UNIT ONE (1)
UNIT ONE (1)
BUDGET
For most of such projects the cash flows are uncertain, and this uncertainty
creates risk.
In this unit, we discuss procedures used to assess risk, incorporate risk in the
capital budgeting process and conclude by discussing how firms determine
optimal capital budgets.
The higher the risk, the higher the rate of return required to compensate for the
higher risk.
Project risk can be assessed from three separate and distinct levels of risk
analysis, which are:
1) Stand – alone risk, which views a project’s risk in isolation, that is without
regard to portfolio effects. A project is evaluated only on its own merit.
2) Within firm risk, also called project’s corporate risk, which views project
risk within the context of the firm’s portfolio of already existing and running
projects.
3) Project’s market risk, which views the project risk in the context of the
firm’s stockholders holding diversified portfolio of stocks.
The coefficient of correlation is a very crucial measure of risk, because it
moderates the level of risk that a specific project contributes to corporate risk
and market risk. Coefficient of correlation measures the size and direction of the
relationship between two variables.
σF - standard deviation of the rate of return on the firm’s assets before the firms
takes on the project under viability evaluation. Rate of return in this context is
measured as [(Net Income + Interest)/(Debt + Equity)]. If the company has been
in existence for sometimes (σF) is based on average returns realised by existing
projects over the past few years. A high corporate risk ( σF) implies high chances
of bankruptcy.
The estimate of a corporate risk for the past years can be done statistically, but
changes in the firm’s situation may make its expected future corporate risk to
differ from its past levels, in which case subjectively estimated ( σF) would be
preferable for use in the analysis.
Remember that when using historical returns this way, we are assuming that the
historical returns will prevail into the future thus they are a good prediction the
returns that will be generated in the future.
rP,F - coefficient of correlation between the rate of return on project and the
average rate of return on the firm’s other assets. Are the two returns dependent
or independent of each other? Are they negatively or positively correlated? Is
the project related to the firm’s core business or it is outside the core.
From the above equations, we can notice that the project’s stand alone risk ( σP)
is also an input variable in the formulae for project’s corporate beta and
project’s market beta.
Contrary to most people’s believe that stand alone risk and corporate risk are
not important to stockholders whose aim is to maximise their wealth, stand
alone and corporate risk are important for the following reasons:
The starting point for analysing a project’s stand alone risk is to determine the
project’s cash flows.
In capital budgeting, most of the individual cash flows used to produce the
yearly expected cash flows are subject to uncertainty and the level of
uncertainty must be quantified and this can be done through using four stand
alone risk assessment techniques – sensitivity analysis, scenario analysis, Monte
Carlo simulation and decision trees.
Before project risk can be quantified be it on a stand- alone, corporate level or
market level, cash flows have to be estimated as we did on the excel for the RIC
watering project.
The input variables and how to calculate the cash flows and the resultant NPV
and IRR on excel sheet were discussed in class and excel sheet is available on
Tsimeonline. It was noted that most variables for estimating cash flows – sales
units, selling price, variable costs etc – are uncertain, and that when input
variables deviate from expected values, the yearly cash flows as well as the
NPV and IRR will also change.
As written on the excel sheet - the sales units, selling price and variable costs,
etc – are the expected values taken from respective probability distributions of
the input variables. The distributions of the input variables can either be
relatively tight reflecting small standard deviation and low risk or they can be
flat denoting a great deal of uncertainty about the variables under consideration.
Therefore, the variables’ distributions and their correlations with one another
affect the project’s NPV and IRR distributions, thus the project’s stand alone
risk. Note that anything that affects a project’s stand alone risk also affects a
project’s corporate and market risk because σP appears in the formulae for
calculating project’s corporate and market betas.
There four techniques for measuring stand -alone risk (sensitivity analysis,
scenario analysis, Monte Carlo simulation and decision trees)
I. Sensitivity Analysis
It is a technique which indicates exactly how much the NPV or IRR will change
in response to a given change in a key input variable, other things held constant.
Sensitivity analysis begins with a base case situation developed using each
input’s expected value. For example, the values for unit sales, sales price, fixed
costs, and variable costs are the expected or base case values and the resulting
NPV $12 076 984 and IRR 25% are the base case NPV and IRR (see excel
sheet).
Sensitivity analysis is concerned with finding out how sensitive the NPV is to
changes in key input variables. For example, in the RIC’s watering project the
analysts will have to identify key input variables that affect NPV of the project
the most, and if possible take corrective measures such as entering into hedging
contracts to mitigate against unfavourable movements in key input variables.
Please note the word input variables in this context is used to refer to the several
variables that are added and subtracted to arrive at annual cash flows that are
used in capital/project appraisals.
In sensitivity analysis, the level of stand- alone risk is denoted by the gradient of
the sensitivity lines. The steeper the sensitivity line, the greater the risk.
Secondly, sensitivity analysis ignores the range of likely values of the key input
variables as reflected in the inputs’ probability distributions.
Sensitivity analysis does not take into take into account the range of likely
values of key variables as reflected in input variables’ probability distributions.
1) Worst case scenario NPV – in which the least possible NPV is calculated
using lowest possible unit sales, lowest possible selling price, the highest
possible variable costs, highest possible construction costs and so on.
2) The average or the most likely NPV. The NPV of $12.076 million was
calculated assuming all input variables take their expected values.
3) Best case NPV – which could be obtained assuming the highest possible unit
sales, highest possible selling price, lowest possible variables and construction
costs etc.
To illustrate using the RIC watering system project, the company might be very
confident about all other input variables except sales quantity and selling price.
For the project, the lowest possible unit sales figure is estimated to be 15 000
units and the maximum to be 35 000 units.
On the other hand, the lowest possible price is estimated to be $1700 and the
best price is to be $2700.
To do scenario analysis, the company will have to calculate the NPV expected
under the 3 scenarios. Each scenario has a specific probability of occurring. The
table below shows how the NPVs under the three scenarios are treated to
calculate the expected NPV, NPV standard deviation and NPV coefficient of
variation.
To get the NPV under the worst case scenario, go to the excel sheet and change
the sales figure in year 2021 to 15 000 units and the selling price to $1 700. All
other variables remain the same, because we have assumed that the managers
are confident that the figures as they are correct estimates.
To get the NPV under the best case scenario, again go to the excel sheet and
change the same sales units cell to 35 000 and the same selling price cell to $2
700.
A closer look at project’s stand alone risk can be made since scenario analysis
gives managers the E (NPV), standard deviation of NPV, and coefficient of
variation.
1) Firstly, the analysis considers only 3 discrete NPVs for the project (worst
case NPV, most likely NPV and the best case NPV); although in reality there
are an infinite number of possibilities.
Limitations
Decision trees
Its emphasis is both on measuring and reducing project risk.
Sometimes it is not feasible for the company to make an outright investment
outlay at time zero. Instead, the firm can stagger the capital outlays over a
period of time such that the outcome at each stage affects the next stage. The
project can be abandoned if an earlier stage shows that the project is not
feasible, hence avoiding further investment on non-viable projects thus
minimising overall company losses.
For example suppose company X is considering the production of an
industrial robot for the television manufacturing industry. The net investment
for the project, of $11.5 million, can be broken into 3 stages:
Stage 1
Stage 2
Stage 3
Under high cash flows, the company would have net cash flows of $10
million per year from year 3 to 6.
Under medium cash flows, the firm would have net cash flows of $4 million
from yr 3 to 6
Under low cash flows, the company will have negative net cash flows of $2
million in yr 3 through yr 6
The figure attached shows how the company can do a decision tree analysis for
the project.
Since the expected NPV is negative, it would appear that the project
should be rejected.
However, the use of decision trees allows the incorporation of the project
abandonment option in the capital budgeting process.
In the third branch of the attached decision tree, the company can
abandon the project at the beginning of year 4, if negative cash flows of
$2,000,000 have been realised at end of year 3, and if based on latest
information available at that time, the company suspects the negative
cash flows to continue through year 6.
The abandonment option will change the branch to look like this:
3
0.3 Joint Prob NPV Prob X NPV
Managers can reduce project’s stand alone risk if they structure the
decision process to include several decision points rather than just one.
A negative project’s corporate beta means that the project’s returns move in
the opposite direction to the returns of the firm’s other assets/projects. It
implies that when the returns on a company’s existing projects/assets
increase, the returns of a project with negative corporate beta fall, and vice-
versa.
We use two methods, which are the pure play method and the accounting beta
method.
In the pure play method, the company tries to find one or more non-
integrated, single product companies in the same line of business as
the project being evaluated.
For example, RIC will have to find publicly traded firms that only
deal with watering control systems and we assume the pure play
companies have the same business risk as the watering project. RIC
should then determine the betas of these firms through the regression
process find the average of these betas and use it as a proxy for the
project’s beta.
Therefore the average beta that we got from the regression process
will have to be adjusted for the differences’ in the capital structures
and tax rates of pure play companies versus the tax rate and capital
structure of RIC. The adjustment is not necessary if RIC has the same
capital structure and tax rate as the pure play companies.
To illustrate, assume that RIC’s analysts have identified three publicly owned
companies engaged only in the production and distribution of watering control
systems. Further, assume that average stock beta (note that because of one line
of business, the stock beta can also be called project market beta), is 2.23; that
their average debt to equity ratio, D/S is 0.4/0.6 = 0.67; and their average tax
rate is 36%.
We cannot conclude that the project’s appropriate leverage adjusted beta is
2.23, because we already know RIC’s D/S ratio of 0.5/05 =1 and tax rate of
40% are different from those of the pure play firms.
To adjust for the differences in financial leverage and tax rates, we use the
Hamada equation and proceed with the following four steps.
Step 1: Note that the proxy firms’ average stock beta of 2.23 reflects their
average D/S ratio of 0.67 and their average tax rate of 36%
Step 2: We insert the values in step 1 above into the Hamada equation to get the
3 firms’ unlevered beta.
bU = 2.23/[1 + (1-0.36)(0.4/06)]
= 1.56
Step 3: We can now find what the proxy firms’ stock betas would be if they had
the same capital structure and tax rate as RIC.
bL = bU [1 + (1-T) (D/S)]
=2.50
Step 4: Determine the project’s cost of equity and its weighted average cost of
capital, using 2.5 as the estimate of its beta.
KE = Kf + (Rm - Kf)b
The RIC watering control systems average cost of capital WACC P = 0.5(10%)
(0.6) + 0.5(20.5%) = 13.25%
WACCp = WdKd(1 – T) + WeKe
The major limitation of the pure play method is that it can be difficult to find
pure play proxy companies.
In summary, through analysing the project’s market risk RIC can come up
with the following important conclusions:
If RIC takes on the new project, its corporate beta would rise from 1.8
to 1.94;
Its cost of equity would rise from 17% to 17.7%;
Its corporate cost of capital would rise from 11.5% to 11.85%; and the
new project would have to earn at least 13.25% to avoid lowering the
RIC’s stock price.
In appraising the watering project, the right discount rate to use is
13.25% not 11.85%.
11.85% is the discount rate for average risk projects, given that beta of
the watering project which is high implying more risk, the appropriate
discount rate for use in appraising the watering project is 13.25%.
When it is difficult to find single product, publicly traded firms for the pure play
approach, then companies can use the accounting beta method.
The accounting beta entails regressing the company’s basic earning power
(earnings before interest and taxes/total assets) against the average basic
earning power for a large sample of companies.
The accounting beta method can also be used to different divisions and projects’
within firm risk.