0% found this document useful (0 votes)
4 views4 pages

Method Statement for Fire Detection & Protection System -BAURS-GP

This document outlines the method statement for the installation of a fire detection and protection system at A Baur & Co. in Colombo. It details the scope of work, including dismantling existing systems, installation of new components, and testing procedures, along with responsibilities, health and safety measures, and quality assurance protocols. The document also specifies the materials and tools required for the project and emphasizes compliance with local regulations and standards.

Uploaded by

kmas1612
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4 views4 pages

Method Statement for Fire Detection & Protection System -BAURS-GP

This document outlines the method statement for the installation of a fire detection and protection system at A Baur & Co. in Colombo. It details the scope of work, including dismantling existing systems, installation of new components, and testing procedures, along with responsibilities, health and safety measures, and quality assurance protocols. The document also specifies the materials and tools required for the project and emphasizes compliance with local regulations and standards.

Uploaded by

kmas1612
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 4

METHOD STATEMENT FOR FIRE DETECTION SYSTEM INSTALLATION

1. INTRODUCTION

 Project Name : A Baur & Co. (PVT) Ltd.


 Location : 62, Jethawana Rd, Colombo 01400
 Scope of Work : Fire Detection & Protection System Installation
 Purpose : Outline the technical details and working procedure for the
fire detection and protection system.

2. SCOPE OF WORK

DETECTION SYSTEM

 Dismantling and removing existing defective smoke detectors, cables, conduits, and
all associated components at Building C and Building B.
 Supply, Installation and Programming of fire alarm panel with Smoke detectors,
Heat detectors, Manual Call Points, Sounders, Strobes, and Interface modules. Brand:
Context plus, Addressable, made in UK.
 Connecting the Existing Conventional Panels and Detectors to the Main Panel
through Monitor Modules.
 Cabling and conduit works, fire rated, LPCB, Polychromate conduit and GI conduit
where ever required mechanical impacted area.
 System testing and commissioning of the entire system before handing over.

PROTECTION SYSTEM

 Removing existing Hydrant GI Pipeline laid along the new building from the pump
room to Building A.
 Clean and Install GI Pipeline from new building to ABC 3 warehouses completed
with oil primer and painting.
 Supply and Installation of heavy-duty ERW hot-dipped GI Pipes with necessary
accessories completed with Oil primer and Painting.
 Supply and Installation of Two Way Pillar Hydrant and necessary accessories.
 Supply and installation of fire hose and fire hose reels complete with required with
necessary accessories.
 Supply and installation of outdoor type wall-mounted firehose and fire hose reel
cabinets complete with pull handle, door frame and accessories.
 System testing and commissioning after pressurizing the whole system before
handing over.

3. STOCK AVAILABILITY OF THE ITEMS


SI DESCRIPTION | CODE BRAND /MAKE /CERTIFICATION STOCK
DETECTION SYSTEM
Main Fire Panel, 4 loop, Addressable Availabl
1 Context Plus, Made in UK, LPCB, EN54
Z045040NS/X/CON e
Context Plus, Made in UK, UL listed, Availabl
2 Smoke Detector 55000-685IMC
EN54 e
Context Plus, Made in UK, UL listed, Availabl
3 Heat Detector 58000-450IMC
EN54 e
Multi Detector (Smoke +Heat Combination) 58000- Context Plus, Made in UK, UL listed, Availabl
4
750IMC EN54 e
High Heat Detector
Availabl
5 Sounder CON430A/CX/DR Context Plus, Made in UK, LPCB, EN54
e
Sounder Beacon CON433A/CX/DR & Availabl
6 Context Plus, Made in UK, LPCB, EN54
CON456A/CX/W e
Availabl
7 Detector Base Sounder 45681-702IMC Context Plus, Made in UK, LPCB, EN54
e
Availabl
8 Manual Call point, Resettable SA5900-908IMC Context Plus, Made in UK, LPCB, EN54
e
Availabl
9 Monitor module 55000-845IMC Context Plus, Made in UK, LPCB, EN54
e
Availabl
10 Control module 55000-852IMC Context Plus, Made in UK, LPCB, EN54
e
Context Plus, Made in UK, UL listed, Availabl
11 Detector Base 45681-210IMU
EN54 e
Availabl
12 1.5sqmm two core fire rated wire LLT, made in China, LPCB
e

4. REFERENCES

 Approved drawings: initial drawings approval will get from Colombo fire
department before start installation.
 Follow Manufacturer’s installation manuals for installations
 Follow Local authority regulations for installations.
 BS 5839 / NFPA 72 standards (or applicable local codes)
 Apply Health and Safety Regulations while installation process.

5. MATERIALS & TOOLS REQUIRED

 Fire Alarm Control Panel (FACP)


 Detectors (Smoke, Heat, Multi-sensor)
 Manual Call Points
 Alarm Sounders/Strobes
 Cables (Fire-rated)
 Conduits /Trunking /Casing
 Power tools, testing equipment, and hand tools
6. RESPONSIBILITIES

 Project Manager: Overall supervision


 Site Engineer: Installation supervision
 Electricians: Installation and wiring
 QA/QC Inspector: Quality checks
 HSE Officer: Safety compliance

7. WORK PROCEDURE
7.1 SITE PREPARATION

 Ensure site is ready with clear access before commencing the installation. (Done
from the Baurs’ end)
 Ensure the access to the stores and office areas one day prior to the installation
process. (Done from the Baurs’ end)
 Verify approved drawings and materials.
 Conduct toolbox talk for the workforce.

7.2 INSTALLATION PROCESS

Detection System

 Mark the detector locations as per approved layout.


 Install conduits, casing or trunking as per approved layout.
 Pull and laying fire-resistant cables as per standards.
 Removing of cables and detectors where detectors are defective.
 Installation of detectors, manual call points, and sounders as per design.
 Programming the fire alarm control panel with Detectors, Manual Call Points,
Sounders and Modules.
 Connect the devices to the fire alarm control panel.
 Perform cable insulation and continuity tests.

Protection System

 Mark the Hydrant line locations as per approved layout.


 Install GI Pipes and accessories where necessary.
 Cut and removing the existing GI Pipes as per standards.
 Installation of Pillar Hydrants, Fire Hose and Fire Hose Reels as per design.
 Connect the Gi Pipeline to the existing pump line.

7.3 TESTING & COMMISSIONING

Detection System

 Power up the entire system.


 Perform point-to-point testing.
 Check for detector activation, sounders activation, and fault signals.
 Simulate fire conditions and verify alarm response.
 Obtain client approval.

Protection System

 Pressurize the entire system.


 Perform water leak testing.
 Check for pressure drop after pressurization.
 Obtain client approval.

8. HEALTH & SAFETY MEASURES

 PPE (Helmet, Gloves, Safety Shoes and Eye Protection) will be worn.
 No hot work will be done without a permit.
 Ladder safety procedures will be followed.
 Proper cable management to avoid trip hazards.
 Fire extinguishers at the workplace to maintain fire safety.

9. QUALITY ASSURANCE

 Follow installation manuals


 Test 100% of devices for their functionality.
 Inspection request before closing any ceiling works.

10.TOOLS CALIBRATION

 Multimeter
 Insulation Tester
 Sound Level Meter
 Portable Hydraulic Pump Tool

11.WASTE MANAGEMENT

 Proper disposal of packing materials


 Ensure cables and conduit cuttings are cleared daily
 Ensure Pipeline cutting particles are cleared daily