Water Logging and Drainage
Water Logging and Drainage
Importance of drainage
The introduction of drainage system in an area has the following advantages:
(a) Adequate drainage improves soil structure and increases and helps the
productivity of soil.
(b) Waterlogged saline and alkaline loads can be reclaimed (Reclamation means
process by which an uncultivable lands made fit for cultivation)
(c) Adequate drainage leads to early ploughing (done before sowing) and planting.
(d) Drainage of the area lengthens crop growing seasons.
(e) Drainage reduces water table in an area and thereby:
(i) Provides more available plant food by increasing depth of root zone soil.
(ii) Increases soil ventilation
(iii) Favors growth of soil bacteria
(iv) Assures high soil temperature
(f) Drainage decreases soil erosion.
Types of Drainage (Surface and Sub-Surface Drainage)
Two types of drainage can be provided, i.e.
(a) Surface drainage and
(2) Sub-surface drainage
Surface drainage is also called open drainage system while sub-
surface drainage is also called as tile drainage and underground
drainage.
Surface drainage system
Surface drainage is the removal of excess rain water falling on the
fields or the excess irrigation water applied to the fields, by
constructing open ditches, field drains, and other related
structures. In this process, the land is sloped towards these
ditches or drains, as to make the excess water flow in to these
drains.
Types of surface drain
Shallow surface drain
The open drains, which are constructed to remove the
excess irrigation water collected in the depressions on the
fields, as well as the storm (rain) water, are broad and
shallow, and are called shallow surface drains. These rains
carry the runoff to the outlet drains.
They are trapezoidal in cross-section.
They should be designed to carry the normal storm water
from the fields, plus the excess irrigation water.
Deep surface drain
These drains are large enough to carry the flood water of
the catchment area from the shallow surface drains, and
are of sufficient depths to provide outlets even for the
underground tile drains, if provided are called deep surface
drains.
These drains carry the storm water discharge from the
shallow surface drains, and the seepage water coming from
the underground tile drains and are therefore, designed for
the combined discharge of the shallow surface drains as
well as that of the tile drains.
Layout planning for drainage
As far as possible open drains should be located so as to follow
the path of natural drainage of the area. All the open drains
should discharge into an outfall drain which is either a large open
drain or a natural stream. The location of outfall drain can be
adjusted to give the required bed slope to the open drain.
Limitations
Providing underground tile drains, however, is a costly proposition
and may be required only in areas of high water table, and where
the ground soil has a poor internal drainage capacity.
Numerical 1
Design the surface drainage for the field having rainfall
intensity of
P3 = 450 mm for the area of 30 ha.
First trail q = 50 mm/day (drainage discharge)
h = 40 + – Q × t
Initial
Final water
Day depth Q
depth
(mm)
1 40 150 50 140 = 40 + 150
× 1 – 50 × 1
2 140 150 50 240 = 140 +
150 × 1 – 50 ×
1
3 240 150 50 340
Here, water depth > 300 mm, second trail is required.
Here, 'h' is greater than 300 mm, but theoretically 'h' should not
greater than 300 mm. So, next trail required. To meet our
requirement 'Q' should be increased and h may tend to 300 mm.
Second trail, Q = 75 mm/day
Da Initial Final water
Q
y depth depth
1 40 15 7 115 = 40 +
0 5 150 – 75
2 115 15 7 190 = 115 +
0 5 150 – 75
3 190 15 7 265 = 190 +
0 5 150 – 75
4 265 – 7 190 = 265 –
5 75
5 115 – 7 115 = 190 –
5 75
Here, no water depth greater than 300 mm
Depth excess of 200 mm occur in one day so, theoretically this
design is ok but uneconomical so, take next trail Q = 65 mm/day.
Initial
Da Final water
depth Q
y depth
(mm)
125 = 40 +
1 40 150 65
150 – 65
210 = 125 +
2 125 150 65
150 – 65
295 = 210 +
3 210 150 65
150 – 65
4 295 – 65 230
5 230 – 65 165
Here, water level greater than 200 mm occur for 3 days.
No water depth greater than 300 mm
Hence, design is ok, and also economical
Hence, design discharge is 65 mm/day
If area, A = 30 Ha
Q=A×V
or, Q = = 0.226 m3/sec
Assumptions for hilly region
Rain fall for 5 or 10 year return is considered
Initial water level in the field should be considered as 40 mm
for design
No rain fall follows the design rain fall for several days
Evaporation and transpiration losses are neglected
Irrigation flows are neglected
If P3 = maximum yearly rainfall
Q = drainage discharge in mm/day
Now, using W.B. equation; we have,
40 + P – Q = 100
Design criteria of surface drainage channel
Bed slope should be 1 : 300 to 1 : 500
Velocity v 0.85 m/s
B / D ratio 4 : 1 ( irrigation)
B / D ratio 3 : 1 (drainage)
Capacity of drain should be designed for storm water crop
sustainability
The drain alignment should follow natural drain as far as
possible
Numerical 2
Design a surface drainage for a field of 40 ha area in Terai
with following data. Design maximum yearly precipitation
for three consecutive days = 50 mm, longitudinal slope of
channel 1 : 400, Manning roughness coefficient 0.025,
Maximum water level is 300 mm which may persist per up
to one day and depends in excess of 200 mm persists for
up to 3 days. Assume other suitable values if necessary.
Here,
Maximum yearly precipitation for 3 day is 50 mm, which is not
reasonable. So, assume maximum yearly precipitation (P 3) =
450 mm
Assume initial water depth = 40 mm
Out let discharge (Q) = 50 mm/day
Now, using water balance equation (W.B.)
h = 40 + × t – Q × t
Initial water Final water
Day Q
depth depth
1 40 150 50 115
2 115 150 50 240
3 240 150 50 340
4 340 – 50 290
Here,
Water depth (h) > 300 mm, so second trail is needed.
Theoretically 'h' should not greater than 300 mm.
To meet our requirement 'Q' should increased and 'h' may
tends to 300 mm
Second trail
Q = 75 mm/day
Initial
Da Final water
water Q
y depth
depth
1 40 15 7 115
0 5
2 115 15 7 190
0 5
3 190 15 7 265
0 5
4 265 – 7 190
5
5 190 – 7 115
5
Here,
No water depth > 300 mm
Depth excess of 200 mm occurs only in one day
Theoretically this design is ok but uneconomical
So, take next trail
Q = 65 mm/day
Da Initial water Final water
Q
y depth depth
1 40 15 6 125
0 5
2 125 15 6 210
0 5
3 210 15 6 245
0 5
4 245 – 6 230
5
5 230 – 6 165
5
Here,
Water level greater than 200 mm persist for 3 days.
No water depth greater than 300 mm. Hence, design is ok and
Here,
Area (A) = 40 ha
Q = AV
∴ Q = 0.301 m3/sec
or, Q = [∵ 1 ha = 104 m2, 1 day = 24 × 3600 S]
Given that;
Bed slope = 1 : 400
Manning roughness coefficient (N) = 0.025
Assume side slope = 1 : 1
Bed width to depth ratio (B : D ) = 3 : 1
Now,
Q=×
Where, A = BD + D2 = 3D × D + D2 = 4D2
P = B + 2= (3D = 2= 5.828 D
Now,
0.301 = ×
On solving; we get,
D = 0.224 m
Take available size D = 0.3 m
and, B = 0.9 take free board (F.B.) = 0.1 m
When x =
qy = 0
When x = 0;
qy =
or, qy = – ×
or, qy= q ×
From equation (1) and (2); we have,
qy × = k × y ×
On integration; we get,
dx = y dy
or, =+C
When x = 0;
y=a
C=
or, = –
When x = = y = b
or, q × s × =
or, = (b2 – a2)
or, s =
Again;
q = s × drainage recharge (rain fall)
S2 = 4k (b2 – a2) ×
S2 = 8.64 × 106 ×
Formula for steady flow
Smooth flow (Q) = 50d257i0.57
Corrugated pipe (Q) = 22d267i0.50
Formula for unsteady flow
Smooth pipe (Q) = 89d271i0.57
Corrugated pipe (Q) = 88d267i0.5
Numerical 3
Design a suitable subsurface drainage 250 m × 900 m
plot. The depth of impervious layer is 10 m. The root zone
depth is 1 m. The drainage recharge is 5 mm/day.
saturated conductivity = 2.5 m/day and slope of drainage
is 1 : 100.
Here,
a = 8.7 m
b = 9.0 m
Re = 5 mm/day
= 0.005 m/day
K = 2.5 m/day
But, S2 =
= = 103
Adopting s = 100 m
Q = 100 × 250 × 5 mm/day = 0.00144 m3/sec
For unsteady flow;
Smooth pipe (Q) = 89d271i0.57
or, 0.00144 = 89d271i 0.57 = 89d271× (2.5)0.57
or, d = 0.045 m = 45 m
Example 4
Determine the size of a tile outlet of a 6 hectare drainage
system if the DC is 1 cm and the tile grade is 0.3%.
Assume the rugosity coefficient for the tile drain material
as 0.011.
Solution:
1 cm coefficient of discharge means that 1 cm of water from
an area of 6 hectares entering the tiles per day.
Volume of water passing the drain in 1 day =
∴ Q = m3/sec
= 600 m3/day
Now,
Q=
For circular drain pipe of diameter 'D'; we have,
A=
P = D
R=
or, = × × ×
On solving, we get,
D = (0.00447)3/8 = 0.132 meter = 13.2 cm.
Adopt 15 cm diameter pipe which is available in market.