1. INTRODUCTION
2. SCOPE OF WORK
DETECTION SYSTEM
Dismantling and removing existing defective smoke detectors, cables, conduits, and
all associated components at Building C and Building B.
Supply, Installation and Programming of fire alarm panel with Smoke detectors,
Heat detectors, Manual Call Points, Sounders, Strobes, and Interface modules. Brand:
Context plus, Addressable, made in UK.
Connecting the Existing Conventional Panels and Detectors to the Main Panel
through Monitor Modules.
Cabling and conduit works, fire rated, LPCB, Polychromate conduit and GI conduit
where ever required mechanical impacted area.
System testing and commissioning of the entire system before handing over.
PROTECTION SYSTEM
Removing existing Hydrant GI Pipeline laid along the new building from the pump
room to Building A.
Clean and Install GI Pipeline from new building to ABC 3 warehouses completed
with oil primer and painting.
Supply and Installation of heavy-duty ERW hot-dipped GI Pipes with necessary
accessories completed with Oil primer and Painting.
Supply and Installation of Two Way Pillar Hydrant and necessary accessories.
Supply and installation of fire hose and fire hose reels complete with required with
necessary accessories.
Supply and installation of outdoor type wall-mounted firehose and fire hose reel
cabinets complete with pull handle, door frame and accessories.
System testing and commissioning after pressurizing the whole system before
handing over.
4. REFERENCES
Approved drawings: initial drawings approval will get from Colombo fire
department before start installation.
Follow Manufacturer’s installation manuals for installations
Follow Local authority regulations for installations.
BS 5839 / NFPA 72 standards (or applicable local codes)
Apply Health and Safety Regulations while installation process.
7. WORK PROCEDURE
7.1 SITE PREPARATION
Ensure site is ready with clear access before commencing the installation. (Done
from the Baurs’ end)
Ensure the access to the stores and office areas one day prior to the installation
process. (Done from the Baurs’ end)
Verify approved drawings and materials.
Conduct toolbox talk for the workforce.
Detection System
Protection System
Detection System
Protection System
PPE (Helmet, Gloves, Safety Shoes and Eye Protection) will be worn.
No hot work will be done without a permit.
Ladder safety procedures will be followed.
Proper cable management to avoid trip hazards.
Fire extinguishers at the workplace to maintain fire safety.
9. QUALITY ASSURANCE
10.TOOLS CALIBRATION
Multimeter
Insulation Tester
Sound Level Meter
Portable Hydraulic Pump Tool
11.WASTE MANAGEMENT