Operation Research-converted (1)
Operation Research-converted (1)
One mark
UNIT 1
1) Operation research is the application of methods to arrive at the
problems
a) Economical
b) Scientific
c) Both a and b
d) Physical
Ans b)scientific
2) In operations research the are prepared for situations
a) Mathematical models
b) Physical models
c) Diagrammatic models
d) Economical
Ans a) Multi-disciplinary
Ans a) true
Ans a) Scientists
a) System approach
b) Team approach
c) System orientation
d) Economic apporach
Ans b) three
Ans a) solution
18) Which model can answer for ‘ what if’ type of question
a) Deterministic model
b) Normative model
c) Predictive model
d) Mathematical model
a) Scienitific approach
b) Holistic approach
c) Objective oriented approach
d) none of the above
a) it is an iconic model
b) it is easy to construct
a) 4
b)3
c) 2
d)1
Ans b)3
22) Iconic model is a physical representation of a real project on same scale- state
this statement true or false
a) true
b)false
Ans a) true
23) Cash flow planning credit policy planning of deliquent account strategy are
some of the areas in accounting where are used.
a) analogue model
b) iconic model
c) OR technique
24) Almost all the models in OR are symbolic –state this statement true or false
a) true
b) false
c)none of above
Ans a) true
a) It is most general
b) It is most abstract
c) Both a and b
UNIT -2
4. If there are more than one optimum solution for the decision variable the
solution is _______
a) Infesable
b) Unbounded
c) Alternative
d) All the bove
10.If resource availability increase by some percentage then the output shall
also increase by some percentage –this statement is applicable in case of
a. Optimality
b. Divisibility
c. Additivity
d. Proportionality
UNIT-3
1) is a transportation problem is the set of all non-negative
allotments .
a) Feasible solution
b) Optimal solution
c) Basic solution
d) none of the above
Ans c) five
Ans a) Assignment
Ans b) two
11) The number of person is less than the number of jobs which has no
equal matrix.This kind of assignment is called?
Ans b) two
22) In modified distribution method the basic feasible solution can one of
the following method can be used?
a) North west corner method
b) Least cost method
c) Both a and b
d) None of the above
Ans a) true
Ans a) true
Unit 4
1) ______ is a technique which determines the various sequences of jobs
concerning a project and the project completion time
a) Network analysis
b) PERT
c) CPM
b) two
c) three
d)four
Ans b) two
c) network analysis
a) three
b)two
c)one
d) four
Ans b) two
a) normal time
b)crash time
c) both a and b
d) either a or b
a)CPM
b)PERT
d) crash time
ans a) CPM
a)CPM
b)PERT
d) crash time
ans a) CPM
8) using which technique the management was able to obtain the expected
project completion time and the bottleneck activites in a project
a)PERT
b)CPM
d) crash time
ans a) PERT
a) activity, eventually
b) eventually, activity
c) once, twice
d)twice,once
a)CPM
b)PERT
c) network
d) crash time
ans c) network
11) the path that takes the longest duration is called _____
a) bottleneck
b) critical path
c) project duration
d) crash time
a) project duration
b) bottleneck
c) critical path
d) crash time
13) the activities coming along this path are called _______
a) critical path
b) project duration
c) bottleneck
d) crash time
ans c) bottleneck
14) the amount of time a path of activites could be delayed without affecting
the overall project duration is called _______
b) total float
d) crash time
15) the amount of time an activities can be defined without affecting the
commencement of a subsequent activity at its earliest start time is called___
a) independent float
b)free float
c) total float
d) crash time
a) independent float
b) free float
c) total float
d) crash time
a) tail event
b) head event
c) end event
d) crash time
a) tail event
b) head event
c) end event
d) crash time
19) the activites which does not consume time or resources is called ___
a) regular activity
b) irregular activity
c) dummy activity
20) the shortest possible time estimate for finishing an activity is called ____
d) estimate time
d) estimate time
d) estimate time
a)true
b) false
d) either a or b
ans a) true
b) true
d) either a or b
ans a) false
25) non repeatative in the nature of job in CPM- state whether true or false
a) true
b)false
c) none of the above
d) either a or b
ans b) false
UNIT 5
1) The possible alternatives to be considered for taking a decision is called
_____
a) States of nature
b) State of action
c) Pay-off
d) none of the above
2) To identify all the possible events but the difficulty is to identify the
event which will occur is called ______
a) States of nature
b) States of action
c) Pay-off
d) none of the above
3) The possible profits for the different alternatives under diffrednt, states of
nature is called ____
a) States of nature
b) States of action
c) Pay-off
d) none of the above
Ans c) Pay-off
5) How many types of are available in criteria for decision making under
uncertainty
a)three
b)four
c) five
d) two
ans c) five
7) _____ criterion for the selction of the best among the wrost
a) Maximax criterion
b) Maximin criterion
c) Minimax regret criterion
d) none of the above
Ans b) Maximin criterion
8) The opportunity loss under each states of nature we take the largest pay-
off for each states of nature and subtract all other pay-off under the state
from the largest – state the statement true or false
a) True
b) False
c) None of the above
d) Either true or false
Ans a) true
9) A weighted average of the best and the worst pay off of the alternative is
called _______
a) Hurwicz criterion
b) Laplace criterion
c) Maximax criterion
d) none of the above
10) _______ associate equal probabilities for the different states in the
absences of information about these probabilities
a) Hurwicz criterion
b) Laplace criterion
c) Maximax criterion
d) none of the above
13) how many types of loss are there in minimizing expected loss?
a) One
b) Two
c) Three
d) four
Ans a) two
Ans b) two
16) The particular branch leaving a decision mode which leads to the
states of nature mode with highest expected monetary value. This is
known as____
a) Roll back technique
b) Decision tree
c) Decision making tree
d) none of the above
18) A player is a plan specifies his actions for every possible action of his
opponent is called ______
a) Strategy
b) Competitor
c) Player
d) none of the above
Ans a) Strategy
19) the number of strategies of the players is finite the game is called
_______
a) Infinite game
b) Finite game
c) Player
d) none of the above
20) if atleast one of the players has infinite number of strategies the game
is called ___
a) Infinite game
b)Finite game
c) player
d) none of the above
21) a game with two players wherin on person is the loss of the other is called
_____
22) the pay offs corresponding to various strategies of the players are represented
in a matrix is called ____
a) game matrix
23) the best strategy for each player is for play one particular strategy throughtout
the game it is called _____
c) game matrix
d) none of the above
24) the optimal plan for each player is to choose different strategies at different
situation is called ______
c) game matrix
a) Optimal solution
b) Value of game
c) Mimimum solution
d) none of the above
26) The pure strategies corresponding to the value of the game are ____
a) Optimal strategies
b) saddle point
c) Value of game
d) none of the above
27) The positions in the pay off matrix corresponding to optimal strategies
is called a ______
a)Optimal strategies
b) saddle point
c) Value of game
d) none of the above
ans b) saddle point
28) Maximum guaranteed gain to the palyer B _____
a) Saddle point
b) Value of game
c) Optimal strategies
d) none of the above
30) The problem can be reduced into a game which can be solved either
by reducing it to a game with pure strage
by reducing it to a game with pure strategy or reducing it into 2*2 game
which can be solved by mixed strategies is called____
a) Dominance property
b) Saddle point
c) Value of game
d) none of the above