TariffOrder 2025annexure 9
TariffOrder 2025annexure 9
ANNEXURE - 9
ELECTRICITY TARIFF-2026
GENERAL TERMS AND CONDITIONS OF TARIFF:
(APPLICABLE TO BOTH HT AND LT)
2. The tariffs are applicable to only single point of supply unless otherwise
approved by the Licensee.
3. The Licensee does not bind himself to energize any installation, unless the
Consumer guarantees the payment of minimum charges. The minimum
charges are the power supply charges, in accordance with the tariff in force
from time to time. This shall be payable by the Consumer until the power supply
agreement is terminated, irrespective of the installation being in service or
under disconnection.
4. The tariffs in the schedule are applicable to supply of power within the area of
operation of the licensee.
5. The tariffs are subject to levy of Tax and Surcharges thereon as may be decided
by the State Government, from time to time.
6. For the purpose of these tariffs, the following conversion factor would be used:
1 HP=0.746 KW. 1HP=0.878 KVA.
7. The bill amount will be rounded off to the nearest Rupee, i.e., the bill amount
of 50 Paise and above will be rounded off to the next higher Rupee and the
amount less than 50 Paise will be ignored.
9. LT power supply can be given where the requisitioned load is less than 150 kw
/ 201 HP. The applicant is however at liberty to avail HT supply for lesser loads.
ANNEXURE – 9 Page 523
Karnataka Electricity Regulatory Commission Tariff Order 2025 All ESCOMs
10. The Consumer shall not resell electricity purchased from the Licensee to a third
party except:
(a) Where the Consumer holds a sanction or a tariff provision for distribution
and sale of energy.
(b) Under special contract permitting the Consumer for resale of energy in
accordance with the provisions of the contract.
11. Non-receipt of the bill by the Consumer is not a valid reason for non-payment
of bills. If the bill is not received within 7 days from the meter reading date, the
Consumer shall notify the licensees’ office, which issues the bill. Otherwise, it will
be deemed that the bills have reached the Consumer in due time.
12. The Licensee will levy the following charges for non-realization of each Cheque.
13. In respect of power supply charges paid by the Consumer through money
order, Cheque /DD sent by post, receipt will be drawn and the Consumer has
to collect the same.
14. In case of any belated payment, simple interest at the rate of 1% per month
will be levied on the actual No. of days of delay subject to a minimum of Re.1
for LT installation and Rs.100 for HT installation. No interest is however levied for
arrears of Rs.10 and less.
16. All payments made by the Consumer will be adjusted in the following order of
priority: -
Penalty and other clauses shall apply if the sanctioned load is exceeded.
18. The bill amount shall be paid within 15 days from the date of presentation of
the bill failing which the interest becomes payable.
19. In view of introduction of single slab for energy charges, the LT consumers may
avail multiple connections to their premises.
20. In case of multiple connections in a building, all the meters shall be provided
at one easily accessible place in the ground floor.
22. Payments upto and inclusive of Rs.10000/- shall only be made by cash or DD or
digital payment. Payments above Rs.10,000 shall be by cheque or D.D or
through digital payment.
Note: The Consumers can avail the facility of payment of monthly power supply bill
through Electronic clearing system (ECS)/ Debit / Credit cards / RTGS/ NEFT/ Net
Banking through ESCOMs/ Bank/ Bangalore One and Karnataka One website, on-
line E-Payment / Digital mode of payments as per the guidelines issued by the RBI
wherever such facility is provided by the Licensee in respect of revenue payments
up to the limit prescribed by the RBI.
23. If any of installations is not covered under any Tariff schedule, the Licensee is
permitted to classify such installations under appropriate Tariff schedule under
intimation to the K.E.R.C and approval thereon.
i) The industries that intend to avail this benefit shall have Electronic Tri- Vector
Meter / Smart Meter installed to their installations.
iii) The consumption during any month of the declared off-season shall not be
more than 25% of the average consumption of the previous working season.
iv) The ‘Working season’ months and ‘off-season’ months shall be full–calendar
months. If the power availed during a month exceeds the allotment for the
‘off-season’ month, it shall be taken for calculating the billing demand as if
the month is the ‘working season’ month.
31. Metering for 400 Voltas, 3 phase supply with requisition load above 50 kw to
150 kw:
The accuracy class of metering for arranging power supply to consumers at
Low Tension for loads between 50 KW to 150 KW shall be the same as prescribed
for HT consumers.
ELECTRICITY TARIFF-2026
PART-I
2. Use of power within the Consumer premises for bonafide temporary purpose is
permitted, subject to the conditions that, total load of the installation on the
system does not exceed the sanctioned load.
3. Where it is intended to use power supply temporarily, for floor polishing and
such other portable equipment, in a premises having permanent power supply,
such equipment shall be provided with earth leakage circuit breakers of
adequate capacity.
6. A rebate of 25 Paise per unit will be given for the House/ School/Hostels
meant for Handicapped, Aged, Destitute and Orphans, Rehabilitation
Centres under Tariff schedule LT-1.
7. A rebate of 20% on fixed charges and energy charges will be allowed in the
monthly bill in respect of public Telephone booths having STD/ISD/ FAX facility
run by handicapped people, under Tariff schedule LT 3.
8. A rebate of 2 paise per unit will be allowed if capacitors are installed as per
Clause 23 of Conditions of Supply of Electricity of the Distribution Licensees in
the State of Karnataka in respect of all metered IP Set Installations.
(i) The specified P.F. is 0.85. If the PF is found to be less than 0.85 Lag, a surcharge
of 2 Paise per unit consumed will be levied for every reduction of P.F. by 0.01
below 0.85 Lag. In respect of LT installations, however, this is subject to a
maximum surcharge of 30 Paise per unit.
(ii) The power factor when computed as the ratio of KWh/KVAH will be determined
up to 3 decimals (ignoring figures in the other decimal places) and then
rounded off to the nearest second decimal as illustrated below:
(a) 0.8449 to be rounded off to 0.84
(b) 0.8451 to be rounded off to 0.85
(iii) In respect of Electronic Tri-Vector meters / Smart Meter, the recorded average
PF over the billing period shall be considered for billing purposes.
(v) In the case of installations without electronic Tri-vector meters / Smart Meter
even after providing capacitors as recommended in Clause 23.01 and 23.03 of
Conditions of Supply of Electricity of the Distribution Licensees in the State of
Karnataka, if during any periodical or other testing / rating of the installation by
the Licensee, the PF of the installation is found to be lesser than 0.85, a
surcharge determined as above shall be levied from the billing month following
the expiry of Three months’ notice given by the Licensee, till such time, the
additional capacitors are installed and informed to the Licensee in writing by
the Consumer. This is also applicable for LT installations provided with electronic
Tri-vector meters / Smart Meter.
10. All new IP set applicants shall fix capacitors of adequate capacity in
accordance with Clause 23 of Conditions of Supply of Electricity of the
Distribution Licensees in the State of Karnataka before taking service.
11. All the existing IP set Consumers shall also fix capacitors of adequate capacity
in accordance with Clause 23 of Conditions of Supply of Electricity of the
Distribution Licensees in the State of Karnataka, failing which, PF surcharge at
the rate of Rs.100 per HP/ year shall be levied. If the capacitors are found to be
removed / not installed, a penalty at the same rate as above (Rs. 100/-per HP
/ Year) shall be levied.
14. The Consumers under IP set tariff schedule, shall use the energy only for
pumping water to irrigate their own land as stated in the IP set application /
water right certificate and for bonafide agriculture use. Otherwise, such
installations shall be billed under appropriate Industrial / Commercial tariff,
based on the recorded consumption, if available, or on the consumption
computed as per the Table given under Clause 42.06 of the Conditions of
Supply of Electricity of the Distribution Licensees in the State of Karnataka.
15. The water pumped for agricultural purposes may also be used by the
Consumer for his bonafide drinking purposes and for supplying water to
animals, birds, Poultry farms, Dairy farms and fish farms maintained by the
Consumer in addition to agriculture.
16. The motor of IP set installations can be used with an alternative drive for other
agricultural operations like sugar cane crusher, coffee pulping, arecanut cutting
etc., with the approval of the Licensee. The energy used for such operation
shall be metered separately by providing alternate switch and charged at LT
Industrial Tariff (Only Energy charges) during the period of alternative use.
However, if the energy used both for IP Set and alternative operation, is
measured together by one energy meter, the energy used for alternate drive
shall be estimated by deducting the average IP Set consumption for that
month, as per the IP sample meter readings for the sub division, as certified by
the sub-divisional Officer.
17. The IP Consumer is permitted to use energy for lighting the pump house and
well limited to two lighting points.
18. Billing shall be made at least once in a quarter year for all IP sets.
19. In the case of welding transformers, the connected load shall be taken as:
a) Half the maximum capacity in KVA as per the nameplate specified under
IS: 1851
OR
ANNEXURE – 9 Page 532
Karnataka Electricity Regulatory Commission Tariff Order 2025 All ESCOMs
b) Half the maximum capacity in KVA as recorded during the rating by the
Licensee, whichever is higher.
20. Electricity under Tariff LT 3 / LT 5 can also be used for Lighting, Heating and Air-
conditioning, Yard-Lighting, water supply in the respective of premises of
Commercial / Industrial Units.
21. LED fittings shall be provided by the Licensee for the Streetlights in the case of
villages covered under the Licensee’s electrification programme for initial
installation.
In all other cases, the entire cost of fittings including Brackets, Clamps, etc., and
labour for replacement, additions and modifications shall be met by the
organizations making such a request. Labour charges shall be paid at the standard
rates fixed by the Licensee for each type of fitting.
22. Lamps, fittings and replacements for defective components of fittings shall be
supplied by the concerned Village Panchayaths, Town Panchayaths or
Municipalities for replacement.
b) The industries that intend to avail this benefit shall have Electronic Tri-Vector
Meter / Smart Meter fitted to their installation.
c) Monthly charges during the seasonal months shall be fixed charges and
energy charges. The monthly charges during the off seasonal months shall
be the energy charges plus 25% of the applicable fixed charges.
Also applicable to the installations of (i) Hospitals, Dispensaries, Health Centres run by
State/Central Govt. and local bodies; (ii) Houses, schools and Hostels meant for
handicapped, aged, destitute and orphans; (iii) Rehabilitation Centres run by
charitable institutions, AIDS and drug addicts Rehabilitation Centres; (iv) Railway staff
Quarters with single meter (v) fire service station offices.
(c) “Home Stay” means a private owned residence including a residence in a farm /
plantation where the owner or any of their immediate family (spouse /children) is
physically residing in the same residence and letting out minimum one room and
maximum six rooms where any tourist can stay on payment of boarding and
lodging charges. Such installations shall be billed under LT-1 tariff.
(b) Use of power within the consumer's premises for temporary purposes for bonafide
use is permitted subject to the condition that, the total load of the installation on
the system does not exceed the sanctioned load.
(c) Where it is intended to use floor polishing and such other portable equipment
temporarily, in the premises having permanent supply, such equipment shall be
provided with an earth leakage circuit breaker of adequate capacity.
2. Besides Lighting, Heating and Motive power, electricity supply under this Tariff can
also be used for Yard lighting/ air Conditioning/water supply in the premises.
5. A rebate of 20% on fixed charges and energy charges shall be allowed in the
monthly bill in respect of telephone Booths having STD / ISD/FAX facility run by
handicapped people.
6. Demand based Tariff at the option of the consumer can be adopted as per Para
1 of the conditions applicable to LT installations.
The GoK shall release full subsidy to meet the revenue requirement on the
approved quantum of IP sets sales in terms of Section 65 of the Electricity Act,
2003. In case, there is any variation/ shortfall in the release of required subsidy by
the GoK, the quantum of sales to IP sets of 10 HP and below shall be either
proportionately regulated or the ESCOMs shall collect the CDT from the IP set
consumers.
(ii) This Tariff is applicable for Coconut and Arecanut plantations also.
2. The motor of IP set installations can be used with an alternative drive for other
agricultural operations like sugar cane crusher, coffee pulping, arecanut cutting
etc., with the approval of the Licensee. The energy used for such operation shall
be metered separately by providing alternate switch and charged at LT Industrial
Tariff (Only Energy charges) during the period of alternative use. If the energy used
both for IP Set and alternative operation, is however measured together by one
energy meter, the energy used for alternate drive shall be estimated by deducting
the average IP Set consumption for that month as per the IP sample meter readings
for the sub division as certified by the sub-divisional Officer.
3. The Consumer is permitted to use the energy for lighting the pump house and well
limited to 2 lighting points.
4. The water pumped for agricultural purposes may also be used by the Consumer for
his bonafide drinking purposes and for supplying water to animals, birds, Poultry
farms, Dairy farms and fish farms maintained by the Consumer in addition to
agriculture.
5. Billing shall be made at least once in a quarter year for all IP sets.
6. A rebate of 2 paise per unit will be allowed if capacitors are installed as per Clause
23 of Conditions of Supply of Electricity of the Distribution Licensees in the State of
Karnataka in respect of all metered IP Set Installations.
7. Only fixed charges as in Tariff Schedule for Metered IP Set Installations shall be
collected during the disconnection period of IP Sets under LT 4(a), LT 4(b) and LT
4(c) categories irrespective of whether the IP Sets are provided with Meters or not.
outside the premises of the installation for which the power supply is availed, LPG
bottling plants and petroleum pipeline projects, Piggery farms, Analytical Lab. for
analysis of ore metals, Satellite communication centres, Mineral water processing
plants / drinking water bottling plants soda fountain units and Solid Waste Processing
Plant, Animal husbandry activities, Transformer Repair Centres, Data Centres (on
production of necessary certificate issued by Department of Electronics, Information
Technology & Biotechnology and Science & Technology).
2. Rebate of Re.1/- per unit in Energy Charges shall be extended to Ice Manufacturing
Units / Cold Storage plants used for fisheries purpose that are situated in the coastal
belt area of Karnataka State within radius of 5 Kms from Sea. In case these plants
are situated beyond the radius of 5 Kms from Sea, such consumers are also eligible
to avail the rebate benefit, provided that such consumers have to submit a
certification from the authorities of Fisheries Department that their activities are
actually meant for fisheries purpose only.
3. Consumers under the LT5 tariff category are permitted to utilize electricity within
their premises for internal modifications and expansions, provided that the total
load of the installation does not exceed the sanctioned load.
2. Seasonal Industries: The industries which intend to utilize seasonal industry benefit
shall comply with the conditionality under para no. 26 of general terms and
conditions applicable to LT.
3. In the case of welding transformers, the connected load shall be taken as, (a)
Half the maximum capacity in KVA as per the name plate specified under-
IS1851, or (b) Half the maximum capacity in KVA as recorded during rating by
the Licensee, whichever is higher.
LT-6(c): ToD Tariff for the EV charging stations in the Depots of BMTC / KSRTC / NEKRTC
/ NWKRTC who have availed HT power supply for charging the Electric Motor Vehicles
From July to November From December
Time of Day (monsoon period) to June
(paise / unit) (paise / unit)
06.00 Hrs to 09.00 Hrs 0 (+)100
09.00 Hrs to 18.00 Hrs 0 0
18.00 Hrs to 22.00 hrs 0 (+)100
22.00 Hrs to 06.00 Hrs 0 (-)100
3. This Tariff is also applicable to touring cinemas having licence for duration less than
one year.
PART-II
1. Billing Demand
A) The billing demand shall be the maximum demand recorded during the month
or 90% of the CD, whichever is higher.
B) If at any time the maximum demand recorded exceeds the CD, the Consumer
shall pay for the quantum of excess demand at two times the normal rate per
KVA per month as deterrent charges as per Section 126(6) of the Electricity Act,
2003. For over-drawal during the billing period, the penalty shall be two times
the normal rate.
C) During the periods of disconnection, the billing demand shall be 90% of CD,
had the installation been in service. This provision is applicable only, if the
installation is under disconnection for the entire billing month.
D) For the purpose of billing, the billing demand of 0.5 KVA and above will be
rounded off to the next higher KVA, and billing demand of less than 0.5 KVA
shall be ignored.
(i) The specified P.F. is 0.90. If the power factor goes below 0.90 Lag, a
surcharge of 3 Paise per unit consumed will be levied for every reduction
of P.F. by 0.01 below 0.90 Lag.
(ii) The power factor when computed as the ratio of KWh / KVAh will be
determined up to 3 decimals (ignoring figures in the other decimal
places), and then rounded off to the nearest second decimal as
illustrated below:
The above rebate will be allowed in respect of all the installations of the
above voltage class, including the existing installations, and also for installations
converted from 13.2 KV and below to 33 KV and above and also for installations
converted from 33/66 KV to 110/220 KV, from the next meter reading date after
conversion / service / date of notification of this Tariff order, as the case may
be. The above rebate is applicable only on the normal energy consumed by
the Consumer including the consumption under TOD Tariff and base
consumption in respect of any concessional scheme, approved by the
Commission. and is not applicable on any other energy allotted and
consumed, if any, viz.,
i) Wheeled Energy.
ii) Energy drawal under special incentive scheme / DERS / any other
concessional schemes approved by the Commission.
The above rebate is not applicable for BMRCL and Railway Traction.
5. Energy supplied may be utilized for all purposes associated with the working of
the installations, such as, Office, Stores, Canteens, Yard Lighting, Water Supply
and Advertisements within the premises.
7. Power supply under HT-4 tariff schedule may be used for Commercial and other
purposes inside the colony for installations such as Canteen, Club, Shop,
Auditorium etc., provided, this load is less than 10% of the CD.
9. Seasonal Industries
a. The industries, which intend to utilize seasonal industry benefit, shall conform
to the conditionality’s under Para no. 24 of the General terms and
conditions of tariff (applicable to both HT & LT).
b. The industries that intend to avail this benefit shall have Electronic Tri-Vector
Meter / Smart Meter fitted to the installation.
c. Monthly charges during the working season, shall be the demand charges
on 90% of the contract demand, or the recorded maximum demand during
the month, whichever is higher, plus the energy charges for the energy
consumed.
d. Monthly charges during the off season shall be demand charges on the
maximum demand recorded during the month or 50% of the Contract
Demand whichever is higher plus the energy charges for the energy
consumed.
10. The ToD tariff approved by the Commission in this Tariff Order is not applicable
to the extent of the energy consumed and billed under the new ‘Discounted
Energy Rate Scheme’. However, ToD tariff shall be applicable up to the base
monthly average consumption, as computed by the licensee.
Railway Traction, Effluent treatment plants and Drainage water treatment plants
owned other than by the local bodies, independently serviced outside the premises
of industries/ Buildings for which the HT power supply is availed. LPG bottling plants,
petroleum pipeline projects, Piggery farms, Analytical Lab for analysis of ore metals,
Saw Mills, Toy/wood industries, Satellite communication centres, Mineral water
processing plants / drinking water bottling plants and Solid Waste Processing Plant,
Data Centres (on production of necessary certificate issued by Department of
Electronics, Information Technology & Biotechnology and Science & Technology. Bulk
Ice Cream and Ice Manufacturing Units (including storage units established within the
premises of the manufacturing unit)
All the activities listed under LT3 tariff schedule and not included under HT2(b) tariff
schedule shall be classified and billed under HT-2(b), if they avail power under HT
supply.
2. Energy under this tariff may be used for commercial and other purposes inside the
colonies, for installations such as, Canteens, Clubs, Shops, Auditorium etc.,
provided, this commercial load is less than 10% of the Contract demand.
recorded demand of the main HT meter is allowed. Common areas shall be billed
at Tariff applicable to the predominant Consumer category.
NOTE:
"Common Areas" shall mean and include the shared facilities and amenities
specifically including water pumping, lift, motor, parking areas lighting, sewage
treatment plant, firefighting equipment, swimming pool, gym, clubhouse.
Provided that such areas and facilities shall be utilized exclusively for bona fide
purposes and shall not be used for any commercial activity or business enterprise
whatsoever.
2. This Tariff is also applicable to touring cinemas having licence for duration less than
one year.
*********