The document outlines the detailed bill of quantities for construction work, including various items such as reinforcement concrete, brick masonry, plastering, and installation of electrical and HVAC systems. It provides measurements, unit costs, and total costs for each item, culminating in a grand total of approximately 68,893,513.64 RS. Additional costs for wastage, electrification, sanitation, GST, and labor welfare cess are also included in the final total.

Uploaded by

Sayan Dutta Bar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2 views4 pages

2

The document outlines the detailed bill of quantities for construction work, including various items such as reinforcement concrete, brick masonry, plastering, and installation of electrical and HVAC systems. It provides measurements, unit costs, and total costs for each item, culminating in a grand total of approximately 68,893,513.64 RS. Additional costs for wastage, electrification, sanitation, GST, and labor welfare cess are also included in the final total.

Uploaded by

Sayan Dutta Bar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

1ST FLOOR

Sl. Item
Item Description No. L B H Quantity Unit
No Code

19 19 Reinforcement Cement Concrete grade M20


as per IS:456 or nominal mix of 1 cement : 1
1/2 course sand and 3 stone aggregates 20mm
down graded.
a) COLUMN
14.00 3.10 0.30 0.65 8.463 CUM

b) For R.C.C. Slab


1.00 200.00 0.15 30 CUM

c) ROOF beam
1.00 265.00 0.30 0.70 55.65 CUM

94.113 CUM
@ Rs. 5500.00 /cum. 517621.5

20 20 Supplying & fixing steel renforcement in

2.2 %of Total R.C.C. work incum 2.20 94.11 7850.00 16253.3151 Kg
162.533151 Qtl
@ Rs. 6500.00 /Qtl 1056465.482
21 21 Providing and constructing Brick masonry and
locations using best approved quality K.B.
bricks from local available with a minimum
crushing strength 75kg/cm2, after immersing
the bricks for six hour in water before using in
cement mortar 1:6 to correct line, level &
plumb, including, scaffolding, watering, curing,
recking out joints etc. including cost of all
materials, labour, transportation, loading,
unloading Taxes, royalties etc. complete.
a) For superstructure
1.00 51.00 0.13 3.10 19.7625 CUM

head room 1.00 10.00 0.13 2.40 3 CUM

parapet 1.00 125.00 0.25 0.90 28.125 CUM


50.8875 CUM

Net Total 50.8875 CUM


@ Rs. 4500.00 /cum. 228993.75

22 22 Providing and applying cement plaster 12mm


thick at all floors in cement mortar 1:6 in
internal brick / concrete surface including
scaffolding racking out joints, hacking,
finishing smooth to correct line, level plans &
plumb as required, curing etc. complete.
INSIDE PLASTER 150 SQM

Nett 150 SQM


@ Rs. 350.00 /sqm. 52500
23 23 Same as above, but plaster thickness 19mm
(for all floor).
(Outside Plastering) 200 SQM
200 sqft
200 SQM
@ Rs. 250.00 /sqm. 50000

24 24 Distempering in three coats with a coat of P O


P in all floors & locations for ceiling & wall,
including sand papering & cleaning the
surface, filling the Cracks & Crevices if any with
approved putty, scaffolding etc. complete.

inside plastered walls:- 150 SQM


150 SQM
@ Rs. 350.00 /sqm. 52500

25 25 Applying weather coat two coats with a coat


of primer in all floors & locations Out Side
wall, including sand papering & cleaning the
surface, filling the Cracks & Crevices if any with
approved paint, scaffolding etc. complete.

outside plastered walls:- 200 SQM


200 SQM
@ Rs. 285.00 /sqm. 57000 RS

26 26 150 KV TRANSFORMER 1 PC WITH FITTINGS,


TESTING, INSTALLING, PORTING, 650000 RS
27 27 DUCTABLE AC 16 TON WITH 150’ PIPE LINE
AND DUCT , AIR CURTAIN, INSTALLING OF 4
SQMM CABLE, 2 SQ MM CABLE, 1 SQMM
CABLE, WITH LABOUR 7,40,000 RS
28 28 FIRE EXTINGUISER SYSTEM INSTALATION 2000000 RS
29 29 CONSULTANCY CHARGE 200000
30 30 TRANSPOTATION 440000
31 31 LABOUR CHARGE 1860000
32 32 COTA SOTONE FLOORING 5421.83 SQFT 65.00 352418.742
33 33 PAVER BLOCK 5704.92 SQFT 80 456393.6

TOTAL ROOF FLOOR CIVIL WORK 7973893.07 RS


TOTAL GROUND FLOOR CIVIL WORK 39094162.98 RS
SUB TOTAL 47068056.05 RS
ADD 1% FOR WASTAGE 470680.5605 RS
ADD 12% FOR INTERNAL ELECTRIFICATION 5648166.726 RS
ADD 10% FOR SANITATION WORK 4706805.605 RS
SUB TOTAL 57893708.94 RS
ADD 18% FOR GST 10420867.61 RS
ADD 1% LABOUR WELFARE CESS 578937.0894 RS
TOTAL 68893513.64 RS