2025 Project Management and Evaluation
2025 Project Management and Evaluation
NASPW
PROJECT MANAGEMENT &
EVALUATION
Course Objectives
By the end of this course you will be able to:
• Define a project, project management, and evaluation as well as its scope.
• Understand different types of projects, their characteristics, and their objectives.
• Understand projects in organization structure
• Appreciate the project management process
• Understand who a project manager is, types of project managers, selection,
roles, and responsibilities of a project manager.
• Examine more closely project evaluation and post-project evaluation
Understand some issues that are associated with project management
Further Studies
Harrison, F. L. & Lock, D. (2004). Advanced Project Management: A
Structured Approach. Gower Publishing, Ltd
Basics, (n.d.). “Basics of Project Management.”
https://www.manage.gov.in/studymaterial/PM.pdf
Meredith, J. R. & Mantel, S. J. (2010). Project Management: a managerial approach,
(7th ed.). Asia: John Wiley.
Najaragan, K. (2012). Project Management. New Age International (P) Ltd. Nokes,
S. (2008). The Definitive Guide to Project Management, (2nd ed.),
London: Financial Times / Prentice Hall.
Olsson, E. & Samset, K. (2006). Front-end management, flexibility, and project
success. Paper presented at PMI® Research Conference: New
Directions in Project Management, Montréal, Québec, Canada.
Newtown Square, PA: Project Management Institute
Pacific Invasive (n.d.). Pacific Invasive Initiative resource kit for rodent and cat
eradication. Available at http://www.pacificinvasivesinitiative.org/
Project Management Institute (2021). What is project management? Available at
https://www.pmi.org/about/learn-about-pmi/what-is-project- management
Project Management Institute (2017). A Guide to the Project
Management
Body of Knowledge, (6th ed.), Pennsylvania: Project Management Institute
PART TWO
In the case of a building project, we can understand more clearly what is meant
by a series of activities that are involved from the table below
Table 1: Major Activities in Building A Custom Home
Event Description Time Preceding (weeks)
activity
C Pour footers 1 B
E Frame house 4 D
J Install insulation
K Install Sheetrock 2 J
P Install flooring 1 N
A good look at Table 1 above shows that the project name is “Construction of
Custom Home.”
The hierarchy or series of tasks or activities that are involved are labeled A-Q, each
with its individual description. The time frame (in weeks) for performing each
activity is spelled out and the activities that can go on at the same time and those
that must be completed before the next one can begin are also labeled. A delay
in one task translates to a delay in the next task and will ultimately affect the
completion date of the project. In essence, when we are talking about a project it is
important that we know the specific goals of the project, the start date and the
conditions within which it will be executed. It is also important to define
responsibilities, plan the budget, fix the end date for the project, and identify the
parties that will be involved in executing each of the tasks or activities.
Another thing to note is that projects cost resources in the form of men,
material, money and time and it is expedient that these resources are available for a
project to be completed. It is equally important that all these resources are properly
allocated and managed to get the desired outcome or deliverable. Therefore, projects
are usually an organised unit with the aim of attaining a definite goal. There is
always time duration for any project as well specification according to the needs
of the end-user. Each project is executed within a budget that is reflective of the
specification and the expectation is that the project will be completed within the
projected time as well as meet specifications. Anything short of this is not desirable.
In summary, a project is the purposed outcome consisting of a series of
tasks/activities to be carried out within a specified time and financial constraints.
Therefore, there is recognition that projects are subject to constraints, especially
funds, and this can affect the completion time. Furthermore, projects vary in size and
scope, from the construction of a cathedral to an activity as seemingly mundane as
planning a wedding.
Let us consider another project, say a library project such as automation. This will
also involve a number of steps within which many activities will be involved.
So as soon as a decision is taken to automate, all the activities/steps from planning
to implementation will be outlined. This will also require that time and resources are
carefully planned and allocated. The project is expected to run within specifications
and there will be a need to monitor it as it goes on to ensure that it meets the
specifications. The project will not be considered successful unless the deliverables
are according to specifications and also meet performance standards and objectives
for embarking on it in the first place. This takes us to the objectives of projects.
1.1.1 Objectives of Projects
As observed, all projects have a set of objectives, goals or missions. It is only when
the objectives are achieved that the project can be said to be completed. As shown in
the Construction of a Custom Home diagram earlier, the objective of that project is
to construct a custom home. As soon as the custom home is completed and certified
alright in terms of functionality and performance, the project comes to an end. The
same thing goes with your educational pursuit. You complete it the day your graduate
because no one is expecting you to continue attending lectures after your successful
graduation from a course. The only way you can continue attending lectures is if you
gain admission into another programme or even the same programme. This time, it
is a different educational pursuit. That is why we say a project has a start date and
an end time. Therefore, the objective of a project depends on what it is meant to serve
and also the requirements of the client. Generally, however, Sindjuha (n.d.) has
outlined three project objectives as discussed below:
(i) To Ensure Function or Performance:
Every project has its objectives. The project objectives outline the project’s goals and
aims. The type and size of a project will determine the objectives therefore, one
project can have just one objective while another project has several objectives that
could be completed at various times in the course of executing the project.
Project objectives should be practical and implementable and limited within the scope
of the project.
As observed, every project has its end-user. The end-user makes his specification
according to what he wants. Therefore, the final result of any project must satisfy
the requirements of the end-user. If for instance, the end- user wants a block of offices
for leasing, the project has to produce a block of offices for leasing at the end of it
and nothing less. Not only that, the building must satisfy the specified standards for
performance, reliability, and safety. In other words, the block of offices for leasing
should not only be the final outcome, but at the end of the day, it is important that in
terms of function or performance, reliability and safety, the project is delivered to
satisfy the requirements of the end-user.
(ii) To Ensure Containment of Expenditure within Budget:
Project management aims at containing expenditure within budget because project
execution is costly in terms of resources. Ensuring containment of expenditure within
budget is a project objective.
At the planning stage, every effort is made to attach costs to activities. This gives an
idea of the entire cost of the project. Baring serious unforeseen circumstances, it is
expected that projects are carried out within the stipulated costs or something very close
to it. This is a very important criterion for project success. In our example of a block of
offices for leasing, it is obvious that this is a commercial venture. If the development
costs of the building exceed what has been planned, it means that the project owner
would have to lease his offices at a much higher cost than planned so that he can recoup
his extra expenditure. However, increasing the cost of leasing may not be favourable
because there are other competitors in the business. Therefore, if his block of flats is
charged far above the prices charged by his competitors for the same product, it will
affect his business. This is why it is important that projects are completed within their
budgeted costs. It is also why containment of expenditure within budget is one of the
objectives.
(iii) To Keep to Project Time Scale:
We have mentioned that projects are put on a time scale. The successful completion
of a project within the time scale is important. This is important to ensure not only that
the project does not overshoot its budget but also so that it can be put into use within the
time planned. Assuming the end-user or project owner was targeting a time within which
if he sells he will make the most gain, it is important that the project is fully developed
and ready for the market within the stipulated time scale. This is also true of other kinds
of projects be it products or services. This point is important if the project is one that has
a known peak period of the business. Therefore, a major objective of a project is to see
that it is executed within the stipulated time scale in order to remain
within budget as well as meet the needs for its execution.
Time Cost
End User
Fig. 1 Triangle of Project Objectives
Projects can take any form or shape. For instance, the development of software for an
improved business process, the construction of a building, the relief effort after a
natural disaster, the expansion of sales into a new geographic market are all examples
of projects (Project Management Institute Book of Knowledge, 2021).
While appreciating that there are different types of projects according to their unique
classifications, the classifications outlined by Nagajaran (2012) and Sindhuja (n.d.)
will be discussed at length here. Nagarajan (2012:7-9) classifies projects under six
headings as follows: (i) based on the type of activity; (ii) based on the location of the
project; (iii) based on project completion time, (iv) based on ownership, (v) based on
size, and (vi) based on need. These are discussed below
Under this classification, projects are further classified under two broad headings:
industrial projects and non-industrial or developmental projects. An example of an
industrial project is a manufacturing project set up for the production of some
goods. Under non-industrial projects, we talk about projects such as health
care projects, irrigation projects, water conservation projects, pest control projects,
preservation projects and so on. Non-industrial projects are usually executed by the
government and they are concerned with bettering the lives of the generality of people
in the society. Although the products of such non-industrial projects cannot be
quantified in terms of tangibles such as goods as we have in manufacturing projects,
they are very important for the welfare of people and the general development the
society. An electrification or water project will serve the purpose of providing light
and water respectively to the citizens. This in turn betters their living conditions
and enables them to be more productive in their individual pursuits.
Table 2. Difference between Industrial and Developmental
Projects
Investment …. High
Interest rates and Market rate and the Very low for borrowed
repayment period: repayment period is funds and the repayment
generally 7 to 10 years period extends up to 25
years and even beyond.
Source: https://www.manage.gov.in/studymaterial/PM.pdf
In this category are projects that can be classified as national projects and
international projects. As implied, national projects are set up within the
national boundaries of a country, while international projects are set up by one
country in other countries. Furthermore, international projects may be set up by the
government of a country or by the private sector of a particular country in another
country. Note that the handling of international projects requires more expertise and
greater efforts because they involve higher risks in terms of proportion and procedural
formalities that are involved since they are international in nature. Some examples of
international projects include:
• Setting up fully-owned subsidiaries abroad
• Setting up joint ventures abroad
• Setting up of projects abroad by way of mergers and acquisitions
Projects can be classified based on constraints such as project completion time, and
based on that, they can be classified into two types: normal projects and crash
projects. Normal projects are projects in which there is no constraint of time. In other
words, they are not time-constrained or bound and so are not necessarily designed to
be completed within a specified time. That is to say that there is no compelling reason
to rush or complete the project on a given date.
On the other hand, crash projects are those that have to be completed within a
stipulated time, sometimes at the cost of incurring higher project costs. For example,
the Federal Government of Nigeria commissions a dam rehabilitation project which
has to be completed before the next rainy season. This is a crash project because it
must be completed before the coming rainy season to ensure that any envisaged
disaster in the rainy season is averted. The fact here is that the project was embarked
on to forestall an impending disaster during the next rainy season. So, the project has
to be completed and commissioned before the next rainy season. Therefore, if it is
not completed within the planned time, it has failed to achieve the expected end.
Here, projects are categorised into three groups: private sector projects, public sector
projects, and joint sector projects. A private-sector project as the name implies is
completely owned by private promoters and investors. The major objective for
establishing a private sector project is profit maximisation given that they are funded
by private investors who are interested in recouping not only their investment but also
gaining some good financial returns.
Public sector projects are owned by the state or government (federal, state or local).
The major objective of executing public sector projects is the government’s
obligation to undertake development projects. Public sector projects vary from
country to country depending on the kind of economic system that is run in the
country. For instance, in a purely capitalist economy such as that of the United States
of America, there is hardly any public sector enterprise except those that concern
defence, public utility services etc. On the other hand, in mixed economies such
as the kind we have in developing countries, both private and public sector
enterprises exist.
Joint sector enterprises are those in which the ownership is shared between the
government and private entrepreneurs. The overriding interest of the government in
venturing into joint sector projects is to make use of the managerial talents,
entrepreneurial capabilities, and marketing skills of the private enterprises.
Therefore, projects can be undertaken by these enterprises and are said to be owned
either by the government or private based on the ownership of the enterprise.
v. Based on Size
There are three types of projects under this category: small projects, medium- sized
projects, and large projects. Size in this sense is expressed in terms of the amount of
investment that is required to fund the project. The investment limit for the different
categories of projects is announced by the government, and the investment is subject
to periodic reviews keeping in mind such things as inflation, and the decision to
offer certain incentives to projects categorised as small, medium, or large.
This categorises projects based on the need they are set up to meet. They include
New Project: This is a project that is conceived and implemented to satisfy customer
needs. This occurs when a company notices a gap in customer needs that should be
filled and appropriate steps are taken to fill that gap. For instance, a quantity of
a product or service that is being provided is no longer able to meet market demand,
the company goes ahead to increase the quantity that is supplied to close the gap.
Balancing Project: Generally, projects do not stand alone. They actually have many
product units that are linked with one another. In this case, all the projects are
able to service each other in one way or another in the sense that the output of one
production unit exactly matches the input required for the next production unit.
This ensures full utilisation and maximisation capacity of all the production units.
Forward Integration Project: In this case, a company decides to own and control
business activities at the end of its production line. This is done after the
organisation is fully satisfied that including new business will be profitable.
For instance, a company that produces clothing and used to supply them to boutiques
for sales might decide to own a line of boutique outlets to which they supply their
products. In essence, rather than depend on other sales outlets, they now have their
own and deal directly with buyers. This is a value-adding service.
For instance, the development and introduction of a new classification scheme that
will make the library material easier and faster to classify can be considered
a library management project. Management projects can also be the design and testing
of a new computer package, and relocation of a company’s headquarters among
others. All of these projects involve the management coordination of a series
of activities before a successful outcome can be achieved.
Time Cost
Scope
Fig.2: Project Performance Dimensions (Source: https://www.academia.edu/)
From the figure below, it can be seen readily that the three dimensions are interrelated
and interactive to the extent that a change in one, will most definitely affect the other.
To illustrate this, assuming that there is a change in the project scope, it will require
that the project completion time be extended and this will invariably entail that the
project cost would go up.
On the other hand, if there is a reduction in time, the scope and cost would also have
to be reduced. In the same vein, if there is any change in cost, it will also reflect in
scope and time. The implication is that to successfully complete a project, there is a
requirement that specified goals be accomplished within the scheduled time and
budget. In essence, the performance of a project “is measured by the degree to which
these three parameters (scope, time, and cost) are achieved. Mathematically
Performance = f (Scope, Cost, Time). In management literature, this equilateral
triangle is also referred to as the
“Quality Triangle” of the project” (https://www.academia.edu/, n.d.).
Having defined the concept and types of projects, the next important thing is to look
at the characteristics of projects. Eighteen characteristics of a project have been
highlighted by Nagarajan (2012: 3-4) as discussed below
Every project has a life circle. The project life cycle includes the steps that the project
manager has to take to successfully execute a project from start to finish. The
life cycle comprises the following stages which include:
What is being explained here is that every project has a life cycle however, the life
cycle of a project does not start when the work begins. Rather, it starts from the time
the idea is conceived. As soon as the idea is conceived, the next thing is to begin to
design all the stages that are involved in the project in the manner they will follow.
Then the implementation starts using the design that had been outlined. This
continues until the project is completed. As soon as it is completed and certified to
have met all the requirements as outlined in the design, the project is commissioned.
The commissioning marks the end of the life of the project.
A
B C D
Commissioning
Implementation
Procurement
Design &
TIME
Definite Time Limit: Every project has a definite time limit/line. Projects are not
meant to continue indefinitely but after they are completed, there can be
maintenance exercises as required. Note that maintenance work is not considered
a project because while maintenance is an ongoing process, the project itself
cannot continue forever.
Complexity: Just as projects have diverse areas of expertise, so also, they have
complex sets of activities relating to each diverse area. Factors such as technology
survey, choosing the appropriate technology, procuring the appropriate machinery
and equipment, hiring the right kind of people, arranging for financial resource,
execution of the project in time by proper scheduling of the different activities, etc.
contribute to the complexity of a project.
To buttress the point above, it could be that certain technology or equipment had
been proposed to be used at the planning stage. But during implementation, better and
more efficient ones became available. The rational thing to do would be to switch to
the latest technology. This is informed by the need to keep the project up to date.
This can affect the life span of the project considering the lapse in the period between
procuring and installing the new equipment.
Response to Environments: Projects take shape in response to environments.
For instance, countries set up projects in response to environmental needs. Projects
that do not take into consideration the need of the environment will most likely end
up as white elephant projects. We have a lot of abandoned white elephant projects
in Nigeria.
For instance, let us assume that there is a need for developing the health sector, and
also a need for building a recreational centre. Given that both projects will demand
huge resources, the most rational choice among the two should be made based on
the most compelling need at the time.
Meredith and Mantel (2010) define project selection as “the process of evaluating
proposed projects or groups of projects, and then choosing to implement some out of
them so that the objectives of the parent organsiation will be achieved.” Another
definition says that project selection is a process to assess each project idea and select
the project with the highest priority (Pacific Invasive, n.d.). The definitions further
reinforce the point that the whole purpose of embarking on project selection is to
be able to choose the most important out of other competing interests. The decision
to choose one project or a number of projects out of many is not an easy one. As
a result, some criteria have to be borne in mind to do it objectively.
Some criteria that have been articulated by Mansinghka & Mohan (2021)
include:
Strategic Alignment with Business Goals: There is no business that does not have
its set of strategic goals, a defined vision, and a mission. This is necessary to give
them a sense of direction toward the path to success. All projects that an organisation
seeks to embark on must be strategically aligned to its goals. This will ensure that
they stay on course and prevent any temptation to go into frivolous expenditure as
they allocate their resources judiciously. Having this in mind will also keep an
organisation from wasting time and effort on endeavours that steer them away from
the organisational objective.
o How will the final output of the project solve the existing problems for the
client?
o Will the project improve the client’s perception of the firm’s products and
services?
Once a consensus is reached and it is believed that the project can enhance
customer satisfaction and improve brand loyalty that might be a pointer to
the right direction to take up the project.
Data Availability and Expected Revenue: This is concerned with finding out
if there is enough data available on the project and, if not, is it possible to collect data
from varied sources? When working on a project and the essential data is in place,
implementing it at the right place and the task becomes easy. In the absence of
relevant data, the tendency is that resources will be spent over a long period in
gathering the right information, analyzing it, and then implementing it. Where there
is limited data available, the possibility of hindering a project’s progress is increased.
Along with this, there is a need to ensure that the ROI or Return on Investment is
calculated based on the approximated revenue that the project is expected to
generate. This is a very crucial activity since it is not wise to use resources, skills,
time and effort, and the company’s finances on a low-revenue generating project. If
this is not done properly, it will lower profitability and also keep the organisation
from taking up a higher revenue-generating project. Managers follow a benefit-
evaluation model to calculate this.
The concept is also defined as “the application of knowledge, skills, tools, and
techniques to project activities in order to meet or exceed stakeholder needs and
expectations” (Darwish, 2017). From the definition by Darwish, we are made to
understand that project management requires some knowledge, skills, The purpose
of project management is to minimise, contain or counter the risks, and organise
and direct the resources so that the project is finished in time, within budgeted
costs, and with the functional or other design objectives fulfilled (Sindjuha, n.d.). In
another definition, Project Management Institute (2021) defines project management
as “the use of specific knowledge, skills, tools, and techniques to deliver something
of value to people.
Going through the definitions carefully, you will notice that there cannot be any
project management without projects, and projects are executed using men and
materials such as finance and will also involve the use of knowledge, skills, and
tools to ensure that expectations are met. The project manager is responsible for
ensuring that all this is done successfully.
Your levels are arranged according to a series of tasks and activities (courses,
lectures, quizzes, seminars, projects, etc.) which must be completed and achieved to
qualify you for the next level. Your examinations are the project evaluation while
your graduation is the project completion/date. Any student who seeks to achieve the
desired outcome must work according to the specifications. Also, there has to be
funding for all that is concerned with schooling. Therefore, the whole process of you
managing all that goes into a successful educational outcome from start to end can
be deemed project management, and you, the project manager tools, and techniques
that must be brought to bear on a project for a successful outcome.
We have established that the basic reason for initiating any project is to
accomplish some goals. Also, although there is no rule that says that project
management must be applied in executing a project, however, the need to focus the
responsibility for the project on an individual known as the project manager
and a small group also known as the project team makes it necessary to
organise the task as a project.
1) Project management approach will help in handling complex, costly and risky
assignments by providing an interdisciplinary approach to handling the assignments.
This stems from the fact that projects usually require multidisciplinary expertise or
teams for their execution. This implies that not one single individual has all the
expertise needed to execute a project successfully;
• The achievement of the project’s main goal within the given constraints:
The most important project constraints are, Scope in that the main goal of the
project is completed within the estimated time while being of the expected
quality and within the estimated budget. Staying within the agreed limitations always
feeds back into the measurement of a project’s performance and success.
Project management aims to ensure that all resources that are provided for project
implementation are fully and beneficially allocated and that they are deployed in
such a way as to achieve pre-set goals. It is also the objective to ensure that the
human resources are fully utilized towards achieving project goals. That being the
case, it also aims to see that all impediments against the full actualization of a
successful project are addressed. According to Clarizen (2020), project
management ensures that “all processes and procedures can be reformed and
upgraded to enhance the sustainability of a project and to lead the team through the
strategic change process.”
Scoping
Scoping in project management is concerned with setting boundaries for the project
by clearly defining the goals, deadlines, and project deliverables that one is working
to achieve. It is important that the project team works within the scope of the project
to manage funds appropriately and deliver within the timeline.
Project Planning
The saying “if one fails to plan, one plans to fail” is an axiom that is often used to
drive home the importance of planning in all life endeavours. This is also true of
project management. Planning is a very important aspect of project management
because good planning anticipates all the factors that are associated with the
project right before the project starts and puts them down in a document to serve as a
working guide. Simply put, a project plan or project management plan is a document
that describes the objectives of the project, and how the project will be executed,
monitored, controlled, and closed or finished. As Ahmad (2010) puts it, “the project
plan effectively outlines the objectives and scope of the project and serves as an
official point of reference for the project team, larger company, and stakeholders”.
Estimating
Project Scheduling
Project scheduling is concerned with outlining the actual activities of the project
with time assigned in the time order/sequence in which they are to be performed.
1. Company registration
3. Appointment of consultants
4. Resource mobilization
6. Preparing civil work designs, plans, and estimates and entrusting the
construction work to civil contractors
9. Erection of machinery
All this are mapped out and timelines are attached to them. The essence is to provide
some type of guidelines to ensure that time and other resources are used wisely.
Organising
As already explained, projects are grouped into activities. Also, resources are an
important requirement in project execution. In organising, the project activities are
clearly defined and analysed in such a way that they are clearly grouped according
to their distinct areas or departments. It also entails establishing the authority and
responsibility relationships by clearly defining who is responsible for what and who
reports to who. It also involves organising the resources that are required for the
accomplishment of organisational objectives. Essentially, project organisation is a
structure that facilitates the coordination and implementation of project activities.
The structure defines the relationships among members of the project management
and the relationships with the external environment.
Directing
Projects are executed with resources including people. Effectiveness and efficiency
demand that the project manager who is directly responsible for the day-to-day
running of the project directs people to work in the desired manner towards achieving
the stated goals. Put simply, directing is “the process of guiding the subordinates
towards achieving the organisational goals. To achieve this, there is the need to
issue orders, directives, instructions, and commands. For the subordinates, directing
enables them to know what the expectations are. Using the tools of instructions,
orders, requests, guidance, supervision, coaching, advice, etc., the project manager is
expected to get the subordinates to work according to expectations, and he is also to
inspire them to achieve the project goals (Nagarajan, 2012).
Controlling
There are three important factors over which control is exercised in projects. These
are time, resource, and quality. It is important to ensure that the project is running
within the time scale, that the needed resources are available, and that the project
meets standards in terms of quality. Controlling ensures that things are done
according to the plan. It is the process of comparing the actual performance of the
project with the planned performance i.e. the ideal and the reality. Controlling aims
to check up on whether the project progresses exactly in line with what was planned.
If in the course of controlling deviations also called variances are noticed, in terms of
time, resource, and quality parameters, the variances must be analysed, with a view
to identifying the reason for it and applying suitable remedial measures to correct
them and then put the project back on the right track (Nagarajan, 2012).
Closing
As often mentioned, every project is a temporary undertaking. To that extent, a
project has a start date and a finish date. Closing a project is the process of
finalising all activities for the project, phase, or contract. This is an indication
that the project has been successfully completed. It is called the close project or
phase. However, while it is expected that the close project or phase indicates that
the project has been successfully completed, a project may also be closed when
it is terminated before it is finished. The close project or phase can be seen as
the last phase of the project life cycle. At this stage, the project is closed,
and reports of the level of success of the project are made to the owner. Other
activities involved in the closing project or phase include handing over the
deliverables to the customers, passing documentation to the business,
releasing staff and equipment, canceling contracts with the supplier, and
informing the stakeholders about the closure (Nagarajan, 2012).
In essence, this activity is heavy on document verification. All the project documents
have to be gone through carefully and care taken to ensure that there are no
unfinished items, that all the agreements concerning work items are delivered and
signed off officially, and that all the objectives and plans, and obligations are met.
Therefore, there cannot be a close project or phase until the owner has formally
signed off on the project outcome or deliverables. A number of steps are involved
in a close project or phase. The benefit of close project or phase can be said to be that
the tool provides a formal method to end the project. As soon as the organisations’
resources are released, new projects or endeavours can be pursued.
Some of the processes that have been explained above are captured diagrammatically
below denoted as project management face.
Planning
Process
Executing
Initiating Process
Process
Controlling
Process
Closing
Process
Close Project or Phase
1. Project charter
1. Expert judgment 1. Project documents
2. .Project management Plan
2. Data analysis updates
• All Components
• Document • Lessons learned
3. Project documents
analysis register
• Assumption log
• Regressionanalysi 2. Final product, service,
• Basis of estimates
s or result Transition
• Change log
• Trend analysis 3. Final report
• Issue log 4. Organisational process
• Variance analysis
• Lessons learned register assets update
3. Meeting
• Milestones list
• Project communication
• Quality control
• Requirements
• Documentation
• Risk register
• Risk report
4. Acceptable deliverables
5. Business documents
• Business case
• Benefits management plan
6. Agreements
7. Procurement documentation
8. Organisational process assets
Fig.5: Close Project or Phase: Inputs, Tools & Techniques, and Output (Source:
GreyCampus.com).
A simple example can be a construction project. There are certain things that must
be done in order to have a strong structure. Any attempt to do it differently
will certainly result in a building that will not stand the test of time. Therefore,
principles are expected to guide how things are done and where principles are
neglected in the pursuit or execution of a thing or activity, it can lead to some
unpleasant circumstances that are bound to attract some consequence(s).
So, when we talk about a principle guiding a system, we are saying that systems
have their essential characteristics that take into consideration the reason for their
design or their purpose and the only way that systems can be effectively operated or
used would depend on whether the principles are acknowledged and adhered to or
whether they are ignored. Therefore, refusal to adhere to the principles guiding a thing
is to be likened to short-circuiting the process (Guido, also cited in Wikipedia, 2021).
The principles that must be followed will include 1) defining the project goals and
objectives, 2) defining the project deliverables, 3) clarifying team roles and
responsibilities, 4) creating a strategy for initiation and execution, 5)knowledge of
numbers, 6)careful budgeting, and scheduling, 7) identifying priorities and milestones
ahead of time, 8) accountability and responsibility, 10) communicating plan, 11)
transparency, 12) risk assessment, and 13) monitoring and measuring progress.
Definition of project goals and objectives is important because the goals that are
set for a project play a critical role in its success or failure. Goals must be set before
work begins and must not be ambiguous so as to enable all the work team to be on
the same page and avoid future misunderstandings. Also, set goals must be
realistic, clear, and measurable. When the goals are ambiguous, it makes it difficult
for the project to be understood or achieved by the project team. This can result in
delays in meeting milestones. With undefined goals, the project manager may
encounter problems on a daily basis in the area of project organisation. All said, the
project goal is the expected outcome and should be known ahead of time because it
also leads to the project structure plan. It is important to state that the successful
achievement of all project goals lies with the project manager, and he can better
define the goals using the
SMART paradigm (specific, measurable, ambitious, realistic, time-bound).
Define Deliverables
In the case of a building project, assuming the objective is for the end-user(s) to have
a residential home, the deliverable that will be the final product should be a residential
home that meets expectations in terms of function/quality and performance.
Therefore, anything short of the client’s specifications is not acceptable and can
be regarded as a failure of a project.
Projects are structured around teams. To that extent, it is important that members of
teams understand very cleanly, what their roles and responsibilities are. Unclear
definition of roles and responsibilities of team members is the cause of most
confusion and tension among team members. This is because team members will
most certainly cross their boundaries and may not be able to relate with each other
if they are ignorant of the roles and responsibilities. This will usually lead to conflicts
among team members. Therefore, the project manager has the responsibility to define
the role of each team member to help everyone to work more harmoniously with
each other. This point is driven home by the fact that in many cases, a project is
multi-disciplinary in nature and as a result requires the expertise of members from
different specialities. It is important that each knows where their roles and
responsibilities begin and end in order to prevent avoidable conflicts. Project
teams that are conflict- prone will never agree and this has the tendency to further
delay the completion of the project. A delay in completion time entails more financial
involvement.
The project initiation and execution strategy are very important. For instance, it is
during the project initiation phase that all preliminary work that must be done
before any other project activities can take place is outlined. The preliminary work
must be carried out before any other thing that is concerned with the project is done
if not the project will run into murky waters. Incidentally, people tend to just focus
their minds on project execution when they think about project management. Project
execution starts with a project kick-off meeting. This meeting officially begins the
project. It is at this meeting that the project manager shares the vision and plan for the
project. It is also the time he delegates tasks and responsibilities to team members
and sends everyone on their way to get things going. To ensure smooth execution of
projects, during the execution phase, the project manager should ensure that there is
a plan in place to document errors, corrections, and other changes.
Undoubtedly, projects require resources for their execution. While the project
manager has at his disposal the resources that he requires to run the project, it is a fact
that the resources are not inexhaustible rather they are limited. To this end, there is a
need for judicious utilisation of the resources. To ensure that the project remains
within the resources available, it is important that the project manager budgets his
financial resources very carefully. In the budget, he should allow for certain
flexibility by giving himself some margin for unexpected expenses. He should also
ensure that he takes reasonable measures to save costs during the course of the
project. Since the project manager’s budget is unavoidably linked to his project
schedule, if he is not able to keep to the timelines, his budget will most likely suffer
and affect the entire project. Therefore, it is important for the project manager to
account for not just how long each project task should take, but he should also
endeavour to work within the timeline. exigencies factor in exigencies such as
holidays, corporate and stakeholder events, and team members’ vacations. These
should also be provided for in the budget.
Milestones define certain phases of the project and the cost and results that are
associated with each phase. Milestones represent decisive steps during the project
execution and they are set after a certain number of work packages that belong
together. Work package means breaking down large project into parts that are related.
This series of work packages leads to the achievement of a sub- goal.
Projects cannot be executed without a team(s). Teams are made up of people who
have certain expectations. It is therefore important to ensure that they are motivated.
Motivating team members has the advantage of keeping them committed to the
project; it goes a long way in keeping them focused on the goals. One of the best
ways to achieve this is to empower them by giving them a sense of responsibility and
accountability. When individuals are given responsibility for their own work, it not
only motivates them but also makes the job of the project manager less burdensome.
It also has the positive effect of enabling the employees to work from their strengths
and to learn new project management skills. This is advantageous to both the
organisation and the employees in the long run.
Communicate Plan
The project manager should be clear about the kinds of information that needs to be
communicated, and who needs to be notified in certain circumstances. He should also
model the kind of communication he expects from all stakeholders. It is important
that the channels of communication are clearly defined and understood by all the
people that are involved with the project.
Be Transparent
Transparency here entails creating a system in which all team members can access
all relevant information about a project easily and efficiently. Transparency
is important because it is related to efficiency. There is appropriate software in
existence for this and it is the responsibility of the project manager to ensure that
the software that is appropriate for the work he is doing is utilised if he hopes to
achieve transparency. Transparency also entails ensuring that every one that is part
of the project is able to key into the system and understand the objectives and
components of the project. There is a need to make project data available to the team.
This can be achieved by providing good tools for collaboration and by sharing
calendars among team members and even outside stakeholders.
Project transparency leads to better outcomes for both the team and the project itself.
On the one hand, the team will be more motivated if there is a tangible sense of
progress on the project, and on the other, it will improve trust.
Some useful tools for ensuring transparency include flowcharts, structure plan, and a
milestone plan. These tools help the project manager to stay on track. Transparency
also entails that the project manager should be able to present a brief report about
the status of the project to his principal or stakeholders at each stage of the
project. At such meetings, he should be able to give overviews of the costs, the
timeline, and the achieved milestones. This ensures that he not only carries them along
but also that he gains and retains their trust.
Assess Risks
In the course of planning the project, the project manager must endeavour to establish
key performance indicators (KPIs). A key performance indicator is one type of
performance measurement which is quantifiable and used to evaluate the success of
an employee, organisation, project, activity, product, etc. in which it is engaged so
as to ascertain whether it meets the objectives for performance. In projects, KPIs
come in the form of budgets, project management timelines, and quality expectations.
An organisation determines what it considers important to it. As the project
progresses, the project manager should regularly keep track of project progress and
check his KIPs so as to catch issues and make corrections quickly as delays can be
costly. While he is monitoring and measuring progress, it is also not out of place to
celebrate when his KPIs tell him that the team has achieved a goal. This can be a
boost to his team because it will not only give them a sense of belonging but it also
conveys to them that their efforts are noticed and appreciated.
Project initiation is the first phase and is often considered the most important in the
project management life cycle because it is concerned with starting a new project. It
is at this stage that organisations decide whether or not to take up the project. This is
called value judgement. Project value judgement is measured using two metrics
called business case and feasibility. The essence of it is to determine whether the
project will add more value in business terms and how will it be accepted in the
market. These are very important considerations for a number of reasons including
the fact that no organisation wants to execute a project that will not benefit them
given the fact that enormous resources are expended on project execution.
2. Identify Key Stakeholders: The key stakeholders are individuals that are an
important part of the project and whose signature will be required to approve the
project charter of the business card. Initiation stakeholders include the customers,
external persons, and the project team.
Other individuals, who though not stakeholders are important in pushing the project
and who can support the project should also be involved.
Without teamwork, it will be difficult for the members of the team to cooperate with
each other. Teamwork refers to the ability of individuals in a work team to work well
with others to achieve a common objective. Teamwork is a skill that can be developed
through regular practice. An individual who is a team player is always putting the
interest of the team before his/her personal interests.
There are many skills that a project team should possess. Three basic essential skills
that project team members should possess are outlined here. This includes 1.
Good communication skills, 2. Basic management skills, 3. Amicable writing skills,
4. Skills management skills (MyClientSpot, n.d.). These essential skills are
explained below
To identify these skills, from time to time, the project manager should delegate certain
tasks and duties to his team. This will provide him with the opportunity to recognise
the management strengths that each team member possesses. Identification of
such skills is beneficial to the project manager as it goes a long way in the formation
of a self-sustaining team that can multi-task on multiple projects at the same time.
Look out for Amicable Writing Skills: The project manager should look out for
amicable writing skills because like good communication skills, amicable writing
skills is important for sharing and passing information around clearly, correctly and
effectively. Like good communication skills, amicable writing skills play a big part
in ensuring information is shared and passed around clearly, correctly and effectively.
There may be a need for documentation of technical information, if this skill is
lacking, the job will not be done accurately.
Possession of Skills in Risk Management: Risks cannot be totally ruled out from
projects even with the best planning. Even though this is an essential skill requirement
from the project leader, it is also very important that this skill is possessed by team
members.
Everyone in the team must see risk management as a shared concern. The ability
of a team member to detect potentials risks and threats to the project and possibly
prevent them is an essential skill that is desirable among team members. A project
manager should take note of team members that possess this skill.
Project risk has to do with any unforeseen or uncertain events that may or may not
crop up during the project execution phase. However, it is important to note that risks
are not necessarily negative. There are also positive risks. Because uncertainties
cannot be completely eliminated, it is important to plan for and identify possible risk
events that may impact the project.
Risk identification is important for risk management. According to Project Risk Coach
(2022), to identify risks in project management, it is necessary to do the following
Project planning is an important part of the project life cycle and in fact can be said
to be at the heart of the project life cycle. It can be described as a kind of road map
that tells everyone involved in the project where you are going and how you intend
to get there. Let us take for instance a decision to set up a digital library. It will
be foolhardy for management to simply rush into it without sitting down to plan what
it will entail.
Considerations must be made about personnel, finance, equipment etc. that will be
needed to complete the project.
Hassan (2006) opines that it is at the planning phase that considerations are given to
resource availability, resource allocation, staff responsibilities, and forecasting of
cash flow. In other words, the project plan states the resources that are available,
how the resources will be allocated, what each staff is responsible for, and the
timeline of the project. As a result, a well-conceived plan will most assuredly
produce a successful outcome. It must be noted, however, that the project plan is
not cast in iron i.e. it is not foolproof. As a result, there is a need to monitor and if
necessary, re-plan the project as it progresses towards the specified goal to avoid
project derailment.
At the project planning stage, it is important that all the parties involved in the project
understand clearly its facets, the expected results or the processes involved in
achieving the project (deliverables), the tasks that are associated with the project, and
roles and responsibilities of all the team members. Also, it is at this stage that the
time constraints within which team members are working are made clear. In
essence, during the process of planning, the various activities/operations involved in
the project, their sequences/order as well as how they relate to each other are
established
Nagarajan (2012) outlines the following as the main steps in project planning: (a)
(c) Identifying the alternative courses of action for achieving the goals
The three basic components of a project plan are scope, budget and timeline. The
scope is concerned with the boundaries of the project so that the project team
understands what they can or cannot do. This also sets the deliverables and the
performance goals. The budget is concerned with taking a good look at the material
and human resources that are needed to meet the project goals and estimate the project
costs.
The timeline on the other hand is concerned with revealing the length of time that is
expected for each of the phases of the project to be completed and this also includes
the project schedule and milestones that will be met.
In project management, a project plan includes three important documents: Project
Charter, Scope of Work Statement (SOW) And Work Breakdown Structure (WBS).
Project Charter is the section of the plan that presents a general overview of the
project. In this section, the purpose and objectives of the project including the
constraints and risks are outlined. It also defines the stakeholders as well as the
general strategy that will be employed in the project’s execution.
Scope of Work Statement (SOW) describes the scope, schedule, activities and
deliverables of the project including key milestones.
Work Breakdown Structure (WBS) is the aspect of the document that breaks down
the project scope into phases, deliverables and the individual activities that will lead
to the closing deliverable. The Project Execution Plan (PEP) describes the execution
strategy, roles and responsibilities of the project team,
detailed schedule, project assurance, and risk management (Dey, 2022).
• Establish business requirements: It specifies what the project needs are and also
the criteria for success. This includes the goals of the project and the performance
criteria for success.
• Establish cost, schedule, list of deliverables, and delivery dates: With the
project plan, it is possible to have a view of the cost, schedule, list of deliverables
and delivery dates. This serves as a guide for the project team from the execution
through the closing of the project.
• Establish resources plans: Projects require resources in the form of humans and
materials for their execution. The project planning describes all the aspects and
activities of the project with assigned resources for meeting the tasks that are
involved.
• Obtain management approval and proceed to the next phase: The project plan
provides all the information which is needed by management, company or
organization to understand the objectives of the project, the expected
deliverables, scope, costs, and timeline of activities among other things. A
well-detailed project plan is a basis for seeking and receiving approval for the
project which takes the project to the execution phase (Barron & Barron, n.d).
Although the process of developing the project plan differs from one
organisation to another, the basic elements of project planning as outlined by
Meredith and Mantel (2010) are:
• Overview – A short summary of the objectives and scope of the project mostly
directed to the top management. This contains a statement of the goals of the
project including a brief explanation of their relationships to the firm’s
objectives, how the managerial structure that will be used for the project is and
also a list of the major milestones in the project schedule.
• Objectives or scope – While the overview gives a summary of the objectives
and scope of the project, this gives a more detailed statement of the general goals
as noted in the overview section. The statement should also contain information
on the profit, competitive aims and technical goals.
• General approach – This is where the managerial and technical approach that
will be adopted in the work is outlined.
• Contractual Approach – This aspect provides information on the complete list
and description of issues such as reporting requirements, customer-supplied
resources, liaison arrangements, advisory committees, project reviews and
cancellations procedures etc.
• Schedules – Here, the various schedules and milestone events are listed. Also
attached is the estimated time for each task as obtained from the people that are
responsible for them.
• Resources – This specifies the resources required according to tasks.
Project scope defines what the project will deliver and what it will not. It is important
to define the scope because one major setback for projects is the failure to determine
or define the scope. If the scope is properly defined and managed, it will be easier to
contain it within time and budget which ultimately results in the successful delivery
of the project. Failure to define a project scope clearly and manage it efficiently will
most likely result in an unsuccessful project
As mentioned, the project scope is a detailed outline of every aspect of the project.
This includes related activities such as resources, timelines (deadlines), and
deliverables. Deliverables are the tangible things that the project produces. Other
aspects that are outlined in the project scope are key stakeholders, steps that will be
taken, assumptions, and obstacles, as well as what the project is about, what is
included, and what is not. This could be a house or software, among other things.
One important thing is that a project is not expected to extend beyond its scope. The
project scope also serves to provide the key stakeholders, with a clear understanding
of why the project is being initiated as well as defines what the key goals are. This
is important for the avoidance of ambiguity. All of this essential information is
documented in a scope statement.
To that extent, the scope of a project must be clearly stated in the planning phase.
To ensure success in the business of carrying out a new project, therefore, three steps
are necessary:
(ii) Work with key stakeholders to define and create a scope statement by
identifying what is within scope, and out of scope. Collaborating with
stakeholders helps to ensure essential things do not fall through the cracks.
(iv) Gain buy-in (acceptance and commitment) for the scope statement with the
stakeholders who are most impacted to ensure that (Alexander, 2020).
• Scope exclusions, which can be anything that will not be part of the project or
its deliverables
• Milestones that provide the exact date that something will be delivered or
completed
• The final deliverables that will be provided to the customer at the end of the
project — for example, a report, a software feature, any process insights or
analysis, or any product or service that a customer needs.
• Acceptance criteria that spell out exactly how success will be measured
• Final approval whereby the customer will sign off on the scope statement
confirming that all parameters have been included and the document is complete
and accurate (Ahmad, Masood & Mohmmed, 2013).
Essentially, “a budget is a document that translates plans into money - money that
will need to be spent to get your planned activities done (expenditure) and money
that will need to be generated to cover the costs of getting the work
done (income). It is an estimate, or informed guess, about what you will need in
monetary terms to do your work” (Civicus, n.d.).
Following this general definition of a budget, we see project budgeting as a laid down
plan for allocating resources. It is important to note that resources are scarce and so
must be used judiciously to achieve the desired results. So, no project can proceed
without funds and funds cannot or should not be disbursed without a laid down project
budget.
A project budgeting is also defined “as the total projected costs needed to complete a
project over a defined period of time. It is used to estimate what the costs of the
project will be for every phase of the project. It will include such things as labour
costs, material procurement costs and operating costs” (Bridges, 2019).
The definitions help us to understand that the project budget is usually an estimated
cost of how much it will cost to execute a project. The estimation is done to cover
the different phases of a project.
Arguably, one important aspect of project execution is the source of obtaining the
funds that will be used to execute it. Another important issue is ensuring that the
funds that are allocated to a project are used carefully so as to successfully
complete the project. So, the judicious allocation of funds starts with estimating the
cost of the different phases that are involved in a project to ensure that there is a view
of how much will be involved in completing the project. So, the project budget can
be viewed as a control mechanism that ensures that funds are used judiciously in
achieving the project’s objectives and deliverables.
• Defining the Budget: It is the responsibility of the project manager to define the
budget by estimating the budget required to complete the project. The process
involves the allocation of costs to all project activities and all aspects of the project.
This includes the cost of internal and external human resources, equipment, travel,
materials and supplies. The budget has to be more detailed than it was in the project
proposal and if it is a new budget, should carefully cover all the project activities. In
the event that there was already a contracted budget before the project manager
starts his job, there should be no assumptions. There is a need for that budget can
accommodate the project scope. Where this is not the case, the budget should be
reviewed and updated.
The whole point of controlling and monitoring the project is to ensure that resources
are deployed appropriately. There should be accountability for the project costs. All
expenses must be formally identified, approved and paid for. The roles and
responsibilities of the individuals charged with project control should be clearly
defined.
To locate this process in the library. In the university system, the Bursary
department is charged with the responsibility of controlling and managing the
budget. Normally, calls for budget submissions is made by them from the various
units and departments in the university system. If the university prepares their budget,
it must be approved before it can operate it. The first step in the process is articulating
all the needs and attaching financial implications to them. When the budget is
approved by the Vice-Chancellor, the Bursary will be directed to release funds. The
library management must ensure that the funds are used as stated. Any new additions
or changes must be approved and the budget updated. Without approval, no
additional expenses can be included. Also, as the activities are being carried out, all
receipts on expenditure will be carefully kept and used to retire the released fund.
The Bursary department will then ensure that expenditure is tallied with budget
submission.
1. Pre-planning: This is the first step in project budgeting and it should start with
identifying the tasks, activities, and milestones of the project since the project cost
estimation will be based on it. Having the project tasks, activities and milestones broken
down in such detail can help in detailed cost estimations and allocation of resources in full.
2. Cost estimation: The budgeting process should not end with outlining the tasks,
activities and milestones of the project, rather, they should be assigned estimated
costs. Project activities and resources should be assigned estimated costs to provide an
insight into the expected overall cost of the project.
3. Contingency planning: Projects are prone to contingencies and so provision should
be made for contingencies in the budget. This is necessary to avoid mishaps during
the project execution and helps to cushion any shortcomings in the pre-planning stage.
4. Real-time management: The real-time management of the budget involves real-time
costs and expenses during the project activities. This step is the actual movement of
money into and out of the project. It serves to give project managers an idea about
their pre-planned cost estimates. This is can be seen as the estimate vs the actual step.
5. Variances: As noted earlier, a project budget is not cast in iron. The actual money is
spent during the project execution phase. The variance is any difference between the
amount that was budgeted and the actual outcome. The estimated cost can be affected
by positive or adverse budget variances. These operational variances can arise from a
number of reasons including idle labour hours, and machine inefficiencies among
others.
6. Reconciliation: This is the process involved in checking the differences between budget
estimation and the outcome. Generally, the project cost is determined by computing the
cost of the different aspects of a project at completion. However, reconciliation of costs
cannot be left until the completion of the project. It can take place during the project
and will serve to control spending.
The cost estimation technique is the process that involves estimating all the
costs that are associated with the completion of a project from start to completion
within the scope and timeline. There are a number of forecasting techniques that can
be used in project estimation. They include 1. Bottom-top estimation, 2. Top-down
estimation, 3. Analogous estimation, 4. Parametric estimation, and 5. Three-point
estimation (CFA Journal, 2022).
The top-down approach to budgeting is literarily set in stone as it does not have
enough room for change. The fact that every project experiences an increase in scope
and planned tasks as it progresses, means that with this technique frequent
changes to the plan and revisions of the budget are discouraged. The technique is
best suited for projects that of a recurring nature where the nature and scope of the
project are fully understood.
4. Parametric Estimation:
The drawback however is that it may be difficult to find similar and relevant data
sets; it is time-consuming and only applies where there are similar projects in
existence.
5. Three-Point Estimation:
The three-point estimation technique is used to estimate activity and
duration/time and costs of work items. The strength of this technique is that it
minimises the risk of exceeding the project budget. It also allows the project manager
to deliver within the budgeted estimates. The only drawback is that it is time-
consuming.
Even in construction projects, it is also the project manager that takes that
responsibility. He is the one that the stakeholders go to on any issue concerning
a project. Therefore, project management is the responsibility of a project
manager. This individual seldom participates directly in the activities that
produce the result, but rather strives to maintain the progress, mutual
interaction, and tasks of various parties in such a way that reduces the risk of
overall failure, maximizes benefits and minimizes costs (Wikipedia, 2021).
Therefore, it can safely be said that the success or failure of a project depends
on the project manager. Any project manager that is worth his salt will stake
everything to ensure that the project is successful.
In this section, however, we are considering project managers based on the type of
industry or their job description. Wikipedia (2021) identifies five types of project
managers: (i) architectural project manager, (ii) construction project manager, (iii)
engineering project manager, (iv) insurance claims project manager, and (v) IT
project manager.
i. Architectural Project Manager: This type of project manager manages
projects in the field of architecture. The architectural project manager possesses
many similar skills to a project manager in the construction industry. In fact,
the architectural project manager will often work closely with the construction
project manager. In addition, the architectural project manager coordinates the
work design team and many consultants who contribute to a construction project.
He is also in charge of managing communication with the client. Specifically,
he is responsible for budgeting, scheduling, and quality control.
ii. Construction Project Manager: This project manager works in the construction
industry such a building construction. Often times, the construction project
manager works closely with an architectural project manager.
iv. Insurance Claim Project Manager: Insurance policies are taken by individuals
or organisations to cover losses through fire, flood, or other kinds of disaster.
Therefore, an insurance claims project manager often oversees and manages the
restoration of a client's home/office after a fire, flood, or other disaster, covering
the fields from electronics through to the demolition and construction contractors.
Software is those instructions that enable the user to interact with a computer, its
hardware, or perform tasks. Essentially, most computers will be useless without
software. Therefore, the development of software is an important project in the IT
industry. The project manager in an IT industry plays a vital role. A software project
manager has many of the same skills as their counterparts in other industries.
Beyond the skills normally associated with traditional project management in
industries such as construction and manufacturing, a software project manager will
typically have an extensive background in software development. Many
software project managers hold a degree in computer science, information
technology, management of information systems, or another related field.
The foregoing discussions, undoubtedly, have helped you to understand the unique
role and responsibilities of a project manager. The fact that a project manager is
entrusted with the responsibility of running a project from initiation to closing phases
reinforces the point that it is not a job to be given to one who is not well grounded.
As mentioned severally, the success or failure of a project largely depends on the
project manager. Therefore, care must be exercised to ensure that the one
commissioned to manage a project is capable of meeting expectations.
The success of a project may be made more likely in having a qualified project
manager. Egeland (2010) contends that careful thought should be given to selecting
the right person for a project because even the qualities of this particular
individual can have a direct impact on the outcome of the engagement. Reinforcing
his position, Egeland (2016) further notes that the sole criteria for selecting a
project manager should not be based on qualification because many qualified
people can do the mechanics of project management, but not everyone is a project
leader. The technically competent person is not necessarily a competent project
leader. A person may have the best logical and analytical mind in the group and yet
lack the qualities that lead a project to a successful conclusion. Because the project
manager must interact with many people (such as sponsors, senior management,
client, and team members), it is important that that person have good “people skills.
Indeed Editorial Team (2021) also posit that irrespective of the industry a project
manager works in, it is imperative that he possesses some soft or peoples skills
in addition to having technical skills as these skills can boost his success. not
exhaustive, Indeed Editorial Team (2021) has also outlined these eight key qualities
to include: 1. Leadership skills, 2. Communication skills, 3. Problem-solving skills,
4. Delegation skills, 5. Enthusiasm, 6. Team-building skills, 7. Integrity and 8.
Competences.
1. Leadership Skills: Strong leadership is an important skill that a project manager
should possess if he is to be successful on the job. The project manager is tasked
with the responsibility of overseeing the project from start to finish. To achieve
this responsibility, he will require team from start to finish. Being a good leader
means that the project manager should be able to motivate his team to perform at
their best throughout the project and ensure all team members have a clear
understanding of what is expected of them. He should also be able to assess his team’s
strengths and weaknesses and decide how to best utilize them throughout the project
completion process.
4. Delegation skills: A lot of activities and sub-teams are involved in any project.
Even the best of project managers will need other people to help him oversee some
aspects of the project since he cannot be everywhere at the same time. Being able
to assign and oversee tasks is a fundamental component of successful project
management. A project manager should have the ability to access the skills of his
team and sign tasks based on these skills. Effective delegation also requires him to
trust his team members to fulfill their duties and allows him to avoid micromanaging
them. Delegation has the advantage of equipping other people with supervisory skills.
7. Integrity: The project manager should have enough integrity to commit to the
finishing of a project. Integrity, sometimes also referred to as loyalty or honesty, is
an important quality for a project manager to have. Integrity can help him set a good
example for his team and make them more likely to follow that example. It also
shows his team that they are committed to the project and are willing to see it through
to the end at all costs. Integrity additionally fosters trust from his team and promotes
an ethical and responsible work environment.
Project managers are charged with certain responsibilities, and in line with the type
of project one is involved in. However, the specific tasks that consume a project
manager’s time will vary substantially depending on which phases of the life cycle
their projects are in. What this means is that the responsibilities will vary as they get
into one stage or phase of the project or another. However, there are a number of
general tasks that any good project manager can expect to perform on a daily basis.
The mark of a good project manager is in how efficient and effective he is in
carrying out his responsibilities because the success or failure of a project will to a
large extent depend on him.
Miller (2019) cautions that one should not see the project life cycles listed above
as steps as such because these are processes that project managers continually
return to throughout the duration or life of a project. However, they form the basis
on which the role of a project manager can be discussed. The processes are
discussed more closely below.
1. Initiating: Every project is new and unique and project managers start each
new project by defining what the main objectives of the project are. He is also the
one to define the purpose and scope of the project. Because every project has
stakeholders, the project manager identifies key internal and external stakeholders,
discuss shared expectations, and gain the required authorization necessary to move
the project forward (Miller, 2019). These are things that need to be done to ensure
that everyone is on the same page. Miller (2019) has gone on to identify important
questions that project managers ask during the initiating phase. This includes:
e. Who are the stakeholders on this project? Who is impacted by, or who impacts,
this project?
j. Has this project been executed before? If so, what was the result? What
information from that past project should be considered in this project?
5. Closing: The closing stage is the end of the project. During this phase, the project
manager strives to ensure that all activities necessary to achieve the final
result are completed. During the close of a project, project managers will:
a. Work with the client to get formal sign-off that the project is complete. This is
because it is only the client that can certify the project completed because the
client is the one who assigns the project.
b. Release any resources (budget or personnel) who are no longer needed for the
project
d. Archive project files for future reference and use when there is a need for it.
After the project has been completed, all the stakeholders will meet for a post-
implementation review which is often used to identify key lessons learned.
Understanding what went well, what could be done differently, and what to
stop doing can help inform and improve project management practices moving
forward.
Furthermore, there are specific demands that are made on the project manager
on a daily basis. As mentioned earlier, while the demands that are made on the
project manager may vary according to the type of project or the phase that a
project is in, there are some general demands that are expected for the project
manager to meet. Miller (2019) outlines and explains these responsibilities as
they relate to communicating (with team members and stakeholders), issue
identification and resolution;
4. Budgeting: Project managers work with money and it is important that proper
budgeting is done so that every aspect of the project is covered. However, the scale
of the budgeting that he does would normally be dependent on the size of the project.
For small-scale projects, cost estimation may be a weekly or even a monthly task.
But for larger projects with many different expenses to keep in mind, project
managers may spend time reviewing budgets each day to ensure the project does
not exceed resource allocations. This may also include reviewing, processing, and
approving invoices from outside vendors if the project includes such partnerships.
Indeed, the organisation structure that any organisation adopts or selects will largely
influence how projects are carried out in it. It is therefore important that one
understands the organization structure in place as well as the culture within which the
project manager is working. In a nutshell, the project organisation structure facilitates
the coordination and implementation of project activities. The major aim is to ensure
that the environment of work is such that fosters interactions among the team
members thereby reducing to the minimum, incidences of disruptions, overlaps and
conflicts. Given that “each project has its unique characteristics, the design of an
organisational structure should consider the organisational environment, the project
characteristics in which it will operate, and the level of authority the project
manager is given” (PM4DEV, 2016). PM4Dev further observes that creating the
structure is not the issue because it is only a part of organizing the project. There are
three major types of project organization: functional organisation structure, pure
project structure, and matrix structure. In terms of organisation of project teams and
their leadership structures, the differences lie in who the project leader is, who has
certain responsibilities and who makes the decisions (Odedayo, 2021).
Training
Coordinator
Accounts/Administrator
Provincial Provincial
Coordinato Coordinator
It is relevant to note that all firms start small usually with a few human and material
resources. At the initial stages of their operations, they can manage to function
without a sophisticated structure. However, as they become successful, and
begin to grow and add more resources and people along the way, the pressure
arises for them to develop an organisational structure according to their need.
This is important because if the organisation is left as it were without a defined
structure, the system in place will no longer be capable of supporting the
business and activities that take place, and the inevitable result is that the work
will be affected negatively. To ensure that this does not happen, organisations adopt
one form of structure or another. So then, what is organisational structure?
IPL.org (2021) defines organisational structure as “how activities such as
task allocation, coordination, and supervision are directed toward the achievement
of organisational aims.” In essence, organisational structures are created to ensure
that activities or the work factors are divided, organized and coordinated. This
includes also the performance of members of work teams
There are three major types of organisational structures including the functional
organisation structure. The type of structure that an organisation chooses or adopts
will be dependent on a number of factors that are peculiar to it. Where there are
projects in the organisation, they are most likely to be carried out based on the
organisation structure that is in place.
Each unit is managed by a functional manager who reports to the strategic direction
of the organisation. In a large organisation, the heads of the individual functional units
may have other operational managers working under them and that report directly
to them. The larger the organisation the more functional units you have. Each of
the unit functions independently and has its own vertical management structure.
Note that it is not mandatory that all units of an organisation are present in a project.
The employees will in fact be assigned only on the basis of the requirements
of the given project. For some projects, for example, no member from a particular
department may be needed while more specialists of another department may be
required.
University
Librarian
Project
Manager
Fig. 7: Functional Project Structure (Adapted from Cristobal and Diaz, 2018)
Although functional organisation structure has its advantages, there are also some
disadvantages that are associated with it. Twproject (2021) has articulated some
of these advantages to include:
Monotony/Boredom: Given the repetitive nature of the job done in a
functional organisation structure, the likelihood of boredom exists as
employees may find it boring to repeat the same task over and over, and
become less enthusiastic over time. If promotions are not handled well, an employee
may be discouraged if a lower-performing peer is promoted over them. Problems
may arise among management if department heads are only focused on their
department and do not communicate effectively with other departments. This can
cause poor communication and "silos" that are too independent of one another.
If employees and management are only loyal to their teams, there will be a lack of
teamwork and coordination.
Rigidity: It is a rigid structure where changes, innovations, and flexibility can be
difficult to implement. An employee in any department may lack knowledge of
information about all other departments. Managers tend to make decisions without
consulting the department first, which can lead to problems. A department can
become too autocratic and put its goals above those of the organisation as a whole.
With so many specialists involved in a process, it is difficult to pin the blame for
a specific product or service malfunction on any individual.
Lack of Ownership: The motivation of the people assigned to the project may be
weak. The project can be seen as additional work not directly related to one’s
professional development. Moreover, since project members only work on one
part of the project, they do not identify with the project as a whole. Lack of ownership
thus discourages team members who may not engage enough in project-related
activities. The result, even in this case, will be a problem of quality of the results.
Lack of Attention: Each functional unit has its own basic work to do. Because of
this project responsibilities are set aside to meet these primary obligations. This
becomes even more difficult when the project has different priorities for different
units. For example, the marketing department can consider one project urgent while
other departments consider it only of secondary importance – if not a real waste of
time. This can lead to delays and quality problems.
Here are the important facts regarding the role of the project manager within a
functional organisational structure as outlined by Twproject (2021).
• Power and authority are in the hands of the functional manager, not in those of
the project manager.
• The functional manager has the authority to release the resources based on their
knowledge and their competence – the project manager is therefore always
dependent and pending on the decision of the different functional managers.
• The resource goes back to the functional manager after completing the project
– and in any case it is never “completely” separated.
• The resources that work in this type of organisation are always under the
authority of the functional manager, in any situation.
• The project manager generally has much less power in this type of
organisation.
• Project manager skills are much less used in this type of organisation.
• The resources for the project must be negotiated with the functional managers
and the accessibility of these resources will be based on the business
conditions.
• Since the “project manager” has low or no authority, the project can last longer
compared to other organisational structures. Generally, there is no recognized
project management methodology or best practices used.
• The project manager practically assists the functional manager.
• The project manager spends a lot of time doing administrative tasks and often
works as a PM only part-time.
Human
Project “A”
Pr
R& D
M
arketing
oduction
Res.
nance
Fi
Manager
Project “B”
Production
Marketing
Manager
General Manager
Program Program
manager
Human Res.
Res. & Dev.
Finance
Fig. 7 Pure Project Organisation Structure (Source: Bobera, 2008)
The diagram of a pure project organisation structure clearly shows that the
project manager is independent. In this organisation structure, more than one
project can go on if the duration is long. The project manager has control over
the team members and reports directly to program manager where the project is
part of a larger program. Where there is no program manager, he reports
directly to the general manager. This is clearly different from what happens
under functional organisation structure.
• Insecurity of Jobs: Since the focus is on the project, there usually is not a
permanent job position for team members who are usually assembled for
the purpose of the project. They are not necessarily employees of the
organisation. Consequentially, when the project comes to an end there is the
fear of loss of jobs as some may be redundant as they await another
opportunity. In essence, disengagement is a part of the issue with pure project
organization structure.
• Costly: In most cases, the project team are not members of the project
organisation but are rather hired for the sake of the project. Some equipment
may also have been hired. Therefore, if the project is not delivered within
the time frame, it affects the budget.
In a pure project organisation, the project manager has all the power and
authority and everybody working directly in the project team reports to the
project manager. In essence, in a pure project organisation, it is either that there
is no functional manager in existence, or if he exists, he will have a very
limited role. The implication is that in a pure project type of organisation
project managers have a high level of authority to manage and control the project
resources. The project manager in this structure has total authority over the
project and can acquire resources needed to accomplish project objectives from
within or outside the parent organisation, subject only to the scope, quality,
and budget constraints identified in the project. In the project-based structure,
personnel are specifically assigned to the project and report directly to the
project manager. The project manager is responsible for the performance
appraisal and career progression of all project team members while on the
project. This leads to increased project loyalty. Complete line authority over
project efforts affords the project manager strong project controls and centralized
lines of communication. This leads to rapid reaction/response time and
improved responsiveness. Moreover, project personnel are retained on an
exclusive rather than shared or part-time basis which is not the case in
functional projects where project members are mostly members of the
organisation. As a result, project teams develop a strong sense of project
identification and ownership, with deep loyalty efforts to the project and a good
understanding of the nature of project’s activities, mission, or goals (GEC 524,
n.d.).
2.3 Matrix Organisation
A matrix organisation structure is one in which the reporting relationships are set in
a grid form. What this entails is that the traditional hierarchy which is top down is
totally done away with in the chain of command. Instead of having a worker(s) report
directly to one supervisor or manager, he reports to two. This is because in matrix
organisations, there is both a functional as well as a product manager that see to
the daily productivity. As a result, workers report to the two unlike what you have in
functional organisation structure. According to Business Talk (2012), the matrix
project attempts to blend properties of functional and pure project structure.
Wikipedia, (2021) notes that under a matrix organisation structure, team of
employees are frequently used to accomplish work. The objective is to take advantage
of the strengths, as well as make up for the weaknesses, of functional and
decentralized (pure project) forms. In their illustration of how this works, Wikipedia
(2021) explains that “an example would be a company that produces two products,
"product A" and "product B". Using the matrix structure, this company would
organize functions within the company as follows: "product A" sales department,
"product A" customer service department, "product A" accounting, "product B" sales
department, "product B" customer service department, "product B" accounting
department. In essence, the matrix structure is an attempt to balance between the two
extremes that functional and pure project structures present. Referring to the o matrix
as rows and functional as columns, Business Talk (2018) further says that if the
choice of structure is a matrix, different projects (rows of matrix) borrow resources
from functional areas (columns). Given the nature of this structure, the decision
regarding the type of matrix to use in executing a project (weak, balanced, or strong)
rests with senior management.
staff
Staff
Staff
Project
manager A
Staff
Staff
Staff
Project
Manager C Staff Staff Staff
Fig. 8: Pure Project Organisation: Adopted from GEC 524 & Nagarajan, 2012
The diagram above depicts a matrix organization structure. There are three
project managers (A, B & C) who are in charge of three different projects. The
project managers report to the General manager and to that extent are
independent and have authority over the projects. There are also four functional
managers who report to the General Manager.
• Common Structure: The matrix structure requires that everyone uses the
same project management lifecycle and methodology. As a result, moving
between projects is easy. People can join a project team with relative ease when
the terminology and processes are common.
• Overload: The matrix has a common structure and this is a disadvantage in the
sense that it also presents with work overload for team members who are also
be part of a functional unit and to that extent are have their regular jobs to carry
out. The work overload is compounded by the fact that the systems that should
manage and monitor the overload is not in place. As a result, team members are
prone to burnout. They may also neglect their tasks or not complete it. This can
in turn affect both the quality of the work or the completion schedule.
• Conflict: There is more than one project at a time, project teams or individuals
will likely fight over the same resources as another project. There can be some
conflict between business-as-usual tasks and project work for individuals,
especially when both managers are giving them different priorities. Moreover,
the structure gives the project manager an edge over the functional manager.
This could lead to conflicts and power struggle between the project department
and functional department as each tries to assert their authority. Therefore,
there is likelihood of frequent conflicts and conflict resolution processes.
• Role Ambiguity: Since there is more than one manager, there are more
chances of role ambiguity among managers and employees. This can result in
more discussions than actions (Nagarajan, 2012).
One of the responsibilities of a project manager is to find the resources that are
suited to the project he is executing and to also allocate them properly. Where
the resources do not match the project, there is bound to be project failure. This
is referred to as poor resource project planning and allocation. When the
resources are not planned and allocated properly there could be shortage of
resources that could lead to project delays or even abandonment.
3.1.1 Types of Resources in Project Management
There are different types of resources in project management. Some attempts
have been Resources that are used in project management into people,
equipment, materials, facilities and costs. These have been categorised into
three main areas: work, materials and costs (Microsoft Project, 2010).
Work Resources: The work resources are the people that are part of a project,
also called the project team. This category of resources is highly important
because the project largely depends on people to make things happen. While
material resources are important, they cannot do any work by themselves. This
drives home the point that the quality of human beings in a project team will
determine the success or failure of the project. This makes it imperative for the
project manager to intentionally recruit the best possible team.
The work of the project manager does not end with recruiting the work resources.
It is also his responsibility to manage them to get the most benefit from them.
Part of what the project manager should look out for as he gathers his work
team is the skills that are possessed by each person. Nobody can perform beyond
their skills level.
However, to get the best out of his work team, the project manager must ensure
that he pays attention to the welfare needs of his team.
Material Resources: Material resources are tools and assets that are required
to get the work going. The work resources or project team needs tools and
assets to execute the tasks that are assigned to them.
In cases where the company does not have some of the needed equipment, the
project manager should hire them or outsource the tasks to external teams.
Costs Resources: Regardless of the size or type of project, money will be needed
to execute it efficiently. The project manager also needs money to procure vital
tools and equipment and also pay the salaries of team members. Inadequacy of
funds will definitely make project execution difficult.
However, it is not just enough that money is provided. It is imperative that the
project manager how to budget and allocate money properly. Without this skill,
no amount of money will be sufficient. Financial accountability is also required
from the project manager as the project sponsors want be assured of efficient
deployment of their money.
3.1.2 Project Resources Allocation
The need for assigning and scheduling available resources in the most and effective
and economical way possible stems from the fact that resources are not
inexhaustible. Projects need resources from the initiation phase to the closing
phase. The onus is on the project manager to know the right time and allocation of
the resources within the project schedule. The resources are expected to be
planned and scheduled proper.
We should remember that projects consist of tasks and activities. These tasks and
activities must be completed before the expected deliverables can come. Delay in
completing any of the tasks will most likely result in a delay in meeting
deadlines. Most project delays are caused by either insufficient or inappropriate
allocation of resources.
The importance of resource allocation therefore lies in the fact that with proper
resource allocation, there is less delays and more favourable outcomes. It also means
getting the best result and paying lower costs. This cuts across all types of resources:
work, material and cost.
Reduction of Incidences of Conflicts: Although conflicts cannot be ruled out
completely from project management, negative conflict is not the desire of any
project manager. Unmanaged or improperly managed conflicts can affect the project
schedule and to that extent is costly. One of the ways to prevent conflicts on
the project site is to ensure that workers are paid salaries are paid promptly and that
their welfare is taken seriously. Proper planning and allocation ensure that there are
no delays in salaries and so no delay in project completion.
Prompt Procurement/Replacement of Tools and Equipment: Proper allocation
of resource makes it possible for the project material to procure and/replace broken-
down tools and equipment promptly. Invariably, there will be no delays in the work
process. This in turn significantly reduces team burn outs and improve retention.
Ease of Accountability: Although the project manager is responsible for the
resources, he is expected to allocate the resources properly. Proper allocation means
that all financial expenditure and use of other resources are properly documented and
accounted for. Lack of accountability results in mistrust of the project manager and
could make the stakeholders lose faith in him. Practice of proper resource allocation
enables the project manager to keep correct accounting.
Lower Overhead Costs: Proper resource allocation encourages efficient
resource allocation which in the long run discourages wastage and saves resources
for the organisation. For instance, it goes a long way in making it possible to choose
the best available assets and use them for multiple projects, and manage them
throughout the work and by so doing, avoid under utilisation or overutilisation of
employees.
Project resource management includes the processes to identify, acquire, and manage
the resources needed for the successful completion of the project (Course Hero, n.d.).
This definition includes the gamut of processes that include identification, acquisition,
and management of resources. In other words, management is not limited to the
ensuring that the resources are utilized in the best way possible.
Since it is possible for changes to occur in the budget, the project manager must
ensure that he receives approval for such changes and then go ahead to re- baseline
the project baseline. Re-baseline here implies that the original baseline has been
changed as a result of the later changes made in the original project budget.
Be that as it may, the project manager should avoid frequent and unexpected budget
change that results in significantly running over the budget. Although there is
provision for contingency in the project budget to handle variance, too
much of it is detrimental and care must be taken to avoid it where necessary.
During this phase, it is important that the project manager understand how to do
resource planning, resource scheduling and resource allocation.
Resource Planning is the stage where all the project is broken down into tasks and
estimated resources that would be used to complete each task. This is done as soon
as the project scope is determined. Changes that may occur in the future are also
factored into the project plan.
Resource Allocation: This is the actual process of assigning and managing the
project assets of resources in such a way that it supports the strategic goals of the
organisation. Part of resource allocation is managing tangible assets such as
equipment and human capital in such a west that the best use can be made of them.
• Resource Histogram: This is also a chart but unlike the hierarchical RBS
chart, this is a bar chart and is used for resource allocation. The resource
histogram is essentially a planning graph that shows the amount of time that
a resource is scheduled to work over a period of time. With this graph, it is
possible to determine when a resource is available at any time during the
project resource management life cycle.
3.2.4 Constraints to Resource Management
1. Resource constraints can be described as any limitation or barrier or risk that is
associated with project resource allocation. It is important that they are identified
because they act as roadblocks that can derail and prevent or delay the
successful Time Constraint: As we have already determined, a project is a
temporary endeavor with a definite start and end time. In essence, project
managers work with a timeline within which they are to produce the project
deliverables. Therefore, the time constraint has to do with the project’s
schedule for completion. This also includes the deadlines for each phase of the
project, and the date of the final project delivery.
It is the wish of every project manager to work within the time constraint as
any delay will tamper with the phases and of course date of completion of the
project.
To mitigate against time constraint, the project manager should ensure proper
planning, scheduling and monitoring.
• Provide clear documentation of the full project scope at the beginning of the
project, including all requirements.
• Set up a process for managing any changes, so if someone proposes a change,
there is a controlled system in place for how that change will be reviewed,
approved or rejected, and implemented if applicable, and
• Communicate the scope clearly and frequently with stakeholders
3. Cost Constraint: The cost of the project also known as the project’s budget
encompasses all of the financial resources that are needed for the timely
completion of the project in line with its predetermined scope. The cost here
includes the costs for labor, vendors, quality control and other factors. well.
Insufficient budget constitutes project cost constraint. It also has its multiplier
effect including delay in providing deliverables.
Depending on the type and size of the project, budget estimation techniques such
as parametric estimation, bottom-top estimation etc. can be used to check against
this in the planning phase.
In project management, there are three major constraints: time, scope and cost.
3.2.5 Guide for Project Resource Management
To ensure that resource allocation is done properly, there is a need to consider some
tips that can guide one through the process. While there is no authoritative
guide on how to go about it, some authors have identified some guides that can help
to make the process more effective and efficient.
Landau (2022) has outlined a number of guiding principles along this line.
1. Knowledge of Project Scope: Before the project manager, he should be clear
on the scope of the project including size and duration of the project. As soon
as this is determined, he needs to decide on the resources he would be needing,
including how many of those resources that will be necessary to complete the
project. With a good knowledge of the project scope, it will be easier to
determine how to allocate resources to take care of everything.
2. Identify the Project Resources: With knowledge of the scope as well as the
project objective and the tasks, approval received, the next thing to do is to
identify the resources that are available including the equipment that may be
purchased or hired. Again, it is important to ensure that the available resources
will serve throughout the timeline.
3. Avoid Procrastination: The project manager should go to work to plan his
resource allocation. Waiting for the perfect time to carry out this responsibility
is not advisable. Granted that resources needs may change, it is better to go ahead
and plan and then as time goes on, changes can be made. Setting up a resource
plan enables him to detect potential red-flags and responding to them beforehand
before the arise.
4. Holistic Thinking: All aspects of the project including the time schedules for
the project team should be planned for. What time is for holidays and what
happens in the event of illness among the project team. Also, if some
equipment or site has been leased, how long will that last? In essence, the project
manager should pay attention to detail.
5. Knowledge of Resource Dependencies: Oftentimes, there are several projects
running at the same time, it will be wrong to over depend on one project team
for the accomplishment of all the major project work across the projects,
especially if it is an external team as it could result in work overload blocks and
resource shortages. areas.
6. Track Time: Time is critical in project management so, ensure that you are
closely watching the job performance of you team to ensure efficiency. This is
important to avoid job delays or procrastination.
You can improve time tracking by keeping track of the team’s workload using
the right tools that makes real-time data collection on one page where one can
see and schedule ahead of time.
7. Invest in/Use Productivity Tools: There are available online project
management software that are great at managing resources more productively.
Online tools can also get project data instantly updated. These will enable you
see where the resources are allocated. With such tools, it is possible to know
what the current situation is with the team members.
8. Avoid Over-Allocation: Over-allocation of resources is not helpful and can
result in team burnout. Project team members should not be stretched to their
breaking point. The key for getting result is to allocate resources evenly.
9. Realistic Approach: Do not favour one aspect of the project over another by
allocating more resources to it. For instance, in the project estimate, do not
allocate more resources by adding more people or days to the schedule. This will
be detrimental in the long run.
10. Create a Routine: The project manager plans before executing and
monitoring, expectedly. However, even with the best of resource allocation,
something could go wrong and if not caught on time could mar the process.
Therefore, it is not wise to leave monitoring/checks for later. It is important to
build in regular monitoring into the plan. Ideally, this should be set up to
happen on a particular day and time every week. The project manager should
go through the resources, check the project management tools and ensure that
no one is over-tasked for the coming week.
Also, have regular conversations with your team and update them on the
progress of the progress while also getting their feedback on any issues of
concern. Setting up a routine check-in and keeping updated with the project
management software will help you to have a good idea of your resources
spread.