PRO/CDO Engineering Substation
Actual
Plan
M-PRO/CDO Engineering Substation
Actual
Plan
M-PRO/CDO Engineering Substation
Actual
Plan
M-PRO Substation
Actual

Plan
M-PRO Substation
Actual

Plan
M-PRO Substation
Actual
Plan
CDO Engineering Substation
Actual
Plan
M-PRO Substation
Actual
Plan
M-PRO Substation
Actual
Tentative Shutdown Schedule

8:30 8:40 8:50 9:00 9:10 9:20 9:30 9:40 9:50 10:00
11:00
OWNER: INTEGRATED MICROELECTRONICS INC.
PROJECT: PABLO FACILITATION PROJECT
LOCATION : LTI BIÑAN, LAGUNA
SUBJECT: SHUTDOWN TOOLS, EQUIPMENTS & MATERIALS
DATE: DECEMBER 25, 2020

Declared Qty Actual Qty Unit


I Installation equipment
1 pliers 1 unit
2 screw drivers (philip) 1 pcs
3 screw drivers (flat) 1 pcs
4 Socket Wrench 1 set
5 Wrenches 1 set
II Testing equipment
1 insulator tester 1 unit
2 Multi Tester 1 unit
3 Phase Rotation Tester 1 unit
III Safety Paraphernalias
1 safety gloves 1 pcs
2 Face Shield 1 pairs
3 Eye Googles 1 pcs
4 Hard Hat 1 pcs
5 Caution Sign 2 set
6 Warning Tape 5 mtr

Prepared by:

Ramon Alisen
Project-in Charge
MPRO Industrial Construction Corp