Insulation Installation

This document provides a checklist for ensuring piping and equipment is ready for insulation installation. The checklist includes verifying fabrication and testing is complete, required materials and equipment are on site, permits and safety requirements are addressed, drawings and specifications are included, and sign off once installation is complete. It lists over 30 items to confirm are in place covering piping/equipment preparation, cranes, rigging, transportation, training, permits, safety, inspections, vendors, scaffolding requirements, drawings and finally sign off of the completed work. The checklist aims to comprehensively cover all pre-installation requirements.

Uploaded by

mayasolani
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
85 views

Insulation Installation

This document provides a checklist for ensuring piping and equipment is ready for insulation installation. The checklist includes verifying fabrication and testing is complete, required materials and equipment are on site, permits and safety requirements are addressed, drawings and specifications are included, and sign off once installation is complete. It lists over 30 items to confirm are in place covering piping/equipment preparation, cranes, rigging, transportation, training, permits, safety, inspections, vendors, scaffolding requirements, drawings and finally sign off of the completed work. The checklist aims to comprehensively cover all pre-installation requirements.

Uploaded by

mayasolani
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

MAJOR PROJECTS

Appendix - 8
Department: Subject:

CONSTRUCTION FIWP INSULATION CHECKLIST

Number:

PCM-CP-000X-8
Revision:

FIWP ID Number: FIWP Description:


ITEM DESCRIPTION Piping / Equipment Ready For Insulation Installation: a) Fabrication Complete b) Hydrotesting Complete c) Tracing Installed And Verified d) Release For Insulation Signed-Off Type And Thickness Of Insulation Clearly Identified And Listed Type Of Cladding And Thickness Clearly Identified And Listed Crane(s) To Support Work Package Activities: a) Onsite b) Available c) Scheduled Required Rigging And Accessories Onsite And Available To Support Work Package Activities Transportation Requirements For Materials And Tools Etc.: a) Available b) Scheduled Material Requisitions Complete Ready To Be Submitted For Work Package Materials In Warehouse Bagged And Tagged Special Training / Qualification Requirements: a) Safety; SCABA, High Level Rescue Etc b) Equipment Operation; Manlift Etc. c) Other d) Training Complete Permit Requests Complete Ready To Be Submitted For Work Package Safety Items And Concerns Clearly Identified, Listed And Addressed Hazard Assessments / Requirements: a) Hazard Identified b) Assessment Performed c) Mitigated Additional Personnel Protection Equipment Requirements Clearly Identified, Listed, Onsite And Available For Use Inspection And Testing Requirements Clearly Identified And Listed Including Hold And Witness Points QC forms inserted into package for required

Date Prepared:
YES / NO / N/A COMMENTS

UNCONTROLLED DOCUMENT PRINTED ON 04/21/08


File: INSULATION INSTALLATION.doc

Page 1 of 2

MAJOR PROJECTS

Appendix - 8
Department: Subject:

CONSTRUCTION FIWP INSULATION CHECKLIST

Number:

PCM-CP-000X-8
Revision:

inspection and sign-off Third Part Inspection And Testing: a) Available b) Scheduled Vendor Requirements: a) Required b) Available c) Scheduled Scaffolding / Manlift Requirements: a) Identified b) Available c) Scheduled d) Built (Scaffold Only) Man Basket Requirements: a) Identified b) Available d) Scheduled All Required Drawings, Details And Specifications Included In Work Package: a) Piping / Equipment; Drawings To Be Insulated b) Signed Copy Of Release For Insulation c) Insulation Details d) Insulation Specification e) Special Requirements f) Design Change Notices g) Request For Information h) Inspection And Test Plan i) Lessons Learned Suggestion Form Insulation And Cladding Installed, Inspected And Sign-Off As Complete

Planner Name (print):

Planner Signature:

Issue Date:

Superintendent Name (Print):

Superintendent Signature:

Issue Date:

Work Foreman Name:

Work Foreman Signature:

Work Start Date:

Work Foreman Name:

Work Foreman Signature:

Work Completion Date:

UNCONTROLLED DOCUMENT PRINTED ON 04/21/08


File: INSULATION INSTALLATION.doc

Page 2 of 2