Old_Project_Schedule_02

The document outlines a detailed project schedule for construction activities from October 2023 to March 2024, including tasks such as mobilization, demolition, earthworks, concrete works, and mechanical installations. Each task is associated with specific durations, start and finish dates, and responsible resources. Milestones are indicated throughout the schedule to mark significant points in the project timeline.

Uploaded by

adnan.lazem
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2 views1 page

Old_Project_Schedule_02

The document outlines a detailed project schedule for construction activities from October 2023 to March 2024, including tasks such as mobilization, demolition, earthworks, concrete works, and mechanical installations. Each task is associated with specific durations, start and finish dates, and responsible resources. Milestones are indicated throughout the schedule to mark significant points in the project timeline.

Uploaded by

adnan.lazem
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

ID TaskTask Name Duration Start Finish Predecessors Resource Names

Mod October 2023 November 2023 December 2023 January 2024 February 2024 March 2024 April 2024
23 28 3 8 13 18 23 28 2 7 12 17 22 27 2 7 12 17 22 27 1 6 11 16 21 26 31 5 10 15 20 25 1 6 11 16 21 26 31 5
1 1 Mobilization Works 10 days Sun 10/1/23 Thu 10/12/23 Project Manager,Civil Engineer ,Mechanical Engineer ,Electrica
2 1.1 Mobilization works 10 days Sun 10/1/23 Thu 10/12/23
3 1.2 Civil Site Developmen 6 days Mon 10/2/23Mon 10/9/23 2
4 1.3 Install Temparory 5 days Tue 10/3/23 Mon 2
Structures 10/9/23
5 1.4 MileStone -1- 0 days Thu 10/12/2 Thu 10/12/232,3,4 10/12
6 2 Demolition Works 15 days Fri 10/13/23 Thu 11/2/23 1 Project Manager,Civil Engineer ,Survey Engineer,Supervisor ,la
7 2.1 Demolition of 10 days Fri 10/13/23 Thu 1
Sanitary and Plumbing 10/26/23
works for Restrooms,
Patisions, floor tiles,
and fixtures
8 2.2 Demolition of old 8 days Fri 10/13/23 Tue 1
Generators, Deisel 10/24/23
Tank, Boards and HVAC
package
9 2.3 Demolition of 12 days Fri 10/13/23 Mon 1
Electrical Boards, 10/30/23
Cables, Wirings,
fixtures ceiling Tiels
10 2.4 MileStone -2- 0 days Mon 10/30/2Mon 10/30/2 7,8,9 10/30
11 3 EarthWorks & Excavat 12 days Sat 10/14/23Mon 10/30/231 Project Manager,Civil Engineer ,Survey Engineer,Supervisor ,la
12 3.1 Earthworks (I); 7 days Sat Mon
Power Cables and 10/14/23 10/23/23
conduit Excavation
works
13 3.2 Earthworks (II); 8 days Sat Tue
Water, Sewer and 10/14/23 10/24/23
Drainage piping
excavation works
14 3.3 Soil Staibilization, 12 days Sat Mon
Backfilling, Compaction, 10/14/23 10/30/23
and surface finishing
works

15 3.4 MileStone -2- 0 days Sun 10/29/2 Sun 10/29/2312,13,14 10/29


16 4 ConcreteWorks for 12 days Mon Tue 11/14/23 11 Project Manager,Civil Engineer ,Survey Engineer,Mechanical
Fuel Tank & Generators 10/30/23 Engineer ,Electrical Engineer ,Plumbing
P 4.1
d Foundation Technician Carpenter Reinforcing worker Cement
17 5 days Mon Fri 11/3/23
Formworks; steel rebars 10/30/23
mesh and lumber
formworks installation

18 4.2 Foundation Works; 11 days Mon Mon


strip footing & stap 10/30/23 11/13/23
beams IAW approved
Design Drawings
19 4.3 Floor Repairing 10 days Mon Fri 11/10/23
Works; Walkways, floor 10/30/23
slabs, & Restrooms IAW
approved Design
Drawings
20 4.4 MileStone -3- 0 days Wed 11/15/2Wed 11/15/2 17,18,19 11/15
21 5 Masonry and 11 days Wed Wed 16 Civil Engineer ,Supervisor ,Electrical Engineer ,Generator
11/1/23 11/15/23 Operator,Helper,labor Foremen,Iron Worker,Project
Patitions Works
Manager Survey Engineer Welder Truck Driver Painter and
22 5.1 BrickWorks 10 days Wed 11/1/23Tue 11/14/23
23 5.2 Concrete Masonry 11 days Wed Wed
Units works 11/1/23 11/15/23
24 5.3 Thermal & 7 days Tue 11/7/23 Wed
Insulation Works; Roof 11/15/23
and walls (Acoustic,
Thermal, Fireproof and
Waterproof ) Roof
Drainage

25 5.4 MileStone -4- 0 days Wed 11/15/2Wed 11/15/2 22,23,24 11/15


26 6 Doors and Window 16 days Thu Thu 12/7/23 21 Civil Engineer ,Supervisor ,Electrical Engineer ,Generator
Metal Works 11/16/23 Operator,Helper,labor Foremen,Iron Worker,Project
Manager Survey Engineer Welder Truck Driver Painter and
27 6.1 Doors and Windows 6 days Thu Thu 22,23
frames installations 11/16/23 11/23/23
28 6.2 Installations of 14 days Thu Tue 12/5/23 22,23
Doors Units; Wooden, 11/16/23
Aluminum, and steel.
29 6.3 Installations of 12 days Thu Fri 12/1/23 22,23
Aluminum windows 11/16/23
Units and Glazing
Panels for ATC Tower

30 6.4 Thermal & 8 days Sat Tue 12/5/23 27


Insulation Works; for 11/25/23
doors and windows
frame spaces (Acoustic,
Thermal, Fireproof and
Waterproof )

31 6.5 MileStone -4- 0 days Fri 12/8/23 Fri 12/8/23 27,28,29,30 12/8
32 7 Interior & Exterior 16 days Sat 12/9/23 Fri 12/29/23 26 Civil Engineer ,Supervisor ,Electrical Engineer ,Generator
Finishing; Walls, Operator,Helper,labor Foremen,Iron Worker,Project
Ceilings, and Floor Manager,Survey Engineer,Welder,Truck Driver,Painter and
Plasters,Metal-Sheet installer Worker,Mechanical Engineer
33 7.1 Floor Tiles Finishing 15 days Sat 12/9/23 Thu 12/28/2326
34 7.2 Walls & Partitions 12 days Sat 12/9/23 Mon 26
Repairing and Paintings 12/25/23
35 7.3 False Ceiling and 15 days Sat 12/9/23 Thu 26
supporting Grids 12/28/23
installation; Gypsum &
metalic board Tiles

36 7.4 MileStone -5- 0 days Sat 12/30/23Sat 12/30/23 33,34,35 12/30


37 8 Mechanical-Works I 21 days Fri 12/1/23 Fri 12/29/23 21,26 Civil Engineer ,Electrical Engineer ,Electrical
(HVAC, Generators, and Technician,Equipment Mechanic,Carpenter,Deputy
Fuel Tanks) Manager,Excavator and Front loader Operator,Cement
Finisher,Hand tools operator,Generator Operator,Heavy
38 8.1 Mechanical Works; 8 days Fri 12/1/23 Tue
HVAC 15 TON Package 12/12/23
[ROOF TOP UNIT]
System installation, All
Ductworks Roating and
Rigid Insulations works

39 8.2 HVAC Equipment; 20 days Fri 12/1/23 Thu


ductworks, Rigid 12/28/23
insulation Supply and
Installation works

40 8.3 Generators, 20 days Fri 12/1/23 Thu


Equipment; and Fuel 12/28/23
steel Tanks Supply and
Installation works
41 8.4 MileStone -6- 0 days Sat 12/30/23Sat 12/30/23 38,39 12/30
42 9 Mechanical-Works II 32 days Fri 12/1/23 Sun 1/14/24 21,26 Cement Finisher,Civil Engineer ,Deputy Manager,Electrical
(Plumbing & Sewer Engineer ,Electrical Technician,Equipment
Network) Mechanic,Excavator and Front loader Operator,Generator
Operator,Hand tools operator,Heavy Machinery
43 9.1 Substructure; SITE 8 days Fri 12/1/23 Tue
MAIN WATER & SEWER 12/12/23
PIPING SYSTEM
CONNECTION WORKS

44 9.2 Substructure; Floor 6 days Wed Wed


Drains, Cleaning pits 12/6/23 12/13/23
and Manholes
Installation and Supply

45 9.3 Plumbing Works; 5 days Wed Tue


potable Water Tank 12/6/23 12/12/23
Supply and installation
46 9.4 Plumbing Works; 6 days Fri 12/8/23 Fri 12/15/23 43
Connection to Sewage
Tanks, lift statiuon
pumps supply and
installation

47 9.5 Plumbing Works; 4 days Thu Tue 1/2/24 43,44


Water Electric Heater 12/28/23
Supply and Installation
48 9.6 Plumbing Works; 18 days Thu Mon 1/8/24 46,45
Cold Water distribution 12/14/23
piping Lines
49 9.7 Plumbing Works; 12 days Wed Thu 1/4/24
Hot Water distribution 12/20/23
pipin Lines
50 9.8 Supply & Installation 12 days Wed Thu 1/11/24 46,45
of water pumps, 12/27/23
plumbing lines, and
Sanitary fixtures

51 9.9 MileStone -7- 0 days Sun 1/14/24 Sun 1/14/24 43,44,45,46,4 1/14
52 10 Mechanical-Works III 8 days Mon 1/1/24 Wed 1/10/24 4,11,6,37 Civil Engineer ,Deputy Manager,Electrical
(Fire Alarm & Fire Technician,Equipment Mechanic,Excavator and Front loader
Fighting System) Operator,Generator Operator,Hand tools operator,Heavy
Machinery Operator,Helper,HSE Engineer ,Labor (Non-Skilled
53 10.1 Fire alarm and 8 days Mon 1/1/24 Wed
suppression Systems 1/10/24
54 10.2 MileStone -8- 0 days Wed 1/10/24Wed 1/10/24 11,12,13,6,7,8 1/10
55 11 Electrical-Works I 14 days Mon 1/1/24 Thu 1/18/24 32 Carpenter,Civil Engineer ,Deputy Manager,Electrical Engineer
(Power and Lines) ,Electrical Technician,Equipment Mechanic,Generator
Operator Hand tools operator Heavy Machinery
56 11.1 Electrical MAIN 13 days Mon 1/1/24 Wed
POWER DISTRIBUTION: 1/17/24
from MDB (Main
Distribution Board)
57 11.2 Electrical BUILDING 12 days Mon 1/1/24 Tue 1/16/24
POWER DISTRIBUTION:
from SDB (SUB
Distribution Board)

58 11.3 Electrical System; 10 days Wed 1/3/24 Tue 1/16/24


Exterior and Interior
59
P bl 1/19
11.4 MileStone -10- 0 days Fri 1/19/24 Fri 1/19/24 56,57,58
60 12 Electrical-Works II 26 days Mon Mon 2/19/24 21,52,26,42 Carpenter,Civil Engineer ,Deputy Manager,Electrical Engineer
(Lighting, Outlets, & 1/15/24 ,Electrical Technician,Equipment Mechanic,Generator
Wirings) Operator,Hand tools operator,Heavy Machinery
Operator,Helper,HSE Engineer ,Iron Worker,Labor
61 12.1 Electrical 26 days Mon Mon 42
connections, Wirings for 1/15/24 2/19/24
lighting, outlets,
equipements and
62 12.2 MileStone -11- 0 days Tue 2/20/24 Tue 2/20/24 61 2/20
63 13 Site Completion Work13 days Wed 2/21/24Fri 3/8/24 60,42,37 Carpenter,Cement Finisher,Civil Engineer ,Deputy Manager,Ele
64 13.1 Site Preparations 12 days Wed Thu 3/7/24
for final checks and 2/21/24
65
l
13.2 Site Improvements 10 days Sat 2/24/24 Thu 3/7/24
66 13.3 MileStone -13- 0 days Sat 3/9/24 Sat 3/9/24 3/9
67 14 Final Checking Tests 12 days Sun 3/10/24 Mon 3/25/24 63,60,55 Civil Engineer ,Deputy Manager,Electrical Engineer ,Electrical T
68 14.1 Site Civil & 11 days Sun Fri 3/22/24
Mechanical Utilities; 3/10/24
69
fi l h k
14.2 Site Electrical 10 days Mon Fri 3/22/24
Utilities; final checks 3/11/24
70 14.3 MileStone -14- 0 days Mon 3/25/24Mon 3/25/24 17 3/25
71 15 Demobilization Work 5 days Tue 3/26/24 Mon 4/1/24 67,69,68 Civil Engineer ,Deputy Manager,Helper,HSE Engineer ,Labor (N
72 15.1 Demobilization 5 days Tue 3/26/24 Mon 4/1/24 69

Sun 10/1/23 Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress
Mon 4/1/24
Project_Steel_Warehouse_01

Page 1