0ZDK.466.181 ZHW-145 Manual V04 (EN)
0ZDK.466.181 ZHW-145 Manual V04 (EN)
Instructions Manual
Hybrid Compact Gas Insulated Switchgear
for Rated Voltage 72.5/126/145kV
0ZDK.466.181
Version:V04
familiar with this Instructions Manual and the structure and action principle of the switch. This Instructions Manual introduces the basic
parameters, structure and basic principle of the installation, commissioning and maintenance of the equipment. The Operator is
recommended to be familiar with this Instructions Manual and other materials furnished, in order to understand the characteristics of
the switchgear used. Please find the following Figure 1 to know the structure
1.Bushing 1 2. Current Transformer1 3.Fast Earthing Switch1 4.Three position DES3 5.Mechanism of Circuit
Breaker1 6. Steel Structure 7. Control Panel 8. Steel Structure Support 9. Mechanism of Fast Earthing Switch1
10.Circuit Breaker1 11.Mechanism of DS2 12.Mechanism of Three position DES3 13.Two position DS2 14. densimeter
15. Three position DES1 16. Mechanism of Three position DES1 17.Bushing2 18. Bushing1
4
Tips:
This Instructions Manual introduces installation and operation, maintenance instructions and warnings of switch. It indicates the
Pure sulfur hexafluoride gas (SF6) is colorless, odorless, tasteless, non-toxic and non combustible gas. When the inhaled air carries
sufficient oxygen, SF6 is harmless to human body. SF6 is a greenhouse gas, and direct emission of SF6 gas into the environment should be
avoided. SF6 gas is heavier than air. When large quantity of SF6 leaks, the air will be squeezed out, and the risk of suffocation is present
The staff must be fully familiar with the installation, operation, maintenance and repair procedures and relevant precautions
The Users of Product must be responsible for the safety rules prevailing in their respective countries and the instructions on
In addition to considering the safety rules and operating regulations prevailing in their respective countries, the following
Switch installation, operation and maintenance and accessories (Protective clothing, manual operation tools, warning signs,
distribution box, flashlight tools, fire extinguishers, etc.) required for general safety must be obviously placed and carefully kept at
designated places, and their completeness and good condition shall be checked regularly, including complete set of installation and
Instructions Manual.
The maintenance intervals and the provisions for repair and replacement as previously described should be followed.
Detailed warning instructions describing hazardous work are covered in relevant sections of the Instructions Manual, which
Tips
The meaning of "Tips" in this Manual refers to the following operation information related to the plan and improvement of
△
! Warning
"Warning" in this Manual means that death, serious injury or huge property loss and environmental damage can be caused
△
! Note
"Note" in this Manual means that minor injury or property loss and environmental damage will be caused if corresponding
5
2. Product Description
Hybrid Compact Gas Insulated Switchgear is a compact multi-functional hybrid gas insulated switchgear (HGIS). It is an advanced
hybrid SF6 HV switchgear integrating the advantages of open-type and closed-type switchgear. On the basis of GIS combined electrical
apparatus, the Circuit Breaker, isolating/earthing switch and CT are integrated into one module, and the bus with very low accident
probability is arranged in the way of conventional air insulated switch (AIS). Meanwhile, the disadvantages of large floor area, low
reliability and heavy maintenance workload of the original conventional AIS equipment are solved. It is suitable for power transmission,
transformation (distribution) systems of 145kV and below in power plants, substations, stations and wharfs, large industrial and mining
Equipment Advantages:
Flexible combination, high operation reliability, intuitive, and small maintenance workload.
Flexible installation method, and capable of installation outdoors, indoors and on the roof.
The workload of civil engineering and electrical installation is very small, and the installation is simple.
The consumption of SF6 gas is small (Only 20% of GIS consumption), which meets the requirements of environmental
protection.
Small volume and light weight (Aluminum alloy cylinder), so it has high pollution resistance, hydrophobicity and
earthquake resistance.
Due to short installation time and fewer power outages, it is suitable for new construction, expansion or transformation
Tips
Unless indicated as absolute pressure, all pressure values are the gauged values.
3. Environmental Conditions
Installation type: Outdoors/Indoors
Altitude: No more than 1000m (Altitude higher than 1000m can be discussed separately.)
Wind pressure (Not greater than 35m/s for wind speed): 700Pa
Air pollution index grade: Grade d or e (Or according to the actual needs of Users)
6
△
! Notes
If the above environmental conditions are exceeded, please specify it when ordering.
(1) When used in alpine areas (Where ambient temperature is lower than -20℃), measures shall be taken to prevent
4. Technical Parameters
Table 1 Rated Parameters of Circuit Breaker for Hybrid Compact Gas Insulated Switchgear
The Circuit Breaker shall meet the requirements of IEC62271-100 High-voltage Alternating-Current Circuit-Breakers. The Circuit
7
Breaker uses SF6 gas as the insulation and arc extinguishing medium, adopts the self-energy arc extinguishing principle, and is
equipped with CT30 spring operating mechanism, which features strong breaking capacity, small operating power and high reliability.
Parameter
Item
Isolation Switch Earthing Switch (Maintenance)
(Valid value)
Opening time s ≤4 ≤4
Closing time s ≤4 ≤4
Parameters
Item
Mechanical Linkage
Opening time s ≤6
8
Closing time s ≤6
Material - Porcelain/Composite
insulating medium. The Circuit Breaker adopts aluminum alloy tank structure and is of outdoor design. The three phases share one
spring operating mechanism, which features center arrangement, three-phase linkage, novel and exquisite appearance. The Circuit
Breaker uses SF6 gas as insulation and arc extinguishing medium. Since the self-energy arc extinguishing principle is adopted and the
optimal design is made in the Circuit Breaker motion system, the mechanical efficiency is effectively improved and the operating power
is minimized.
5.1.1 The Circuit Breaker consists of three phases installed on the common frame, and the three phases are mechanically connected
to one other through the transmission device. The three phases are operated by one spring operating mechanism CT30 mounted on the
same frame.
5.1.2 Each phase of the Circuit Breaker is an independent tank, and each phase of the three-phase air chamber is interconnected by
independent density relay or pipeline.
temperature changes to cause the pressure change of SF6 gas, the Controller will not act. Only when SF6 gas leakage results in
pressure change of gas, the Controller will send alarm and locking signal.
When the gas pressure drops to 0.62MPa, the gas replenishment alarm signal will be sent.
When the gas pressure drops to 0.60MPa, the gas locking signal is sent and the Circuit Breaker is disabled from acting. The User needs
to connect the locking signal to the protection relay and start the "low pressure locking Circuit Breaker operation" function.
9
5.1.4 The Circuit Breaker mechanism box is equipped with temperature and humidity Controller and electric Heater. When the
temperature drops to below 5℃ or the humidity is higher than 85%, the Heater is powered on automatically. When the temperature
rises to above 10℃ or the humidity is lower than 80%, the Heater will be powered off automatically (The starting temperature or
humidity of the Heater equipment can also be customized according to the User's needs, which shall be specified when ordering.).
5.1.5 The operating principle of the Circuit Breaker is based on the arc extinguishing mechanism: The pressure difference
"automatically" generated by heat energy of the arc itself causes the flow of SF6 gas to extinguish the arc. The closing spring of the
operating mechanism provides kinetic energy for closing the Circuit Breaker, and the opening spring of the Circuit Breaker provides
△
! Note
When the pressure of the air chamber drops and the low air pressure alarm signal is sent, the corresponding air chamber of the
equipment shall be replenished in time, and the possible causes of low air pressure shall be investigated.
move downward under the action of opening spring. During movement, the static main contact finger is separated from the moving main
contact (i.e. cylinder), the current is transferred to the two arc contacts that are still closed, and then the arc contacts are separated to form an
arc.
When breaking the short-circuit current, as the breaking current is large, the arc energy between the arc contacts is large, and the hot gas
flow in the arc area flows into the thermal expansion chamber for heat exchange in the thermal expansion chamber to form low-temperature
and high-pressure gas. At this point, the check valve is closed because the pressure of thermal expansion chamber is greater than that of
compressor chamber. When the current crosses zero, the high-pressure gas in the thermal expansion chamber blows to between open
contacts to extinguish the arc. During the opening process, the air pressure in the compressor chamber is compressed at the beginning, but
when a certain air pressure value is attained, the elastic pressure relief valve at the bottom is opened to compress and deflate at the same time,
so that the mechanism does not need to overcome more air pressure reaction force, thus greatly reducing the operating power (See Fig. 2b).
10
losing Position Breaking Large Current Breaking Small Current Opening Position
1. Static arc 2. Main contact finger 3. Nozzle 4. Dynamic arc contact 5. Cylinder
contact
6. Check valve 7. Pressure relief valve 8. Pressure relief 9. Compressor chamber 10.Thermal expansion chamber
spring
Figure 2 Arc Extinguishing Principle
When breaking a small current (Usually below several thousand amps), the pressure generated in the thermal expansion chamber is
small due to the small arc energy. At this point, the pressure in the compressor chamber is higher than that in the thermal expansion chamber,
the check valve is opened, and the compressed gas is blown to the open contacts. When the current crosses zero, these gases with certain
pressure blow to the open contacts to extinguish the arc (See Fig. 2C).
△
! Warning
Pay attention to the dangerous voltage when breaking. When close to the live part, it may suffer burns and electric shock
Under the action of arc, gas decomposition products and particulate dust will be formed. The decomposition products of SF6 are
toxic, which may cause irritation of skin, eyes and respiratory mucosa, nausea, dizziness and pulmonary edema during contact and
when inhaled.
operation includes two types: Remote control and local opening and closing electric operation and manual operation.
The mechanism can carry out slow opening and slow closing operation with the assistance of special tooling. The manual energy
storage is realized by 17mm hexagon socket, extension rod, ratchet wrench and other tools; Fix the sleeve to the hexagon of the motor
conversion bevel gear of the spring mechanism, connect the extension rod and ratchet wrench at the same time, and rotate
clockwise.(see Table 5)
11
Table 5 Manual storage of energy
Operating
Graphical representation Introduction
steps
Prepare manual charging tools, as shown on the left: 17mm hex socket,
1
extension rod, ratchet wrench
The initial state of the hand crank hole of the mechanism (with baffle
3
plate)
Turn the 10000-turn switch shown in the figure 90° clockwise to leak out
4
the manual energy storage operation hole
Insert the manual energy storage tool into the hexagon on the bevel gear
5
as shown on the left
Turn the ratchet wrench clockwise to charge the spring mechanism, when
6
you hear a click, it means the end of manual charge
Tips
The above operations are only emergency operations in the event of an accidental power failure of the power supply circuit of
the mechanism, and operations are prohibited when the product is running
12
The manual slow-opening and slow-closing operation can be carried out with the help of a special slow-opening and slow-closing
tooling. Manual energy storage uses a 30mm ratchet wrench, a slow-opening and slow-closing tooling, bearings and shaft pins, etc. One
end of the tooling is connected to the lower crank arm and the other end of the mechanism. Connect to the tooling plate at the
auxiliary switch of the mechanism, and set the ratchet wrench to realize the manual slow opening and slow closing operation, as shown
in Table 6.
As shown in the figure on the left, install the slow open and
split operation.
2
In the case of slow opening and closing operation, the
△
! Warning
As shown in the figure below (see Figure 3), the plate with the indicator ball installed on the front of the mechanism is not a
tooling plate for manual slow opening and closing. If manual slow opening and closing is performed here, the mechanism will be
damaged!
13
5.3.2 Structure and working principle of spring operating mechanism
See Fig. 4 for the cross section of mechanism structure and mechanism box. It is mainly composed of mechanism frame, opening
(closing) brake spring, energy storage motor, buffer, opening (closing) brake electromagnet, cam, ratchet, large (small) crank arm,
opening (closing) brake holding stopper, piston rod, shaft, pin and other parts, and realizes three-phase mechanical linkage through
mechanical transmission. The closing operation of the Circuit Breaker is carried out by the closing spring of the mechanism energy
storage. After closing, the opening spring is compressed. During opening operation, the opening spring is fully released to complete the
opening process. It can be achieved by either remote electric control or local manual control. The electrical control is arranged as an
independent unit, and the auxiliary switch and travel switch can provide 24 pairs contacts for use by the Circuit Breaker. In order to
meet the requirements for outdoor installation, the mechanism box is made of stainless steel and installed with anti-rust screws, and
the interface is sealed with excellent sealing rings. The most prominent features of the mechanism are: Advanced and reasonable
design ideas, simple structure, reliable performance, fewer operation maintenance and low operation noise.
1.Cam 2. Ratchet 3.Closing pull rod 4. Closing stopper 5. Cam shaft 6.Pawl
7. Pin shaft 8.Opening spring 9.Crank arm 10.Pin 11.Holding stopper 12.Opening stopper
13.Opening coil 14.Motor 15.Stopper 16.Closing stopper 17.losing coil 18.Closing spring
14
3-18. Big crank arm 3-17.Pawl shaft 3-16.Pawl
3-13.Opening holding stopper 3-12. Opening stopper 3-11. Opening electromagnet moving iron core
(Closing Spring Release at Closing Position) (Closing Spring Energy Storage at Opening Position)
operation of the mechanism are completed, the closing spring 3-5 is in release state (Fig. 3), and the pawl shaft 3-17 is connected with
the motor through the bevel gear. After the Circuit Breaker is closed in place, the motor is switched on to start energy storage for the
closing spring.
Operation steps: During energy storage, the motor drives the pawl shaft 3-17 to rotate counterclockwise, and the two pawls 3-16
on the eccentric pawl shaft 3-17 alternately push the ratchet wheel 3-2 in the transmission of the pawl shaft to rotate the ratchet wheel
counterclockwise and drive the pull rod to compress the closing spring 3-5 for energy storage. When the closing spring is compressed in
place, the energy storage shaft 3-4 is applied with counterclockwise rotation torque by the closing spring 3-5. This torque is locked by
the energy storage holding stopper 3-6 through pin B to complete the energy storage of the closing spring.
small crank arm 3-14 and the large crank arm 3-18 are subjected to the counterclockwise torque of the opening spring 3-3, which is
locked by the opening holding stopper 3-13 and the opening stopper 3-12.
Operation steps: After receiving the opening signal, the coil of the opening electromagnet 3-10 is charged, the moving iron core of
the opening electromagnet is pulled in, the action of the iron core 3-11 is started, and the opening guide rod is driven to impulse the
opening stopper 3-12. The opening stopper 3-12 rotates clockwise to release the opening holding pawl 3-13. The opening holding pawl
15
rotates clockwise and releases the pin A. The crank arms 3-14 and 3-18 rotate counterclockwise driven by the opening spring 3-3, and
the crank arm 3-18 quickly separates the dynamic and static contacts of the arc extinguishing chamber of the Circuit Breaker through
the connecting rod and other transmission parts, and the Circuit Breaker is opened. Meanwhile, the crank arm 3-14 presses the opening
Under the stored energy of the mechanism spring, if emergency operation is required, you can directly tap the button on the
opening electromagnet to open the circuit breaker. The opening button on the electromagnet is shown in Figure 8.
spring does not coincide with the meridional center line of the energy storage shaft, the energy storage shaft 3-4 sustains the
counterclockwise torque of the closing spring 3-5 connected to the ratchet 3-2, which is locked by the energy storage holding stopper
Operation steps: After receiving the closing signal, the closing electromagnet 3-8 is charged, and the moving iron core of the
closing electromagnet is pulled in to drive the opening guide rod to impulse the stopper 3-9 and impulse the closing stopper 3-7. The
closing stopper 3-7 rotates clockwise and releases the energy storage holding stopper 3-6 at the same time. The energy storage holding
stopper 3-6 rotates counterclockwise to release pin B, the ratchet 3-2 rotates counterclockwise under the action of the closing spring
force and drives the ratchet shaft 3-4 to rotate, so that the cam 3-1 pushes the crank arm 3-14 to rotate clockwise, and drives the crank
arm 3-18 on the crank arm shaft 3-15 to rotate clockwise, and compresses the opening spring 3-3 to store energy. The crank arm 3-18
drives the pull rod to quickly close the Circuit Breaker Meanwhile, the opening spring 3-3 is compressed to store energy ready for
opening operation. After the closing operation is completed, the motor stores energy for the closing spring again, the mechanism
restores to the state as shown in Fig. 3-b, and pin A is re-locked by the opening holding stopper 3-13.
Under the stored energy of the mechanism spring, if emergency operation is required, you can directly tap the button on the
closing electromagnet to close the circuit breaker. The closing button on the electromagnet is shown in Figure 9.
16
5.3.7 Automatic Reclosing
The closing energy storage state of mechanism is as shown in Fig. 6 and gives the re-closing signal. The opening spring releases
energy to open the Circuit Breaker, and the energy-stored closing spring releases energy to close the Circuit Breaker. After closing, the
opening spring is compressed to store energy, which can drive the Circuit Breaker to re-open.
electromagnet are checked according to Fig. 11: Check the clearance and stroke of closing electromagnet according to Fig. 12. The
△
! Note
The closing spring and the opening spring may have stored energy. If the control power supply and motor power supply are not
disconnected, the closing spring will automatically re-store energy after closing operation. The spring status indicator only displays the
position of the closing spring. Accidental operation may cause personal injury.
17
5.3.9 Commissioning after connection with Circuit Breaker
The circuit breaker mechanism has a mechanical position indicator, see Table 7
isolating switch is installed in the spherical metal tank above the Circuit Breaker and belongs to a three-position switch. Its electric operating
mechanism is installed on Edge phase cover plate and drives the three-phase knife switch through the pull rod. The earthing switch can be
located on the circuit-breaker side (For tie cell) or on the line side (For incoming and outgoing line bay). The main components of the line
1. Moving Contact 2. Static Contact at Circuit Breaker Side 3. Rotating Insulator 4. Rotating Insulator Shield 5. Cover Plate
5.5 Structure and Working Principle of Operating Mechanism for Isolating/Earthing Switch
5.5.1 General
The three-position mechanism (See Fig. 14) is used to control the operation of the three-phase isolating/earthing switch in driving
the moving contact to rotate clockwise or counterclockwise for a certain angle to realize the line closing, opening and earthing closing
operations.
18
In case of emergency, the operating crank can be used for manual operation. Shaking to the indicating signage of indicating ball
extension rod and ratchet wrench, open the cover plate of the manual hole of the mechanism, and extend the extension rod into the
mechanism to connect the ratchet wrench with the square drive shaft. The switch can be opened and closed by manual rotation
19
5.5.3 Electric operation and interlocking
The electric operating mechanism of the three-position switch can be operated electrically through the local centralized control
box button or remote control signal, both of which can be switched over and interlocked with each other through the change-over
switch.
Through the electrical interlocking of the control circuit, the isolating/earthing switch is allowed to act only when "(1) opening
position of the Circuit Breaker, and (2) the manual switch is disconnected" are true at the same time. In addition, the User can add other
interlocking conditions between the "external interlocking terminals" of the control circuit as required.
For the earthing switch on the line side, the external interlocking can also be realized through line PT secondary voltage or other
outgoing line bay on a project. The moving contact of fault earthing switch is made of pure copper plus alloy materials, and the
The three-phase moving contacts of the FES are respectively arranged in the three-phase shell, independent with each other.
When the moving contact of the FES is in closing state under the drive of the electric spring mechanism, the moving contact is
inserted into the static contact, and the conductor connected with the static contact is connected with the earthing grid through
electrical connection. When the moving contact is in opening state under the drive of the electric spring mechanism, the moving
contact is operated to the opening position, and an obvious open contact is pulled open between the static contact and the moving
contact.
The FES is equipped with an electric spring mechanism, which drives the moving contact through the connecting rod to realize
Confirm that the interlocking conditions are satisfied by manual opening and closing operation of the FES. Open the mechanism
operation cover, toggle the manual operation interlocking board to expose the square operation hole. At this point, the electrical
operation is closed by interlocking, and the electrical operation is impossible. Insert the operating lever and use the operating handle to
operate in direction as indicated by the arrow on the mechanism. The opening and closing indicators will not change synchronously
during the operation process (The operation before the change-over is the process of spring energy storage, and the operating torque is
larger than that of the earthing switch). When operated in place, an impact sound indicating release of the spring can be heard.
1.FES output shaft 2.FES crank arm 3.FES enclosure 4.FES moving contact
5.FES Intermediate contact 6.FES fixed contact 7.FES support conductor of fixed contact 8.DES esclosure
20
5.7 Structure and Working Principle of Operating Mechanism for Fast Earthing Switch(FES)
5.7.1 Manual operation
The mechanism can be operated manually with the help of special manual tooling for energy storage switching. In manual
operation, the ratchet wrench, tooling rod and other tools are used to open the cover plate of the mechanism's hand crank hole, insert
the extension rod into the mechanism and connect the ratchet wrench with the square drive shaft, and rotate according to the direction
indicated on the mechanism to complete the switching operation of the quick ground switch, as shown in Table 9.
Operation
Picture Illustration
Procedure
FES switching in FES separating brake storage and opening and closing action of
the mechanism
Tips:When the fast ground switch is in the opening state, the mechanism indicates that the ball leaks the green "O" letter (for
foreign customers or some domestic customers), or the green "fen" Chinese character (for domestic customers).
When the fast ground switch is in the closing state, the mechanism indicates that the ball leaks the red "I" letter (for foreign customers
or some domestic customers), or the red "he" Chinese character (for domestic customers).
through motor and mechanical transmission parts. When the spring moves to a specific position, the spring energy is quickly released to
drive the extension and contraction movement of the moving contact to realize the closing and opening operation of the earthing
switch.
In case of emergency, the operating crank can be used for Manual operation. Shaking to the tripping position means that the
closing or opening has been in place, and the opening and closing state of the mechanism is judged in combination with the opening
21
and closing indication on the mechanism.
or remote control signal, both of which can be switched over through the switch-over switch and interlocked with each other.
Through the electrical interlocking of the control circuit, the earthing switch is allowed to act only when "(1) the Circuit Breaker is at
the opening position, and (2) the manual switch are disconnected" are true at the same time. In addition, the User can add other
interlocking conditions between the "external interlocking terminals" of the control circuit as required.
For the earthing switch on the line side, the external interlocking can also be realized through line PT secondary voltage or other
Fig. 17 Schematic Diagram of Mechanism Opening Fig. 18 Schematic Diagram of Mechanism Closing
internal pressure, bending load, etc.). A conductive rod (6) is installed in the liner. The lower flange (5) and the upper flange (2) are fixed
on the liner by heat treatment bonding process. The silicone rubber umbrella skirt bushing and the liner are bonded into a whole by
22
Excellent characteristics, especially in dirty environment and rainfall conditions;
Sandstorm resistance;
Light weight;
1. Main Terminal 2. Upper Flange 3. Silicone Rubber Insulator with a Step-shaped Umbrella Skirt
as shown in Fig. 20. The primary circuit is the conductive rod in the compound insulating bushing or porcelain sleeve.
The Current Transformer is generally installed under the bushing on the line side. If there are special requirements, it can also be
installed on the bus side or both sides, but the installation requirements must be specified when ordering. Double bus arrangement is
As limited by the installation height, a maximum of 4 iron cores can be installed on one side of each phase. If the transformation
ratio is large, the accuracy is low and the load is small, the number of iron cores can also be increased to 5~6.
23
5.10 SF6 Densimeter
The Hybrid Compact Gas Insulated Switchgear generally adopts the oil-filled density meter is used, and when the equipment is
8 Altitude , m ≤4000
9 Anti-seismic AG5
the alarm and the rated pressure), mesh or light green (above the rated pressure).
24
6 Packaging, Transportation and Storage
6.1 Packaging
The Hybrid Compact Gas Insulated Switchgear are packaged and transported as a whole set.
Before packaging, all the switching components in the equipment are in the mode of opening transport, the circuit breaker
mechanism anti-moving pin has been inserted, the spring mechanism is in the state of no energy storage, all the valves on the
product are in the state of closed, and the mechanism box and LCP cabinet doors are fully locked
Before packaging, the equipment is filled with 0.02Mpa ~ 0.05Mpa SF6 gas to prevent moisture and dust from entering
6.2 Transportation
When the equipment is used in any environment and any place, the transportation pressure inside the equipment must be 0.02
Mpa ~ 0.05 Mpa SF6 gas. Otherwise, there will be serious safety hazards during transportation.
In all conditions, the equipment must be transported at a speed of not more than 40km/h and equipped with a
three-dimensional shock recorder to record the number and severity of shocks encountered during transportation. If any
exception is found, notify the device supplier immediately. Do not operate the device without clear advice from the supplier
No matter in what form the equipment is transported, all the switches of the equipment must be in the opening position, the
breaker mechanism anti-action pin is inserted, the spring mechanism is in the state of no energy storage, all the valves on the
product are closed, and the mechanism box and LCP cabinet doors are locked in good condition
6.3 Storage
If the equipment is not installed immediately after arrival, it should be stored indoors. If it is stored outdoors, it should be placed
in a dry place with good drainage measures, all packaging should be covered by waterproof tarpaulin and regularly ventilated to
keep the equipment dry. If it is stored for a long time, the integrity of the packaging and covering must be checked regularly
Store SF6 cylinders indoors or in temporary buildings, not directly exposed to sunlight, and not near places with heat sources
Tips
If the equipment cannot be assembled immediately after delivery, it is recommended to consider effective protection, rainproof
and moisture-proof measures when storing the equipment and its accessories. In order to avoid the influence of moisture on the
If the storage time of equipment is longer than three months, the anti-condensation heater in the centralized control cabinet
7 Installation
7.1 General
The work on field installation of the Hybrid Compact Gas Insulated Switchgear mainly includes the following items:
Open the package and check whether the equipment and accessories are in good condition. If any abnormality is found, please notify
Chint Electric immediately. Do not move or touch the equipment without clear advice to prevent accidents. If the equipment is in
good condition and meets the requirements of Chint Electric factory documents, follow the following steps.
HGIS itself is transported with SF6 gas with small positive pressure (0.02 ~ 0.05Mpa). After opening the package, confirm
Check the foundation and embedded anchor bolt (Note: If the anchor bolt adopt the secondary pouring method, the
25
Lift steel structure support;
Rotate the Circuit Breaker A and C outward at the specified angle (See Fig.18);
Fill with SF6 gas (Note: The cable terminal products need to be connected with cable head, then treated by nitrogen
Tips
Unless specially required under the supply Agreement, the lifting sling and accessories required for lifting are beyond the scope
The centralized control box is installed on the assembled support and lifted integrally to the qualified foundation (With a total
weight of about 450kg). After the foundation is tightened, check that the upper mounting plates of the two legs should be on the same
horizontal plane; Otherwise, it is necessary to take measures (Such as adding adjusting nuts under the leg base plate) for leveling.
After the installation and adjustment of the support, the gap between the base plate of leg and the foundation shall be filled.
During the lifting stage, care shall be exercised on the position of bus and centralized control box to avoid wrong direction.
the confirmation data of relevant products for the weight of Circuit Breaker. During the lifting stage, align the mounting hole on the
base of the Circuit Breaker with the corresponding hole on the top plate of the leg, insert the connecting bolt, and tighten it with flat
washer, spring washer, nut and 140Nm torque wrench. Remove the lifting sling after the Circuit Breaker is in place and tightened.
is lifted onto the support, the phase A and C bushings are necessary to be opened. When the bushings are opened, a 5T crane shall be
used to keep an upward pull force during phase-splitting, and then the personnel shall assist on standby. The crane shall slowly drop
its hook to make the phase A/C bushing slowly offset outward. After being positioned in place, the bushings shall be threaded with
fixing screw. If the position of phase A/C bushing deviates from the original position, it shall be re-aligned to restore to the factory
When the equipment leaves the factory, the position after phase separation will be marked with a marker pen at the edge of the
equipment, the position of the chassis frame A, and the position of the chassis frame B. When the on-site phase separation is offset,
After the equipment is divided into phases, it is necessary to connect and install facilities such as current transformers,
phase-to-phase connection brackets, transmission connecting rods, DES mechanisms, FES mechanisms, density meter assembly,
grounding wire assembly, and lower support rods of edge-to-phase shells of the equipment. After assembly, it is shown in Figure 23.
The above accessories are shipped with the equipment and placed in the spare parts box.
26
Tips
Upon arrival of the goods and before installation, the integrity of the delivered materials shall be checked immediately
according to the Delivery Note and Check List. In case of any damage to the goods is found, the damage scope shall be identified
immediately and the possible causes of damage shall be analyzed. For transportation damage, immediately notify the freight agent
For HGIS installation, only bolts provided by the Manufacturer can be used. For missing of bolts during installation, a few spare
△
! Warning
If the mismatched bolts are used, the serious damage to equipment and casualties may occur.
If the quantity of bolts provided for pressure vessels is not enough, the spare bolts shall be obtained from the
Manufacturer in principle, or the bolts of specified models shall be purchased from the local market after technical
After the bolts are fixed, which shall be checked and confirmed, or otherwise the equipment damage, environmental
During the HGIS installation, do not touch or step on the HGIS mechanism, lever arm, tie rod, connecting rod,
densitometer, valve seat, cable, aviation plug and other auxiliary facilities. Failure to operate the HGIS in accordance with
the regulations may cause abnormal operation or even damage to the HGIS.
Before and after operation, commissioning, and operation of HGIS, it is necessary to check that the equipment connected
to each other, such as brackets and support rods, is fully installed, all bolts are fastened in place according to standard
requirements, and all connecting bolts between the bracket and the foundation and body chassis are used correctly and
fastened as required. If the equipment such as the fixed brackets and support rods are not connected as required, and all
bolts are not fastened according to the standard, it may cause abnormal operation of the HGIS equipment or even
When using HGIS in a vehicle-mounted mobile substation, in addition to following the requirements of this manual, the
following regulations must also be followed. If not used in accordance with the regulations, it may cause abnormal
a) The fixed connection between the HGIS equipment foundation and the car board is reliable, and the connection
between the fixed phases is reliable. It is recommended to add shock absorption facilities between the HGIS and
b) During the transfer of the vehicle-mounted mobile substation, HGIS equipment SF (6) gas recovery to transport
c) During the transfer of the vehicle-mounted mobile substation, all switch components in HGIS are in the open state,
and the inter-phase transmission connection of each switch is reliable with no risk of misoperation. The circuit
d) During the transfer of the vehicle-mounted mobile substation, the HGIS casing cannot be mechanically hardwired
and fixed.
27
e) During the transfer of the vehicle-mounted mobile substation, personnel should be appointed to supervise the
driving status of the vehicle body. When the road conditions are bad, the speed should be reduced. If the distance
exceeds 200km, equipment inspections should be carried out every 50km during the transfer. If any abnormalities
are found, they should be reported to the relevant departments for timely handling. The HGIS body is equipped
with a collision recorder throughout the transfer process, and the collision acceleration in three directions should
not exceed 3g. The tilt angle of the vehicle-mounted mobile substation transfer should not exceed 15 °.
Personnel should observe the HGIS equipment when passing through height and width-limited places to prevent
f) For other requirements, please refer to the "DL/T-2284 Vehicle-mounted Mobile Substation Operation and
Maintenance Specification".
28
1. connection bracket between phase to phase 2. Current transformer 3. FES interphase drive 4. DES mechanism
5. Side phase support rod 6. FES mechanism and bracket 7. Ground row assembly 8. Density meter assembly
29
7.5 Installation of Transmission Rod
7.5.1 Transmission rod of Circuit Breaker
When the equipment is in the transportation state, the Circuit Breaker is in the opening state without energy storage. Before
installing the connecting rod of the Circuit Breaker, first observe the state of the Circuit Breaker. If it is not in the state of opening and
no energy storage, the Circuit Breaker is strictly prohibited to operate. Select the correct phase-to-phase connecting rod, align the
connecting rod positioning hole of the middle phase (Phase B), fix it and then adjust phase A/C. When adjusting the phase A/C, the
four adjusting screws on phase A/C can be adjusted to enter the appropriate position (See Fig. 25)
△
! Warning
The opening and closing position of the Circuit Breaker crank arm has been properly adjusted before leaving the factory. The
position of the factory crank arm may not be changed during on-site phase-splitting operation. Operation against the regulations
may result in serious damage to the equipment or casualties. In the event of any deviation in the installation of phase-to-phase
connecting rod, it can only be adjusted by adjusting the deflection angle of side phase.
the Factory,
FORBIDDEN to
change it.
30
Fig. 26 Fixing Bolt of Phase-splitting
△
! Note
The bolt (Phase-splitting bolts of Circuit Breaker, one for each phase) circled at the position shown in Fig. 26shall be specially
customized (the bolt head is thinned and supplied by the Supplier, drawing No.: 8ZDK.920.029). If these bolts are not used according
to the regulations, abnormal opening and closing operation of the Circuit Breaker and even damage to the equipment may occur.
(1) Remove the lock plate on the adjusting flange and all binding objects used to fix the connecting rod and transmission rod.
(2) Confirm that the three-phase contacts are in the earthing closing position through the viewing window. If the contact position is
inappropriate, loosen the M10 screw, turn the adjusting flange for adjustment, and tighten the M10 screw after adjustment.
(3) Keep the adjusting flange in place, sleeve the connecting rod joint bearing on the connecting shaft of the crank arm, and insert the
cotter pin.
(4) Adjust the crank arm of the operating mechanism to make the isolating switch in the closing position, insert the connecting rod joint
bearing on the connecting shaft of the crank arm, insert the cotter pin, and observe if the contact is displaced.
(5) Manually operate the isolating switch to open and close by once, and observe the contact position again.
(6) After all the contact positions are appropriate, draw lines for marking, record the opening and closing positions as appropriate, and
then fix the fixing bolts on the crank arm and the fixing bolts of the adjusting flange. All the three phases are adjusted according to this
1. Connecting rod 2. Arm 3. Adjusting flange 4. Drive shaft 5. Fastening bolt 6. Knuckle bearing
31
△
! Warning
In Figure 27, the S view is the closing position of the non-mechanism phase lever arm (lever arm 1), the T view is the closing
position of the middle phase lever arm (lever arm 2), and the R view is the closing position of the mechanism drive phase lever arm
(lever arm 3). This position has been adjusted before delivery, and there is no need to change the position of the lever arm on site.
After manual and electric closing, it is necessary to observe whether the lever arm is consistent with the position in the S, T and R
views. If they are inconsistent, adjust the length and serial number of the tie rod. 6 Adjust the flange position. If the closing
position of the crank arm is not consistent with the position shown in Figure 26, it may cause equipment damage in serious cases!
according to the requirements of the project drawings. Before the installation of the quick ground switch connecting rod, the quick
ground switch should be determined to be in the on-off state to ensure that the operating mechanism and the three-phase body are in
the on-off position, and then the correct inter-phase connecting rod should be selected according to the requirements of the project
drawings. At the same time, adjust and fix the connecting rod according to the marking position of the crank arm before delivery, and
the installation of the quick ground switch is completed. After the installation, the FES transmission is shown in Figure 28.
1. Mechanism arm (1) 2. Tie rod (1) 3. Transmission arm (2) 4. Pull rod (2) 5. Drive lever (3) 6. Pull rod (3) 7. Drive
△
! Warning
In Figure 28, the S view is the closing position of the lever arm of the mechanism drive phase (lever arm 2), the T view is the
closing position of the middle phase lever arm (lever arm 3), and the R view is the closing position of the side phase lever arm
(lever arm 4). This position has been adjusted before delivery, and there is no need to change the position of the lever arm on
32
site. After manual and electric closing, it is necessary to observe whether the lever arm is in the same position as in the R, S and
If the closing position of the crank arm is not consistent with the position shown in Figure 28, it may cause equipment damage
in serious cases!
can monitor and control HGIS on site. The LCP has the functions of local operation, signal transmission, protection, relay and monitoring
of SF6 system. Generally, each bay is equipped with one LCP. According to different layout methods, the LCP can be divided into
integrated LCP and split-type LCP, as well as intelligent cabinet and ordinary cabinet. See Fig. 29. The specific panel configuration shall
1. Panel 2. Cabinet Door 3. Switch ON/OFF Indicator 4. Local Operation Button 5. Analog Bus
The LV cable shall be laid in the cable trough and bound with cable tie. Excessive stretching or bending of cables shall be avoided.
One end of the control cable is fixed and connected to the terminal strip of the centralized control box, and the other end is connected
with a multipole industrial plug with anti-mis-plug, which is respectively inserted into the socket of the corresponding equipment. Care
shall be exercised on leveling of the sealing ring and buckling up the fastening buckle.
Introduction to anti-tripping function: Prevent the continuous closing and switching of the Circuit Breaker (Jumping Phenomenon)
due to failure of the closing contact of the control switch or automatic device to return in time (For example, the operator does not
release the handle, and the closing contact of the automatic device gets stuck.) and just closed on the faulty line and equipment.
Note: Both ends of the secondary winding connecting cable of the Current Transformer are fixed and connected to the terminal
without plug.
earthing bolts. The field earthing grid leads are usually connected to the specified earthing position under the support with M12 bolts.
33
7.9 SF6 Gas-filling
See Fig. 30
Gas shall be filled through pressure relief valve. Before gas-filling, slightly open the cylinder valve, use appropriate tools to prop up
the joint valve port on the charging pipe for a few seconds, flush the gas-filling pipe, and then close the cylinder valve.
The Hybrid Compact Gas Insulated Switchgear adopts automatic closed gas-filling joint. Remove the protective cap, insert the
gas-filling pipe connector, and tighten the connecting nut. Then the valve will open, the pressure relief valve can be opened for
gas-filling until the rated gas-filling pressure is attained, then the connector is removed and the protective cap is screwed on.
The SF6 pressure gauge used together with the Hybrid Compact Gas Insulated Switchgear is equipped with temperature
compensation device, and the reading value has nothing to do with the ambient temperature. However, for the ordinary pressure
gauge on the cylinder side, the reading of the Hybrid Compact Gas Insulated Switchgear rated gas-filling pressure needs to be corrected
as follows:
Ambient Temperature (℃) -30 -20 -10 0 +10 +20 +30 +40
Gas-filling Pressure (MPa, gauge pressure) 0.54 0.56 0.58 0.60 0.63 0.65 0.67 0.69
Tips
When leaving the factory, the Supplier supplies special gas-filling tools, including gas pipeline, pressure relief valve, and
gas-filling joint. Before on-site gas-filling, it is necessary to check the Packing List, identify the corresponding tools, and use the
△
! Warning
Installation personnel may suffer from hazard under the following circumstances:
Dangerous voltage;
SF6 gas;
Failure to follow the Safety Instructions may cause death, serious injury, huge property loss and environmental damage.
SF6 gas is heavier than air. When great quantity of SF6 leaks, it will crowd out the air, and the risk of suffocation is present due
to lack of air in the closed section. Special equipment shall be used for gas recovery. Pump out the filled SF6 gas and do not discharge
△
! Notes
During gas-filling, the gas cylinder shall be upright and may not be placed horizontally;
When the temperature is too low and the liquid SF6 gas is not easy to gasify, the cylinder heater or room heater can be used for
heating. Open fire MAY NOT be used for heating the cylinder, as shown in Fig. 31.
34
1. Cylinder 2. Pressure Relief Valve 3. Pressure Gauge
In order to avoid accidents, fires and unacceptable environmental damage, and to support the reliability of switchgear functions,
Specially assigned person is responsible for the implementation of operation, and an Inspector is staffed when necessary.
Only qualified personnel upon training are allowed to participate in the installation work.
The working rules and operating procedures for safe maintenance and safe operation and the treatment methods in case
of accident or combustion shall be accessible at any time, and can be posted in the workplace if necessary.
Tools, instruments and equipment required for safe production and personnel protection equipment required for specific
In principle, only materials, lubricants and auxiliary equipment allowed by the Manufacturer can be used.
The Safety Instructions in this Manual are the minimum requirements, which do not affect laws and regulations, work rules and the
company's internal regulations, nor include any requirement for integrity. In any case, the terms of reference must be clarified at the
latest before starting the work. While paying attention to operation control and specific working conditions, User should also take into
account the Product Description and Instructions Manual of tools, instruments, equipment & materials, lubricants and auxiliary
materials.
35
8 Commissioning and Inspection
△
! Note
In addition to the requirements in the scope of supply, check if the required instruments and equipment are complete.
△
! Warning
The switch may not be operated until SF6 gas is filled to the rated pressure, otherwise the switchgear may be damaged.
Primary equipment: Check whether the positions of switch components (CB, DES, FES) are consistent with the instructions of
the mechanism, whether the external transmission link is abnormal and redundant attachments, whether the back nut on the
transmission tie rod is tightened according to the requirements, whether the bolts installed in the equipment are tightened
according to the standard torque requirements, and whether the anti-moving pin on the circuit breaker mechanism and the
secondary control part: check whether all the wiring is reliable, loose, virtual connection phenomenon; The connectors
between the LCP cabinet and the mechanism are properly installed; Whether the terminal of current transformer meets the
Manually operate the circuit breaker five times to check whether the operation is reliable
Manually operate the isolation switch, grounding switch, and quick grounding switch five times to check whether the
operation is reliable
Switch the position of the transfer switch and check the interlocking under various states;
36
8.6 SF6 Moisture Measurement
In order to give full play to the role of molecular sieve, it is recommended to measure the gas moisture 48 hours after filling SF6
gas. A special micro water meter is used for moisture measurement. It is recommended to flush the sampling pipeline with qualified SF6
The lock device cannot be unlocked or disabled at will. During normal operation, the lock control key in the sink control cabinet shall
1
be kept and used in strict accordance with the power safety working regulations of the power grid company
The heating device should be comprehensively inspected and put into operation before the winter, and the defects should be dealt
2
with in time
The moisture-proof device should be invested for a long time, and a comprehensive inspection should be carried out before the rainy
3
season, and the defects should be dealt with in time
For the maintenance requirements of the cabinet body and the humidification heating, moisture-proof and anti-condensation
4 modules and circuits, and lighting circuits in the cabinet, refer to the related contents of the terminal box of the power grid company
Before replacing the indicator, disconnect the power supply and use a multimeter to check that there is no voltage on the power
5
supply side. During replacement, O&M personnel should wear gloves, and wrap insulation when disassembling secondary cables
If the energy storage circuit breaker does not meet the operating requirements, replace it. Before replacing the energy storage circuit
6 breaker, disconnect the upper power supply and use a multimeter to check that there is no voltage on the power supply side. During
replacement, O&M personnel should wear gloves, and insulation measures should be taken for open secondary cables
When the opening and closing is abnormal, check whether the opening and closing indicator is falling off and deformed, and whether
the mechanical transmission part of the operating mechanism is deformed and falling off. Check the monitoring system displacement,
7
protection device, telemetry, remote information and other information to confirm the actual location of the equipment in
combination with the operation mode and operation command, and contact the maintenance personnel for processing if necessary
Tips
If there are no special requirements in the Technical Agreement, the Supplier will not supply relevant instruments and
equipment in principle. If there are such requirements for the project, it shall be noted when ordering the Product.
Tips
If there are no special requirements in the Technical Agreement, the Supplier will not supply relevant instruments and equipment
in principle. If there are such requirements for the project, the requirements must shall be noted when ordering the Product.
37
9 Inspection and Maintenance
Except for the bushing, the working conditions of the Hybrid Compact Gas Insulated Switchgear are basically not affected by the
atmospheric environment, while the composite insulating bushing has stronger pollution resistance, so in practice, the Hybrid Compact
Gas Insulated Switchgear can operate over extended time without maintenance.
(2) The equipment shall be checked once a year, and the following items shall be checked without exiting the operation:
Heater function;
Visually check the multipole plug, earthing connection and etc, and if the equipment is deformed, corroded and damaged.
In addition to the above items, for the equipment with few operations, it is recommended to have local and remote operations by
once respectively.
Check the multipole plug, earthing connection and etc., and if the equipment is deformed, corroded and damaged.
9.2 Maintenance
The equipment shall be overhauled when it meets one of the following conditions.
(2) The short-circuit breaking times reach the values listed in the following table 13:
Note: The above values are selected based on product- type test and years of operation experience.
See the Following Table 14 for Overhaul Items. Repeat the Cycle in Table 10.2 Below after 15 Years.
38
Tips
Frequent breaking of switchgear has greater contact wear than accidental breaking, which is distinguished here:
The amount of wear should be estimated so that in most cases, check and maintenance services can be carried out at fixed
intervals. Only when the switchgear is disconnected very frequently, and the operation times or fault current disconnection times
reach or exceed the specified required values, the corresponding maintenance services shall be provided in advance (See the
relevant chapters of the corresponding type test report for the allowable breaking times of the equipment).
use of Product at the end of its service life to reduce resource waste and pollution.
instructions: End-of-life products contain a large amount of materials and energy, and the degree of recycling is classified according to
material
9.3.2 .2 Metal
Metal materials are sorted by type and surface treatment method and then sent to an approved recycling company for processing.
When the paint is removed from the surface or after other surface treatment, the metal can generally be melted and used in new
products. Many iron, steel and aluminum components are large and easily identifiable, such as frames and mechanical housings.
Chint Electric aims to reduce the use of precious metals and the emission of metals that are harmful to the environment. Recycling
Precious metals like steel and silver are very expensive and present in very small amounts in the Earth's crust. Copper is mainly
used in current channels, interrupters, electrical contacts and cables. Sometimes the contacts are silvered. Some metals can be
hazardous if disposed of. These metals include, but are not limited to, copper, as well as bell zinc and brocade nickel, which are used as
9.3.2 .3 Plastic
Different types of plastic are sorted and then sent to an approved recycling center or company for processing. The energy in
thermoplastics and thermosets can be recovered by burning it in a dedicated facility. Typically, thermoplastics can be melted down and
used again without much impact on quality. Composites can be fractionated and used as fillers for other materials, or disposed of.
The small amount of composite materials found in insulators, pipes and explosion-proof cable joints are thermosetting plastics.
39
Thermoplastics can be found in components such as guide rings, straps, and support rings. Thermoplastics in casings, nozzles, tubes and
rings contain gas fluorine and are not suitable for recycling, however, they can be disposed of without leaking hazardous materials
equipment must be cleaned, and by using gravity, the waste oil can be broken down into oil, water and different pollutants. In many
to prevent leakage and pollution of the environment [Note 1], gas can be divided into several solutions according to the situation:
When the circuit breaker is filled with mixed gas, SF in the treatment process. The gas should be separated from the mixture first,
and the gas mixture sent for destruction does not need to be separated.
The insulating and extinguishing SF6 gas should be collected by appropriate equipment, and can be used again after being
and may cause irritation of the skin, eyes and respiratory mucosa during contact and inhalation, resulting in nausea, dizziness and
pulmonary edema. Personnel should avoid direct contact with SF6 gas containing the decomposition. When the space smells
uncomfortable and harsh odor, personnel should evacuate to a safe area in time and open ventilation facilities.
Note 1: SF6 gas at high concentrations can cause difficulty breathing, wheezing, blue skin and mucous membranes, and general
convulsions. After inhaling a mixture of 80% sulfur hexafluoride and 20% oxygen for a few minutes, the human body will experience
numbness in the limbs and even suffocation. The decomposition of sulfur hexafluoride gas under the action of electric arc, such as
sulfur tetrafluoride, sulfur fluoride, sulfur difluoride, thionyl fluoride, sulfur difluoride, thionyl tetrafluoride and hydrofluoric acid, etc.,
△
! Warning
DO NOT eat, drink, smoke or store food in the room of system or equipment, which containing SF6.
During the overhaul and maintenance of SF6 switchgear, the room must be well-vented (Open the ventilation and exhaust
When filling and collecting SF6 gas, safety goggles, gloves and appropriate protective clothing shall be worn to prevent frostbite
Industrial vacuum cleaner with filter shall be used to remove powdered decomposition products. Industrial vacuum cleaner
40
shall meet the specification of dust grade L (Light).
Avoid skin exposure to powdered decomposition products and prevent swallowing or inhaling powdered decomposition
products.
After end of work, wash the respirator, safety goggles, gloves and clothes with water, and flush your whole body with soap and
plenty of water.
Table 14 Maintenance Cycle and Operation Items of Hybrid Compact Gas Insulated Switchgear
Parts Out of
Operation items In service 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
service
Moisture
■ ★ ★ ★
measurement
Operating mechanism
Isolating Switch ■ ★ ★
lubrication
Mechanical test ■ ★ ★
Overhaul ■ ★
Mechanical test ■ ★ ★ ★
Overhaul ■ ★
Material surface
Steel Support and □ ★ ★ ★ ★
corrosion
Earthing
Re-tighten bolt □ ★ ★ ★
(1)
Note: Recommended check items for equipment with fewer operations.
41
Appendix A Requirements for Installation Environment
A.1 Environmental Requirements
A.1.1 Clean the Product base and the floor in the surrounding area, and there shall be no dust, metal particles and foreign matters
that are easily to be stirred up when walking.
A.1.2 The Product surface shall be cleaned until free of foreign matters as listed in A.1.1;
A.1.3 The surface of tools, lifting sling and lifting ropes shall be free of foreign matters (dust) such as easily-falling soil blocks or small soil
particles;
A.1.4 The operation area is required with humidity of ≤ 80%. When the humidity is > 80%, the corresponding treatment measures as
specified herein shall be taken;
A.1.5 The operation area must be free of other operations that produce dust and metal particles, such as grinding, welding and
cutting, and the operation area must be kept clean;
A.1.6 At the surrounding of the operation area, shall be NO dust-raising operations, such as loading and unloading of san
A.1.7 The illumination of the operation site shall be ensured. Installation is not easy in dim light, and explosion-proof lamps shall be
A.1.8 Outdoor engineering installation may not be carried out on rainy, snowy, strong windy and sandy days. If necessary, temporary
dust-proof and moisture-proof tent (hereinafter referred to as dust-proof tent) shall be built for the assembly of Product docking parts.
A.1.9 The indoor installation of products shall be carried out after the completion of indoor decoration;
A.1.10 Garbage can shall be placed on the operation site, and the consumables, waste paper, conductor packaging waste generated,
shall be put into the garbage can in time, and may not be discarded arbitrarily;
A.1.11 Outer packaging of Product, including wooden cases, metal objects, and etc, shall not be placed in the assembly operation
area to avoid affecting the assembly, but shall be properly placed in other positions.
A.2 Treatment Measures
A.2.1 Treatment measures for outdoor engineering assembly floor and under sandstorm weather.
a) When the on-site assembly floor is cement floor, the floor shall be cleaned and sprinkled with an appropriate amount of water
before assembly. The amount of water shall be appropriate as not to cause dust or form clay (If conditions permit, the use of
b) When the floor of the installation site is the soil floor, the assembly operation area shall be leveled and compacted. If there is
standing water, the water shall be drained first, and then the floor shall be leveled, and a layer of color-stripped cloth is paved.
The uppermost layer shall be paved with plywood with thickness of no less than 3.5mm. The single piece of plywood shall be in
area of more than 1m2, and length-width ratio of less than 1.5. As shown in Fig.6, the color-stripped cloth shall be leveled during
laying, and must be free of any wrinkle, damage, dirt and, etc. In principle, brand-new color-stripped cloth shall be used.
c) When the floor on the installation site is sand and gravel floor, the same treatment measures as those in A.2.1b) shall be
adopted.
d) For assembly in non-continuous windy and sandy areas, the scaffolds and color-stripped cloth shall be used to build temporary
fence around the Product assembly area to reduce the wind speed. The height of temporary wall shall not be less than 3m.
e) Temporary dust-proof tent shall be set up when installed in environment with strong sandstorm, and the dust-proof tent shall
42
The dust-proof tent shall be able to effectively prevent wind and sand from entering the inner space of the tent from the
surroundings and the top (The hole through which the lifting rope passes can be reserved at the top, but the hole may not be too large);
The tarpaulin for dust-proof tent should be made of materials with high light transmittance;
The main structure of the dust-proof tent should be steel pipes that can be assembled and disassembled;
The dust-proof tent can cover GIS product in whole or in part, and there is enough space in the tent to facilitate personnel
A passage for personnel to enter and exit is reserved on one side of the dust-proof tent, and two door curtains are
installed inside and outside, where personnel can clean off the floating dust on the surface of clothes after entering;
Jacket cuff hole is reserved on the side of the dust-proof tent, which can wrap the Product bus shell, and also be removed
Movable.
a) For the floor with floor tiles, before installation, the indoor floor shall be cleaned, sprinkled and wiped clean, and the
construction may not be started until the air is still for 12 hours.
b) For the cement floor and cement rough floor, before installation, clean the indoor floor, sprinkle water on the floor, and start
construction after the air is still for 12 hours. If sand particles fall off the floor during cleaning, flooring covering shall be laid
during installation.
c) During assembly, all the doors and windows need to be closed. If doors and windows are not installed due to the progress of
work, plastic film and other materials can be used for temporary blocking, so that wind and sand can be blocked out of the
d) The surface of crane and track used for indoor installation shall be cleaned, and free of dust falling. (cement, wall paint, etc. may
build up on the crane track, which may fall off during crane operation.)
△
! Notes:
1) Before use, the crane shall be effectively verified by concerned departments and can be used only when it is qualified. Before
lifting, confirm whether the operator buttons of the crane are flexible and the directions are marked correct.
2) When filling gas for indoor products, air circulation must be ensured (Start the ventilation equipment if necessary) to prevent
personnel from hypoxia and suffocation due to excessive gas leakage caused by operation and other reasons.
43
Appendix B Instruments, Tools and Equipment Used for Equipment Installation and
Commissioning
B. 1 See Table B-1 for Equipment and Instruments for On-site Installation and Commissioning (User-supplied).
Table B-1
Model, Specification and
No. Description Quantity Application
Parameters
2 SF6 Gas Recovery Unit With vacuum gauge 1 Vacuumize and recover SF6 gas
3 Electric Welding Machine About 45kW 1 Underframe and foundation welding, etc
6 Ventilator 1 Ventilation
17 Withstand Voltage Test Equipment 300kV 1 For product withstand voltage test
B. 2 See Table B-2 for Special Tools (See the Provisions of the Order Contract or Technical Agreement for Details).
Table B-2
Table B-3
44
Table B-3 (Continued)
8 Manual Hoist Varying specifications of 1t~5t Several pieces Lifting and connecing of the equipment
9 Lifting Jack 3t、5t 2 sets for each type Support and tranfer of equipment
11 U-shaped Lifting Ring Pin diameter D=12mm, D=16mm 4 pieces for each type Moving the equipment
21 Wrench M6~M24 (Series No.1) 1 piece for each type Thread tightening operation
22 Open End Wrench M6~M24 (Series No.1) 1 piece for each type Thread tightening operation
24 L-shaped Wrench 8#、10# 1 piece for each type Thread tightening operation
37 Circlip Pliers Elbow \ straight head circlip pliers 1 piece for each type Loading and unloading retaining ring
45
B4 See Table B-4 for Auxiliary Consumables Used on Site (See the Provisions of the Order Contract or Technical Agreement for Details).
Table B-4
2 Silicone Grease 7501 Used with O-ring seal, metal flange anti-corrosion
4 Absolute Ethyl Alcohol (Analytical Purity) Purity ≥ 99.5% Washing and cleaning of internal parts
6 Industrial Clean Paper (Blue) Washing and cleaning of other parts free paper towel
Film by farm-oriented
8 Plastic Film SF6 gas leak detection, dustproof and others
13 Pressure-sensitive Adhesive Tape SF6 gas leak detection and others Transparent tape
18 Red and Green outdoor Sticker 3M Basin-type insulator gas barrier identification
Tips
The instruments, tools and equipment listed above are based on the valuable experience accumulated by CHINT Electric during
on-site installation, but which does not mean that all are necessary. The tools and instruments accompanied to the goods shall be
46
Appendix C Instruments, Tools, Equipment, and etc Used for Equipment Installation and
Commissioning
Table C-1
Bolt Bolt Torque (kg/cm) Bolt Torque (N.m) Bolt Torque (Ib.ft)
Specification Standard Value Special Value Standard Value Special Value Standard Value Special Value
Note: The special value is applicable to the tightening of cast insulated parts.
47
Appendix D Relevant Operation of SF6 Gas
D.1 SF6 gas parameters
See Table D-1 for SF6 Gas Parameters
48
D.2 Packaging and storage of SF6 gas
a) SF6 gas shall be filled in clean and dry gas cylinder. When the design pressure of gas cylinder is 8Mpa, the filling factor shall not be
greater than 1.17kg/L. When the design pressure of the gas cylinder is 12.5 MPa, the filling factor shall not be greater than 1.33kg/L,
and the gas cylinder shall be equipped with safety helmet and shockproof rubber ring.
b) The SF6 storage container shall not be exposed to the sun, and may not be proximate to flammable and greasy places. It shall be
stored in the warehouse with shed cover. The warehouse shall be shady & cool and well-ventilated, and its temperature shall not
exceed 50 ℃.
c) Sulfur hexafluoride gas stored in a new cylinder for more than half a year shall be spot-checked again before use, and can be used
49
D.5 SF6 pressure/temperature curve
a) Sulfur hexafluoride is a colorless and tasteless gas. Its density is 6.07g/l at 20℃ and 1bar, which is five times that of air. The gas is in
liquid state under high pressure, so it is stored and transported in gas tank;
b) At normal ambient temperature, SF6 is chemically and thermally stable, inactive (inert), almost insoluble in water and uninflammable;
c) SF6 has become a desirable insulation and arc extinguishing medium for its high dielectric strength and excellent arc extinguishing
characteristics;
d) If SF6 gas overflows from SF6 equipment, the SF6 gas will not mix with large quantity of indoor air, the gas may settle on the ground
and penetrate into the basement due to its high concentration; Once SF6 is mixed with the surrounding air, the SF6 gas will no longer be
50
separated out;
e) If SF6 is exposed to electric spark and arc, it will cause decomposition until cooled down, and a wide range of recombination will
occur.
corrosive compounds such as gaseous low hexafluoride, solid metal fluoride and hydrofluoric acid may be generated. They may cause
skin, eye and mucous membrane allergy, and nausea, dizziness and pulmonary edema if inhaled in excessive amount;
b) The adsorbent can absorb most decomposition accompaniment. Even if there is small quantity of gaseous decomposition products,
attention should be paid to their harm. Before the risk of poisoning is present, it should be judged by the unpleasant pungent smell.
health hazard. However, SF6 will displace oxygen. When the concentration of SF6 reaches more than 19% by volume, we need to be
particularly vigilant! Such quantity of concentration can occur in open and non-ventilated GIS rooms, closed basement and lower floor
rooms.
substances;
b) Used clothing, materials, filters, respiratory equipment, maintenance tools or vacuum cleaner, switch dust and cleaning liquids in SF6
device must be disposed of to prevent them from releasing dust and water-soluble fluoride;
c) Ensure that the skin, clothing and workplace are free from contamination. If the skin is stained with any dust, it should be washed
d) Thoroughly wash face, neck, arms and hands with plenty of water at the break of working or after the task is completed;
e) Food, beverage, cigarette or stored food is forbidden to be brought into the room with open SF6 device containing dust concentration
switch;
D.6.3.2 The requirements for all environments in GIS room are as follows:
a) Well ventilation must be provided, and significant ventilation effect must be ensured on the ground floor;
b) It must be ensured that there is no open fire or hot surface near the workplace;
c) Each gas chamber can be opened only after SF6 is recovered and reduced to atmospheric standard;
d) The maintenance equipment used for closed system operation must be used to fill gas into and recover the SF6 unit. After docking
the GIS equipment with SF6 recovery unit, the air tightness of the connection must be checked.
b) Do not expose to dust and decomposition products, and wear dust-proof clothes, gloves and goggles;
c) Use a special vacuum cleaner filled with micron filter to clean the dust;
e) Wash the decomposition accompaniment and contaminated equipment and clothes with clean water. Neutralize the waste water
with baking soda (NaHCO3) before discharge to make its pH value reach 7~8.
51
D.6.5 Medical measures
In case of asphyxia, the victim shall be immediately carried out of the contaminated area for appropriate treatment at the first
time. At any time, the symptoms of such poisoning and the risk of delayed treatment must be explained to the doctor.
b) SF6 recovery and treatment unit shall be equipped with air storage tank;
g) First-aid equipment.
chamber;
c) Cotton gloves;
d) Oversleeves;
d) Double-layer plastic waste bags and plastic containers for placing used cleaning materials;
f) High-power vacuum cleaner with fine dust filter adsorbing 0.3um particles;
required, an accurate pressure gauge shall be used during gas-filling. Other pressure readings can be read through the density relay. The
a) Carefully dry the gas-filling equipment to prevent moisture from entering the air chamber;
b) If the charging gas pressure to the air chamber is too high, overpressure alarm or rupture of explosion-proof membrane is susceptible,
c) The gas should be filled at a slower speed to avoid inhaling dust or freezing the gas-filling valve.
52
D.7.2 Interpretation of density relay readings:
a) The effect of temperature compensation is accurate only at the minimum operating pressure. If the pressure is other than the
minimum operating pressure, the pointer is unable to accurately point to the corrected pressure value at 20℃;
b) If the relative pressure standard gauge is used for gas-filling, the relative pressure shall be calculated and the ambient temperature
D.8 Gas-filling
D.8.1 Before gas-filling:
a) Put in adsorbent;
c) Vacuum pumping;
b) Close the air chamber as soon as possible after installation and vacuumizing. If the gas-filling operation is delayed, fill the air chamber
with SF6 gas at pressure of higher than the atmospheric pressure before disconnecting the vacuum pump.
c) Ensure that condensation does not occur before opening the air chamber or when allowing air to enter. When the temperature of air
chamber is lower than or equal to the ambient temperature, internal condensation is likely to occur.
D. 8.3.2 Start vacuumizing and leak detection, and fill in with SF6 gas to rated pressure
D. 8.3.3 Measure and record the moisture content
D.9 Leakage Rate Measurement
D.9.1 There are many methods for leak detection of GIS products. while CHINT Electric adopts the partial binding method.
D.9.2 Partial binding method
D. 9.2.1 Binding methods at several common parts for partial binding and leak detection:
a) Flange connection part of tank body: Wrap the flange connection part of tank body with plastic cloth, firmly seal the middle opening
with adhesive tape, and firmly and tightly bind both ends to the tank body with adhesive tape;
b) Crank arm box of isolating switch, earthing switch and Circuit Breaker: Wrap the whole crank arm box with a plastic bag sealed at one
end, and bind the open end firmly and tightly on the tank body with adhesive tape;
c) End cover plate: Wrap the whole crank arm box with a plastic bag sealed at one end, and bind the open end firmly and tightly to
D.9.2.2 Matters requiring attention for partial binding and leak detection:
a) The plastic cover (Bag) may not have any hole;
53
d) The Inspector shall be earnest and responsible, and the testing equipment and instruments must be sound and reliable.
54