3. Methodology Adopted for the Feasibility Study
3. Methodology Adopted for the Feasibility Study
Construction
of Road Tapa-Karu-Sering-Bagan (New Alignment) From Km 0.00 To Km 68.00 (Net Length 68.00 Kms) Green Field Alignment
to NHSL Specifications In The AOR of 85 RCC Under 756 BRTF Project Arunank in the state of Arunachal Pradesh (2nd Call)
3.1 GENERAL
Feasibility Study comprises of Site Surveys as well as Desk Studies of various design
alternatives to arrive at engineering solutions which are:
Economically Justified
As per the terms of reference (TOR), Consultants are required to carry out Engineering
Surveys and Investigations comprising of Topographical survey, Traffic Surveys,
inventory and condition surveys of road and bridges/structures, Geo-technical survey and
material survey, as well as Environmental screening and preliminary environmental
assessment, Initial Social Impact Assessment & preliminary land acquisition/
Resettlement plan, Bill of Quantities (BOQ) including the Preliminary Cost Estimate and
also the Economic and Financial Analysis of the Project Improvement.
As per the Terms of reference to the study, the consultants have to study various
alternate alignments at the feasibility stage and then conduct the detailed study of the
alignment option approved by the authority. Accordingly, this feasibility is based on the
reconnaissance surveys, available data, inventory and condition survey of existing
corridor, study of alignment options on satellite imagery, traffic surveys etc. and detailed
surveys like topographic surveys and material investigations will be carried out during
detailed design stage of the project after the approval of the alignment.
Past reports and documents available with BRO for the project road have been collected
and studied for trend analysis and past scenarios. This is important activity for traffic
studies as it gives information of past vehicle numbers and types. For other design
activities of road, past pavement surfacing/ widening of carriageway information and
other associated data viz. accident, road overtopping during heavy rains have been
sought from concerned Govt. departments.
Hydrological data from CWC and Canal data from concerned Irrigation
departments will be collected after the approval of the Alignment.
Survey of India Topo sheets have been collected from Survey of India.
Forest Divisions working plan from Respective Forest Divisions will be collected
after the approval of the Alignment.
Detailed road inventory surveys have been carried out to collect details of all existing
road and pavement features along the existing road sections. The inventory data
includes but not limited to the following:
c) Carriageway width, surfacing type @ every 200m and every change of feature
whichever is earlier;
d) Shoulder surfacing type and width @ every 200m and every change of feature
whichever is earlier;
j) Culverts, bridges and other structures (type, size, span arrangement and
location)
m) Inventory of all road side facilities for the public that is (educational, health,
communication facilities & Government buildings) and road user based facilities.
Before undertaking field surveys of existing structures, all concerned authorities were
contacted to ascertain the availability of any past inventory and condition survey reports
of existing bridges, sub-surface and geotechnical data, hydraulic data, as-built drawings,
etc. However, substantial past data could not be obtained from any of the agencies and
therefore detailed field survey, site investigation and collection of data were carried out
by the Consultant’s team of Engineers in order to carry out project preparation.
Subsequent to the collection of the secondary data and its desk study & analysis, a
detailed reconnaissance survey was taken up by the Consultant’s team.
The main objective of reconnaissance survey is to examine the physical features of the
project influence area in terms of land-use pattern, alignment alternatives, traffic pattern
along probable routes, determination of traffic homogeneous links, identifying
congested/habituated sections, critical areas requiring detailed investigations,
requirements of carrying out supplementary investigations, type and extent of utility
services, soil and drainage conditions, probable river/channel crossings and bridge
locations.
The information derived from the above activity was analyzed, for the purpose of
determining the most feasible routes for selection of proposed alignment to cater for
subsequent detailed investigations, as well as selecting Traffic Survey locations. The
survey facilitates in determining any deviations necessary in the basic geometric
standards to be adopted for the proposed highway facility.
The basic objective of the topographic survey is to capture the essential ground features
along the alignment and for working out detailed design, working drawings, quantity and
cost estimation, land acquisition, shifting of utilities, removal of plantation, road side
drainage design and related features. The topographical features mainly include
establishment of permanent traverse stations for GPS and temporary bench marks,
longitudinal section levels, cross sectional levels along with existing alignment,
realignments, cross roads, intersections and streams. The topographical survey will be
carried out as per the scope of work and methodology which is adopted for project
highway with data processing also has been discussed detail in this chapter.
The topographical survey will be carried out using Lidar/UAV/Drone after LAC Stage-1
approval of greenfield alignment. Following steps will be undertaken for topographic
survey.
3.4.1 Approach
We will use hybrid technology by utilizing the key features & advantage of latest
drone/UAV Photogrammetry technology & Traditional survey technology such as DGPS
& Total station for the fast and high accurate topographical survey for the development of
road corridor.
Unmanned Aerial Vehicle is considered as efficient way to carry out aerial survey of the
road project by leveraging the latest technology. The Geographical intelligence captured
by drone technology will help in efficient and accurate road project planning.
The Low altitude aerial mapping systems (LAAMS) which use SKYNETRA UAV
(Unmanned aerial Vehicle) with high quality calibrated camera to capture geo-ref aerial
images and later process them using the PHOTOGRAMMTRY TECHNOLOGY for
ii. Exact Navigation: AutoPilot with GPS, Glonass & IMU for precise position &
Orientation to ensure aerial survey with high precision.
iii. Exact Flight Planning – Flight planning Application to collect the Road ROW
from the Aerial sensors over project area.
iv. Stable Aerial Photography – 3-Axis Gimbal stabilized high resolution Calibrated
Camera.
Draft Feasibility Study Report
4
Consultancy Services for Preparation of Feasibility Study (FS) and Detailed Project Report (DPR) On EPC mode for Construction
of Road Tapa-Karu-Sering-Bagan (New Alignment) From Km 0.00 To Km 68.00 (Net Length 68.00 Kms) Green Field Alignment
to NHSL Specifications In The AOR of 85 RCC Under 756 BRTF Project Arunank in the state of Arunachal Pradesh (2nd Call)
3.4.2 Methodology
The detailed project planning will be done after visiting the whole length of alignment by
understanding the road conditions and marking the area to be surveyed, geographical
challenges, point of interests, tentative location of the controls. Based on the information
an inception report will be submitted to the client containing detailed work plan,
mobilization plan, permission coordinating with client etc.
Primary control pillars shall be constructed in pairs at 5.00 km interval for the
establishment of co- ordinates. Permanent Bench Mark will be fixed at any nearby
safe location or considered from any existing Permanent Building to be constructed
nearby proposed alignment.
Dual frequency global positing system will be used to survey and locate the control
pillar at 5KM with the accuracy of 1 CM. RCC pillar will be fixed as per dimension.
Total Station will be used to survey the existing road alignment and make the secondary
control location at every 250 M and a RCC piller will be fixed as per dimension mentioned
in the Scope.
Planning of flight using flight planning application involves the Geographical Analysis of
the area of Interest for elevation, forest, habitation etc. Flight Planning including flying
height, Image Resolution, Overlaps etc.
Flight planning operation involves the Setup of the Skynetra flying platform, Validating
the flight planning, transferring flight plan in Auto Pilot, Takeoff, landing and data
transfer from UAV to PC and preliminary validation of captured data.
o Calibrated focal length, Principal point offset, redial and symmetric distortion,
pixel size, each photo size.
C. Creating a Digital Elevation Model Using mass points and break lines at
every elevation change such as embankments, slopes, retaining walls, water
features etc.
o Features such as Edge of the Roads, Railway line and assets, Buildings,
Fences, Wall, Water Bodies, Tree / Vegetation, Manhole, Electricity poles,
trails, paved area, unpaved areas.
3.4.3 Deliverable
(a) Topographical Base map at 1:500 scale covering all features including but not
limited to buildings and structures, monuments, burial grounds, cremation
grounds, places of worship, railway lines, stream/river/canal, water mains,
severs, gas/oil pipes, crossings, trees, plantations, utility services such as
electric, and telephone lines and poles. The survey will cover the entire right-of-
way of the road on the adequate allowance for possible shifting of the central
lines at some of the intersection’s locations. In dwg / dgn / dxf / ESRI Shape
Format.
(b) Sub meter Contours at 25 cm interval with Spot Elevation Grid at Every 2 Meter
in dwg / dgn / dxf Format.
(c) Orthophoto (Mosaic in ECW / JPEG2000 and Tiles in Tiff Format) (Compatible to
Road CAD software).
(d) Digital Terrain Model (TIN Format / DGN /DWG) (Compatible to Road CAD
software).
(e) Digital Elevation Model with Level Grid at every 1 M (ASCII Format / ARC GRID
format / Tiff Format) (Compatible to Road CAD software).
(a) Reference Pillar and Bench Mark/ Reference pillar of size 15 cm X 15 cm X 45cm
shall be cast in RCC of grade M 15 with a nail fixed in the centre of the top
surface. The reference pillar shall be embedded in concrete up to a depth of
30cm with CC M10 (5 cm wide all around). The balance 15 cm above ground
shall be painted yellow. The spacing shall be 250m apart, incase Bench Mark
Pillar coincides with Reference Pillar, only one of the two need be provided.
(b) Establishing Bench marks at site connected to GTS Bench marks at an interval of
250 meters on Bench mark pillar made of RCC as mentioned above with RL and
BM No. marked on it with red paint.
The topographic surveys for longitudinal and cross-sections shall cover the following:
(a) Longitudinal section levels along final centre line at every 25m interval, at the
locations of curve points, small streams, and intersections and at the locations of
change in elevation.
(b) Cross sections at every 50m interval in full extent of survey covering sufficient
number of spot levels on existing carriageway and adjacent ground for profile
correction course and earth work calculations. Cross sections shall be taken at
closer interval at curves.
(c) Longitudinal section for cross roads for length adequate for design and quantity
estimation purposes.
(d) Longitudinal and cross sections for major and minor streams shall cover Cross
section of the channel at the site of proposed crossing and few cross sections at
suitable distance both upstream and downstream, bed level up to top of banks
and ground levels to a sufficient distance beyond the edges of channel, nature of
existing surface soil in bed, banks & approaches, longitudinal section of channel
showing site of bridge etc. These shall be as per recommendations contained in
IRC Special Publication No. 13 (Guidelines for the Design of Small Bridges and
Culverts) and provisions of IRC:5 (“Standard Specifications & Code of Practice
for Road Bridges, Section 1 – General Features of Design”).
To capture traffic flow characteristics and travel pattern of users passing through the
project road, the following primary traffic surveys were conducted.
Classified Traffic Volume data available with IHMCL for the intersecting NH will be used;
however Automatic Traffic Classified Counts (ATCC) will be carried out for 7 days (24hrs-
direction wise) at survey station wherever data is not available. Manual Survey for 7 days
will be carried out on surrounding network (24hrs- direction wise) wherever ATCC
equipment cannot be used due to site constraints. The vehicle classification system will
be followed as per IRC guidelines. The ATCC equipment's functioning would be
monitored by technicians. Manual survey would consist of counting of each category of
vehicle in both directions for successive 15 minutes periods. Counts and recording of
data (by manual tally-marking) would be done by trained enumerators in two shifts of 12
hours each per day under the presence of supervisors.
The method and vehicle classification used for all the traffic surveys are based on TOR,
IRC Guidelines IRC: 64-1990 and IRC: SP-41:1994.
Analysis of traffic survey data would give the following traffic information on project road.
Average Daily Traffic (ADT)
Traffic composition
Major trip generating zones within the project influence area and its share in total trips
Lead and load pattern of the vehicular movement on the project alignment
The Origin-Destination survey was carried out with the primary objective of studying the
travel pattern of goods and passenger traffic along the new alignment and the
connecting. The results have also been useful for identifying
Draft Feasibility Study Report
10
Consultancy Services for Preparation of Feasibility Study (FS) and Detailed Project Report (DPR) On EPC mode for Construction
of Road Tapa-Karu-Sering-Bagan (New Alignment) From Km 0.00 To Km 68.00 (Net Length 68.00 Kms) Green Field Alignment
to NHSL Specifications In The AOR of 85 RCC Under 756 BRTF Project Arunank in the state of Arunachal Pradesh (2nd Call)
the influence of connecting road over the project road, and also for estimating the growth
rates of traffic and diversion of traffic on the project road.
The O-D survey was carried out for one day (24 hours) at three locations simultaneously
along with the classified traffic volume count survey. Roadside interview method was
adopted for the survey. The vehicles were stopped on random sample basis with the help
of police, and trained enumerators interviewed the drivers to obtain the required data.
During the surveys the information pertaining to trip length, commodity types, loading
pattern and trip purpose as applicable for various vehicle types were recorded.
Axle Load Survey would be carried out at the identified locations. The main purpose for
carrying out the survey is to assess the loading pattern on the corridor and to estimate
Axle Load Spectrum as well as Vehicle Damage Factor of the commercial vehicle likely to
use the road.
During the survey, commercial vehicles, i.e. 2-Axle, 3-Axle, Multi Axle Trucks and a few
Buses, would be weighed on random sampling basis. The vehicles will be stopped with
the help of police and the drivers will be directed to stop their vehicles in such a way that
wheel of each axle can be weighed using portable Axle Load Weighing Pad. Readings
would be recorded by trained enumerators.
The surveys will be carried out for duration of 2 normal days (48 Hours).
Typical survey format containing information as per TOR is furnished in QAP document.
To quantify the problems of congestion and the causes for delay, speed and delay study
will be conducted on the entire project stretch. For this purpose, the project road would
be divided into homogenous sections of traffic mix, roadside developments, road
conditions and geometry, etc. Vehicle-borne enumerators will note down the time at each
control point, while moving in each direction along with reasons for slow movement below
20kmph, wherever such situation occurs. Average of runs will be used to obtain average
running speed of each section along the project road.
The calibrated network, along with each expressway alignment option developed and
superimposed on it, has been used to distribute the trip ends; and obtaining the horizon
year O-D matrices for different modes. These matrices, when assigned to the road
network provided the expressway traffic in various sections of the expressway for the
horizon years.
Assessment of truck parking requirements along the project road & way side amenities
The inventory & condition survey of existing bridges & all cross-drainage works will be
done by 2 teams consisting of a Senior Bridge Engineer, a two Junior Engineers and
supporting staff carried out as per data prescribed in IRC: SP: 35-1990. Standard formats
based on the given data were prepared. Instruments and tools such as measuring tapes,
GPS devise, Hilti, plumb bob, small hammer, mirror and camera were used for the
survey. The data collected will be analyzed and strategy proposed for treatment of each
structure in terms of maintenance, rehabilitation or replacement during widening and
improvement. Various details of individual structures/culverts taken at site are as under-
1. General
Main objective of hydrology is to determine anticipated flood and other parameters such
as Design Discharge, Flow Velocity, HFL, and Scour Depth. Bridge structure shall be
designed so as to cater for the anticipated floods without endangering the structure. The
hydrological and hydraulic studies shall be carried out in accordance with IRC Special
Publication No. 13-2004 (“Guidelines for the Design of Small Bridges and Culverts”) and
IRC: 5-2015 (“Standard Specifications & Code of Practice for Road Bridges, Section- I
(“General Feature of Design”) and specific Flood Estimation Report for particular Sub-
Zone published by the Directorate of Hydrology (Small Catchment) Central Water
Commission¸ New-Delhi¸ Government of India. Detailed Hydrological Investigations for all
Structures shall be done in Hydrology report.
2. Data Collection
The various essential data shall be collected for hydrological investigation. Catchment
area will be calculated from the Topo sheets available. Highest flood level will be
observed and measured during site visit supplemented by local enquiry. Attempts shall
be made to collect the data of existing bridge and their performance during past floods
from the Governing Departments.
The most common methods to estimate the flood discharge are as under:
a) Empirical Method
b) Rational Method
c) Unit Hydrograph
a) Empirical Method:
Dicken’s Formula can be used for the project area, as per IRC SP-13:
Q = C M 3/4
Where,
The catchment area M is determined from the Topo sheet, Coefficient of run-off ‘C’ is
determined from IRC SP-13 depending upon the intensity of rainfall. This formula gives a
simplified approach and results are approximate. Comparisons are made with alternative
methods for important structures.
The rational formula for assessment of peak discharge from project catchment takes into
account rainfall, runoff under various circumstances, and time of concentration and
critical intensity of rainfall. Basic formulae are as under:
Where,
tc = Time of concentration i.e. time taken by runoff from farthest point on the periphery of
catchment (hrs)
Draft Feasibility Study Report
13
Consultancy Services for Preparation of Feasibility Study (FS) and Detailed Project Report (DPR) On EPC mode for Construction
of Road Tapa-Karu-Sering-Bagan (New Alignment) From Km 0.00 To Km 68.00 (Net Length 68.00 Kms) Green Field Alignment
to NHSL Specifications In The AOR of 85 RCC Under 756 BRTF Project Arunank in the state of Arunachal Pradesh (2nd Call)
P = Coefficient of runoff for the catchment characteristics (Ref: Table - 4.1, P-13 and IRC
SP: 13-2004)
L = Distance from the critical point to the structure (Length of path in Km)
H = The difference in level from the critical point to the structure in meter
f = A fraction of maximum point intensity at the centre of the storm and related with the
catchment area (Determined from Fig.4.2, Page-14, IRC: SP: 13-2004.)
In the present study, storm rainfall and storm duration data of 100 Years return period
shall be utilized from design flood hydrograph of nearby project sites, developed on the
basis of Hydro-meteorological studies as per relevant Flood estimation reports of the
particular region/area.
The unit hydrograph (UG) of a drainage basin is defined as the direct runoff (outflow)
hydrograph resulting from one unit of effective rainfall which is uniformly distributed over
the basin at a uniform rate during the specified period of time known as unit time or unit
duration.
This method is applicable for Catchment area varying between 15-25 Sq. Km to 2500-
5000 Sq. Km. In present study, the design discharge calculations shall be done for 100
Years return period.
The area velocity method uses Manning’s formula (as per IRC SP:13-2004 manually for
calculating flow velocity as under.
Q=AxV
Where,
V = Velocity of flow
n = Rigidity coefficient
Draft Feasibility Study Report
14
Consultancy Services for Preparation of Feasibility Study (FS) and Detailed Project Report (DPR) On EPC mode for Construction
of Road Tapa-Karu-Sering-Bagan (New Alignment) From Km 0.00 To Km 68.00 (Net Length 68.00 Kms) Green Field Alignment
to NHSL Specifications In The AOR of 85 RCC Under 756 BRTF Project Arunank in the state of Arunachal Pradesh (2nd Call)
P = Wetted perimeter
Cross sections of the streams are taken both upstream and downstream at a distance as
specified in IRC SP -13 by Topo survey in the field. Longitudinal slope of the bed is also
calculated by taking long section over a reasonably long reach of the stream. HFL can be
observed in the field by flood marks and local enquiry. This formula gives fairy
reasonable estimation of flood discharge.
4. Design Discharge
Design discharge is fixed as per provisions of Clause 6.2 of IRC SP-13. The values of
peak discharge calculated by above methods are compared. The highest of these values
is adopted as design discharge, provided it does not exceed the next highest discharge
by more than 50 percent. If it does, restrict it to that limit.
5. Scour Depth
Determination of scour depth is important factor for deciding depth of foundation and
shall be derived as per Cl. 703.2 of IRC: 78 – 2014 according to which:
Where,
The maximum depth of scour below the highest flood Level (HFL) for the design of piers
and abutments located in a straight reach and having individual foundations without any
floor protection works is taken as under.
6. Vertical Clearance
Provision of Vertical clearance in bridges above HFL shall be kept as per IRC SP-13,
Clause 12.3 as under.
The Bridge Specialist and his team has thoroughly inspect all bridges and structures as
per IRC-SP:35-1990 and IRC-SP:40. Identification of deterioration/damage to the bridges
will include spalling of concrete, visible cracks, state of bearings (neoprene pads in
particular), bridge deck transversal joints and bridge deck features such as railing, curbs,
wearing course etc., marks on abutments for flood levels etc. All deterioration will be
noted, photographed and measured; concurrently, the team will consult the design and
construction reports, where available, in order to evaluate the design local capacity of the
bridges.
The necessary surveys and investigations to establish the remaining service life of each
retainable bridge or structure, with and without the proposed strengthening and
rehabilitation, will be carried out according to acceptable international practice in this
regard.
We shall carry out a detailed inspection of every bridge and other structures as per
IRC:SP: 35 and IRC:SP:52.
To evaluate the subsoil properties needed for the design of foundations, detailed geo-
technical investigations need to be conducted at all bridges, ROB’s, flyovers,
underpasses, ROBs, embankment locations along the project road. As per term of
reference, the minimum scope followed for geo-technical investigations for bridges &
other structures is as under:
The depth of boring shall be conducted as per provision in IRC: 78-2014, MORTH
specification. The Depth of bore-Logs is based on expected type of foundation.
Deep Foundation:-
In case of deep foundation, the depth of bore may be increased suitably in view of other
deeper foundation which shall be not less than:
a. 1.5 times the estimated length of pile/well in soil but not less than 15.0m beyond
the probable length of pile
b. 15 times the diameter of pile in weak/ jointed rock but minimum of 15.0m in such
rock.
In case of open foundation, the bore hole shall be done as per IRC: 78 i.e. 1.5 times the
width of the foundation below the proposed foundation level.
Open Foundation:-
In case of open foundation, the bore hole shall be done as per IRC: 78 i.e. 1.5 times the
width of the foundation below the proposed foundation level. The depth of drilling/ boring
shall be 5.0m in soft rock & 3.0m in hard rock.
1. The Consultant will identify sources (including use of fly-ash/ slag), quarry sites
and borrow areas, undertake field and laboratory testing of the materials to
determine their suitability for various components of the work and establish
quality and quantity of various construction materials and recommend their use
on the basis of techno- economic principles. The Consultant will prepare mass
haul diagram for haulage purposes giving quarry charts indicating the location of
selected borrow areas, quarries and the respective estimated quantities.
Various government departments were approached to obtain from them the details of
existing bridges, their condition, proposals for their repairs, replacement or widening if
any, under consideration.
Inventory of all the existing bridges/structures has been carried out as per provisions of
IRC: SP-35 and also the required parameters has been collected which help in adopting
a scientific approach for retention / repair & rehabilitation / reconstruction and widening of
existing structures. Inventory gives technical and administrative data for each structure
such as name, location, administrative unit, type of road, construction data and technical
data such as overall length, details of spans, waterway, type of foundations, type of
substructure and superstructure carriageway width, overall deck width, design loading,
structure classification and functioning of structure in the past both from hydraulic and
structural considerations. Inventory will help in deciding the geometry, configuration and
structural framework of new structures and widening of existing structure if necessary.
A preliminary visual inspection of bridges and other structures has been carried out as
per provision of Appendix 4 of IRC: SP-35 in order to assess their present condition from
functional, structural and serviceability requirements. Based on distresses, if any,
observed during inspection, the bridges will be categorized as under:
The structures where the extent of distress has a consequent effect on the structural
adequacy will be identified for detailed inspection to be carried out. Only the visible
portion above ground or water level will be examined. Preliminary repair plans based on
preliminary designs will be prepared along with likely cost for approval of BROI
authorities. Those structures which are beyond economical repair will be specially
identified for replacement.
Where the existing bridge is proposed to be replaced is on a straight alignment the new
bridge shall be provided at the site of existing bridge. In such cases the span
arrangement has been chosen such that foundations of new bridge do not interfere with
those of existing bridge. In such cases the construction of new bridge can be taken up
after completion of a temporary diversion.
In cases where it has been possible to slightly shift the alignment towards upstream or
downstream side without jeopardizing the geometry of road new bridge has been
proposed in the vicinity of existing bridge either on upstream or on downstream. In such
cases there will be no need to provide any diversion as the traffic can continue to ply over
existing bridge till the new bridge is ready.
The existing bridge would be dismantled or abandoned only after the new bridge is
commissioned.
Where altogether new bridges are proposed (on realignment) siting of minor bridges has
been governed by road alignment. However, in case of major bridges guidelines given in
Ministry’s Pocket Book for Engineers has been followed as detailed below.
Straight reach of the river towards u/s and d/s of the proposed site to the
extent possible.
Freedom from islands or any form of obstruction both towards u/s and d/s
Deck Width
For the alignment options where the project road is to be developed as per 2-lane
standards, hence keeping in view the provisions of Manual for 2-laning of Highways i.e.
IRC: SP:73-2018 carriageway width of bridge 7m.
Crash Crash
Barrier Barrier
Figure 3.1: Cross Section of Bridge Deck Level-with Footpath 2-Lane width Paved
Shoulder
For bridges having Girder type superstructure or having pile/ well foundation were
widening of bridge is not feasible and structure width is adequate for 2-lane traffic.
Span Arrangement
In case the existing bridge proposed to be replaced is hydraulically adequate the length
of new bridge has been kept the same. In case the new bridge is proposed to be
constructed on existing alignment after dismantling an existing bridge, span length as
large as possible has been proposed keeping in view the soil data and proposed type of
structure. However, if the new bridge is constructed in the vicinity of existing bridge the
span length for new bridge has been kept the same or in multiples of the span length of
existing bridge so that piers of new bridge are in line with those of existing bridge to
ensure streamline of flow. Efforts has been made to adopt as large spans as possible to
improve riding quality keeping in view the type of founding strata met with at site.
Overall lengths of new bridges have been fixed on the basis of hydraulic studies
for the respective streams. Span arrangement, type of superstructure,
substructure and foundations are fixed on the basis of hydraulic data and sub-soil
properties.
All the Rail crossings have been proposed with ROB / RUB, further ROBs / RUBs have
been planned in accordance with MOU between Ministry of Railways and Ministry of
Road Transport and Highway dated 10th November. 2014. As far as possible RDSO
standard composite type superstructure having steel girders and RCC deck slab or
RDSO standard Bow String Girder and RCC deck slab to be adopted as per guidelines
issued by Railways.
Environment includes the three components physical, biological and the socio-economic
environment. Environmental screening is first stage of Environmental Impact
Assessment. The objective of the Environmental Screening is:
to determine the category of the project depending on the length, extent of land
acquisition, location, sensitivity and magnitude of its potential environmental
impacts;
During the reconnaissance survey, location of following areas within 15 km radius of the
project road has also be identified:
The consultant has collected secondary data from various sources such as Central
Ground Water Board, Indian Meteorological Department, Forest Department,
Archaeological Department, Mineral Resources Department etc. The information
collected includes:
Project categorization has been carried out by analyzing the improvement proposal of the
proposed highway and applicable Acts, Policies & Guidelines of Government of India for
projects proposed to be funded by MORT&H/ BRO.
Based on the site assessment; review and analysis of secondary data collected;
“Environmental Screening and Preliminary Environmental Assessment Report” has been
prepared as a part of Feasibility Report covering
The Initial social assessment and preliminary land acquisition/ resettlement plan study
consists of the following Components:
3.9.1 Study and Review of Policies, Legislation and Administrative Framework & Social
Assessment
Resettlement and Rehabilitation Draft Principles and Policy Frame Work of the
concerned states.
Analysis of any other existing state and central Government’s norms, policies,
guidelines, statutory and legislative provisions, regulatory framework for land
acquisition, as applicable to communities in the project area and its influence
zones, special provisions for scheduled castes and other vulnerable
communities, and multilateral conventions.
The main objective of initial social assessment and preliminary land acquisition/
resettlement plan study is to determine the magnitude and sensitivity of direct and
indirect socio-economic and cultural impacts likely to result from the proposed project, to
identify stretches likely to pose not-so-easily mitigable impact issues, requiring detailed
analysis, and facilitate integration of social considerations in the selection of alignment
and engineering designs. While conducting the initial social assessment of the project,
the requirements of applicable land acquisition act (RFCTLARRA-2013), Govt. of India
and state Govt. requirement and the existing guidelines of the funding agencies, if any,
has been considered. The initial social assessment will make use of available data on
socio-economic and cultural conditions of the project area (s).
As per scope of work under resettlement and rehabilitation study, a micro level
information/ study is required for the approved alignment, however, at this point of time
neither it is economical nor feasible to go for the detailed study for all the alternate
alignment options. Hence, a macro level study has been carried out primarily using
secondary sources of data satellite / Google imagery at this stage. In line with the above
approach a proper methodology for the preparation of initial social impact assessment
and preliminary land acquisition/ resettlement plan study has been followed.
Relevant baseline data on socio-economic and cultural conditions were collected from
various available secondary sources, like Census Handbooks and District Gazetteers,
Different concerned governments’ official websites maintained by the NIC, etc. review of
policies and guidelines of national and different states and to ensure people’s concern to
understand the socio-Economic context of the proposed project and for providing
necessary inputs for social analysis of the project. The consultant also collected the circle
rate or valuation rate of land of concerned districts of each state from different websites
for the preparation of tentative land cost
The proposed alignments have been transferred on the KML/KMZ file. A KMZ file is a file
that stores map locations viewable in Google Earth, a global mapping program. It
contains place marks that may include a custom name and the latitudinal and longitudinal
coordinates of the location. KMZ files provide a bird's eye view of locations throughout
the world. The KMZ files on Google earth is very important for assessment of properties,
habitations, congestions and many other social features which is required for initial
assessment of land requirement and other social impacts at preliminary stage of project
planning.
Baseline information, collected from secondary sources, primarily from Census of India
Data, has been documented. The documents have relevant information human
environment/area of influence of the project and the existing social conditions and trends.
Baseline simply means a geographical and time line to start the assessment. This
information will describe the socio-economic features of the people to be affected by the
project (gender, occupation, income and asset levels, employment, education, access to
health services, social organization, cultural distinctions, vulnerable groups, indigenous
population, cultural/religious sites and properties) etc.
In order to have an in-depth knowledge of the project and its area, and analysis of initial
social impact assessment, a Desk study through satellite/google imagery of alternate
alignment options along existing alignment within proposed Corridor of Impact (CoI) of
60/70 m and green field alternate alignment options having 100/130 m PROW
respectively was performed. In addition, to gather the first-hand information on impact of
population, structures, and other sensitive areas, collected secondary data from different
sources was studied and analysed.
The requirement of land acquisition was also assessed to meet the requirement of
proposed ROW, which varies from 60 to 70 m. While assessing the land and property
acquisition, due care was taken to reduce the available ROW on specified locations of all
the alignment options.
A Draft Initial Social Impact Assessment and Preliminary Land acquisition / Resettlement
Plan will be prepared in accordance with the guidelines of Govt. of India and
RFCTLARRA-2013. The Draft plan will be concise and clearly address significant land
acquisition, resettlement and other social issues.
The unit rates are based on Schedule of Rates for Road & Bridge Works of Arunachal
Pradesh 2021. For road embankment borrow areas have been identified along the
project road. For stone metal, quarries have been identified along the road. Average lead
has been worked out for earth and stone metal and cartage cost has been considered
from State Schedule of Rates. The unit rates have been worked out by taking the cost of
materials as provided in the State Schedule of Rates (except for cement, steel and
bitumen for which market rates have been considered). The components of labor,
material and machinery have been considered as per Standard Data Book of the Ministry
of Road Transport and Highways.
These basic costs, together with the haul distances estimated for the construction
materials, will then be computed to obtain unit rates for the principal work items
subsequently to be included in the Cost Estimate.
For preliminary costing, the quantities of earthwork and pavements have been worked
out from applicable Cross -sections.
The quantities of bridges and structures have been worked out from their general
arrangement drawings. Quantities of cross drainage works have been worked out from
their preliminary drawings.
Preliminary cost estimates have been prepared for each improvement option identified
during the feasibility stage. The following elements will be accounted for to obtain the
total costs in each case:
Construction costs,
Contingencies
Construction Supervision,
Administrative Charges,
Quantities have been estimated for each component of road construction comprising the
various carriageways and widening configurations developed during feasibility stage. The
unit rates will then be applied to obtain the per kilometre cost of each configuration. The
lengths of each configuration necessary for the construction of the various project
alternatives will then be estimated for the calculation of total costs by the application of
the per kilometre cost concerned after addition of cost of structures, bridges and culverts.
Similar method has been also followed for the estimation of costs arising from
rehabilitation works, utility diversions and environmental mitigation measures.
Land acquisition and resettlement costs have been evaluated as per MORT&H policy
and latest guidelines in consultation with other concerned authorities.
The economic appraisal is mainly based on the “project costs and project benefits”,
based on the principles of life cycle cost analysis. The project costs include the capital
expenditure required for the proposed intervention and the required routine and periodic
road maintenance on the proposed expressway during the appraisal period, also
including the environmental and social mitigation costs to take care of the proposed
interventions.
The difference between the two compatible streams of total costs (including construction
and operating costs) will represent the time streams of the incremental net cost
savings/benefits arising from the proposed investment in the project road.
The economic internal rate of return (EIRR) and Net Present Value (NPV) has been
estimated for the proposed highway. The estimated EIRR for the project has been
compared with the prescribed cut off rate of return in order to determine the viability or
otherwise of the highway project with single lane divided carriageway. The net presents
value (NPV) has been estimated at 12% cut off or the prescribed rate of discount, using
the discounted cash flow (DCF) technique.
To gauge the financial viability of the total project length, and of discreet homogeneous
sections thereof, for private funding on a Build-Operate-Transfer (BOT) basis, a detailed
financial analysis has been carried out. Various combinations of revenue resources and
funding options will be analysed.
Toll/user tariffs
Other revenue resources, e.g. income from utilities along the ROW, publicity
hoardings etc.
A) Total project cash flows have been determined from the following groups of
basic input parameters:
a) Policy Parameters:
Construction Period
Concession Period
Toll Rates
b) Costs:
Construction Costs
Operation Cost
Maintenance Cost
c) Macro-economic Indicators
Interest Rates
Discount Rates
Inflation Rates
Debt/Equity Norms
Capital grant
From the cash flows for the complete project length, financial/commercial internal rate of
return (FIRR) is arrived at, using the discounted cash flow (DCF) technique. This will be
compared with the target cut off equity IRR.