Pratus Group Inc. | Mission Flats Lot 12 | PR-25-813
UDP
Lines 51
PRE-REQUISITE INFORMATION
1 Pre-requisites
2 Equipment Information
4 Responsibility Matrix
5 Record date and time of start of L4 testing. Date: _________ Time: _________
7 Confirm a suitable test environment has been provided by marking off the recommended Arc Flash distance using electric
caution tape around the equipment.
Standard Question | N/A ALLOWED Yes
8 Confirm equipment under test has been set to its normal operating condition.
9 Confirm equipment under test has been set to Auto and is alarm free.
Standard Question | ANSWERS Passed (Passed), Failed (Failed), N/A (N/A) | N/A ALLOWED Yes
14 Confirm as-found settings match the approve settings – equipment settings, firmware, set points, control parameters, limits,
delays, lockouts, & schedules.
Standard Question | N/A ALLOWED Yes
15 Record set temperature settings: Warning: ____°C Alarm: ____°C Trip: ____°C
16 Verify tamper proof seal has been applied to each circuit breaker with adjustable trip settings. Record seal number in a log
and take a photo of circuit breaker with seal. If the temporary seal has not been applied, request electrical contractor to
confirm set trip settings are as per SCCS and install tamper proof seal prior to proceeding with testing.
Standard Question | N/A ALLOWED Yes
21 Energize UDP.
Standard Question | ANSWERS Passed (Passed), Failed (Failed), N/A (N/A) | N/A ALLOWED Yes
Standard Question | ANSWERS Passed (Passed), Failed (Failed), N/A (N/A) | N/A ALLOWED Yes
24 Confirm control power transformers are energized and control power is available.
Standard Question | ANSWERS Passed (Passed), Failed (Failed), N/A (N/A) | N/A ALLOWED Yes
28 Confirm downstream breakers from UDP are ON and ready to carry load during test.
Standard Question | ANSWERS Passed (Passed), Failed (Failed), N/A (N/A) | N/A ALLOWED Yes
30 Apply 25% of rated load for 15 minutes. Increment load by 25% every 15 minutes. Record the following values below and
perform an IR scan (on all terminations and circuit breakers) every 15 minutes:
Table | N/A ALLOWED Yes
31 Apply 100% of rated load for 4 hours. Record the following values below and perform an IR scan every (on all terminations
and circuit breakers) 30 minutes:
Table | N/A ALLOWED Yes
32 Reduce load to 0% of rated load and allow load bank to cool down.
34 Verify that breakers associated with the UDP are mapped properly to the EPMS and branch circuit monitoring system.
Standard Question | ANSWERS Passed (Passed), Failed (Failed), N/A (N/A) | N/A ALLOWED Yes
35 Simulate ALARM for breaker status, open/close. Confirm that it is visible on EPMS.
36 Simulate ALARM for warning/alarm status by jumpering contacts. Confirm that it is visible on EPMS.
38 Include all EPMS screenshots of every condition listed in the step above. Upload EPMS screen shots to shared file folder and
title document
Standard Question | ANSWERS Passed (Passed), Failed (Failed), N/A (N/A) | N/A ALLOWED Yes
NOTES/COMMENTS
39 Additional Notes or Comments
CONTRACTOR SUBMITTAL
The above system and/ or equipment integral to it are complete and ready for functional testing. The checklist items are
complete and have been checked off only by parties having direct knowledge of the event, as marked below. This pre-
functional checklist is submitted for approval, subject to minor outstanding items; none of the minor outstanding items restrict
the safe and reliable execution of the functional tests.