0% found this document useful (0 votes)
3 views6 pages

Method Statement of Door Window

This document outlines the method statement for the installation of doors and windows at the PepsiCo GF Project in Nalbari, Assam. It includes the purpose, scope, equipment, materials, sequence of works, and responsibilities for quality control and safety during the installation process. Key installation procedures for both doors and windows are detailed to ensure compliance with project specifications and standards.

Uploaded by

qc.pepsico
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
3 views6 pages

Method Statement of Door Window

This document outlines the method statement for the installation of doors and windows at the PepsiCo GF Project in Nalbari, Assam. It includes the purpose, scope, equipment, materials, sequence of works, and responsibilities for quality control and safety during the installation process. Key installation procedures for both doors and windows are detailed to ensure compliance with project specifications and standards.

Uploaded by

qc.pepsico
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

METHOD STATEMENT OF DOORS AND WINDOWS

INTALLATION
PROJECT- PEPSICO GF PROJECT NALBARI ASSAM

METHOD STATEMENT
OF
DOORS AND WINDOWS
INTALLATION
For
Name Designation Sign
SEMAC

Prepared By KULDIP MODI QA/QC Engineer

Reviewed By

Approved By

For CLIENT Name Designation Sign

Reviewed By
METHOD STATEMENT OF DOORS AND WINDOWS
INTALLATION
PROJECT- PEPSICO GF PROJECT NALBARI ASSAM

LIST OF CONTENTS

1. PURPOSE
2. SCOPE
3. PLANT AND EQUIPMENT
4. MATERIALS
5. SEQUENCE OF WORKS
6. Delivery, storage, and handling
7. DOORS INSTALLATION
8. WINDOWS INSTALLATION
9. RESPONSIBILITY
METHOD STATEMENT OF DOORS AND WINDOWS
INTALLATION
PROJECT- PEPSICO GF PROJECT NALBARI ASSAM

1. PURPOSE
1.1. The purpose of this method statement is to execute the scope of work, provide and
maintain an effective quality control in compliance with standards and good practices at all
stages/activities for doors and windows installation.
1.2. Construction stages shall be delivered according to the Inspection and Test Plan (ITP).

2. SCOPE
2.1. The scope of this procedure covers the general procedure for doors and windows
installation.
The purpose of the documentation is to implement the procedure & to ensure that the
quality control aspects are maintained and accurate records are established.
2.2. The objective is to ensure that the construction plan is executed, controlled and
documented in compliance with Contract Drawings & Specifications

3. PLANT AND EQUIPMENT


Following is a list (not limited to) of the mechanical equipment to be utilized in this
operation:
 Drilling machine
 Trowels and roller
 Grinder machine
 Measuring tape
 Calibrated survey tools
 Hand Tools & PPE

4. MATERIALS
Following is a list (not limited to) of the material to be utilized for installation of rolling up
doors, metal doors and windows
 Hollow metal doors & FRAM
 Hinges
 Stoppers

5. SEQUENCE OF WORKS
 Site Planning & Preparation
 Site Clearing
 Marking and confirm opening size
 Doors/ windows installation
 Glazing/Grouting/sealant application
 Protection and cleaning
6. Delivery, storage, and handling
METHOD STATEMENT OF DOORS AND WINDOWS
INTALLATION
PROJECT- PEPSICO GF PROJECT NALBARI ASSAM

 Store doors in clean dry ventilated areas. Stack doors flat and off floors, supported to
prevent wharfing. No other materials are to be placed on top of stacked doors.
 All doors will be packed with plastic and cardboard protection to the edges.
 Store flat over level surface above the floor on wood blocks.
 Each door and frame are tagged with a sticker indicating the door number and
location.
 All doors and frames delivered with finished factory painting, if there is any paint
damages final touch will be at the site before handing over.

7. DOORS INSTALLATION
 Physical dimensions for the clear opening and doors to be check
 Anchoring: Install minimum four anchors per jamb. Locate the anchors at the hinges
and as close to the bottom as feasible, in the hinge jamb and in a corresponding
position in the shim strike jamb
 Wall Preparation: Place the frame in the completed wall opening. Check for square
nests. Mark the wall through the holes in the jamb provided at the anchor points.
Drill appropriate holes at the marks. Install the sleeve anchors. Frame installation:
Insert bolts (3/8 in. flat head sleeve anchors must be seed on the fire rated frames)
through the frame soffit into the expansion shield. Shim behind anchors above bolts
to ensure a plumb frame
 The methods of plumbing the frame and the use of the spreader noted under
masonry wall, also apply to this wall condition.
 Tighten the screws continually check plumb, square and twist in the jambs as
tightening progresses.
 Doors installation: After installation of frame doors will be installed and aligned
properly.
 Grouting of frames: Plaster guards and junction boxes are intended to protect
hardware preparations and tapped mounting holes from masonry grout of 4 in. (100
mm) max. slump consistency which is hand toweled in place. If a lighter consistency
grout (greater than 4 in. (127 mm) slump when tested in accordance with ASTM
C143) is to be used, special precautions must be taken in the field to protect the
hardware preparations. Any grout or other bonding material shall be promptly
cleaned off of frames or doors following installation. Hollow metal surfaces shall be
kept free of grout, tar or other bonding materials or sealers. Grouting materials
which require air to dry (cure) are not recommended for use in any closed section,
such as a mullion.
METHOD STATEMENT OF DOORS AND WINDOWS
INTALLATION
PROJECT- PEPSICO GF PROJECT NALBARI ASSAM

8. WINDOWS INSTALLATION
 Proper dimensional control and setting out of the wall opening are critical in
ensuring the quality of window installation.
 The use of cement grout to fill up large gaps should be avoided as this may lead to
cracks in the grout which would lead to water seepage through the building
envelope.
 Reference line should be set up at appropriate location to facilitate proper alignment
of the wall openings and installation of the window frames.
 Close dimensional control on wall opening should be exercised to ensure the gap
between the wall and window frame is within the range of 7-20mm wide.
 Place the window frame and mark the location for anchors and drill appropriate
holes at the marks. Install the sleeve anchors.
 Insert bolts through the frame soffit into the expansion shield. Shim behind anchors
above bolts to ensure a plumb frame.
 Check the levelness and squareness of the installed frame by carrying out a diagonal
dimensional check as shown the figure
 After fixing the window in their opening the glass doors will be installed.
 Apply silicone sealant at aluminum window frame boundary. Cleaning is required
before applying silicone sealant to ensure that the contact surfaces are clean
enough.

9. RESPONSIBILITY

1. Project Manager will ensure that the works have been carried out as per
Project requirements with regards to Quality, Health, Safety and the Environment.
2. Construction Manager will directly supervise the Land surveyor, the Project
Engineer and Foreman. He is responsible to ensure that all the correct procedure
have been followed, and that any necessary permits for the works have been
obtained in advance He has full control over the use of the labour, plant &
equipment. He reports directly to the Project Manager.
3. Project HSE Engineer ensures that all operations are carried out in a safe
manner and in accordance with the minimum requirement set out in the health,
safety and environmental regulations and related documents.
4. Shop drawings and technical submittals as required.
5. . Site Engineer is responsible to ensure the works have been carried out as per
approved drawing and this Method Statement.
6. QA/QC Engineer is responsible for ensuring the works are carried out as per
approved Method Statement, Specifications and the requirements of the Project.