PE511 Spring2023 Chapter 04
PE511 Spring2023 Chapter 04
1
18/10/1444
2
18/10/1444
3
18/10/1444
4
18/10/1444
5
18/10/1444
6
18/10/1444
7
18/10/1444
8
18/10/1444
9
18/10/1444
Hierarchical
Breakdown of
the WBS
10
18/10/1444
11
18/10/1444
Work Packages
• A Work Package is the Lowest Level of the WBS
– It is output-oriented in that it:
• Defines work (what)
• Identifies time to complete a work package (how long)
• Identifies a time-phased budget to complete a work
package (cost)
• Identifies resources needed to complete a work package
(how much)
• Identifies a single person responsible for units of work
(who)
• Identifies monitoring points (milestones) for measuring
success
12
18/10/1444
13
18/10/1444
14
18/10/1444
WBS Coding
15
18/10/1444
Project Roll-up
• Cost Account
– The intersection of the WBS and the OBS that is a
budgetary control point for work packages
– Used to provide a roll-up (summation) of costs
incurred over time by a work package across
organization units and levels, and by deliverables
16
18/10/1444
17
18/10/1444
Responsibility Matrices
• Responsibility Matrix (RM)
– Also called a linear responsibility chart
– Summarizes the tasks to be accomplished and who is
responsible for what on the project
• Lists project activities and participants
• Clarifies critical interfaces between units and individuals that
need coordination
• Provide an means for all participants to view their
responsibilities and agree on their assignments
• Clarifies the extent or type of authority that can be exercised
by each participant
Responsibility Matrix
for a Market Research Project
18
18/10/1444
Responsibility Matrix
for the Conveyor Belt Project
19
18/10/1444
Key Terms
Cost account
Milestone
Organization breakdown structure (OBS)
Scope creep
Priority matrix
Responsibility matrix
Scope statement
Process breakdown structure (PBS)
Work breakdown structure (WBS)
Work package
20
18/10/1444
Chapter 4 Completed
HW# 2
[Due Saturday, May 20, 2023]
21