Rough Notes - EoT and LD
Rough Notes - EoT and LD
DAMAGES
(1) Purpose of EoT:
(A) EoT clause is provided to
(i) Enable owner/employer (or) to extend the contract and
thereby bind the contractor to complete the work,
which otherwise the contractor may abandon for
various reasons/circumstances, and/or,
(ii) Enable the contractor to complete the work whether
with or without levy of penalty and shall bind the
employer to allow the contractor to finish the work
which the employer might otherwise prevent by
termination of contract.
(2) Power to grant EoT - Qualifying Events:
(A) The Contract must list the qualifying events. Upon
occurrence of any non-qualifying event employer/owner has
no power to per-force grant EoT , that is the contractor is
not bound to accept an EoT. Therefore, if qualifying
events list did not cover employer’s delay, then
employer cannot force an EoT on the contractor.
Peak Construction (Liverpool) Ltd v. Mckinney
Foundations Ltd 1 BLR 111
Rapid Building Group Ltd v. Ealing Family Housing
Association Ltd (1984) 29 BLR 5