CE8401-LN
CE8401-LN
STRUCTURAL SYSTEMS:
A system is an assemblage formed to satisfy specific objectives and subjected to
constraints and restrictions and consisting of two or more components that are interacted
and compatible. Each component being essential to the required performance of the
system. The group of components of a system may also be a system; such a group is
called a subsystem.
FRAMED STRUCTURE:
In RCC framed structure, the whole load supported on beams and slabs and then
transferred from columns to footings.
LOAD TRANSFER MECHANISM:
Any structure is made up of structural elements and non-structural elements. The
structural elements put together constitute the structural system. Its function is to resists
effectively the action of gravitational and environmental loads and to transmit the
resisting forces to the supporting ground without significantly disturbing the geometry,
integrity and serviceability of the structure. Most of the structural element may be
considered from the viewpoint of simplified analysis as one dimensional elements. A few
structural elements may require more rigorous analysis.
Floor system:
Load bearing construction is most appropriately used for building in which the
floor area is subdivided into a relatively large number of rooms of small to medium size
in which the floor plan is repeated on each storey throughout the height of the building.
These considerations give ample opportunity for disposing load bearing walls which are
continous from foundation to roof level and because of the moderate floor spans, are not
called upon to carry unduly heavy concentration of vertical loads. A cellular arrangement
is one in which both internal and external walls are load bearing and in which the walls
form a cellular pattern in plan.
SEISMIC EFFECT
An earthquake is defined as natural vibration of earth crust produced by seismic
forces. The focus is the place beneath the earth’s surface from where an earthquake
originates and the point on the earth’s surface immediately above the focus is called
epicenter. On the basis of depth the earthquake focus are generally distributed in three
general depth ranges.
1. Shallow earthquakes – 60kms
2. Intermediate earthquakes – 60-300kms
3. Deep sea earthquakes - <300kms
The type and extent of damage to structures to structures during earthquakes depends
on only the intensity, depth of focus, duration and location of epicentre but also on the
strength of building materials, structural systems, joint details of members etc., quality of
workmanship, proper anchorage of secondary elements to the main structure and soil
conditions.
EARTHQUAKE EFFECTS:
Direct Effects:
Ground Shaking
Ground Cracking
Differential ground settlement
Soil liquefaction
Lateral Spreading
Land slides
Rockfalls
Indirect Effects:
Landslide
Tsunami
Avalanches
Rockfalls
Floods Fires
Toxic Contamination
During the earthquake effect on individual would be thrown out of bed at night, be
unable to stand upright and be forced to kneel on the ground, fall downstairs, or even be
tossed out of the swimming pool by the violent sloshing of the water.
ECO-BUILDING:
Green Building: Buildings designed considering the concepts of sustainable design
and reduction of environmental impacts due to site selection, water use, energy use
materials and resources the buildings impact on the environment, and indoor air quality.
MATERIALS USED:
The selection criteria for green building material shall be based broadly on
Resource efficiency
Indoor air quality
Energy efficiency
Water conservation
Affordability
Some green building materials
Fly as bricks
Autoclaved aerated concrete terrazzo tiles
UPVC windows
Bamboo jute composite doors
Calcium silicate tiles
Construction Materials:
In this heading new definitions and attitudes about industrialization are presented
by review of new related researches with an explanatory and analytical method to extract
new directions in building industrialization included economical and social trends and
sustainable approach.
The points regarding economy factory production and consistency are as followings:
General organization of continuous production of a product applying similar
knowledge and experience instead of new group formation for each project.
Simplicity of process and reduction of the some of the consumed energy in each
production project.
Working in factory leads to avoid of loss of time arising from climate conditions.
NATURAL BUILDING:
CREATIVE COURTYARDS:
They date back to the Harappan civilization.
They are used for socializing, religious matters and family meetings.
The purpose of the courtyard varied based on the occupation of the family as well.
In large homes, there may be as many as five or six courtyards and each had a
different function.
Home is where health is. Rural huts are usually not more than one room big. As
soon as you enter such a house the first thing you will notice will be the most important
part of the house the kitchen. Cooking and eating takes place on the floor, with entire
family sitting together for meals. They use cow dung cakes wood and bio gas. Utensils
are neatly stacked and are usually of terracotta steel or copper.
Pretty Puducherry
Puducherry is famous for the colonial French and franco-tamil architecture. The
French styled architecture is suited for this town because of the weather with its long and
huge windows with helical vertical cast iron bars as grills ornate balconies large
courtyards, circular arched gates and stucco designs. They have flat roofs an inner
courtyard with garden and colonnaded portions that serve a double function of protection
from the sun and rain.
PASSIVE BUILDINGS
Basic principles:
Basic principles of passive design-I
The objective of this class is to find out the method of passive heating using solar
geometry study the process of passive cooling and shading as one of its methods help
understand the importance of the day lighting in design as a primary element is to study
the importance of materials in sustainable design as well as the crucial element of indirect
lightening.
Basic principle of passive design – 2
What does passive cooling mean? As much as possible passive cooling uses natural
forces energies and heat sink since the goal is to create thermal comfort during the
summer we can either cool the building by removing heat from the building by finding a
heat sink or by raising the comfort zone sufficiently to include the higher indoor
temperature by increasing air velocity so that the comfort zone shift to higher
temperature.
INTELLIGENT BUILDINGS:
In addition to incorporating the major system previously described, intelligent
buildings through the use of computers and communication equipment have the ability to
control the total building environment the equipment & operating personal can be
stationed in a so-called control center or the equipment can be monitored and controlled
remotely via a computer, modem and telephone line.
Various sensors and communication devices feeding information to and from the
control center are located in key areas throughout the building for the purpose of
analyzing and adjusting the environment delivery messages during emergencies and
dispatching repair personal and security guards as needed. To conserve energy lighting
may be operated by sensors that detect people movement HVAC may be adjusted in
accordance with temperature changes. Elevators may be programmed for efficient
handling of variations in traffic patterns and may be equipped with voice synthesizers to
announce floor steps and give advice in emergencies.
SMART SOLUTIONS:
Are not able to inter operate with other vendors solutions without additional
overheads locking customers to specific product lines a major issue if such lines get
discontinuous
Are too complex to be used by non specialized personnel whether they are end-
users or system developers.
Only perform satisfactorily in the exact conditions they were tailored for not
performing so well if the working environment changes thus lacking flexibility and
Do not cover all the desired functionalities expected in a BAS.
DESIGN FEATURES:
Air heating panels designed as an integral part of the south wall
Provide effective heat gain. Distribution of heat gain in the building through a
connective loop that utilizes the stairwall as a means of distributing heated air.
Double glazed windows with proper sealing to minimize infiltration.
Insulated RCC diaphragm walls on the north to prevent heat loss and solar
chimney.
Specially designed solarium on south for heat gain.
UNIT II CONSTRUCTION PRACTICES
Specifications, details and sequence of activities and construction co-ordination – Site
Clearance – Marking – Earthwork - masonry – stone masonry – Bond in masonry -
concrete hollow block masonry – flooring – damp proof courses – construction joints –
movement and expansion joints – pre cast pavements – Building foundations – basements
– temporary shed – centering and shuttering – slip forms – scaffoldings – de-shuttering
forms – Fabrication and erection of steel trusses – frames – braced domes – laying brick –
– weather and water proof – roof finishes – acoustic and fire protection.
FOUNDATIONS
The foundations of the building transfer the weight of the building to the ground.
While 'foundation' is a general word, normally, every building has a number of individual
foundations, commonly called footings. Usually each column of the building will have its
own footing.
Since the weight of the building rests on the soil (or rock), engineers have to study the
properties of the soil very carefully to ensure that it can carry the loads imposed by the
building. It is common for engineers to determine the safe bearing capacity of the soil
after such study. As the name suggests, this is the amount of weight per unit area the soil
can bear. For example, the safe bearing capacity (SBC) at a location could be 20 T/m2, or
tonnes per square metre.
This capacity also changes at different depths of soil. In general, the deeper one
digs, the greater the SBC, unless there are pockets of weak soil in the earth. To properly
support a building, the soil must be very firm and strong. It is common for the soil near
the surface of the earth to be loose and weak. If a building is rested on this soil, it will
sink into the earth like a ship in water. Building contractors will usually dig until they
reach very firm, strong, soil that cannot be dug up easily before constructing a
foundation.
To study the properties of the soil before designing foundations, engineers will ask
for a soil investigation to be done. A soil investigation engineer will drill a 4" or 6"
hollow pipe into the ground, and will remove samples of the earth while doing so. He will
then send these samples to a lab to find out the detailed properties of the soil at every
depth. Soil is usually composed of strata, or different layers, each with its own set of
properties. Drilling technology today makes it easy and economical to drill to great
depths, easily several hundred metres or more, even in hard rock.
The soil investigation team will then prepare a soil investigation report that lists
the engineering properties of the soil at regular intervals, say every 2 meters. Based on
this deport, engineers designing the structure can decide at what depth of soil to provide
the foundations, the type of foundations they should provide, and the size of the
foundations.
Every once in a while, engineers will find fill at a site. This occurs when humans
have previously dug up the earth there, and then filled it back in. This happens if a quarry
was dug or a building built there previously. Since fill is loose and soft and cannot
support weight, engineers will dig to a depth below that of the fill, where strong soil is
found, and construct foundations there.
TYPES OF FOUNDATIONS
Broadly all foundations are divided into two categories: shallow foundations and
deep foundations. The words shallow and deep refer to the depth of soil in which the
foundation is made. Shallow foundations can be made in depths of as little as 3ft (1m),
while deep foundations can be made at depths of 60 - 200ft (20 - 65m). Shallow
foundations are used for small, light buildings, while deep ones are for large, heavy
buildings.
SHALLOW FOUNDATIONS
Shallow foundations are also called spread footings or open footings. The 'open'
refers to the fact that the foundations are made by first excavating all the earth till the
bottom of the footing, and then constructing the footing. During the early stages of work,
the entire footing is visible to the eye, and is therefore called an open foundation. The
idea is that each footing takes the concentrated load of the column and spreads it out over
a large area, so that the actual weight on the soil does not exceed the safe bearing
capacity of the soil. There are several kinds of shallow footings: individual footings, strip
footings and raft foundations. In cold climates, shallow foundations must be protected
from freezing. This is because water in the soil around the foundation can freeze and
expand, thereby damaging the foundation. These foundations should be built below the
frost line, which is the level in the ground above which freezing occurs. If they cannot be
built below the frost line, they should be protected by insulation: normally a little heat
from the building will permeate into the soil and prevent freezing.
Individual footings
Individual footings are one of the most simple and common types of foundations.
These are used when the load of the building is carried by columns. Usually, each column
will have its own footing. The footing is just a square or rectangular pad of concrete on
which the column sits. To get a very rough idea of the size of the footing, the engineer
will take the total load on the column and divide it by the safe bearing capacity (SBC) of
the soil. For example, if a column has a vertical load of 10T, and the SBC of the soil is
10T/m2, then the area of the footing will be 1m2. In practice, the designer will look at
many other factors before preparing a construction design for the footing.
Individual footings connected by a plinth beam. Note that the footings have been
cast on top of beds of plain cement concrete (PCC), which has been done to create a
level, firm base for the footing.
Individual footings are usually connected by a plinth beam, a horizontal beam that
is built at ground or below ground level.
Strip footings
Strip footings are commonly found in load-bearing masonry construction, and act
as a long strip that supports the weight of an entire wall. These are used where the
building loads are carried by entire walls rather than isolated columns, such as in older
buildings made of masonry.
Raft or mat foundations
Raft Foundations, also called Mat Foundations, are most often used when
basements are to be constructed. In a raft, the entire basement floor slab acts as the
foundation; the weight of the building is spread evenly over the entire footprint of the
building. It is called a raft because the building is like a vessel that 'floats' in a sea of soil.
Mat Foundations are used where the soil is week, and therefore building loads
have to be spread over a large area, or where columns are closely spaced, which means
that if individual footings were used, they would touch each other.
DEEP FOUNDATIONS
Pile foundations
A pile is basically a long cylinder of a strong material such as concrete that is
pushed into the ground so that structures can be supported on top of it.
Pile foundations are used in the following situations:
1. When there is a layer of weak soil at the surface. This layer cannot support the
weight of the building, so the loads of the building have to bypass this layer and be
transferred to the layer of stronger soil or rock that is below the weak layer.
2. When a building has very heavy, concentrated loads, such as in a high rise
structure. Pile foundations are capable of taking higher loads than spread footings.
There are two types of pile foundations, each of which works in its own way.
Rigid frame structures provide more stability. This type of frame structures resists
the shear, moment and torsion more effectively than any other type of frame structures.
That's why this frame system is used in world's most astonishing building Burj Al-Arab.
Braced Structural Frames
In this frame system, bracing are usually provided between beams and columns to
increase their resistance against the lateral forces and sideways forces due to applied load.
Bracing is usually done by placing the diagonal members between the beams and
columns.
This frame system provides more efficient resistance against the earthquake and
wind forces. This frame system is more effective than rigid frame system
Pin Ended Rigid Structural Frames
A pinned ended rigid frame system usually has pins as their support conditions.
This frame system is considered to be non rigid if its support conditions are removed.
Portal structural frames usually look like a door. This frame system is very much
in use for construction of industrial and commercial buildings
Load path in Frame Structure:
It is a path through which the load of a frame structure is transmitted to the
foundations. In frame structures, usually the load path is:
Load first transfers from slab to beams then to from beam to columns, then
from columns it transfers to the foundation.
Advantages of Frame Structures
1. One of the best advantages of frame structures is their ease in construction. it is very
east to teach the labor at the construction site.
2. Frame structures can be constructed rapidly.
3. Economy is also very important factor in the design of building systems. Frame
structures have economical designs.
Disadvantages of Frames:
In frames structures, span lengths are usually restricted to 40 ft when normal
reinforced concrete.
Otherwise spans greater than that, can cause lateral deflections.
Comparison of Frame structures with Normal Load bearing Traditional High Rise
Building
Selection of frame structures for the high rise building is due to their versatility
and advantages over the normal traditional load bearing structures. These include the
following:
Actually the performance of load bearing structures is usually dependent on the
mass of structures. To fulfill this requirement of load bearing structures, there is the need
of increase in volume of structural elements (walls, slab).this increase in volume of the
structural elements leads toward the construction of thick wall. Due to such a type of
construction, labor and construction cost increases. in construction of thick wall there will
be the need of great attention, which will further reduce the speed of construction.
If we make the contrast of load bearing structures with the framed structures,
framed structures appear to be more flexible, economical and can carry the heavy loads.
Frame structures can be rehabilitated at any time. Different services can be provided in
frame structures. Thus the frame structures are flexible in use.
Braced domes may be fabricated in any of several common grid configurations.
With different configurations, the dome performance varies considerably affecting both
its competitiveness and suitability for specific applications. The study presented in this
paper is an assessment of the most commonly adopted dome configurations and their
effect on the dome characteristics such as the stiffness/weight value, member stress
distribution, number of joints and members, degree of redundancy and cost. The study is
parametric and covers wide variations of dome span/rise ratio and boundary conditions.
The results of this study could be of significant value to the design of future braced dome
structures.
How to Lay Brick
1. Squared rubble masonry: The rubble masonry in which the face stones are squared on
all joints and beds by hammer dressing or chisel dressing before their actual laying, is
called squared rubble masonry.
2. There are two types of squared rubble masonry.
3. Coursed Square rubble masonry: The square rubble masonry in which chisel dressed
stones laid in courses is called coarse square rubble masonry. This is a superior variety of
rubble masonry. It consists of stones, which are squared on all joints and laid in courses.
The stones are to be laid in courses of equal layers. and the joints should also be uniform.
4. Suitability: Used for construction of public buildings, hospitals, schools, markets,
modern residential buildings etc and in hilly areas where good quality of stone is easily
available.
Begin Laying Bricks
A mason's line acts as a guide for setting bricks in perfectly straight rows. It's
made of two mason blocks with slots to hold a mason line.
Affix the blocks to either end of the row of bricks, with the line pulled tight. The
top of each brick in the row should just touch the top of the line.
Guide the Bricks
A story pole is a strip of wood that acts as a guide for laying bricks. Use a pencil
to mark the height of each course of bricks, including the mortar joints, on the pole.
Apply Mortar
Safety Tip: When working with mortar, always wear gloves and a mask or respirator.
Use a spade trowel to apply a generous amount of mortar to each layer of brick. Score a
line through the center of the pile of mortar to allow it to spread. "Butter" the brick with
mortar, spreading mortar on the sides that will affix to the bricks beside them. Use the
handle of the trowel to knock each brick into place and to release any air bubbles that
may be in the mortar underneath.
Remove Excess Mortar
Using the sharp end of the trowel, scrape off any excess mortar that spreads beyond the
joint.
Finish cleaning off any other debris with a brush. Holding a spade trowel at a 30-degree
angle, carve small lines between the bricks and the mortar. The lines will help protect the
wall from the effects of precipitation.
Cut Bricks
Most walls require smaller bricks at their ends. Before cutting a brick, place it in a bed of
sand or dirt to absorb the shock of the blow. Place the sharp end of a brick chisel at the
line where you want to cut. Use a hammer to tap the end of the chisel, scoring lines on all
four sides where the brick must be cut.
After scoring the lines, hold the chisel on one of them, slightly angled toward the side of
the brick that will be kept and used on the wall. With your other hand, strike the handle of
the chisel with a hammer. The blow should break the brick cleanly in two.
Construction chemicals providing strength to construction industry
Waterproofing begins to fight weak monsoon
Chettinad Cement to acquire AP-based Ajani Portland Cement
Cement firms remain pessimistic after bad Q2 run
BASF to build centre for flooring and waterproofing systems in Germany
Waterproofing of building to prevent the ingress of water is an activity, which, perhaps is
practiced in one form or the other, ever since the first building was built on earth. The
methodology has been changing with the changes in the architectural designs and with
the availability different building materials in construction.
In the initial stages when stone was the main building construction material placed
in position with mud or lime mortar the emphasis used to be to make the construction in
such a way that the rainwater does not collect on the roofs. Hence old architecture relied
mainly on dome structures or slanting roofs. The slow speed of such construction and
unaffordability of common man to build such structures for their own dwelling, made
constant evolution and development in the construction material technology.
With these developments the concepts of waterproofing also changed. Now in
present day construction wherein the ordinary Portland cement and its blends with
pozzolanic and slag materials has come to stay a lot of compatible alternatives are
available for a builder to choose from various waterproofing systems. Some systems are
old and conventional but still practiced successfully and some are modern systems
designed taking the material and structural behavior into consideration.
There are some compounds, which are used in plastic concrete to make it less
permeable to water. These compounds are known as integral waterproofing compounds.
They are based on plasticizing and air-entrainment or water repellence principles. These
are used as a good waterproofing precautions when other factors such as good mix-
design, proper mixing/placing, compacting/curing etc are taken care of. This subject of
integral waterproofing compounds requires in depth discussion hence will not be taken up
here. Similarly there are some water proofing techniques for vertical surfaces. These
techniques are also used for preserving heritage buildings by stopping/minimising the
aging process of these buildings.
For solving water seepage problems, customers use both conventional as well as
modern waterproofing techniques.
Some of the old and conventional waterproofing systems are as follows:
Brick bat coba system or lime terracing
Bituminous treatment
Metallic sheet wrapping
Polyurethane based waterproofing treatment
Epoxy based waterproofing treatment
Box-type waterproofing system
Brick bat coba system
This system was developed during the initial stages of flat roof construction with
lime mortar burnt clay brick pieces. This system involved laying lightweight mortar on
the roof and spreading it to give gentle slopes for draining away the rainwater
immediately. The mortar consisted of lightweight brick pieces as aggregates and ground
brick with lime as binding matrix.
During British rule this system became more popular not because of its water
proofing efficiency but because of its efficiency in keeping the interiors cool. Some
applicators developed better skills in laying these systems, with neatly finished top with
lines engraved on top of plastic mortar now known as IPS.
Some practiced embedding broken tile or ceramic pieces in the plastic mortar and
called it china mosaic.
This type of system remained most popular with multi-storeyed construction in all
major cities. The system lasts up to 15 years if done by skilful applicators. This system
may be considered more from its weather proofing abilities rather than its waterproofing
qualities. Once water starts entering into the brickbat coba the brick pieces absorb too
much of water and the roof becomes an invisible pond of water continuously causing
leakage and increasing burden on the roof slab. It will be highly beneficial if brickbat
coba is laid on a flexible waterproofing membrane as water proofing as well as
economical weather proofing can be achieved with this system.
Bituminous treatment
Discovery of petroleum and its products and by-products has given the
construction industry an indispensable product in the form of bitumen. Bitumen is more
commonly used in the form of felt or flexible membrane formed by sandwiching jute
fabric or fibreglass/polypropylene mats with chemically modified bitumen. These
membranes are laid on the roofing over a bitumen primer. There are two types of
membranes one is cold applied and the other hot applied which means one needs to heat
the edges of the felt with a torch so that they melt and stick to the second layer in the
overlap area.
On the RCC flat roofs the bitumen felts have not been successful because of the
unacceptable black appearance and inaccessibility of the terrace for other social uses.
Technically it is not preferred because bitumen layer or felt on the terrace not only makes
it watertight but also airtight. Concrete has the breathing property. It takes water/moisture
and breathes out water vapour. Hindrance of this breathing property of concrete develops
pore pressure, which causes blisters in the felt.
After a few seasons the blisters multiply and eventually delaminate the felt from
the concrete surface. Hindrance of breathing property of concrete makes the concrete
weak. But on the asbestos cement sheets and zinc sheets in factory roofs, this bitumen felt
is the only dependable waterproofing system. Hence all factory roofs in India adopt this
water proofing system.
Bitumen is very effective in waterproofing of basements from outside. Bitumen
primers have very successfully been used as damp-proof course in earlier days. This
practice is slowly discontinued for whatever reasons now very few engineers now believe
that this was in practice once. As consequence of this absent DPC we have a lot of cases
of rising dampness, which we tend to attribute to wrong reasons such as the quality or
salinity of sand etc. Bitumen still is the product of first choice where it is commonly
recommended, in areas such as industrial roof waterproofing, basement waterproofing,
and damp-proof course. More over bitumen is the most economical product available for
waterproofing.
Metallic sheet wrapping
Because of the non-existence of suitable expansion joint filling compounds before
the discovery of polysulphides, a complex procedure used to be adopted to treat
expansion joints, in concrete dams and such huge structures utilising thick copper sheets.
An extension of this practice was to try thin foils of copper and aluminium for wrapping
the concrete surfaces with nagging leakage problems.
Unavailability of common joining material for these metal foils and the concrete
and mortar created weakness in the system at the joints. This discouraged the system in
its infancy only. But there after the metal manufacturers have been trying to market this
type of waterproofing system with improved adhesives as and when the metal market
slumped.
Polyurethane based waterproofing treatment
Polyurethane consists of two liquid components one is called the base component
and the other is called reactor or curing agent. Base is a polyol and the reactor is an
isocyanide such as TDI or MDI. There are various grades of polyols and so also there are
numerous isocyanides. The combination of these two ingredients results in a formation
liquid applied rigid membrane or a foam depending upon the selection.
In waterproofing, this rigid liquid membrane was tried with fibre glass reinforcing
mats. The systems failed because coefficients of thermal expansion of concrete and rigid
PU membrane being different lateral movement or creep occurred with the passage on
one working climatic cycle. When exposed to ultra violet rays or direct sunlight most
polyurethane rigid membranes became brittle and crumbled.
Apart from this the application of polyurethane coating needed very rigorous
surface preparation. The surface needed to be neutralized by removing alkalinity from the
concrete surface through acid itching then washing and blowtorching to make the surface
bone dry. This kind of surface preparation with acids angered the civil engineering
community and the product ceased to be used as waterproofing material apart from its
several failures. Never the less continuous research in the polyurethane technology gave
the construction industry excellent sealant for glazing industry and foams for thermal
insulations. The new generation polyurethanes, which are alkali stable and water-based,
may find better applications in waterproofing industry.
Epoxy based waterproofing system
Like polyurethane is also a two-component system having a base resin and a
reactor or curing agent. Base resin is obtained by dissolving bis-phenol a flakes in
epichlorohydrin. This base is available in various viscosity ranges to suit different
application conditions. The curing agent is an amine/polyamine aliphatic or aromatic, or
an amine-adduct for general applications and polyamide or an amino-amide for coating
purposes. After mixing base and reactor components the resultant viscous liquid or paste
if some fillers are added to it can be brush applied like a paint or trowel applied like a
mortar.
Here also epoxies notwithstanding the alkalinity of concrete and the concrete
needs to be acid washed and neutralised, which the civil engineers hated. Here again the
coefficient of thermal expansion of concrete and epoxy being different the compatibility
of epoxy in waterproofing exposed concrete surfaces such as roofs became limited. Later
the use of epoxy in waterproofing was discarded. But epoxies have come to stay in civil
engineering industry as bonding agents, floor & wall coatings, coatings for food
processing units, operation theatres and computer and pharmaceutical industries.
Box type waterproofing
This type of water proofing system is used only for basement waterproofing or
waterproofing structures below the ground level from outside to prevent leakages of
subsoil water into the basement.
In this method, limestone slabs (Shahabad Stones) are first laid in the excavated
pit over blinding concrete in a staggered joint fashion to avoid the continuity of the
mortar joints. The joints are effectively filled with rich mortar admixed with integral
waterproofing compound and cured. Over this the raft is laid and shear/brick walls
constructed. The limestone slabs are erected around the walls in a similar fashion leaving
a gap of one to two inches between the external surface of the wall and the inner face of
the stone surface. The joints again effectively sealed with rich admixed mortar and the
same mortar is filled in the gap between the wall and the stones. This stonework is
continued up to ground level. In this system the raft and the sidewalls are protected from
direct exposure to sub soil water.
This system works on two principles of common sense. First, the area exposed to
subsoil water is only the area of the joint where as the whole stone is impervious to water,
hence only a fraction of area, that is, that of the joint is exposed to subsoil water, when
the joint itself is filled with rich and quality mortar.
Second, the path of water to reach the raft or the sidewall is elongated. This
elongated path is through quality mortar. This system seeks to delay the occurrence of
leakages in the basements. A lot of building structures are waterproofed by this system. A
few notable successes are to its credit especially in five star hotels and of-course there are
a few failures as well.
Types of Roofs finishes
Several types of roofs are available for residential construction. Different
materials are chosen according to their various qualities, advantages and disadvantages.
Roofing a house is quite a cost-intensive affair and you need to be prepared with sound
information prior to making your investment. Here s an overview ‟ of some of the most
used types of roofing:
1. Wood Shingle Roofing
Wood shingles are also known as shakes and they are especially ideal if you
appreciate naturally beautiful looks. They will gracefully age with your house while
retaining their aesthetic appeal.
Wood shingle roofing is quite expensive though it makes up for the cost with its
durability. Most people have concerns with this type of roofing especially with issues like
fire, splitting, rotting and molding. Always invest in shingles that have been treated with
special protective glazes and finishes.
2. Slate Roofing
Another beautiful yet very costly roofing material is slate and is especially
appropriate if your house is in the French or Colonial design style.
Slate roofing is ideally composed of thin layers of rock and as such the roof is
bound to be quite heavy. For this reason it is advisable to first put in place adequate
structural support. Laying this type of roof can be quite complicated for a DIY project
and the installation is better off when done by a licensed contractor.
3. Tile Roofing
Tile roofing is an option that goes very well with your house if it is in the Spanish or
Mediterranean design. There are two types of roofing tiles: clay tiles and concrete tiles.
Tiles are generally laid down on relatively new houses that have adequate structural
support since tiles, like slates, are quite a heavy load. The services of a professional
contractor will come in handy if you are not confident about taking on the task yourself.
Tile roofing is also quite costly but if properly maintained it can give proper service for
up to 50 years.
4. Metal Roofing
Metal roofing options are fast gaining a good reputation in building circles despite their
initially high costs. These roof types boast durability as well as low maintenance qualities
that extend their life beyond other conventional roof types.
5. Asphalt Roofing
Certainly the most affordable of roofing types has to be asphalt. Asphalt shingles that are
made from the conventional highway asphalt are the least expensive. You can also invest
in the costlier option that is known as architectural shingles.
Acoustic, Thermal, Fire and Safety
Acoustic
Noise reduction is an increasing priority in both new build and renovation
projects.
Thermal
With an impressive array of products, in both roll and batt formats, to suit every
conceivable application and a wide range of lambda values the Isover thermal insulation
range is second to none.
Fire & Safety
All of our glass mineral wool products are non-combustible, have the highest
possible Euroclass A1 fire rating classification, and do not produce any toxic fumes in the
event of fire.
Many are also fire rated, offering added protection against fire and providing vital
time for building occupants to evacuate.
UNIT III SUB STRUCTURE CONSTRUCTION
BOX JACKING
It is the process in which a pre-cast R.C.C box or a rigid box is pushed into the soil with
the help of hydraulic jacks
It is non-intrusive method beneath the existing surface.
It is more often used when a subway or a aqueduct or a underground structure is to be
constructed.
It enables the traffic flow without disruption.
R.C.C BOX JACKING
First the box section is designed and cast at the site or can be transported to the site
according to the requirement.
The foundation boxes are jacked into the ground designed to carry the dead and the live
loads.
Then the high capacity jacks are placed at the back and it pushes the box into the ground.
A purpose designed tunneling shield is provided in the front end.
Then the box is jacked carefully through the earth.
Excavation and jacking are done in small increments in advance.
Measures should be taken to prevent the soil being dragged towards the box.
METHODS OF BOX JACKING
Box Jacking
Non –intrusive method beneath existing surface infrastructure
Frequently used where an existing road or rail tracks is an embankment and space exists
for the structure to be cast at the side
Enables traffic flows to be maintained disruption
Procedure
It involves the advancement of a site-cast rectangular or other shaped box using high
capacity hydraulic jacks.
An open ended reinforced concrete box is cast on a jacking base.
A purpose designed tunneling shield is provided at its leading end and thrust jacks are
provided at its rear end reacting against a jacking slab
The box is then jacked carefully through the ground
Excavation and jacking take place in small increments of advance.
Measure are taken to ensure stability of the tunnel face and to prevent the ground from
being dragged forward by the advancing box.
When the box has reached its final position the shield and jacking equipment are
removed.
R.C.C box jacking
Is adopted where it is not possible to constructed in situ R.C.C boxes
These boxes are used for canal siphon, road under bridge and culvert for conveying
water/service pipes
The R.C.C box is cast over the thrust bed which is provided with –pockets both in
longitudinal and traverse jacks
The box is provided with a shield in front in front called “Front shield” Which pierces
through the soil by cutting
Thrust boring method
Is a process of simultaneously jacking pipe through the earth while removing the soil
inside the encasement by means of a rotating auger.
In unstable soil conditions, the end of the auger is kept retracted back inside the
encasement so as not to cause voids.
In stable conditions, the auger can be successfully extended beyond the end of the
encasement.
TUNNEL BORING MACHINE
Tunnel boring machine (TBM) as mole recent developments in the tunnel driving
technique. The function of TBM is to loosen the earth or break the rock continuously in
the entire section of the tunnel, in to cuttings and convey to the rear of the machine,
where it can be loaded into muck cars or dumpers or on to conveyor belts for the
transportation to the ultimate disposal site.
Working principle and construction features of TBM
These machines perform the boring operation through rotation of the front head
against the rock face. The mole has circular cutter head in the front provided with fixed
cutters of desired shape. The cutter head while rotating is pressed against the rock to cut
or pulverize it. The cuttings while failing down is collected in the buckets provided
around the cutter head periphery.
These buckets discharge the muck into a hopper to feed it into the belt conveyor
leading to the rear of the machine. This conveyor then discharges the muck either into the
mine car or to another belt conveyor leading to the portal of the tunnel. The muck of
cuttings can also be disposed off by using the slurry pipelines after mixing the fine muck
into water to form slurry.
For driving through full- face on full-face TRMs number of cutter heads is
mounted on a drum. The drum when rotates in one direction, the individually driven
cutter heads having projected Tungsten carbide tipped tools can be rotated in another
direction and the drum advances into the tunnel face, by providing a thrust with the help
of hydraulic systems. The tips of the tools when worn out can be easily replaced. The tips
are kept cooled by spraying a mixture of water and compressed air into the cutting area.
This also suppress the dust formed during cutting.
Advantages of tunnel boring machines
There is very less danger of fall outs in machine bored tunnels, since adjacent or
surrounding rocks are undistributed as no blasting is done.
Mucking is also safe and convenient, since muck is conveyed from the face to the rear of
the machine and is loaded automatically by means to the rear of the machine and is
loaded automatically by means of belt conveyors.
Higher speed of excavation.
Reduction in the tunnel supports requirement.
Less manpower requirement.
Various types of tunneling technique
Tunneling techniques are
Drill Jumbo
1. Drill jumbo
2. Loading and firing
3. Drilling
Drill jumbos used in tunnels are also known as tunnel jumbos. A drill jumbo is a
portable carriage having one more carriage having one or more working platforms
equipped with columns, bars or booms to support and guide the drills, enabling the drills
to perform drilling operation at any desired pattern. These platforms have arrangement
for the supporting the compressed air pipes, water pipes. The booms are operated by
hydraulic fluid or air and supports the drifters, and are equipped with control enabling the
operator to spot a drill in any desired position conforming to the drilling pattern. The
platforms are constructed as per the size of tunnel and can be raised or lowered so as to
allow mockers or hauling equipment to pass under the jumbo several drill can be operated
from each platform for speedy excavation. The jumbos either on rails on pneumatic tyres
depending upon the type of work. The jumbo can be equipped with electricity feeding
cables, pneumatic concrete placers etc. Mobile jumbos of modern design with four wheel
drive and centrally articulated steering speeds production and reduces tunneling costs
Loading and firing
Drilling pattern when followed produces most economical and efficient breakage
of rock for a given tunnel, and is determined by conducting tests using different patterns.
Explosive selected for working in tunnels should have low fumes characteristics.
Ammonium nitrate explosives are therefore preferred over dynamics due to less toxic
fumes.
Drilling
For driving a tunnel number of holes are drilled as per drilling pattern in size and
depth as decided depending upon the size of the tunnel and its formation Drifters are
generally used for drilling in the tunnels where in water is used to remove the cuttings
from the holes instead of compressed air to reduced the amount of dust in the air. Holes
are drilled slightly deeper than the advance per round to taken care of loss in depth during
blasting. Depth advanced due to drilling and blasting operation is called as one round.
ARCHED JACKING
THRUST BORING METHOD
It is a process of simultaneously jacking the pipe through the earth while removing
the earth inside the box by means of a rotating auger.
Unstable conditions- the end of auger is kept retracted inside the encasement so as
not to cause voids.
Stable conditions- the auger can be successfully extended beyond the encasement.
This can be successfully used in any kind of soil conditions.
PROBLEMS ENCOUNTERED IN JACKING
Settlement of the above ground.
Seepage of ground water.
Caving in of soil etc.
FREEZING OF GROUND
This method is used when we encounter the problem of ground water seepage and
settlement of ground.
In this method a brine solution is continuously passed through the pipes fixed in
the soil.
The temperature of the brine would be -30°c.
So when this brine solution is circulated through these pipes it freezes the ground
and the ground behaves like an ice block.
The spacing of the freezing pipes will vary according to the type of soil, its
permeability and other factors.
Generally it is kept at a spacing of 1.2 m
PROBLEMS IN FREEZING
The main problem in the freezing method is the up heaving of the above ground.
To avoid the upheavement problem we should be careful in the ground freezing
process and the temperature of the brine solution.
CASE STUDY - SOUTHERN BOSTON PIERS TRANSIT WAY
The carriageway has to go beneath – a Russian building, 100 years old 2m thick
soil was frozen.
Under pinning was also done using mini piles.
ADVANTAGES
Timely completion of project.
No disruption of traffic.
No need to divert the traffic.
DISADVANTAGES
Cost of project increases.
Skilled personnel required.
Safety precautions to be done properly.
PIPE JACKING
DIAPHRAGM WALL
Diaphragm wall are structure elements, which are constructed underground to prevent the
seepage into the excavated area
Various methods adopted to construct a diaphragm wall
Slurry trench technique
1. Soil mixing method
2. RC continuous diaphragm wall
3. Precast diaphragm wall
4. Glass diaphragm walls
Slurry trench technique
The technique involves excavating a narrow trench that is kept full of an
engineered fluid or slurry. The slurry exerts hydraulic pressure against the trench walls
and acts as shoring to prevent collapse. Slurry trench excavations can be performed in all
types of soil even below ground water table.
Soil mixing method
This is the method used to make continuous walls by churning up piled soil using
an auger, pouring in cement milk and marking soil mortar columns in the ground using
the soil as aggregate. This is an in situ mixing and churning method. In the method after
completing excavation of the groove wall using an excavator, soil cement is produced by
mixing and churning excavated soil. The excavated soil is classified and graded with
cement milk after being put through a tremie. Then the soil cement is poured into the
groove wall, after which the steel material is built as the core material.
RC continuous diaphragm wall
This method of building a very long continuous diaphragm wall. Excavate a given
groove between the surface and underground using a stabilizing liquid. Insert a given
steel bar pour in concrete, thereby building a reinforced concrete wall underground.
Precast diaphragm wall
With this method, a continuous trench or longer panels are excavated under self
hardening cement- bentonite(CB) slurry.
The precast concrete wall sections are lifted and positioned by a crane
The CB slurry sets to form the final composite wall
The trench is excavated under bentonite slurry, which is then displaced with CB slurry.
Glass diaphragm walls
For contained enclosure, a diaphragm wall system consisting of special glass panels with
a sealing made out of glass are used.
The panels are 50cm wide and upto 15cm long
Common uses of diaphragm wall walls
To provide structural support for the construction
To provide retaining wall
To provide deep diaphragms
Applications of diaphragm wall
As permanent and temporary foundation wall foundation walls for deep foundation for
deep basements
In earth retention schemes for highway and tunnel projects
As permanent walls for deep shafts for tunnel access
As permanent cut - off walls through the core of earth dams
In congested areas for retention systems and permanent foundation walls
Deep groundwater barriers through and under dams
CAISSON
Caisson has come to mean a box like structure, round or rectangular, which is suck
from the surface of either land or water to some desired depth. Caissons are of three
types:
(a) Box caisson
(b) open caisson
(c) Pneumatic caissons
Box caisson
A box caisson is open at top and closed at the bottom and is made of timber,
reinforced concrete or steel. This caisson is built on land, then launched and floated to
pier site where is suck in position. Such a type of caisson is used where bearing stratum is
available at shallow depth, and where loads are not very heavy.
Types of well point systems
1. Pumping from open sumps
2. Pumping from well points
Well point systems are installed in two ways:
Types of piles
a) Line system
b) Ring system
3. Pumping from bored wells
(a) Driven piles – Timber, recast concrete, Prestressed concrete , steel H-section, Box and
tube
(b) Driven and cast-in place piles
(c) Bored piles
(d) Composite piles
Use of H-piles
H-Piles are used in construction of bridges where they can be driven through
existing construction in small spaces. They are used useful for driving close to existing
structures since they cause little displacement of soil. It can be withstand large lateral
forces. They require less space for shipping and storing than wood, pipe or precast
concrete piles. They do not require special slings or special care in handling.
DEEP EXCAVATIONS
Problems normally developed during deep excavations
To prevent the collapsing of sides of the trenches
To prevent water oozing or coming out from the sides and bottom of the trenches
The remedial measures to avoid the problems deep excavation
Providing shoring for the trenches
Dewatering of the trenches
Line system
This system is employed when excavation area is long. The header is laid out
along the sides of the excavation, and the pumping is continuously in progress in one
length as further points are jetted ahead of the pumped down section and pulled up from
the completed and back filled lengths and repeated till entire length is completed. For
narrow excavation, like trenches, header is laid only on one laid, while for wide
excavations, the header are required to be placed on both sides of the area.
Ring system
When excavation is done in area of appreciable width, line system is inadequate.
The ring system is used in such condition and the header main surrounds the excavations
completely. This system is used for rectangular excavations such as for piers or
basements.
SHEET PILES
Sheet piles are thin piles, made of plates of concrete, timber or steel, driven into
the ground for either separating members or for stopping seepage of water. They are not
meant for carrying any vertical load. They are driven into ground with help of suitable
pile driving equipment, and their height is increased while driving, by means of addition
of successive installments of sheets.
Functions of sheet piles
1. To enclose a site or part thereof to prevent the escape of loose subsoil, such as sand,
and to safeguard against settlement.
2. To retain the sides of the trenches and general excavation.
3. To protect river banks.
4. To protect the foundations from scouring actions of nearby river, stream etc. To
construct costal defense works
COFFERDAM
Types of cofferdam
1. Cantilever sheet pile cofferdam
2. Braced cofferdam
3. Embankment protected cofferdam
4. Double wall cofferdam
5. Cellular cofferdam
Grout anchors used in constructions
In most cases, however anchorages may be embedded below ground level, with
backstays connecting them to adjacent towers, or they may constitute the end abutments
of the end spans.
In addition to stability sliding, the anchorage structure must also be checked for
stability against tilting and overturning.
Methods o f ground water control
Following methods of ground water control are adopted
1. Pumping from open sumps
2. pumping from well points
3. Pumping from bored wells
(1) Pumping from open sumps
This method is most commonly used where area is large enough for allowing
excavation to be cut back to stable slopes and where there are no important structures
close to the excavation to effect their stability by settlement resulting from erosion due to
water flowing towards the sump. This method is also applicable for rock excavations.
This method costs comparatively low for installation and maintenance. In this method
one or more sumps are made below the general level of the excavation. In order to keep
the excavator area clear of standing water, a small grip or ditch is cut around the bottom
of the excavation failing towards the sump.
For grater depths of excavation the pump is used or submersible deep well pump
suspended by chains and progressively lowered down. Pumps suitable for operating from
open sumps are:
Pneumatic sump pumps
Self priming centrifugal pumps
Mono pump sinking pumps
Pumping is simple and less expensive, but has serious limitations. When fine sand or
cohesion less soil lie below the water, this type of pumping removes the fine material
from the surrounding soil and results in settlement of adjacent structures. To product it
sumps lined with gravel filter are sometimes used.
(2) Pumping from well points
This system comprises the installation of a number of filter wells generally 1m
long, around the excavation. These filter wells are conducted by vertical riser pipes to a
large diameter header main at ground level which is under vacuum from a pumping unit.
The water flows to the filter well by gravity and then drawn by the vacuum upto the
header main and discharged through the pump. This system has the advantage that the
water is filleted as it removed from the ground and carries almost no soil with it once
steady discharge conditions are attained. This system has the limitation of limited suction
lift. Therefore for deeper excavations the well points are installed in two or more stages.
The filter wells or well points are usually 1m long and 60 to 75mm diameter gauge screen
surrounding a central riser pipe. The capacity of a single we point with 50mm raiser is
about 10 lit/min. Spacing between two well points depends on the permeability of the soil
and on the time available to effect the drawdown. In fine coarse sand or sandy gravels a
spacing of 0.75 to 1m is required, while in silty sands of low permeability a 1.5m spacing
is sufficient. In permeable course gravels spacing should be as low as only 0.3m.A
normal set of well point system comprises 50 to 60 points to a single 150 or 200mm
pump with a separate 100mm jetting pump.
(3) Pumping from bored wells
Pumping from wells, for draw-down depth of than the meters can be under taken
by surface pumps with their suction pipes installed in bored wells. When dewatering is
required to be undertaken from a considerable depth, electricity driven submersible
pumps are installed in deep bore holes with rising main to the surface. Since heavy boring
equipment is used, installation of wells can be done in all ground conditions including
boulders and rocks. Due to higher costs of installation, this method is adopted where
construction period is long and other methods of dewatering are not possible. Installation
of bore well consists of sinking of a casting having a dia. of about 20-30 cm larger than
the inner well casting. The dia of inner well casting depends on the size of submersible
pump. This inner well casing is inserted after complete sinking of borehole screen over
the length where dewatering of the soil is required and it terminates in a 3-5 m length of
unperforated pipe to act as a sump to collect any fine material which may be drawn
through the filter mesh. Screen having slots are preferable to holes, since there is less risk
of blockage from round stones.
Component parts of pipe jacking
Pipe jacking is specialist tunneling method for installing underground pipelines by
assembling the pipes at the foot of an access shaft and pushing them through the ground
with the minimum of surface disruption
Component parts of jacking systems
The pump unit has two distinct hydraulic systems
A high pressure systems supplies oil for the main jacking cylinders and till intermediate
jacking stations
A low pressure system supplies oil, via hydraulic lines, for the boring head and conveyor.
An auxiliary power pack may be easily installed to double the low pressure hydraulic
flow. This may be necessary for larger and more powerful boring heads.
Thrust yoke
The yoke is the frame that the main cylinders push against to advance the boring
head and pipe. The ring provides a 360 degree surface against the pipe to minimize point
pressure and reduce the chance of breakage.
Skid base
The skid base is the foundation of the pump unit and yoke. It also acts as a guide
for launching the boring head and pipe into the ground.
Power packs
Power packs with high and low pressure systems typically are matched with the
multiple cylinder system. When tunneling, a lower pressure power pack may be selected
to supply oil for the tunnel boring machine (TBM)
Power required depend on the size and features of the boring head
A mobile electric power pack may be positioned in the boring head/ TBM
Intermediate jacking stations
Installing intermediate jacking stations is a simple economical way of adding and
distributing thrust for pipe jacking. The size and joint of the pipe, cost, length of push and
versatility are important considerations that configure intermediate stations. Most popular
design is effective with a variety of pipe sizes and design. Each design consists of ram
segments. Each segment has 5 rams. All stations are supplied oil by one set of lines from
the power pack and operated from one point in the jacking shaft.
Methods of providing shoring for the trenches
Methods for providing shoring for the trenches
(1) Stay bracing
1. Stay bracing
2. Box sheeting
3. Vertical sheeting
4. Runners
5. Sheet piling
Carried out in moderately firm ground
It is adopted when the depth does not exceed 2m
The vertical sheets are placed opposite each other against the sides of the trench
The vertical sheets are held in position by one or two rows of struts
The sheets are placed at an interval of 3 to 4m and they extend to full depth of the
excavation
The normal sizes of
Polling bores 200*40&200*50mm
Struts 100*100mm (For trench width upto 2m)
Struts 200*200 (For trench width more 2m)
2. Box sheeting
Carried out in loose soil
It is used when depth of excavation does not exceed 4m
A box like structure is formed by providing sheeting, walls, struts and bracing
In this arrangement, the vertical sheets are placed nearer and touching each other. The
sheets are kept in position by longitudinal rows of Wales, usually two and then, struts are
provided across the walls.
3. Vertical sheeting
Carried out in soft ground.
Adopted when the depth is about 10m.
This is similar to box sheeting except that the work is carried out in stages and at each
stage, an offset is provided.
For each stage, vertical sheets, walls, struts and braces are provided as usual.
The offset is provided at a depth of 3 to 4m and it various from 30 to 60cm per stages
Suitable for laying sewers or water pipes at considerable depths.
4. Runners
Carried out in extremely loose and soft ground which requires immediate support as the
excavation progresses
The runners which are long thick wooden sheets or planks are used in this arrangement
One end of runner is made up of iron shoe
These are driven by hammering about 30cm
The walls and struts are provided as usual
5. Sheet piling
Provided when large area is to be excavated for a depth greater than 10m
Used when the soil is soft or loose
Provided when the width of the trench is large
It is also provided when the subsoil water is present
Large reservoir construction with membranes and earth system
The main problem in reservoirs is the loss of water due to seepage
So even if the capacity of the reservoir is large much water by lost due to it
It can be made impermeable by construction of impervious membranes on the
embankment
The impervious membrane can be placed on
1. The upstream face of the dam
2. Core inside the embankment
Most of the major earth dams constructed before 1925 were provided with central
concrete core walls or concrete slabs on the upstream face
The impervious advantages for the impervious membrane placement in the upstream side
or core of the embankment
Concrete slab
Concrete slab can be used successfully up to a height of 150ft
The performance of concrete slab will directly on the quality of concrete
Even through the earth embankment is not required to act as a water barrier, it should be
well compacted in order to minimize post-construction settlement of the upstream slope
When single reinforced slab is adopted, some leakage will occur due to the hairline
cracks so drains should be provided.
Steel plates
Steel plate can be used where reinforced concrete is used
The life is approximately the same as that of concrete
It can be directly placed on the soil containing appreciable percentage of silt or clay
It is expansive but it has two advantages
It is watertight
It is more flexible and can adapt to differential settlement in a better manner
Asphaltic concrete
They are less costly than concrete or steel
They are more flexible than reinforced concrete and can adapt to differential settlement
better
They can be constructed quickly
Under certain circumstances the leaks development are self-sealine
The portion above the reservoir level are easy to repair than either concrete or steel
Advantages of upstream membrane
When the membrane is on the upstream side optimum stability condition are produced ,so
the volume of embankment can be reduced
Since the upstream slab is exposed ,damage can be inspected and repaired easily
The upstream membrane can be built after the embankment is completed
Foundation grouting can be carried out while the dam is being built
The membrane can serve a secondary function as wave protection
Internal impervious membrane
Concrete is used mostly for internal membrane steel is used rarely
Since it is not exposed for investigation very little reliable performance is available
It is less influenced by embankment settlement and less likely to crack as a result
Advantages of internal membranes
The area of the membrane is smaller than that of an upstream facing, so less material is
required
The surrounding embankment protects the internal membrane
The core can be made almost watertight even if cracking develops, by placing thin layer
of clay upstream
A vertical extension of the core membrane below the base of the dam can be used
through soil deposits in the foundation
The length of the grout curtain in is shorter.
Well sinking operation procedures
1. Laying the well curb
If the river bed is dry, laying of well curb presents no difficulty. In such a
case, excavation upto half a meter above subsoil water level is carried out and the
well curb is laid. If, however, there is water in the river, suitable cofferdams are
constructed around the site of the well and is lands are made. The sizes of the
island should be such to allow free working space necessary to operate tools and
plane for movement of labour etc. When the island is made, the center point of the
well is accurately marked and the cutting edge is placed in a level plane. It is
desirable to insert wooden sleepers below the cutting edge at regular intervals so
as to distribute the load and avoid setting of the cutting edge unevenly during
concrete.
2. Masonry in well staining
The well staining should be built in initial short height of about 2m only. It
is absolutely essential that the well staining is built in one straight line from the
bottom to top. To ensure this staining must be built with straight edges preferably
of angle iron. The lower portions of the straight edges must be kept butted with the
masonry of the lower stage throughout the building of the fresh masonry. In no
case should a plumb bob be used to built more than 5m at a time. The well
masonry is fully cured for at least 48 hours before starting the loading or sinking
operations.
3. Sinking operations
A well is ready to be set in after having cast the curb and having built first
short stage of masonry over it. The well is suck by excavating material from inside
under the curb. In the initial stage of sinking, the well is unsuitable and progress
can be very rapid with only little material being excavated out. Great care should
therefore be exercised during this stage, to see the well sinks to true position. To
sink the well straight it should never be allowed to go out of plumb.
Excavation and scooping out of the soil inside the well can be done by
sending down workers inside the well till such a stage that the depth of water
inside becomes about 1m. As the well sinks deeper, the skin friction on the sides
progressively increases. To overcome the increased skin friction and the loss in
weight of the well due to buoyancy, additional loading known as kent edge is
applied on the well.
Pumping out the water from inside the well is effective in sinking of well under
certain conditions. Pumping should be discouraged in the initial stage. Unless the
well has gone deep enough or has passed through a ring of clayey strata so that
chances of tilts and shifts are minimized during this process. Complete dewatering
should not be allowed when the well has been sunk to about 10m depth.
4. Tilts and shifts
The primary aim in well sinking is to sink them straight and at the correct position.
Suitable precautions should be taken to avoid tilts and shifts. The precautions to
avoid tilts and shifts are as follows
1. The outer surface of the well curb and steinings should be as regular and smooth
as possible.
2. The radius of the curb should be kept 2 to 4 cm larger than outside of well
Steining.
3. The cutting edge of the curb should be of uniform thickness and sharpness since
the sharper edge has a greater tendency of sinking than a blunt edge.
4. As soon as tilt exceeds 1 in 200, the sinking should be supervised with special
care and rectifying measures should be immediately taken.
5. Completion of well
When the well bottom has reached the desired strata, further sinking of the
well stopped. A concrete seal is provided at the bottom. The bottom plug is made
bowl shaped so as to have inverted arch action. As generally under watering
concerting as to done, no reinforcement can be provided. Under watering
concreting is done the help of tremie. However if it is possible to dewater the well
successfully, the concrete can be placed dry also.
After having plugged the well at its bottom, the interior space of the well is
filled either with water or sand. It may even we kept empty. The well is capped at
its top, with help of reinforced concrete slab.
UNIT IV SUPER STRUCTURE CONSTRUCTION
Launching girders, bridge decks, off shore platforms – special forms for shells -
techniques for heavy decks – in-situ pre-stressing in high rise structures, Material
handling - erecting light weight components on tall structures - Support structure for
heavy Equipment and conveyors - Erection of articulated structures, braced domes and
space decks.
LAUNCHING GIRDER
Launching girder is a steel or wooden structural member used to support the super
structures such as bridge deck, off shore structures etc. the operation of launching girder
is more difficult. Proper study and local site investigations are the only way to make it
easier.
Uses:
It is used for all type of bridge deck construction
It is used in the field of pier head construction
It is used for off shore platform construction
It is used for deep foundation construction
It is used for lifting heavy equipment
for various constructions.
BRIDGE DECKS
Construction of bridge decks
The various bridge decks are constructed by the following construction sequences. They
are
Traditional or technique for heavy decks
Incremental push launching or launching girder
Cable stayed bridges
Bow string bridge
Precautions during the construction of bridges:
The local site conditions are studied. It is used to give the proper design and
construction of bridges and it includes local weather for whole year. The proposed site
soil conditions should be studied, it is used to avoid any settlement of foundations and
auxillary support etc. and it is also used for the depth of foundation.
The site of the proposed bridge should be located where the materials and labour
are available at cheapest rate.
The proper studies are carried out for velocity if velocity of flow is less than a
particular value the silting will occur.
The proper study or precautions carried out to form embankment on both side of
bridge it should be solid permanent and straight
The suitable precautions are taken about high flood level. This studying is used to
provide the suitable height of the bridge from the water bodies.
The bridge deck should be design for future traffic also. So the proper current
traffic as well as future traffic is carried out.
Correct span length is provided for bridge deck. It may used to avoid any
structural damage.
The proper finishing works are carried out to avoid any cracks on structure.
OFFSHORE PLATFORMS:
Offshore platforms are a structure that is constructed in the ocean or sea to explore
or to produce oil or gas from the sources found below the sea. It is dealt with the
foundations in the sea.
Offshore platforms are made up of either in steel or concrete. Since this
construction is constructed on sea water utmost care should be taken to resist the structure
from the corrosion problems.
Uses:
Oil and gas exploration
Navigation aid tower
Bridges and causeways
Ship loading and unloading facilities
Advantages
Very light form of construction to span 30.0m shell thickness required is 60mm.
Dead load can be reduced economizing foundation and supporting system
Flat shapes by choosing certain arched shapes.
Aesthetically it looks good over other forms of construction.
Disadvantages:
Shuttering problem
Greater accuracy in formwork is required
Rise of roof may be disadvantages
Good labour and supervision necessary.
Design consideration of shell roof
Slope shall not exceed 45o to 65o
Thickness
Singly curved shell <50mm
Doubly curved shell <40mm
End frames
Traverse or end frame provided to protect the shape of the shell.
Reinforcement:
Diameter of reinforcement <5mm in the unthickened portion of the shell.
In the pre tensioning system the tendons are tensioned before concreting.
Post tensioning method is one in which the reinforcement is tensioned after the
concrete has fully hardened. The concrete is first cast and leaving duct for placing the
tendons. The ducts are made in a number of ways by leaving corrugated steel tube or by
providing steel special or rubber or any other ducts forming units
MATERIAL HANDLING
Material handling consists of transporting, securing and stacking or protect the
manufacturing product for the purpose of construction is known as material handling.
In order to handle materials large amount of equipments such as various types of
conveyors, cranes and trucks and labours are involved.
If the length of the area to be roofed is more than twice the breadth. It is more
economical to span one way. If the area is nearer square the more economical solution .
theoretically is to span two ways. The rectangular area can be divided into square or near
square areas with lattice girder and then two way spanning structure can be installed in
the sub-divided roof.
CANTILEVER METHOD
In this method the structure is erected starting from a support point and a section
or strip of the structure is erected to span between two adjacent supports with the help of
movable scaffolding. Once part of the structure is stabilized, the rest of the structure is
assembled by adding separate pieces or units to already erected structure.
LIFT SLAB METHOD
In this method the entire spatial structure is assembled on ground and lifted to the
final location using cranes or other heavy lifting equipment. This method is usually upto
200ft weighing upto 200 Kpa have been erected using this method.
UNIT IV SUPER STRUCTURE CONSTRUCTION
1. Explain the construction techniques for bridge decks with flowchart. (Apr 2019)
2. With flow diagram explain the erection of articulated towers. (Nov 2012)
3. Briefly explain General requirements for launching girders.
4. Describe in detail about shell roof structures. (Nov 2016)
5. Explain about the support structures required for heavy equipments and
conveyors. (Nov 2016)
6. Explain about various types of domes with neat sketch.
7. What is a sheet pile? List the factors for selection of sheet piles. Explain its types
based on materials. (Apr 2019)
8. Discuss in detail about the bridge decks and offshore platform with suitable
diagram. (Nov 2013)
UNIT V CONSTRUCTION EQUIPMENTS
The selection of t appropriate type and size of construction equipment often affects the
required amount of time and effort and thus the job-site productivity of a project. It is
therefore important for site managers and constructions p1anners to be familiar with the
characteristics of the major types of equipment most commonly used construction.
Construction equipments can be classified based on applications under the following
heads:
Excavation an Earthmoving equipments
Concreting equipments
Material handling Erection equipments
Dewatering and Pumping equipments
Typically, construction equipments are used to perform essentially repetitive
operations, and can be broadly classified accord to two basic functions:
Operators such as cranes, graders, etc. which stay within the con of the
construction site haulers such as dump trucks, ready mixed concrete truck, etc. which
transport materials to and from the site. In order to increase job-site productivity, it is
beneficial to select equipment with proper characteristics and a size most suitable for the
work conditions at the construction site.
Excavation and Earthmoving equipments
Factors that could affect the selection of excavators include:
Size of the job larger volumes of excavation will require larger excavators, or smaller
excavator in greater number activity time constraints Shortage of time for excavation may
force contractors to increase the size or numbers of equipment for activities related to
excavation.
Availability of equipment - Productivity of excavation activities will diminish if the
equipment used perform them is available but not the most adequate.
Cost of transportation of equipment - This cost depends on the size of the job, the
distance of transportation and the means of transportation.
Type of excavation - Principal types of excavation in building projects are cut and/or fill,
excavation massive, and excavation for the elements of foundation
Soil characteristics the type and condition of the soil is important when choosing the most
adequate equipment since each piece of equipment has different outputs for different
soils.
Geometric characteristics of elements to be excavated - Functional characteristics of
different types of equipment make such considerations necessary.
Space constraints - The performance of equipment is influenced by the spatial limitations
for the movement of excavators.
Characteristics of haul units - The size of an excavator will depend on the haul units if
there is a constraint on the size and/or number of these units.
Location of dumping areas - The distance between the construction site and dumping
areas could be relevant not only for selecting the type and number of haulers, but also the
type of excavators.
Normally there are three purposes of earth moving equipments,
Excavation of soil from below or above the track/wheel level of the equipment
Clearance of site at the track/wheel level of equipment
Hauling of spoil out of site
A few types of equipments under this head are:
Bull Dozers and Angle Dozers
Graders
Skimmers
Scrapers
Loaders
Face Shovels
Backacters
Draglines
Multipurpose excavators
Bulldozers and Angle Dozers
These machines consist of a track or wheel mounted power unit with a blade at the
front, which is usually controlled by hydraulic rams and sometimes by wire cable
operation. Many bulldozers have the capacity to adjust the mould blade to from angle
dozers and the capacity to tilt the mould blade about a central swivel point. .
Some bulldozers can also be fitted with rear attachments such as rollers and
scarifies.
The main uses of a bulldozer are:
Shallow excavations up to 300CM deep either on levee, ground or side hill cutting
Clearance of shrubs and small trees
Clearance of trees by using raised mould blade as a pusher arm
Acting as a towing tractor
Acting as a pusher to scraper machines
Bulldozers push earth in front of the mould blade with some side spillage whereas angle
dozers and cast spoil to one side of the mould blade.
Graders
These machines are similar in concept to bulldozers in that they have a long
slender adjustable mould blade, which is hung, under the center of the machine. A grader
is used to finish or grade the upper surface of a large area usually as a follow up operation
to scraping or bulldozing. They can produce a fine and accurate finish but do not have the
power of bulldozer. Therefore they are not suitable for over site excavation work. The
mould blade can be adjusted in both the horizontal and vertical planes through an angle
of 360 the latter enabling it to be used for grading sloping banks as well.
Two basic types of graders are:
(i) Four Wheeled Graders
In this type of graders all wheels can be driven and steered. This facility gives the
machine the ability to offset and crab along its direction of travel.
(ii) Six Wheeled Graders
Six Wheeled Graders have four wheels in tandem drive at the rear and two front
tilting idler wheels giving it the ability to counteract side thrust.
Skimmers
These excavators are rigged using a universal power unit for surface stripping and
shallow excavation work up to 300 cm deep where a high degree of accuracy is required
They usually require attendant haulage vehicles to remove the spoil and need to be
transported between sites on a low loader. Because of their limitations and the availability
of alternative machines, they are rarely used today.
Scrappers
Scrapers are multiple-units of tractor-truck and blade-bucket assemblies with
various combinations to facilitate the loading and hauling of earthwork. Major types of
scrapers include single engine two-axle or three aide scrapers, twin-engine all-wheel-
drive scrapers, elevating scrapers, and push-pull scrapers. Each type has different
characteristics of rolling resistance, maneuverability stability, and speed in operation.
These machines consist of a scraper bowl, which is lowered to cut, and collect soil
where site stripping and leveling operations are required involving large volume of earth,
When the scraper bowl is full, the apron at the cutting edge is closed to retain the earth
and the bowl is raised to the disposal area. On arrival of disposal area, the bowl is
lowered, the apron opened and the spoil pushed out by the tailgate as the machine moves
forwards.
(i) Towed scrapers
It consists of a four wheeled scraper bowl with a power unit such as a crawler
tractor. They tend to be slower than other forms of scrapers but are useful for small
capacities with haul distances up to 300 m.
(ii) Two Axle scrapers
These have a two-wheeled scraper bowl with an attached two wheeled power unit.
They are view maneuverable with low rolling resistance and very good fraction.
(iii) Three Axle scrapers
It consists of a two-wheeled scraper bowl that may have a rear engine to assist the
four-wheeled traction engine. Generally, these machines have a greater capacity than
other scrapers, are easier to control and have a faster cycle time.
(e) Loaders
These machines are sometimes called tractor shovels. They are used to scoop up
loose materials in the front mounted bucket, elevate the bucket and maneuver into a
position to deposit the loose material into an attendant transport vehicle. Tractor shovels
are driven towards the heap of loose material with the bucket lowered. The speed and
power of the machine will enable the bucket to be filled. To increase their versatility
tractor shovels can be fitted with a 4 in 1 bucket enabling them to car out bulldozing as
well.
Both crawler mounted and wheel mounted types are available. The tracked loader
being more suitable for wet and uneven ground conditions than the wheeled one, which
has greater speed, and maneuvering capacities.
Face Shovels
The primary function of face shovels is to excavate above its own track or wheel
level. They are available as a universal power unit based machine or as a hydraulic
purpose designed unit. These machines can usually excavate any type of soil except that
which needs to be loosened, usually by blasting, before excavation. Face shovels
generally require attendant haulage vehicles for the removal of spoil and a low ladder
transport lorry for travel between sites. Most of these machines have a limited capacity of
between 0.3 m and 0.4 m for excavation below their own track wheel level.
Backacters
These machines are suitable for trench, foundation and basement excavations and
are available as a Universal power unit base machine or Purpose designed hydraulic unit.
They can be used with or without attendant haulage vehicles since the soil can be placed
alongside the excavation for the use in back filling. These machines will require a low
loader transport vehicle to be transported from one site to another. Backacters used in
trenching operations with a bucket width equal to the trench width can be very accurate
with a high output rating.
Draglines
Draglines are based on the universal power unit with basic crane rigging to which
is attached a drag bucket.
The machine is primarily designed for bulk excavation in loose soils up to 3 m
below its own track level by swinging the bucket out to the excavation position and
haunting or dragging it back towards the power unit.
Dragline machines can also be fitted with a grab or clamshell bucket for
excavating in very soils.
Mu1tIpurpose Excavators
These machines are usually based on the agricultural tractor with 2 or 4 wheel
drive and are intended mainly for use in conjunction with small excavation works such as
foundation excavations, pipe laying and drainage trenches. Most multi-purpose
excavators are fitted with a loading/excavating front bucket and a rear backwater hoe
bucket both being hydraulically controlled. When in operation using the backwater
bucket, the machine is raised off its axles by rear mounted hydraulic outriggers or jacks
and in some models by placing the front bucket on the ground.
The choice of the type and size of haulers is based on the consideration that the
number of haulers selected must be capable of disposing of the excavated materials
expeditiously. Factors which affect this selection include:
1. Output of excavators - The size and characteristics of the excavators selected will
determine the output volume excavated per day.
2. Distance to dump site - Sometimes part of the excavated materials nay be piled in a
corner at the job site for use as backfill
3. Probable average speed - The average speed of the haulers to and from the dumping
site will determine the cycle time for each hauling trip.
4. Volume of excavated materials - The volume of excavated materials including the part
to be piled up should be hauled away as soon as possible.
5. Spatial and weight constraints - The size and weight of the haulers must be feasible at
the job site and over the route from the construction site to the dumping area.
Concreting equipments
It is well known that the process of concreting involves batching, mixing,
transporting, placing, compacting and curing. Accordingly common concreting
equipments are,
Concrete mixers
Concrete Hauling Equipments
Concrete pumps for placement in different conditions
Concrete vibrators for compaction
Concrete mixers
These are generally related to their designed output performance. Machines are
decided based upon what mixing and placing methods are to be employed to mix and
place a certain amount of concrete in a given time period. Generally, a batch mixing time
of 5 minutes per cycle of 12 batches per hour can be assumed as a reasonable basis for
assessing mixer output.
(b) Concrete Hauling Equipments
(i) Wheel barrows he usual means of transporting mixed concrete produced in a
small capacity mixer is by wheelbarrow. The run between the mixing and placing
positions should be kept to a minimum and as smooth as possible by using planks or
similar materials to prevent segregation of the mix within the wheelbarrow
(ii)Dumpers
These can be used for transporting mixed concrete from mixers up to 600-litre
capacity and are available in two forms,
(iii) Ready Mix Concrete Mixers
These are used to transport mixed concrete from a mixing plant or depot to the
site. Usual capacity range of ready mixed concrete trucks is 4 to 6 rn3. Discharge can be
direct into placing position into some form of site transport such as dumpier, crane skip
or concrete pump.
(d) Concrete pumps for placement in different conditions
These are used to transport large volumes of concrete in a short time (say up to
100 m3 per hour) in both the vertical and horizontal directions from the pump position to
the point of placing. The pump is supplied with pump able special concrete mix or with
constant flow of ready mixed concrete lorries throughout the pumping period. Concrete
pumps are usually of a twin cylinder hydraulically driven form with a small bore pipeline
(100 mm diameter) and can be trailer or lorry mounted.
Pumping ranges may be up to 850.00 m vertically and 200 m horizontally
depending on the pump model. It generally requires about 45 minutes to set up a concrete
pump on site including coating the bore of the pipeline with a cement grout before
pumping. After plumbing, the pipeline should be cleared and cleaned. Usually concrete
pump and operator are hired for the period required
(e) Concrete vibrators for compaction
(i) Poker or Internal Vibrators
These consist of a hollow steel tube casting in which is a rotating impeller which
generators vibrations as its head comes into contact with casing. Poker vibrators should
be inserted vertically and allowed to penetrate 75mm into any previously vibrated
concrete.
(ii) External Clamp or Tamping Board Vibrators
These vibrators operate by shaking the formwork. Clamp vibrators powered by
either compressed air or electricity whereas tamping board vibrators are usually petrol
driven.
Formwork must be stronger than is traditional to withstand vibration.
MATERIAL HANDLING AND ERECTION EQUIPMENTS
Horizontal transportation
Vertical transportation
Upward only
Downward only
Upward and downward
Derricks are commonly used to lift equipment of materials in industrial or building
construction
A derrick consists of a vertical mast and an inclined boom sprouting from the foot
of the mast.
The mast is held in position by guys or stiff legs connected to a base while a
topping lift links the top of the mast and the top of the inclined boom. A hook in the road
line hanging from the top of the inclined boom is used to lift loads. Guy derricks may
easily be moved from one floor to the next in a building under construction while stiff leg
derricks may be mounted on tracks for movement within a work area.
Tower cranes are used to lift loads to great heights and to facilitate the erection of
steel building frames. Horizon boom type tower cranes are most common in high rise
building construction.
Inclined boom type tower cranes are also used for erecting steel structures
Forklift trucks are useful for horizontal and limited vertical transportation of
materials. Hoists are used in two-way vertical transportation of materials and passengers,
whereas rubble chutes are used in downward transportation of construction and
demolition debris. Cranes are the most versatile material handling equipments that can be
chosen or designed for any kind of movement.
(a) Forklift Trucks
Forklift trucks are used for horizontal and limited vertical transportation of
packaged materials positioned on paflets or banded together such as brick packs.
They are generally suitable for construction sites where the building height does
not exceed three dories. Although designed to negotiate rough terrain sites, forklift trucks
have a higher productivity on firm and level soils.
Three types of forklift trucks with various height, reach and lifting capacities are in
common use namely,
Straight mast
Overhead thicks
Telescopic boom
(b) Hoists
Hoists are equipments used for transporting materials and passengers vertically.
Common types of hoists are as follows:
(i) Material Hoists
These are designed for the vertical transportation of materials and under no
circumstances should they be used to transport passengers. Most material hoists are
mobile, can be dismantled, folded onto the chassis and moved to another position or site
under their own power or towed by a haulage vehicle. When in use material hoists need
to be stabilized and / or tied to the structure and enclosed with a protective screen.
(II) Passenger Hoists
These are designed to carry passengers although most are capable of transporting a
combined load of materials and passengers within the lifting capacity of the hoist. A wide
selection of hoists are available ranging from a single cage with rope suspension to twin
cages with rack and opinion operation mounted on two sides of a static tower.
(c) Cranes
Cranes are machines designed to move materials vertically (raise by rope pulley
operation) or horizontally. The range of cranes available is very wide, from gear wheel to
a complex tower crane. Therefore, choice must be based on:
The loads to be lifted
Height of lifting
Horizontal distance to be covered
Time period of lifting operations
Utilization factors and
Degree of mobility required
However, it may be possible to place most cranes into one following groups
(i) Mobile Cranes
These are low-pivot cranes capable of horizontal motion, either by itself or
mounting on crawler or truck. They are classified based on the type of mobility as:
Self propelled cranes with wheeled chassis
Truck mounted hydraulic cranes
Truck mounted lattice jib cranes
Crawler mounted cranes
(ii) Static Cranes
These are either operating from affixed position on ground or is capable of
longitudinal motion on rails depending on the height of pivot and operational ability,
static cranes are of three types:
Gantry Cranes which are not pivoted, and are cranes with pulley, rope and hook
are hung from a portal frame
Most Cranes which are similar to tower cranes are low pivot cranes
Tower Cranes are high pivot cranes
Rubble Chutes
These are used in demolition, repair, maintenance and refurbishment. The concept
Involves connecting of several perforated dustbins vertically downwards for expedient
and safe conveyance of materials. In customized forms the tapered cylinders are
produced from reinforced rubber with chain linkage for continuity. Overall unit lengths
are generally 1.1 m, providing an effective length of 1 m. Hoppers and side entry units
are made for special applications.
Dumpers
These are used for the horizontal transportation of materials on and off
construction sites generally by means of an integral tipping skip.
A wide range of dumpers is available depending on their carrying capacities,
discharge control (gravity or hydraulic discharge) and tipping facilities (front tipping,
side tipping).
Special dumpers fitted with flat platforms, rigs to carry materials, skips and rigs
for concrete, skips for crane hosting are also available. Highway dumpers are of a similar
but larger design and can be used to carry materials such as excavated soil along the
roads.
PILE DRIVING EQUIPMENTS
Pile driving equipments are of three types
Impact type drivers which drive piles by impact of weight on or into piles
Vibration type drivers drive pile be vibrating the pile through the soil Piling hammers
combine the desirable effects of both impact and vibration driving.
Piling Hammers
Details of Piling Hammers
These are designed to deliver an impact to the pile to be driven. The hammer
weight and drop height is chosen to suit the pile type and nature of subsoil through which
it will be driven. There are four types of piling hammers depending on the mechanism of
driving
Drop Hammers
Drop hammers are heavy iron blocks, which hammer the pile b free fall onto the
pile top. Drop hammers require special arrangement on top of pile to ensure that impact is
steady, vertical and correctly located. It also needs a winch to lift the weight and release
it.
Single Acting Hammers
These hammers are raised by steam or compressed air and are lowered by free fall.
Guide tugs or rollers are required on the piling frame leaders to maintain the hammer
position but necessity of winches are eliminated.
Double Acting Hammers
These consist of a cast iron cylinder that remains stationary on top of the pile.
Both up and down strokes are powered by steam or compressed air. This eliminates both
winch arrangement and leader arrangements. However blow forces are lower in these
hammers
Diesel hammers
These are self-contained hammers using free fall for down stroke, which in turn
ignites diesel engine for upstroke. Hence, they do not require winches or leaders and
deliver moderate impact energy.
Lifting and Erecting
Derricks are commonly used to lift equipment of materials in industrial or building
construction.
A derrick consists of a vertical mast and an inclined boom sprouting from the foot
of the mast.
The mast is held in position by guys or stiff legs connected to a base while a
topping lift links the top of the mast and the top of the inclined boom. A hook in the road
line hanging from the top of the inclined boom is used to lift loads. Guy derricks may
easily be moved from one floor to the next in a building under construction while stiff
legs derricks may be mounted on tracks for movement within a work area.
Tower cranes are used to lift loads to great heights and to facilitate the erection of
steel building frames. Horizon boom type tower cranes are most common in high rise
building construction.
Inclined boom type tower cranes are also used for erecting steel structures.
Mixing and Paving
Basic types of e for paving” include machines for dispensing concrete and
bituminous materials for pavement surfaces. Concrete mixers may also be used to mix
Portland cement, sand. Gravel and water in batches for other types of construction other
thin paving.
A truck mixer refers to a concrete mixer mounted on a truck which is capable of
transporting ready mixed concrete from a central batch plant to construction sites. A
paving mixer is a self propelled concrete mixer equipped with a boom and a bucket to
place concrete at any desired point within a roadway. It can be used as a stationary mixer
or used to supply slip form payers that are capable of spreading, consolidating and
finishing a concrete slab without the use of forms.
A bituminous distributor is a truck-mounted plant for generating liquid bituminous
materials and applying them to road surfaces through a spray bar connected to the end of
the truck. Bituminous materials include both asphalt and tar which have similar
properties except that tar is used when the pavement is likely to be heavily exposed to
petroleum spills.
CONSTRUCTION TOOLS AND OTHER EQUIPMENT
Air compressors and pumps are wide! used as the power sources for construction
tools and etc
Common pneumatic construction tools include drills, hammers. grinders. saws,
wrenches, staple nuns. Sandblasting guns. And concrete vibrators. Pumps are used to
supply water or to dewater at construction sites and to provide water jets for some types
of construction.
Automation of Equipment
The introduction of new mechanized equipment in construction has had a
profound effect on the cost and productivity of construction as well as the methods used
for construction itself. An exciting example of innovation in this regard is the
introduction of computer microprocessors on tools and equipment. As a result, the
performance and activity of equipment can be continually monitored and adjusted for
improvement. In many cases, automation of at least part of the construction process is
possible and desirable. For example, wrenches that automatically monitor the elongation
of bolts and the applied torque can be programmed to achieve the best bolt tightness. On
grading projects, laser controlled scrapers can produce desired cuts faster and more
precisely than normally manual methods.
Concrete Hauling Equipments
Details of Concrete hauling equipments
Wheelbarrows
The usual means of transporting mixed concrete produced in a small capacity
mixer is by wheelbarrow. The run between the mixing and placing positions should be
kept to a minimum and as smooth as possible by using planks or similar materials to
prevent the mix within the wheelbarrow
Dumpers
These can be used for transporting mixed concrete from mixers up to 600-litre
capacity
Drop Hammers
Details of Drop hammers
Drop hammers are heavy iron blocks, which hammer the pile by free fall onto the
pile top. Drop hammers require special arrangement on top of pile to ensure that impact is
steady, vertical and correctly located. It also needs a winch to lift the weight ht and
release it.
The major components of drop hammers are
Block of iron which comprises the body of the hammer
Rear lug that can be placed into the piling rig guides or leaders, so that the impact may be
in position
A lifting eve at the top for attachment of the winch rope
The number of blows that can be delivered with a free fall of 1.2 m to 1.5 m ranges from
10 to 20 per minute.
The weight of the hammer should be not less than 50% of the concrete or steel pile
weight and 1 to 1.5 times the weight of a timber pile.
Single Acting Hammers
Details of single acting hammers
Single Acting Hammers consist of a heavy falling cylinder raised by steam or
compressed air sliding up and down a fixed piston. Guide tugs or rollers are located in the
piling frame leaders to maintain the hammer position relative to the pile head. The
number of blows delivered ranges from 36 to 75 per minute with a total hammer weight
range of 2 to 15 tones
Double Acting Hammers details of Double acting hammers
Double Acting Hammers consist of a cast iron cylinder that remains stationary on the pile
head.
A ram powered by steam or compressed air for both up and down strokes delivers a series
of rapid blows that tends to keep the pile on the move durin2 driving. The blow delivered
is a smaller force than that from a drop or single acting hammer.
The number of blows delivered ranges from 95 to 300 per minute with a total hammer
weight range of 0.7 to 6.5 tonnes.
Diesel powered double acting hammers are also available. Diesel Hammers
Details of diesel Hammers
These are self-contained hammers, which are located in the leaders of the pile. The
driving action is started by raising the ram within the cylinder that activates the injection
of a measured amount of fuel. The free falling ram compresses the fuel above the anvil.
This causes the fuel to explode and expand resulting in a downward force on the anvil. It
also generates an upward force that raises the ram to restart the cycle. The process repeats
itself until the fuel is cut off
The number of blows delivered ranges from 40 to 60 per minute with a total hammer
weight range of 1.0 to 4.5 tones.
Standard Type Dumper Crane Skip Dumper
Ready mixed Concrete Trucks
These are used to transport mixed concrete from a mixing plant or depot to the
site. Usual capacity range of ready mixed concrete trucks is 4 to 6 m3. Discharge can he
direct into placing position into some form of site transport such as dumpier, crane skip
or concrete pump.
Concrete Pumps
Details of Concrete Pumps
These are used to transport large volumes of concrete in a short time (say up to
100 m3 per hour) in both the vertical and horizontal directions from the pump position to
the point of placing. The pump is supplied with pump able special concrete mix or with
constant flow of ready mixed concrete Lorries throughout the pumping period.
Bore pipeline (100 mm diameter) and can be trailer or lorry mounted.
Pumping ranges made be up to 850.00 in vertically and 200 in horizontally depending on
the pump model.
It generally requires about 45 minutes setting up a concrete pump on site including
coaling the bore of the pipeline with a cement grout before pumping. After plumbing, the
pipeline should be cleared and cleaned. Usually concrete pump and operator are hired for
the period required.
Concrete Mixers
Details of Concrete mixers
Types of mixers are generally related to their designed output performance.
Machines are decided based upon what mixing and placing methods are to be employed
to mix and place a certain amount of concrete in a given time period. Generally, a batch
mixing time of 5 minutes per cycle of 12 batches per hour can be assumed as a
reasonable basis for assessing mixer output.
Small Batch Mixers have outputs up to 200 liters per batch with wheel barrow
transportation on hourly placing rate of 2 to 3 m3 can be achieved. Most small batch
mixers are of the tilting drum type. General. These mixers are hand loaded which makes
the quality control of successive mixes difficult to regulate.
Medium Batch Mixers have output ranging from 200 to 750 liters. Low output
machines are available as tilting drum mixers and high output ones are available as non-
tilting drum mixers.
Non-tilting mixers are either reversing drum or chute discharge, the latter usually
having a lower discharge height. Such mixers usually have integral weigh batching
facility loading hoppers.
scraper shovels and water tanks thus giving better quality control than the small
batch mixers.
Generally they are unsuitable for wheel barrow transportation because of their
high output.
CONSTRUCTION EQUIPMENT
The selection of the appropriate type and size of construction equipment often
affects the requirement amount of time and effort and thus the job-site productivity of a
project. It is therefore important for site managers and construction planners to be
familiar with the characteristics of the major types of equipment most commonly used in
construction.
Excavation and Loading
One family of construction machines used for excavation is broadly classified as a
crane-shove. The crane-shovel consists of three major components:
A carrier or mounting which provides mobility and stability for the machine.
A revolving deck or turntable which contains the power and control units.
A front end attachment which serves the special functions in an operation.
The type of mounting for all machines in Figure 4-3 is referred to as crawler mounting
which is particularly suitable for crawling over relatively rugged surface at a job site
other types of mounting include truck mount1n and wheel mounting which provide
creator mobility between job sites, but require better surfaces for their operation. The
revolving deck includes a cab to house the person operating the mounting and “or the
revolving deck The types of front end attachments in Figure 4-3 mi include a crane with
hook, claim shell, dragline. Backhoe. Shovel and pile driver
A tractor consists of a crawler mounting and a non-revolving cab. When an earth
moving blade is attached to the front end of a tractor, the assembly is called a bulldozer.
When a bucket is attached to its front end, the assembly is known as a loader or bucket
loader. There are different types of loaders designed to handle most efficiently materials
of different weights and moisture contents.
Scrapers are multiple-units of tractor-truck and blade-bucket assemblies with
various combinations to facilitate the loading and hauling of earthwork. Major types of
scrapers include single engine two-axle or three axle scrapers, twin-engine all-wheel-
drive scrapers, elevating scrapers. and push-pull scrapers. Each type has different
characteristics of rolling resistance, maneuverability stability, and speed in operation.
Compaction and Grading
The function of compaction equipment is to produce higher density in soil
mechanically.
The basic forces used in compaction are static weight, kneading, impact and
vibration.
The compaction that may be achieved depends on the properties of soil, its moisture
content, the thickness of the soil layer for compaction and the method of compaction.
Some major types of compaction equipment with different operating characteristics.
Concrete Vibrators
Details of Concrete Vibrators
Poker or Internal Vibrators
These consist of a hollow steel tube casting in which is a rotating impeller which
generators vibrations as its head comes into contact with casing. Poker vibrators should
be inserted vertically and allowed to penetrate 75mm into any previously vibrated
concrete.
External Clamp or Tamping Board Vibrators
These vibrators operate by shaking the formwork. Clamp vibrators powered by
either compressed air or electricity whereas tamping board vibrators are usually petrol
driven.
Formwork must be stronger than is traditional to withstand vibration.
The function of grading equipment is to bring the earthwork to the desired shape and
evasion.
Major types of grading equipment include motor graders and grade trimmers.
Drilling and blasting
Rock excavation is an audacious task requiring special equipment and methods.
The depth of difficulty depends on physical characteristics of the rock type to be
excavated such as grain size planes of weakness, Weathering, Brittleness and hardness.
The task of rock excavation includes loosening, loading, hauling and compacting. The
loosening operation is specialized for rock excavation and is performed by drilling,
blasting or ripping.
Major types of drilling equipment are percussion drills, rotary drills- and rotary-
percussion drills. A percussion drill penetrates and cuts rock by impact while it rotates
without cutting on the upstroke. Common types of percussion drills include a
jackhammer which is hand-held and others which are mounted on a fixed frame or on a
wagon or crawl for mobility. A rotary drill cuts by turning a bit against the rock surface.
A rotary- percussion drill combines the two cutting movements to provide a faster
penetration in rock.
Blasting requires the use of explosives, the most common of which is dynamite.
Generally, electric blasting caps are connected in a circuit with insulated wires. Power
sources may be power lines or blasting machines designed for firing electric cap circuits.
Also available are nonelectrical blasting systems which combine the precise timing and
flexibility of electric blasting and the safely of non-electrical detonation.
Tractor-mounted rippers are capable of penetrating and prying loose most rock
types. The blade or ripper is connected to an adjustable shank which controls the angle at
the tip of the blade as it is raised or lowered. Automated ripper control may be installed to
control ripping depth and tip angle.
In rock tunneling, special tunnel machines equipped with multiple cutter heads and
capable of excavating full diameter of the tunnel are now available. Their use has
increasing replaced the traditional methods of drilling and blasting.
1. List out the different methods of dredging technique and explain with neat
sketches. (Nov 2013)
2. What are the different types of cranes? Explain any three in detail. (Apr 2019)
3. Explain the various equipments for pile driving. (Nov 2016)
4. Mention the various types of earthwork equipments and also give their uses. (May
2013)
5. Distinguish between crawler & pneumatic type of wheel excavators.
6. Analyze the equipment used for erection of structures in detail.
7. Explain the various aspects of graders and scrapers in detail. (Apr 2019)
8. Explain in detail about trenching and the equipment used for trenching
9. Classify the Types of earthwork equipments? Mention its uses (Nov 2014)
10. Explain in detail the various equipments used for compaction, batching and
mixing of concrete. (Nov 2014)
UNIT –V
CONSTRUCTION EQUIPMENT
Selection of equipment for earth work - earth moving operations - types of earthwork equipment -
tractors, motor graders, scrapers, front end waders, earth movers – Equipment for foundation andpile
driving. Equipment for compaction, batching, mixing and concreting - Equipment for
materialhandling and erection of structures – types of cranes - Equipment for dredging,
trenching,tunneling
Introduction: This unit deals with the selection and applications of various construction equipments
for different types of works like different types of earth moving equipments, equipments for pile
driving (like hammers), compaction, batching and mixing and concreting, material handling and
erection of structures (like tower cranes, movable cranes), dredging, trenching, tunneling (Tunnel
Boring Machines)
Part A
Selection of equipment for earth work
2
excavation and fill or backfill. Heavy construction equipment is usually used due to the amounts
of material to be moved — up to millions of cubic meters. Earthwork construction was
revolutionized by the development of the (Fresno) scraper and other earth-moving machines such
as the loader, production trucks, the grader, the bulldozer, the backhoe, and the dragline
excavator.
Types of earthwork equipment - tractors, motor graders, scrapers, front end waders, earth movers
Several types of motorized scrapers with heaped capacity ranging from 15 m3 to 50 m3 are
available to suit varying job requirements. These include single engine scraper, double engine
scraper and elevating scraper. A Single engine scraper requires a pusher bulldozer to provide the
necessary tractive force. Generally one medium sized crawler tractor is sufficient to serve four to
five scrapers.
Scrapers per pusher = Cycle time of each scraper / Cycle time of pusher
Example: Cycle time of scraper is 6 minutes and a pusher to fill a scraper is 1.5 minutes.
Calculate the number of scrapers which a pusher can serve. Determine the number of pushers to
serve 10 scrapers.
Number of pushers for 10 scrapers = No. of scrapers / No. served by one pusher
= 10/4=3
6
more efficient as it uses only the gravity. The drop hammer is basically a block of suitably shaped
cast-iron with its centre of gravity centered near the base in order to facilitate smoothness of fall.
7
the next blow. This could be overcome if the pile ' is driven continuously. The vibratory hammer
takes care of this and allows the pile to move continuously thereby eliminating surface frictional
resistance. In this process the pile sinks fast into the soil due to its own weight and the weight of
the driver assembly. The hammer comprises of a vibratory unit which produces vibrations to
oscillate the pile along its vertical axis, and a clamping device which transmits these vibrations to
the pile. The driving power for the vibrators are given by internal combustion engines or with
electric motors. Vibrations are generated by movement of counter rotating shafts to which
eccentric weights are fixed.
30. Differentiate between single acting and double acting hammer. (N/D ‘15)
They arc advantageous when driving heavy piles in compact or hard soils; the heavy ram striking
at - tow velocity produces least damage due to impact. The disadvantages arc low driving speed
and large headroom requirement. They are generally used to drive piles of light or moderate
weight in soils of average resistance against driving. This type of hammer can drive piles at fast
speed, requires less headroom and can be used to extract piles by turning them [i.e. the double-
acting hammer] upside down.
39. Give the list of equipment needed for the construction of tall structures. (M/J 12)
Some of the equipments used for construction of tall structures are:
Cranes
Derrick cranes
Mobile cranes
Overhead or gantry cranes
Tower cranes
Hauling equipment
Loading equipment
Lifting equipment
1.dipper dredger
2.back hoe dredger
3.bucket or ladder dredger
4.suction dredger
5.grab dredger
44. What is meant by Trenching?
A trench is a type of excavation or depression in the ground that is generally deeper than it is
wide (as opposed to a wider gully, orditch), and narrow compared to its length (as opposed to a
simple hole).
11
In geology, trenches are created as a result of erosion by rivers or by geological movement
of tectonic plates. In the engineering field, trenches are often created to install
underground infrastructure or utilities (such as gas mains, water mains or telephone lines), or later
to access these installations. Trenches have also often been dug for military defensive purposes.
In archaeology, the "trench method" is used for searching and excavating ancient ruins or to dig
into strata of sedimented material
45. Name the equipments used for dredging and trenching.(M / J ’12 ‘13)
The equipments used for dredging and trenching are the following.
Bucket or ladder dredger.
Hydraulic or cutter dredger.
Grab dredger.
Dipper dredger.
Rock dredger.
Clamshell
Grab
48. List out the different types of earth work equipment. (N / D ‘13)
Following are the earth work equipment:
o Excavators
o Excavator - loaders Bucket - Wheel Excavator Cable excavator
o Power Shovels
o Dipper Shovel Drag Shovel or Hoe Dragline Clamshell
12
o Bull dozers
o Dragline
o clamshell
o Scraper
o Tractors Motor Graders Scrapers Loaders
Part B
1. Explain in details about the types of earth work equipment with neat sketches.
13
Clearing and excavating machinery.
Hauling and conveying machinery.
Scrapers
Scrapers are the devices to scrap the ground to load the material, to the transport to the requirement
distances, ton dump at the intended site, to spread the dumped material over the required area, to
attain the desired thickness and to return back to do the next cycle. In simple terms scrapers are
designed to dig, load, haul, damp and spread as a scraper does a multiple works it is also called as
carry all. (7)
Motor grader
A grader is primarily a device for levelling or finishing earthwork. Sometimes it is also used for
mixing gravel,
making windrows and
trimming slope.
There are two types of graders, viz., towed and motorized.
Tunneling
Tunneling with liner plates
Needle beam method
Tunnel Boring Machine (TBM) method: TMB is used as an alternative to drilling and blasting
(D&B) methods. TBMs are used to excavate tunnels with a circular cross section through a variety of
subterranean matter; hard rock, sand or almost anything in between.
14
As the TBM moves forward, the round cutter heads cut into the tunnel face and splits off large
chunks of rock. The cutter head carves a smooth round hole through the rock -- the exact shape of a
tunnel. Conveyor belts carry the rock shavings through the TBM and out the back of the machine to a
dumpster. Tunnel lining is the wall of the tunnel. It consists of precast concrete segments that form
rings, cast in-situ concrete lining using formwork or shotcrete lining.
Shallow tunnels are of a cut-and-cover type (if under water of the immersed-tube type). Deep tunnels
are excavated, often using a tunneling shield. For intermediate levels, both methods are possible.
-- Cut-and-cover method
Cut-and-cover is a method of tunnel construction where a trench is excavated and roofed over. Strong
supporting beams are necessary to avoid the danger of thetunnel collapsing.
-- Shield method
The Shield method uses one or two shields (large metal cylinder) to cut out a tunnel through the soft
ground. A rotating cutting wheel is located at the front end of the shield. Behind the cutting wheel is a
chamber where, depending on the type of the TBM, the excavated soil is either mixed with slurry
(called slurry TBM) or left as is (earth pressure balance or EPB shield). Systems for removal of the
soil (or the soil mixed with slurry) are also present. Behind the chamber is a set of hydraulic jacks
supported by the finished part of the tunnel which are used to push the TBM forward. Once a certain
distance has been excavated (roughly 1.5-2 meters), a new tunnel ring is built using the erector. The
erector is a rotating system that picks up pre-cast concrete segments and places them in the desired
position. Behind the shield, inside the finished part of the tunnel, several support mechanisms can be
found that are part of the TBM: dirt removal, slurry pipelines if applicable, control rooms, and rails
for transport of the precast segments, etc. (6)
3. Describe in detail various equipments used for compaction, batching and mixing of
concrete. (M/J ‘12)(N/D ’14, ‘16) (13)
Batching of Concrete
It is the process of measuring concrete mix ingredients either by volume or by mass and introducing
them into the mixture. Traditionally batching is done by volume but most specifications require that
batching be done by mass rather than volume. Percentage of accuracy for measurement of concrete
materials is as follows:
Cement: When the quantity of cement to be batched exceeds 30% of scale capacity, the measuring
accuracy should be within 1% of required mass. If measuring quantity is less than 30% i.e. for
smaller batches then the measuring accuracy should be within 4% of the required quantity.
15
Aggregates: If the measurement is more than 30% of the scale capacity then the measuring accuracy
should be within 1%. If measurement is less than 30% then the measuring accuracy should be within
less than 3%.
Water: Water is measured in volumetric quantity as 1 litre = 1kg. In case of water, the measuring
accuracy should be within 1%.
Admixtures: For mineral admixtures same accuracy as that required for cement. For chemical
admixtures same accuracy as that required for water. Mineral admixtures accuracy is same as that of
cement because it is used as partial replacement of cement. As chemical admixtures are liquid or
added to water therefore its accuracy is same as that of water.
Mixing of Concrete: The mixing operation consists of rotation or stirring, the objective being to coat
the surface the all aggregate particles with cement paste, and to blind all the ingredients of the
concrete into a uniform mass; this uniformity must not be disturbed by the process of discharging
from the mixer.
Batch mixer: The usual type of mixer is a batch mixer, which means that one batch of concrete is
mixed and discharged before any more materials are put into the mixer. There are four types of batch
mixer.
Tilting drum mixer: A tilting drum mixer is one whose drum in which mixing take place is tilted for
discharging. The drum is conical or bowl shaped with internal vanes, and the discharge is rapid and
unsegregated so that these mixers are suitable for mixes of low workability and for those containing
large size aggregate.
Non tilting drum mixer:A non tilting drum is one in which the axis of the mixer is always
horizontal, and discharge take place by inserting a chute into the drum or by reversing the direction or
rotation of drum. Because of slow rate of discharge, some segregation may occur.
Pan type mixer:
A pan type mixer is a forced–action mixer, as distinct from drum mixer which relies on the free fall
of the concrete inside the drum. The pan mixer consist of a circular pan rotating about its axis with
one or two stars paddles rotating about vertical axis of pan.
Dual drum mixer:
A dual drum is sometimes used in highway construction. Here there are two drums in series, concrete
being mixed part of the time in one and then transferred to the other for the remainder of the mixing
time before discharging.
Charging the mixer:
There are no general rules on the order of feeding the ingredients into the mixer as this depend on the
properties of the mixer and mix. Usually a small quantity of water is fed first, followed by all the
solids materials. If possible greater part of the water should also be fed during the same time, the
remainder being added after the solids. However, when using very dry mixes in drum mixers it is
necessary to feed the coarse aggregate just after the small initial water feed in order to ensure that the
aggregate surface is sufficiently wetted.
16
4. What are the factors that influence the selection of equipment for earthwork? Explain the
types of earthwork equipments. (13)
Some of the factors which affect the out-put of an earthwork machine are
Material Type
Material type of a jobsite forms the topmost criteria in selection of an earthmoving system. Let’s take
the example of tractor scraper and articulated truck. Experienced engineers recommend use of
scrapers if the conditions are right and loading material is smooth and spreads easily. Wheel tractor
scrapers are said to be great for areas that have sandy loam soil because scrapers can pull through this
soil easily and it also loads quickly.
But if the jobsite has rocky soils or wet clay, then scrapers won’t work smoothly. For this, an
articulated truck would be more suitable because scrapers cannot pull through rocky soils easily. The
bottom line is before choosing any earthmoving system, get to know the material well.
Flexibility and Versatility
Sudden weather changes can drastically alter soil conditions. Exceptional heat will toughen the soil
whereas too much rain will make it exceptionally smooth. Therefore, before picking up a system, you
should check on its versatility and flexibility. You should select an earthmoving system which is
flexible enough to adapt to changing weather conditions.
Articulated haulers are considered to be exemplary systems when it comes to flexibility and
versatility. These equipment can perform well under limited traction. Therefore, if your jobsite falls
under region that experiences frequent weather changes, then articulated haulers can be a good
choice.
Hauling Distance
Hauling distance plays a vital role in selection of vehicles and equipment. Small vehicles will do fine
when hauling distance is small. But if earth has to be excavated over longer distances, then a bigger,
stronger vehicle would be required. Smaller vehicles won’t be able to sustain the pressure for so long,
and there are possibilities of break down. You’ll end up paying additional repairing costs.
Cut
Length and depth of cuts in jobsite greatly influences selection of earthmoving system. For example,
it becomes difficult to load a scraper if length of the cut is below 100 feet. But this is not so with
articulated haulers. These systems have top-loading methodology, which enables them to be placed
comfortably under excavators even in the most confined spaces.
Scrapers on the other hand operate pretty well in those areas where there is enough room for outlining
circuits. Similarly, if the task involves digging a borrow pit on a construction site, then articulated
truck becomes the most suitable choice for it.
Condition of Towing Roads
Besides considering towing distance, one should also consider conditions of towing roads before
finalizing an earthmoving system. While both scrapers and trucks can perform well on smooth roads,
rough roads can be a trouble for the former. In addition, rough roads will exert more pressure on
vehicles as they’ll have to exert more power. (8)
17
Tractor
and tractor units
Scrapers
or pans
Grading
and compacting machines.
Earthwork
equipment and operations
There is a wide range of excavating equipments available. In selection a much greater care and
thought needed to find a suitable machine for a particular job. The best performance of a machine
depends on a large number of factors. It should be noted that no machine is designed to suit a
particular set of conditions which may be demanded at a construction project. Thus a best designer
would design the machine such that the machine fits to more construction projects.
5. Mention about the various types of pile driving equipment. (M/J ‘12)(N/D ’16) (13)
Pile driving equipment comprise of the following
Driving rig
Guiding leaders
Pile hammer with accessories
Additional aids for preboring, jetting etc.
Boiler for steam raising or air compressor.
Driving
Rigs.
Driving rig provides basic operations of lifting the pile, holding the pile in position, hammering it
into the ground or of pulling it out of the ground and guiding the pile in the desired direction of
movement. The rig supports the boom and winch mechanism, driving hammer, the guiding leaders,
and a platform for mounting of auxiliary equipment such as a jet pump, drilling auger, steam boiler or
air
compressor.
Guiding
Leaders.
The leaders guide the pile and the hammer during operation which extends to the entire height of the
rig. In case of piles to be driven below the level of the rig into excavations, trenches or water
telescopic or extensible leaders can be used. The leader should enable the hammer to deliver blows
axially to the pile. During the process of driving, the driving rig should be strong and stable In case a
boom is used, adequate space should be available between the pile top and the point for the hammer
to
work.
Concreting equipment.
Concreting generally involves: batching and mixing, handling and transportation, placing, finishing
and
curing
A
concrete plant is provided with arrangements for
1. Receiving all ingredients for making concrete, viz., aggregates, sand and cement and water.
2. Weighing each ingredient of concrete for each batch of the mix.
3. Mixing these ingredient thoroughly to form a concrete of required consistency (7)
Concrete Batching and Mixing Plant.
18
Batching comprises of proportioning of ingredients of concrete, aggregate, sand, cement and water,
separately for each batch. In the construction field, batching and mixing plants consists of the
following (Peurify and Schexnayder 2009).
Aggregate Feeders
Aggregate feed bins are made available for each size of aggregate and sand and mix based on
volume. In important jobs weighing system is adopted. Aggregate feed bins are loaded by the
following methods:
By shovels directly into the bins.
By lorries tipping directly into the bins.
By means of boomscrapers from the aggregates stored in bulk heads on the ground.
6. Explain about the various types equipments for materials handling and erection of
structures. (N/D ‘13) (13)
a. Bulk or units
b. Large or small
c. Heavy or light
d. Shape
Rough or fragile
Volume of the material
Distance over which to be transported
Height to which to be lifted or to be lowered.
Availability of spaces for the equipment
Frequency of material to be handled (6)
Handling devices
Vertical motion devices (lifting and lowering devices)
Block and tackle
Winches Hoists
Elevators
Horizontal motion devices
Wheel barrows and hand trucks
Narrow-gauge mine rail road
Tractors and trailors
Skids
Pipe line
The types of cranes
Cranes are classified as given below:
o Derrick cranes
o Tower cranes
o Pillar cranes
o Overhead or gantry cranes
19
o Self-propelling boom cranes
o Crane trucks
7. What is meant by tunneling? Explain the features of the equipment used for tunneling
operation. (N/D ‘15) (13)
Batching
The measurement of materials for making concrete is known as batching. There are two methods of
batching:
(i) Volume batching: Volume batching is not a good method for proportioning the material because
of the difficulty it offers to measure granular material in terms of volume. Volume of moist sand in a
loose condition weighs much less than the same volume of dry compacted sand. The amount of solid
granular material in a cubic metre is an indefinite quantity. Because of this, for quality concrete
material have to be measured by weight only. However, for unimportant concrete or for any small
job, concrete may be batched by volume. Cement is always measured by weight. It is never measured
in volume. Generally, for each batch mix, one bag of cement is used. The volume of one bag of
cement is taken asthirty five (35) litres. Gauge boxes are used for measuring the fine and coarse
aggregates. Gauge boxes are generally called farmas. They can be made of timber or steel plates.
Often in India volume batching is adopted even for large concreting operations. In a major site it is
recommended to have the following gauge boxes at site to cater for change in Mix Design or bulking
of sand. The volume of each gauge box is clearly marked with paint on the external surface.
(ii) Weigh Batching: Strictly speaking, weigh batching is the correct method of measuring the
materials. For important concrete, invariably, weigh batching system should be adopted. Use of
weight system in batching, facilitates accuracy, flexibility and simplicity. Different types of weigh
batchers are available, the particular type to be used, depends upon the nature of the job. Large weigh
batching plants have automatic weighing equipment. The use of this automatic equipment for
batching is one of sophistication and requires qualified and experienced engineers. In this, further
complication will come to adjust water content to cater for the moisture content in the aggregate. In
smaller works, the weighing arrangement consists of two weighing buckets, each connected through a
system of levers to spring-loaded dials which indicate the load. The weighing buckets are mounted on
a central spindle about which they rotate. Thus one can be loaded while the other is being discharged
into the mixer skip. A simple spring balance or the common platform weighing machines also can be
used for small jobs.
21
9. Explain briefly about the Loaders,in construction,and its types. (13)
Loader is a machine in which a bucket is attached to the arms and capable of being raised, lowered
and dumped through mechanical or hydraulic controls. A very common type is one in which the
loader is having the bucket in the front which is known as front-end loader.
Loaders are self-propelled and versatile equipment which are mounted either on crawler or wheel-
type running gear. These loaders are fitted with front mounted general-purpose bucket.
Types of Loaders
Crawler Loaders
Wheeled Loaders
Crawler
Loaders
These are low pressure type which are generally preferred for digging and loading jobs of poor
ground and rock and sharp stony ground. These are preferred for short moves between loading and
dumping
points when there is no damage to tyres.
Wheeled
Loaders
These are generally four wheel drive. Two-wheel drives are preferred for handling light jobs on
good ground conditions. Protective chains are provided which increases the tyre operating life.
Four-wheel drives are used for bulk handling of coal, cement, fertilizer, etc, into hoppers and trucks.
These are additionally favored rather than more difficult to maneuver crawler.
22
10. Explain various types of vibratory compaction equipment. (13)
Vibratory Compaction Equipment
Vibratory compactors can be categorized into the following groups (Sharma, 1988):
Tandem vibratory compactors
Towed vibratory compactors
Towed sheepsfoot and tamping-footvibratory compactors
Self-propelled vibratory compactors
Hand-guided vibratory compactors
Tandem Vibratory Compactors.
Two types are available, viz., single-drum vibrating or double-drum vibrating. In the compactors
with double-drum vibrating system two tandem wheels are provided with separate controlled
vibrators in the front and rear rolls. Comparing single and double drum vibratory compactors, the
output of double drum vibratory compactor is to be 80 % more than the single-drum vibratory
compactor. The double-drum vibratory type has an option to operate the single- drum or the double-
drum. (6)
References:
1. http://www.heavyequipment.com/heavy-equipment/earthmoving-mining
2. http://www.slideshare.net/hamo92/5-construction-equipment-building-construction
3. http://www.slideshare.net/apashishparihar/construction-equipments-
18612938?next_slideshow=1
23
Part C
1. What are the equipments available for material handling? (13)
(https://en.wikipedia.org/wiki/Material-handling_equipment)
Material handling equipment is mechanical equipment used for the movement, storage, control and
protection of materials, goods and products throughout the process of manufacturing, distribution,
consumption and disposal. The different types of handling equipment can be classified into four
major categories: transport equipment, positioning equipment, unit load formation equipment, and
storage equipment.
Conveyors:Conveyors are used when material is to be moved frequently between specific points
over a fixed path and when there is a sufficient flow volume to justify the fixed conveyor investment.
Different types of conveyors can be characterized by the type of product being handled: unit load or
bulk load; the conveyor’s location: in-floor, on-floor, or overhead, and whether or not loads can
accumulate on the conveyor. Accumulation allows intermittent movement of each unit of material
transported along the conveyor, while all units move simultaneously on conveyors without
accumulation capability.
Jib crane
Cranes are used to transport loads over variable (horizontal and vertical) paths within a restricted area
and when there is insufficient (or intermittent) flow volume such that the use of a conveyor cannot be
justified. Cranes provide more flexibility in movement than conveyors because the loads handled can
be more varied with respect to their shape and weight. Cranes provide less flexibility in movement
than industrial trucks because they only can operate within a restricted area, though some can operate
on a portable base. Most cranes utilize trolley-and-tracks for horizontal movement and hoists for
vertical movement, although manipulators can be used if precise positioning of the load is required.
The most common cranes include the jib, bridge, gantry, and stacker cranes.
Pallet jack
Industrial trucks are trucks that are not licensed to travel on public roads (commercial trucks are
licensed to travel on public roads[7]). Industrial trucks are used to move materials over variable paths
and when there is insufficient (or intermittent) flow volume such that the use of a conveyor cannot be
justified. They provide more flexibility in movement than conveyors and cranes because there are no
restrictions on the area covered, and they provide vertical movement if the truck has lifting
capabilities.
Hand trucks (including carts and dollies), the simplest type of industrial truck, cannot transport or
stack pallets, is non-powered, and requires the operator to walk. A pallet jack, which cannot stack a
pallet, uses front wheels mounted inside the end of forks that extend to the floor as the pallet is only
lifted enough to clear the floor for subsequent travel.
2. List out the types of excavators. What are the advancements made in them? (13)
(http://www.engineeringintro.com/all-about-construction-equipments/excavator-types-
function-of-excavator/)
24
Excavator is the machine that can excavate the soil of various types forcefully and then using
hydraulic system a hydraulic force is generated and utilizing this force bucket is pull back towards
the machine. Bucket of excavator is replaceable. If front bucket is exchange with some other
attachments then excavator can be used for multi-purpose. For example: pile diver, hydraulic jack
hammer etc…
Excavator comes in numerous sizes depending on bucket size, length of boom, length of arm, and
operation speed. Performance of excavator can be measured from the production cycle. Production
cycle is the time that an excavator took to load the bucket from source, swing, dump, return back and
then dig again. Therefore, faster the operation speed, the faster will be the one complete cycle and
hence production cycle will increase. Excavators are mostly used for digging of soils and for loading
dump trucks. It is either of;
Crawler excavator
Crawler excavator runs on two endless tracks (chain wheel system). These types of excavators are
used in hilly areas where risks of sliding of machinery are on the verge. Crawler type excavator has
low ground pressure because of spreading of load on large area. Therefore, it is also used where soil
support is weak.
Wheel excavator
Wheel excavator runs on wheels and are used for excavation and loading of dump trucks and most of
the time it is only used for plain ground operations. Because of wheel, it is not suitable for hilly areas
due to low grip value to the ground.
Excavators are used for;
Digging of earth Crawler Excavator used for digging of earth
Earth Digging
Loading and dumping
Excavator used for loading trucks
Trenching
making Trenching using excavators
Excavator during trenching
Excavating Under Water
Breaking previous layers of highways and loading.
3. What are the modern equipments available for compaction, mixing and concreting? (13)
Concrete Batching and Mixing Plant: A concrete batching and mixing plant is a huge set up of
machines meant to combine cement, aggregates such as sand or gravel, and water to form concrete
(ready-mixed). These plants are either mobile or stationary and their sizes range from portable mixer
to heavy industrial mixing plant. Stationary plant mixer mixes the concrete before it is discharged
into a truck mixer. Revolving drums, conveyor and diesel or electric powered engines are used in this
plant. The truck mixer is used primarily as an agitating haul unit at a central mix operation. Dump
trucks or other non-agitating units are sometimes used for low slump and mass concrete pours
supplied by central mix plants.
25
Apart from stationary concrete plant mixer, mobile concrete mixing plant is also very popular
and widely used. Mobile concrete mixer plant is a unit mounted on a trailer which carries sufficient
unmixed materials, such as cement, sand, coarse aggregates, water, and any chemicals required, for
special mix specifications to the job site. In this type of plant cement, sand and aggregates are carried
in separate bins. The materials mixed proportionately are mixed with water and then discharged
through the conveyor system.
Truck Concrete Pumps: Truck mounted concrete pumps are used to supply concrete to places
which are difficult to reach by other heavy machines. Concrete Pumping Equipments are concrete
pump, heavy-duty pipe, hose and other accessories. When pressure is applied to a column of fresh
concrete by the concrete pump, it forces the concrete through a lubricated pipe. Concrete pumping is
useful in the areas where space available for construction equipment is limited. It is faster and saves
enough man power and energy. It is all weather operation and does not require heavy equipments like
cranes and hoists for other construction operations
Trailer Concrete Pumps: Like truck concrete pump, trailer concrete pump is designed to spread
concrete in an area which is difficult to reach out. The trailer pump is ideally suited for the
construction of foundations and pools, pressure grouting, and rock scaping. Trailer concrete pump
can pump concrete both horizontally and vertically. It can pump concrete to the difficult areas.
Pumping is faster than other methods. It is all weather operations. It saves enough time and energy
and helps in the completion of work with the faster rate. Concrete can be easily handled as it is
pumped to desired spot.
Mobile Concrete Placer: This Machine can be used for Bridges, Culverts, mass Concreting Purpose
and Canal Works. It is available in 56 feet length, pouring at the height of 27 feet and ability to fold
for Towing without removing discharge hopper. Mechanical power for the conveyor is provided by
25 HP (19 Kw) Engine, which drives a Hydraulic Double Pump. Hydraulic steering which pivots the
two under carriage wheels 900 to the Right and 45 0 to the Left and the steering wheel at the charging
end rotates the towing hitch wheel 360 degree about its yoke. So the conveyor can be moved in a
straight line and vertical too.
Concrete Mixer Truck: The hydrostatic truck mixer transports concrete/mortar directly from plant
to the place where it is to be poured. Concrete mixer with various capacities like 3, 4 and 6 cum is
mounted on truck. It has a wide range of applications specially for mass concreting works like Multi-
storied buildings, Bridge works etc. The basic function of transit mixer is to maintain the concrete's
liquid state, through the turning of the drum till the point of delivering at construction site.
4. Explain briefly about the operations involved in Tunnel Boring Machine (TBM) (13)
(http://www.railsystem.net/tunnel-boring-machine-tbm/)
A tunnel boring machine (TBM) also known as a “mole“, is a machine used to excavate tunnels with
a circular cross section through a variety of soil and rock strata. They can bore through hard rock,
sand, and almost anything in between. Tunnel diameters can range from a meter (done with micro-
TBMs) to almost 16 meters to date. Tunnels of less than a meter or so in diameter are typically done
using trenchless construction methods or horizontal directional drilling rather than TBMs.
26
Hard rock TBMs
In hard rock, either shielded or open-type TBMs can be used. All types of hard rock TBMs excavate
rock using disc cutters mounted in the cutter head. The disc cutters create compressive stress
fractures in the rock, causing it to chip away from the rock in front of the machine, called the tunnel
face. The excavated rock, known as muck, is transferred through openings in the cutter head to a belt
conveyor, where it runs through the machine to a system of conveyors or muck cars for removal from
the tunnel.
Open-type TBMs have no shield, leaving the area behind the cutter head open for rock support. To
advance, the machine uses a gripper system that pushes against the side walls of the tunnel. The
machine can be continuously steered while gripper shoes push on the side-walls to react the
machine’s forward thrust. At the end of a stroke, the rear legs of the machine are lowered, the
grippers and propel cylinders are retracted. The retraction of the propel cylinders repositions the
gripper assembly for the next boring cycle. The grippers are extended, the rear legs lifted, and boring
begins again. The open-type, or Main Beam, TBM does not install concrete segments behind it as
other machines do. Instead, the rock is held up using ground support methods such as ring beams,
rock bolts, shotcrete, steel straps, and wire mesh (Stack, 1995).
In soft ground, there are two main types of TBMs: Earth Pressure Balance Machines (EPB) and
Slurry Shield (SS). Both types of machines operate like Single Shield TBMs, using thrust cylinders to
advance forward by pushing off against concrete segments. Earth Pressure Balance Machines are
used in soft ground with less than 7 bar of pressure. The cutter head does not use disc cutters only,
but instead a combination of tungsten carbide cutting bits, carbide disc cutters, and/or hard rock disc
cutters. The EPB gets its name because it is capable of holding up soft ground by maintaining a
balance between earth and pressure. The TBM operator and automated systems keep the rate of soil
removal equal to the rate of machine advance. Thus, a stable environment is maintained. In addition,
additives such as bentonite, polymers and foam are injected into the ground to further stabilize it.
Urban tunneling has the special challenge of requiring that the ground surface be undisturbed. This
means that ground subsidence must be avoided. The normal method of doing this in soft ground is to
maintain the soil pressures during and after the tunnel construction. There is some difficulty in doing
this, particularly in varied strata (e.g., boring through a region where the upper portion of the tunnel
face is wet sand and the lower portion is hard rock).
TBMs with positive face control, such as EPB and SS, are used in such situations. Both types (EPB
and SS) are capable of reducing the risk of surface subsidence and voids if operated properly and if
the ground conditions are well documented.
27
When tunneling in urban environments, other tunnels, existing utility lines and deep foundations need
to be addressed in the early planning stages. The project must accommodate measures to mitigate any
detrimental effects to other infrastructure.
28