Technical Specifications for 10 Kva on-line Ups Systems

The document outlines the technical specifications for a 10 KVA on-line UPS system, detailing requirements such as technology, input/output voltage, efficiency, and protection features. It emphasizes the need for parallel configuration capabilities, battery backup, and compliance with specific performance metrics. Additionally, it mandates testing and certification by the manufacturer to ensure adherence to the outlined specifications before acceptance by the bank.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views7 pages

Technical Specifications for 10 Kva on-line Ups Systems

The document outlines the technical specifications for a 10 KVA on-line UPS system, detailing requirements such as technology, input/output voltage, efficiency, and protection features. It emphasizes the need for parallel configuration capabilities, battery backup, and compliance with specific performance metrics. Additionally, it mandates testing and certification by the manufacturer to ensure adherence to the outlined specifications before acceptance by the bank.
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 7

TECHNICAL SPECIFICATIONS FOR 10 KVA ON-LINE UPS SYSTEMS

Vendor has to duly fill the Technical Specification, attach their catalogue and mark the model in the catalogue.

S.No SBI REQUIREMENT VENDORS OFFER / Confirmation


1. Technology a) UPS systems with pulse width modulation (PWM)
technology in True On-line Configuration, with double
conversion using IGBTs in the Inverter and converter.
b) Provision for configuring three or more UPS system in
parallel load sharing mode. Maximum six nos UPS system
can be connected in parallel configuration in one cluster.
c) The requirement is for fully rated capacity of single
module in parallel with similar module sharing the load
having provision for adding one or two modules of similar
units. Paralleling of UPS should be achieved by paralleling
the output on the power side using control logic signal bus.
Each UPS should be capable of individually starting,
running and feeding to the load apart from parallel
operation.
 Individual battery back up is necessary.
 Inverters should be synchronized with common by
pass supply if required
 can be connected in parallel for forming N + 1
(Configuration)
2. Inversion Technique Adaptive pulse width modulation or sine weighted pulse
width modulation with high switching frequency (> 12
KHZ for IGBTs).
3. Input Voltage Range Three Phase 400 Volts + 15%
There should be input to output Isolation through a inbuilt/
separate Isolation transformer.
4. Input frequency 45 Hz to 55 Hz and it should be compatible with D G Set.
5. Output voltage 220 / 230 V.A.C. + 1% single phase .
6. Output frequency 50 Hz +/- 4% (Synchronous to mains)
50 Hz +/- 1% (Free running)
7. Power factor The UPS shall be provided with Auto input P.F.
correction system to obtain P.F. 0.95 to unity when the
connected load P.F. varies from 0.6 to unity.
8. Total Harmonic < 4% for non-linear load
Distortion (o/p voltage)

9. Total Harmonic < 10% at 50% load.


Distortion (Input < 5% at full load.
current)
10 Waveform (output) Sine Wave
11 Overload capacity 110% for 10 During the test or actual condition, the
minutes load should not get transferred to
150% for 1 minute mains through static switch.
12 Transient response and For 100% Step load i.e. from full load to no load and no
voltage recovery time load to full load :.
for step load Dip < 3%
Peak < 3% with recovery time within 3 cycles to normal
output voltage.
13 Efficiency: It is the Minimum overall Efficiency at % load
ratio of output power in At 100% i.e full load At 66% At 33% load
KW of UPS to the 90% 88% 86%
input power to the Penalty for lower efficiency: If the overall efficiency is
isolation transformer & found to be less than the Bank’s specified value, the UPS
UPS with battery is to be rejected and replacement passing the test to be
disconnected, or, obtained. No further tolerance is permissible.
battery charging power
added to the output.
The overall efficiency
is found to be less than
the Bank’s specified
value, the UPS is to be
rejected and
replacement passing
the test to be obtained.
No further tolerance is
permissible.

14 Rated KVA 10KVA; The UPS should be capable to deliver rated KVA
at 0.8 P.F. i.e 10 KVA UPS should be capable to deliver 8
KW load at 0.8 p.p. (output)
15 Operating Temperature should be designed for delivering rated KVA at ambient
temperature from 0 to 40 Degree Celsius.
It should also be capable to deliver approx. 80% of rated
output at 50 degree Celsius ambient temperature.
16 Relative Humidity Upto 95% at 35 degree Celsius non-condensing
17 Noise level At 1 meter from the UPS.
< 65 decibels
(On demand Proto-type test certificate be submitted).
18 Charger Built in IGBT based solid state float-cum-boost charger
with automatic boost/trickle charge modes with current
limiting features. The charger characteristics shall be such
as to match the float/boost charging of the batteries as per
battery characteristic, for enhancing the life of batteries.
The charger should be designed for 2 hours back up period
at rated KVA
19 Crest factor >3

20 Interface facility The UPS system should have necessary hardware and
software with RS-232 port to work on DOS/SCO Unix
(open screen) Novell / Network/ Current & advanced
window operating system. It should be compatible for
connecting to Building Management System.
(B) Remote manageability through SNMP facility. There is
a facility to monitor and broad cast to server wherever
necessary condition such as :
i) Power failure, back up time, low battery warming & auto
file closure.
ii) The software should be capable of automatically closing
the files (auto closure feature) in the server so that the data /
program files on the server are not lost/ corrupted.

21. Remote Indication unit In system/systems Administrator Room with indications


( It may be asked if like Mains on, Inverter ON / OFF / Faulty / Trip, Battery
required at site) Low and static by-pass ON. 25 meters inter connecting
cable to be included in price quoted.
22 Protection a). Isolation – Separate/ In-built isolation transformer shall
be provided for isolation transformer for fully isolation from
mains and surge / spike suppressors to be incorporated.
b). Current limiting protection (Fuse less Electronic). Built
in overload / short circuit protection with snubber circuits
for current limit.
c). Soft start on Inverter and charger arrangement
*d). Phase locking mechanism for UPS and mains
frequency- for 3 phase output.
e). Over voltage / under voltage protection.
*f). Short circuit protection through HRC fuses (high speed)
for devices such as IGBTs.
g). Short circuit / overload protection through MCB /
MCCB.
h). All other protection systems required for safety of UPS
system, such as over temperature protection etc.
23 *I). Thyristor based Bi-directional with change over time less than 10
Static (Auto) bye-pass milliseconds in free running mode and instantaneous in
switch synchronous mode from Inverter to bye-pass and vice-versa

II). Manual by-pass Should be provided.


switch
24 Indications a). Mains ON with phase indication for single phase / 3
phase separately for all the phases.
b). Inverter ON / OFF / FAULTY / TRIP (Reason)
c). Battery Low
d). Static by-pass ON
e). Over temperature
f). Earth Leakage
25 Alarm i). Low battery alarm to be provided (ii) % load
iii) Failure of invertor
iv) mains failure / load on battery alarm to be provided.
Both should be audio visual.
v) Over temperature alarm in two stages
1st stage : Warning, intermittent audio alarm
2nd stage : Tripping, continuous audio visual and resetable.
26 Metering Digital panel Meter or LCD display system to indicate the
following
i). A.C. voltage : Input/ output
ii). A.C. current : Input/output or % load
iii). D.C. battery voltage
iv). D.C. Charging / discharging current
v). Frequency – Input/ Output
27 Battery set i) Complete with self standing cubicle or cabinet
A. SMF Batteries (To ii) Make like : Exide/ Panasonic, CSB, Numeric/ Amararaja
be installed in Rocket/ New Max , U-plus , AMCO best, HBL..
ventilated/ cooled (iii) Note: Only Valve Regulated Lead Acid (VRLA) type
rooms only) SMF batteries with electrolyte In paste form are acceptable.
Any other type including calcium batteries are not
acceptable date and year of manufacturing of batteries have
to specify alongwith Sr. Nos..

Minimum VAH required as per above details is as under:

UPS Capacity (KVA) Backup required Minimum VAH required

10 KVA 120 Minutes 33216

Batter Details:

Vendor to specify, the make of battery they propose to use, they have to submit detailed literature of battery and battery manufacturers capability
etc.

Sr No. UPS Rating DC Voltage Battery AH Nos. Total VAH Make

a) The back-up time at full load shall be 120 Minutes


b). Battery set details to be indicated by the supplier:
i). D.C. Terminal voltage
ii). No. of batteries and each battery voltage
iii). Ampere-Hour capacity of each battery
c). End cell voltage for cut off shall be considered as 1.75 / cell

27. Testing:

i). The supplier shall have facilities to carry out all the tests at factory center, and tests have to be satisfactorily carried out before acceptance.

ii) Tests shall be carried out and certified by the manufacturer confirming the offered specification.

(iii) If the UPS does not conform to specifications either during factory test or at site, the Bank reserves the right to reject the same. The
successful tenderer shall then have to remove the same at his cost from site and supply a new piece conforming to the specifications.

iv). The Bank reserves the right to randomly decide to carry out testing of UPS systems at site after installation at the cost of UPS vendor, who
will be required to arrange for all the requisite variacs, maters, loads etc. and carry out the tests through vendor’s personnel in the presence of
Bank’s Officials.

I/We hereby declare that I/we have read and understood the above specification.

Place: Applicant’s Signature

Date: Stamp:

You might also like