16CE134-Estimation, Costing and Valuation
16CE134-Estimation, Costing and Valuation
7. Calculate the quantities of the following items for the building shown in fig (4) using Long wall
and short wall method
(a) Earth work in excavation
(b) Brick work in foundation and plinth
(c) PCC (1: 5: 10) below the foundation
(d) Damp Proof Course
(e) Brick masonry in CM (1:6) for super structure.
8. Calculate the quantities of the following items for the building shown in fig (4) using Centre
line method
(a) Earth work in excavation
(b) Brick work in foundation and plinth
(c) PCC (1: 5: 10) below the foundation
(d) Damp Proof Course
(e) Brick masonry in CM (1:6) for super structure.
9. Calculate the quantities of the following items for the building shown in fig (5) using Long wall
and short wall method
(a) Earth work in excavation
(b) Brick work in foundation and plinth
(c) PCC (1: 5: 10) below the foundation
(d) Damp Proof Course
(e) Brick masonry in CM (1:6) for super structure.
10. Calculate the quantities of the following items for the building shown in fig (5) using Centre
line method
(a) Earth work in excavation
(b) Brick work in foundation and plinth
(c) PCC (1: 5: 10) below the foundation
(d) Damp Proof Course
(e) Brick masonry in CM (1:6) for super structure.
Fig: (1)
Fig: (2)
Fig: (3)
Fig: (4)
Fig: (5)
3. The ground levels along the center line of the road are given below.
The formation level throughout 80 m length is 102.75. The road has a rising gradient 1 in 40. If the
width of the road is 12 m and side slopes 2:1, calculate the quantity of earthwork required by any
method.
4. Prepare an estimate for the portion of a road from chain age 14 to 22 from the data given below.
The formation width of the proposed road is 12 m, side slopes 11/2:1 in cutting and 2:1 in banking.
The road formation is proposed at uniform falling gradient 1 in 200 passing through GL at 14 m
chain age. R.L of formation being 108.00 m.
5. The formation width of a road embankment is 9.0 m. The side slopes are 2.5:1. The depths along
the center line of road at 50.0 m intervals are 1.2, 1.1, 1.4, 1.2, 0.9, 1.5 and 1.0 m. It is required to
calculate the quantity of earthwork by: (i) Prismoidal rule. (ii) Trapezoidal rule.
6. Workout the quantity of 6 mm, 10 mm, 16 mm diameter reinforcement for rectangular beam of size
230 mm x 500 mm. The beam is reinforced with 2 Nos - 10 mm dia at top, 2 Nos - 16 mm dia at
bottom, 2 Nos - 16 mm dia bent up. 6 mm diameter two legged stirrups are provided with 150 mm
c/c throughout the length. Length of the beam is 4.5 5 m. Assume suitable cover.
7. A room 600 cm long and 500 cm wide has a flat roof. There is one T-beam in the center (cross
Section below the slab 30cm X 50cm) and the slab is 15 cm thick. Estimate the quantity of iron
Bars required for reinforcement (For the T-beam only) from the data given below.
Main bars: 8 No’s - 25mm dia in 2 rows of 4 each (all 4 in the bottom being straight and others
Bent) Stirrups: 10 mm dia and 15 cm C/C throughout. Anchor bars: 2 No. s - 16 mm dia
8. Estimate the quantity of steel required for R.C.C (1:2:4) slab 130 mm thick provided for a room
3.25 m x 7.5 m, resting over a 300 mm thick walls.
Reinforcement details: Main reinforcement: 10 mm bars at 160 mm c/c (alternate bars are bent –
up), Distribution reinforcement: 8 mm at 200 mm c/c. Also prepare bar bending schedule.
9. Calculate the quantity of steel required by preparing bar bending schedule, for a R.C.C (1:11/2:3)
lintel cum sunshade as per the drawing given below. Take clear span of Lintel as 1.2m and bearing
over the support is 0.3 m on either side.