Amaan Final Report 11
Amaan Final Report 11
Submitted by
2
ACKNOWLEDGEMENT
3
Chapter 1
INTRODUCTION
Objectives:
❖ To orient us with the practical CE works.
❖ To allow us to apply our theoretical knowledge into practical fields.
❖ To let us gaining practical experience.
❖ To let us understand the planning, design, drawing of
construction
❖ Plan should include construction methods to be adopted for
different Construction activities.
❖ To get exposure with the management and communication
functions Performed with in a construction project.
❖ Construction projects are executed based on the drawing and
specifications
4
CHAPTER 2
INTRODUCTION OF FIRM
5
Chapter 3
6
3.1 Drafting and Design of Building:-
1) Software Utilized
During my internship, I worked extensively with industry-standard
software such as AutoCAD, Revit, and SketchUp. These tools were
crucial in creating precise architectural and structural drawings. I
developed detailed floor plans, elevations, sections, and 3D models.
2) Design Process
The design process began with interpreting the client’s requirements
and translating them into feasible designs. I collaborated with senior
engineers to ensure that designs met both functional needs and
aesthetic considerations.
This phase included:
• Conducting site analysis to understand constraints and opportunities.
• Preparing preliminary sketches and refining them based on feedback.
• Ensuring compliance with local building codes and standards.
• Producing final drawings for client approval and construction use.
7
Fig. no. 1 plan
8
Fig. no. 2 plan
9
3.2 Field Work
1) Site Surveys
I participated in site surveys to gather essential data for planning and design.
This involved:
• Using surveying equipment like theodolites, total stations, and GPS devices.
• Mapping the topography and identifying site-specific challenges.
• Documenting existing site conditions.
2) Soil Testing
Understanding soil properties is crucial for any construction project. I assisted in:
• Collecting soil samples for laboratory analysis.
• Conducting field tests such as Standard Penetration Tests (SPT) and Plate Load
Tests.
• Interpreting soil test results to determine load-bearing capacity and suitability
for construction.
3) Construction Inspection
Regular site inspections ensured that construction activities adhered to design
specifications and safety standards. My responsibilities included:
• Monitoring daily construction activities.
• Ensuring compliance with safety protocols.
• Reporting any deviations or issues to the project manager.
• Verifying that materials used on-site met specified quality standards.
10
3.3 Substructure
• The substructure consists of all of the parts that support the
Superstructure.
• The main components are piers or interior bents, footings, and piling.
• Footings also serve to transmit loads borne by the substructure to the
Underlying foundation material.
• When the soils beneath a footing are not capable of supporting the
Weight of the structure above the soil, bearing failure occurs. The
Foundation shifts or sinks under the load, causing structure Movement and
damage
3.4 Superstructure
• The superstructure consists of the components that actually Takes
the load and transfer to substructure.
• It consist frame of columns, beam, and slab.
• Improper concrete placement, such as failure to consolidate the Mix
as the concrete is placed, pouring the concrete so slowly That the concrete
begins the initial set, or not maintaining a Placement rate.
3.5. Sab
One way slab
One way slab is a slab which is supported by beams on the two opposite
sides to carry theLoad along one direction. The ratio of longer span (l) to
shorter span (b) is equal or greater Than 2, considered as One way slab
because this slab will bend in one direction i.e inThe direction along its
shorter span.
Two way slab
Two way slab is a slab supported by beams on all the four sides and the
loads are carriedBy the supports along with both directions, it is known as
two way slab. In two way slab,The ratio of longer span (l) to shorter span (b)
is less than 2
3.6 Estimation
1 Quantity Takeoff
11
Accurate estimation of material quantities is vital for project
budgeting. I was involved in: Performing quantity takeoffs from
construction drawings. Using software tools like MS Excel and
specialized estimation software to streamline the process.
2 Cost Estimation
I assisted in preparing detailed cost estimates, which included:
Calculating the costs of materials, labor, and equipment.
Considering contingencies and potential cost variations.
Presenting estimates in a clear and comprehensive format for
stakeholders. Assisting in the preparation of bills of quantities
(BOQs).
3.7 Government House Permission
1 Documentation
Obtaining government permissions involved extensive
documentation. I learned to prepare and submit:
Site plans, building plans, and structural drawings.
Environmental impact assessments and safety reports.
Applications for zoning variances and building permits.
2 Liaison with Authorities
I gained experience in communicating with local authorities to
ensure compliance with regulations. This included:
Attending meetings with municipal officials.
Addressing queries and providing additional information as
required.
Following up on application statuses to expedite approvals.
3.8 RCC Design
1 Structural Analysis
12
RCC design requires a thorough understanding of structural behavior. I
worked on:
Analyzing loads and stresses on structural elements using software like STAAD
Pro and ETABS.
Designing beams, columns, and slabs to ensure they could safely bear
anticipated loads.
Ensuring that the designs were economical and met safety standards.
Purpose of BBS
1. Accuracy: Provides precise details of the reinforcement, including size,
shape, length, and quantity, which helps in minimizing wastage.
2. Quality Control: Ensures that the reinforcement is placed correctly
according to the design specifications, maintaining the quality of the
construction.
3. Cost Management: Helps in estimating the cost of reinforcement
steel, aiding in budget control and procurement planning.
4. Efficiency: Streamlines the construction process by providing clear
instructions for cutting and bending the rebar, reducing delays.
Chapter 4
Construction of building
14
4.1 Site Clearance
The process of site clearance is generally undertaken as part of enabling works, carried
out to prepare a site for construction. It involves the clearing the site to allow other
remedial, treatment or demolition works to take place before the actual construction
works can begin. It involves clearing a site of any machinery or equipment, unwanted
surplus materials, rubbish, and so on. Site clearance may also involve clearing away
vegetation and surface soil, and levelling and preparing the ground for the planned
construction works.
The construction site is usually prepared in two steps: first the vegetation is cleared,
and then the surface soil layer is removed.
This helps in obtaining the correct measurement without obstruction. In short, site
should be cleaned property by all the way otherwise no any other obstruction
processed carried out further.
A plan is which arrangement of placing site office store room, labor quarter medical
aid store, go down for keeping Construction materials and other facilities is properly
prepared of chalk out, is called as Job Layout or site layout.
15
The arrangement of processes should be such that the work is done smoothly and in
orderly manner. In Job Layout plan, there should be properly co- relation and among
different unit in such a way that site office and Ware house are placed closed to the
entrance of site so as to have better contact to visitor.
The area should be properly allotted in such a way that time require in carrying
material is minimum which Reflects on increasing of efficiency.
A building is set out in order to clearly define the outline of the excavation and the
centre line of the walls, so that construction can be carried out exactly according to
the plan. The centre line method of setting out is generally preferred and adopted.
Accurate setting out is therefore a fundamental part of the construction works, and
errors can be very expensive and time consuming to correct. It should only be
undertaken by competent persons, and all work should be thoroughly checked,
preferably by different personnel.
16
Fig.no. 3 SUBMISSION DRAWING
17
FIG. NO. 4 SUBMISSSION
Excavation :
18
There are two types of excavation preferably done for foundation:
1. Shallow excavation
2. Deep excavation
For small buildings, excavation is carried out manually by means of pick axes, crow
bars. Spades etc. In case of large buildings and deep excavation, mechanical earth
cutting equipment can be used.
For hard soils when the depth of excavation is less than 1.5 m, the sides of the trench
do not need any external support. If the soil is loose or the excavation is deeper, some
sort of shoring is required to support the sides from falling.
19
Fig.no.5 foundation
Footing
A footing is the part of the foundation which supports it and transfers the load to the
larger area on soil, so it safe the foundation from the settlement. It is generally
provided with reinforcement and cast with concrete. Footings are majorly used in
conjunction with shallow foundations commonly. The width and depth of any footing
mainly depend on the type of soil and the size and type of foundation.
It is the portion of Structure which transmit the load to the soil. The footing provided was
20
Column
At Sites Generally Columns of sizes 230mm *350mm and 230* 400 mm with 6 bars of
12mm diameter with spacing of about 75mm c/c are provided with M20 grade of
Concrete where Aggregate of size 20 mm and Cement of grade 53 generally used.
Fig.no.6 column
Construction of plinth beam above the natural ground is another application of this
type of beam.
Strength of plinth beam concrete shall not be smaller than 20MPa. If concrete is mixed
manually, then an extra of 20% cement need to be added to the mixture. Figure 3
show plinth beam concrete preparation placement.
Formwork used for plinth beam construction should be properly installed and
adequately secured prior to concrete placement as shown in Figure-4. The concrete
needs to be compacted sufficiently to prevent steel bars from aggressive elements.
22
That part of the foundation system which supports the exterior wall of the
superstructure.
floor column and short column are become free, which reduces the ability of
earthquake
Resisting.
2-inch clear cover is given in grade beam. (to resist moisture from soil)
23
FIG.NO.7 SITE
24
4.9. Precautions s and checks made during P.C.C laying on Site
Before laying P.C.C, to Check whether the surface has been levelled and
compacted properly
Tools like (randa ) free from any sticked material usually if already used may have
material like cement concrete over resulted if not washed properly after use.
Above mentioned point may lead to improper finishing of supposed P.C.C floor
laying
To see mentioned Grade of Cement being added for Concrete
prepration To see proper Grade of Concrete being followed by workers
on site.
M15 grade on sire means in forms of pan for sand is 12 pans of sand
While the flooring is being done the level of surface maintained properly.
Fig.no. 8 CONSTRUCTION
25
Fig.no. 9 slab casting
The bond in brick masonry, which adheres bricks together, is produced by filling joints
between bricks with suitable mortar. Special cautions shall be practiced while mortar
is mixed and placed since it greatly affect the performance and durability of masonry
structure.
26
2. Brick Work in Cement
This type of brick masonry is construction by laying bricks in cement mortar
rather than mud which is used in brick work in mud. There are three major
classes of brick work in cement which are summarized below as
First Class
Cement of lime mortar is used,
The surface and edges of bricks are sharp,
And the thickness of mortar joints doesn't exceed 1 Omm
Second Class
Ground moulded bricks are used,
Bricks are rough and shape is slightly irregular,
The thickness of mortar joint is 12 mm.
Third Class
Bricks are not hard ,rough surface with distorted shape,
Used for temporary structures,
Used in places where rainfall is not heavy.
Brick must saturate 24 hours and confirm fungus & salinity free before use.
27
During brick work vertical lining check with plum bob and also check for horizontal
lining.
Brick work must leakage free. Check mortar plashing between the bricks.
After rubbing C.C and R.C.C surface then apply brick work in case of in contact with C.C
or R.C.C
4.11 Chipping / Hacking
Cheeping is mainly used to rough the surface.
Minimum of 2- no. Of cheep exist per squar inch
Depth of cheep nearer 2 mm
4.12 Plastering
Plastering is present all around us; there are various types of plastering, with each of
them has different mixing techniques and applications. Hence, it is essential to be able
28
to identify which type is best suitable for us. This step-by-step guide will give you
detailed information on how to perform the Plastering process.
Plastering means plastering done for internal walls in which the work procedure
provides a finished Surface that is firm and smooth. The plaster acts as a thermal
insulating layer to an extent. It acts as a layer for fire protection.
The mortar joints of the wall are kept rough to give a good bonding to hold plaster.
Excess amount of mortar should be removed after block work masonry/block work,
and pointing is to be done for all the joints.
Clean all the surfaces and joints of the wall with a wire brush; there should be no
grease or oil etc., left on the wall surface.
If there are any holes or cavities on the surface, fill it in advance with concrete and dry
for at least a day.
Plaster the entire wall and wash the mortar joints, and keep it wet for at least 6 hours
before applying cement plaster.
29
To reduce the consumption of mortar, if the projection on the wall surface is more
than 12 mm, then knock it off to obtain a uniform surface of the wall.
Hacking/ Chipping must be made on all concrete surfaces such as columns, beams,
ceiling, and retaining wall before plastering to ensure proper bonding between mortar
and surface.
Ensure all the electrical conducting work is complete.
Cover groove cutting by chicken mesh to avoid cracks developed by groves in the
future.
In the case of brick masonry/block work, the thickness of plaster is generally 12 mm,
and in the case of concrete masonry/block work, this thickness varies from 9 to 15
mm.
The ratio of cement and sand for plaster varies from 1:3 to 1:6.
The supervisor should ensure that water is mixed to dry mortar for the quantity of dry
mortar used or consumed within 30 min.
Apply plaster between the spaces formed by the screeds on the wall surface, using the
trowel.
Before starting external plaster, ensure that masonry/block work is complete in all
respects.
Chapter 5
BUILDING MATERIALS
30
5.1 Cement
The cement often called the magic power is a fine ground material consisting of
compound of lime ,silica alumina and iron. When mixed with water it forms a paste
which hardened and bind the aggregates (sand, gravel, crushed rock, etc.) together to
form a durable mass called the Concrete.
Cement is the binder that holds concrete and mortars together. Which is why it play
the most critical role in giving strength and durability to your building.
Cement uses for domestic building such as home are basically of three types.
Portland Slag Cement: Portland slag cement (PSC) conforming to IS:455 A combination
of good quality blast furnace slag (from the iron steel industry) with clinker (which
makes the OPC) and gypsum.
Ordinary Portland Cement: Ordinary Portland cement (OPC) 33 grade conforming to IS:
269, 43 grade conforming to IS: 8112 and 53 grade conforming to IS: 12269 A
combination of clinker and gypsum of good quality. Ordinary Portland cement is
manufactured by first burning at a very high temperature the mixture of calcareous
(mainly calcium carbonate) and argillaceous (mainly clay) and then grinding the
calcined product (i.e. clinker) with small amount of gypsum in to a fine power known
as ordinary Portland cement.
Improve Workability
31
Improved resistance to acid and chlorides
Easier to finish
Reduced shrinkage
1. Ambuja Cement
2. Ultratech Cement
3. Deccan Cement
4. ACC Cement
5. Shree Cement
Sand
These are cohesion less aggregates of either, rounded sub rounded,
angular, sub angular or flat fragments of more or less unaltered rock of
minerals consisting of 90% of particles of size greater than 0.06 mm and
less than 2 mm.
32
Medium sand: It is one, which contains 90 & of particles of particles size greater
than 0.2 mm and less than 0.6 mm.
Fine sand: It is one, which contains 90% of particles of size greater than 0.06 mm
and less than 0.2 mm.
It should be: Clear, angular and hard Free from clay, mica and soft, flaky material
Graded, which means it should be a mix of fine, medium and coarse sand Fee from
contaminates like sea salt Consistent in moisture (water) content which should not
exceed 7%. When mixing concrete the moisture Content must be taken in to
consideration.
The price of sand includes three or four components- base cost, Transportation,
handling and number of Intermediaries. Procuring sand in bulk Directly from the
source will be cheaper.
33
Fig.no.11 sand
34
FIG.NO.13 SIDE VIEW
Aggregate
35
Aggregates is a general term applied to those inert (that chemically inactive) Material,
which when bounded together by cement, form concrete.
Most Aggregates used in this country are naturally occurring aggregates such as Sand
crushed rock and gravel.
l . Fine Aggregates: Most of which passes through 4.75 mm I.S. sieve And retained
on 150 micron.
2. Coarse Aggregates: Most of which passes through 63 mm I.S. sieve And retained on
4.75 micron.
3. All in Aggregate: Mixed aggregate, as it comes from the pit or riverbed.
It is sometimes used for unimportant work without separating into different
Sizes.
The properties should comply with the norms laid down in IS: 38-1970
Specification for C.A. and F.A. from natural sources for concrete.
Free from adherent coating, clay lumps, coal and coal residues and should
Contain no organic or other admixture that may cause corrosion of the
reinforcement Or impair the strength or durability of the concrete. The
shape
36
(rounded,
Irregular, angular and flaky) and sizes of the aggregates should conform to
the
Strength and workability requirements.
5.3.3 Uses of the Aggregates
1) Naturally occurring crushed stone aggregates can be used for producing Any type of
2) Broken brick aggregates is used to produce plain concrete but not suitable For R.C.C.
3) Air- cooled blast furnace slag, which is a by- product in the process of pig iron, Forms
a stronger and durable concrete when mixed with sand, and has a high
BRICKS
Bricks are distinguished by their base (row) material and size. Standard brunt clay
bricks come in the size 10" x 5" x 3". Modular bricks, rarely used because they
are not easily available, come in the size 200mm x 100mm x 100mm
(including mortar thickness) Fly ash bricks, sometimes also come in modular
form.
larger surface bearing the Manufacturer's brand. These also provide a good
The modular bricks do not have the frog on them. Fly ash bricks exhibit almost
37
precise pointing is possible if the shapes are perfect.
appropriate manner. Such concrete is called reinforced concrete and the bars
are called the reinforcement. These bars are provided at various locations to
resist the internal forces, which are developed due to the loads acting on the
structure.
38
5.5.1 Precautions selecting bars
Steel bars/rods should be responsibly clean and free of rust.
Bars that cannot be easily bent manually or mechanically should be rejected.
Optimum length bars must not be chosen to reduce wastage in cutting.
To avoid laps, shorter bars must not be accepted
Welded length of the bars should not be accepted
5.6 Water
The strength and durability of concrete depends also on the amount of water
mixed With it. Too much or too little Water can adversely affect the strength of
concrete. After concrete is cast, water is used to cure it so that the temperature
is Controlled and concrete matures slowly.
It is very important to use clean, potable water in quality concrete production.
Brackish or salty water must never be used. Contaminated water will produce
Concrete mortars with lower durability, erratic set characteristics and
inconsistent Colour.
. Crushed stone produces much more angular and elongated aggregate, Which
have a higher surface to volume ratio better bond characteristics but Require
more cement paste to produce a workable mixture.
The surface texture of the aggregate can be either smooth or rough. A smooth
Surface can improve workability yet a rougher surface generates a stronger
bond Between the paste and the aggregate creating a higher strength.
The grading or size distribution of aggregate is an important characteristic
Because it determines the paste requirement for workable concrete. The
required Amount of the concrete paste is dependent upon the amount of void
space that must be filled and the total surface area that must be covered. When
the particlesare of uniform size the spacing is the greatest but when a range of
sizes is used the void spaces are filled, the less workable the concrete becomes,
therefore, a compromise between workability and economy is necessary.
Plain concrete is very strong in compression but its tensile strength is only About
1/10 of the strength in the compression. So, the use of the plain concrete Is
limited to the structure in pure compression. Steel being equally strong in
Compression and tension, is, therefore, used to reinforce the concrete in a
suitable Way so that it can be used to build supporting structure where tension
also Develops . Concrete, thus reinforced is known as reinforced concrete .
40
This combination is made because long steel bars can develops its full Strength
where it cannot carry equal amount of compressive force due to its Buckling
which is caused by the slenderness. Thus, the combination of concrete And steel
bars has proved to be ideal, as the two material are used to resist the Stresses
for which they are most suitable.
Chapter 6
Design philosophy
R.C.C. design of building is being carried out mainly by three methods of design.
They are namely:
The Limit state method is now is vogue in all government design offices And premier
private
Consulting firms. The B.I.S. have published I.S.: 456-2000 incorporating the Use of the
Limit state method of Design. The designer should therefore get well versed with the
theory of Limit State method.
6.1 Limit State Method is a judicious amalgamation of Working Stress Method and
Ultimate Stress Method, removing the drawback of both of the method but retaining
their good points. It is also based on sound scientific principles and backed by 25 year
of
research.
41
The Limit State Method has proved to have an edge over the Working Stress Method
from the economic point of view. Consequently we need no stick to Working Stress
Besides analytical part of the structural design, following factors should also be kept in
a) Strength of structure.
b) Durability of structure.
lifetime of structure.
f) Aesthetics of structure
42
Chapter 7
Cement concrete
Concrete gains compressive strength progressively with time. The strength Achieved
at the end of the 28 days is called the Characteristics Compressive Strength of the
concrete and is designed as a Grade. About 60% of this strength is Achieved at the end
of the 7 days from the date of casting. Concrete continues to Gain strength even
beyond 28 days, albeit marginally.
Different compressive strength of the concrete can be achieved by Mixing the basic
ingredients in different proportions.
Being a material Moulded at site, the durability of the concrete over a long period of
time depends On its mixing, placement, vibration and curing which together
contribute to Its workmanship .
43
7.1 Properties of Cement concrete
It should be have high compressive strength. The tensile and shear strengths are
Generally about 8 to 12% and 8 To 10% of their compressive strength respectively.
Indicates the ease with which it can be mixed, placed and compacted. Generally
44
7.1.4 Elasticity of concrete
The concrete is not a truly elastic material and elastic modulus is effect by The
strength, age, and moisture content of the concrete and the type of the Aggregate
used. The concrete undergoes an extra strain in addition to instantaneous Strain on
application of a load or stress, sufficient time. This extra strain is called Creep of
concrete and is permanent in character not recovered on the removal of Load.
shrinkage on one-hand causes cracks in concrete, while on the other, it grips The
reinforcement tightly and hence proper bond between concrete and
Reinforcement when used in
R.C.C. work
45
7.2.1 Batching of the concrete
After fixing the proportion of different ingredients of concrete for a particular Work,
the material C.A., F.A., cement and water measured out in batches for Mixing. The
process is known as Batching. This process of batching may be Carried out by weight or
by volume.
a) Weight batching: - The unit of weight, for material of concrete, is usually Kilogram.
b) Volume batching: - In batching by volume, all ingredient i.e. water, cement, Sand
and coarse aggregate are measured in litres, where the resulting concrete (being)
solid measured in cubic meters.
7.5 Compaction
In some types of construction, the concrete is placed in forms, and then Consolidated.
The consolidation compacts fresh concrete to mold it within the Forms and around
embedded items and reinforcement and to eliminate stone Pockets, honeycomb and
entrapped air. It should not remove significant amount Of intentionally entrained air.
46
Vibration either internal or external is the most widely used method for Consolidating
concrete. When concrete is vibrated, the internal friction between The aggregate
particles is temporarily destroyed and the concrete behave like A liquid; it settles in
the forms under the action of gravity and the large Entrapped air voids rise more easily
to the surface. Internal friction is Re-established as soon as vibration stops.
Fig.no.11 compaction
47
7.6 Finishing
Concrete that will be visible, such as slab like driveway, highway or patios often Need
finishing. Concrete slabs can be finished in many ways, depending on the Intended
service use. Options include various colours and textures, such as exposed Aggregate
or a patterned stamped surface. Some surface may require only Strike off and
screendingto proper contour and elevation, while for other Surface a broomed,
floated, or trowelled finish may be specified. In slab Construction screeding or strike
off is the process of cutting off excess concrete to Bring the top surface of the slab to
proper grade.
A straight edge is moved across The concrete with a sawing motion and advanced
forward a short distance with Each movement. Bull floating eliminates high and low
spots and embeds large aggregate particles Immediately after strike off.
This look like a long handled straight edge pulled across the concrete. Joining is
Required to eliminate unsightly random cracks. Construction joints are made With a
groover or by inserting strips of plastic, wood, metal, or performed joints Material into
the unhardened concrete. Saw cut joints can be made after the Concrete is sufficiently
hard or strong enough to prevent the reveling.
After The concrete has been jointed it should be floated with a wood or metal hand
Float or with a finishing machine using float blades. This embeds aggregate Particles
just beneath the surface; removes slight imperfections, humps, and Voids; and
compacts the mortar at the surface in preparation for addition finishing Operations.
Where a smooth, hard, dense surface is desired, floating should Be followed by steel
troweling. Troweling should not be done on a Surface that has not been floated;
troweling after only bull floating is not an Adequate finish procedure.
48
Fig.no.12 certificate
49
CONCLUSION
My internship at NATHANI & COMPANY was an enriching experience that bridged the
gap between theoretical knowledge and practical application. I developed a deeper
understanding of various civil engineering disciplines and improved my technical and
professional skills. This experience has prepared me to take on future challenges in the
field of Civil Engineering with confidence and competence.
50