Getting Started With Project 2010
Getting Started With Project 2010
LINK 2 TASKS
Linking tasks allows you to create relationships between tasks. For example, you may want one task to begin after another one ends. You wouldnt want the Design phase of a project, say, to begin at the same time as construction, or problems will occur. In this case, you would link the Design phase to the Construction phase so that one starts after the other. 1. Select the two tasks that you want to link. Select the first task by clicking its name in the Task Name column, and then hold down the SHIFT key while clicking the second task. 2. 3. Click the Task tab, and then in the Schedule group, click Link Task .]
To change the link type, double click the line between the linked tasks, and select one of the following:
The second task cannot start until the first task finishes. For example, if you have two
tasks, "Construct fence" and "Paint fence," "Paint fence" can't start until "Construct fence" finishes. This is the most common type of dependency.
The second task cannot start until the first task starts. For example, if you have two tasks,
"Pour foundation" and "Level concrete," "Level concrete" can't begin until "Pour foundation" begins.
The second task cannot finish until the first task finishes. For example, if you have two
tasks, "Add wiring" and "Inspect electrical," "Inspect electrical" can't finish until "Add wiring" finishes.
The second task cannot finish until the first task starts. This dependency type can be
used for just-in-time scheduling up to a milestone or the project finish date to minimize the risk of a task finishing late if its dependent tasks slip.
Manually scheduled
Manually scheduled tasks allow greater flexibility in how a task is scheduled. For
example, you can create a duration of Soon for a manually scheduled task without Project displaying an error.
Automatically scheduled
Automatically scheduled tasks require specific types of values for duration and
start fields. These tasks use this information (along with calendar information) to help determine where tasks should begin in relation to other tasks. To change the task mode of a task, do the following:
) or Manually Scheduled (
or
).
Print
Show All With Project 2010, you can create tasks to break the project work into smaller pieces. Some project managers refer to tasks as "activities" or "work packages."
Create a new task Create multiple tasks Create a recurring task Learn tips for working with tasks
2.
In an empty Task Name field, type a task name and then press ENTER.
3.
Type the task name in the inserted row. The task IDs are automatically renumbered after you insert a task.
2.
On the Task tab, in the Insert group, click the top part of the Task button.
3.
Type the task name in the new task box. You can use an outline to organize your schedule as you enter tasks, or you can wait until you enter all of your project tasks. When you outline a schedule for your project, you simplify its organization so that your project is easier to create, manage, and maintain.
TOP OF PAGE
2.
The window is split to display the Gantt Chart view on the top and Task Form view on the bottom. You cannot view the timeline while viewing this split view. 3. 4. In the Gantt Chart view (top), click the first empty row at the end of the task list. In the Task Form view (bottom), type information about the new task:
5.
In the form columns, type detailed information about the task (such as the assigned resources and predecessor tasks). Click OK to save the new task, and then click Next to move to the next row in the Gantt Chart view.
NOTE
In the Name box, type the new task's name. In the Duration box, type the task duration. If you want the task duration to remain fixed regardless of resource assignments, select the Effort driven check box.
You cannot use the Task Form view to enter subtasks into your project. To create subtasks, indent and outdent tasks in
TOP OF PAGE
2. 3.
Select the row below where you want the recurring task to appear. On the Task tab, in the Insert group, click the bottom part of theTask button and then click Recurring Task.
4. 5. 6. 7. 8.
In the Task Name box, type the task name. In the Duration box, type the duration of a single occurrence of the task. In the Recurrence pattern section, click Daily, Weekly, Monthly, or Yearly. Select the check box next to each day of the week that the task should occur. In the Start box, enter a start date and do one of the following:
Select End after, and then type the number of occurrences for the task. Select End by, and then enter the date you want the recurring task to end.
NOTE
If you don't enter a date in the Start box, Project uses the project start date.
9.
In the Calendar for scheduling this task section, select a resource calendar from the Calendar list to apply to the task. If you do not want to apply a calendar, select None.
TIP
If you want to apply a calendar, but not tie that calendar to scheduling for the task, select the Scheduling ignores
resource calendars check box. When you insert a recurring task, the task IDs are automatically renumbered and a recurring task indicator Indicators column. appears in the
If you assign resources to a recurring summary task by typing resource names in the Resource Names field, the resource will be assigned to the total work on the recurring task and not to the individual recurring tasks as they occur.
TOP OF PAGE
Break down tasks to the level of detail that you want to track. You should break them down in more detail for riskier areas. Make sure that tasks have clear criteria for completion. Define the tasks that are short compared with the overall project duration. Shorter tasks allow you to more easily estimate time and resources. Avoid defining such things as vacation or training as tasks. Instead, you can set resource calendars to account for nonworking (administrative) time.
Print
Show All After you create tasks in a project, you need to link them to show relationships between them. Linking tasks creates task dependencies.
TIP
You can also show the relationships between multiple projects by linking tasks across projects, or by using inter-project
dependencies.
In this article
Link tasks in the Gantt Chart view Link tasks in the Network Diagram view Link tasks in the Calendar view Turn autolinking on or off About linking tasks About linking manually scheduled tasks
2.
In the Task Name field, select two or more tasks you want to link, in the order you want to link them. To select tasks that are not next to one another, hold down CTRL and click the tasks that you want to link. On the Task tab, in the Schedule group, click the Link Tasks button.
3.
To select tasks that are next to one another, hold down SHIFT and click the first and last task that you want to link.
Project creates a finish-to-start task link by default. You can change this task link to start-to-start, finish-to-finish, or startto-finish.
TOP OF PAGE
2. 3.
Position the pointer in the center of the predecessor task box. Drag the line to the successor task box.
TOP OF PAGE
2. 3.
Position the pointer on the calendar bar for the predecessor task. Drag the line to the successor task's calendar bar.
TOP OF PAGE
2. 3.
In the Project Options dialog box, click Schedule and scroll to the Scheduling options in this project section. To turn autolinking on, select the Autolink inserted or moved tasks check box. To turn autolinking off again, clear the check box.
TOP OF PAGE
LINK TYPE
Finish-tostart (FS)
EXAMPLE
DESCRIPTION
The dependent task (B) cannot begin until the task that it depends on (A) is complete. For example, if you have two tasks, "Dig foundation" and "Pour concrete," the "Pour concrete" task cannot begin until the "Dig foundation" task is completed.
Start-to-start (SS)
The dependent task (B) cannot begin until the task that it depends on (A) begins. The dependent task can start at any time after the task that it depends on begins. The SS link type does not require that both tasks begin at the same time. For example, if you have two tasks, "Pour concrete" and "Level concrete," the "Level concrete" task cannot begin until the "Pour concrete" task begins.
Finish-tofinish (FF)
The dependent task (B) cannot be completed until the task that it depends on (A) is completed. The dependent task can be completed at any time after the task that it depends on is completed. The FF link type does not require that both tasks be completed at the same time. For example, if you have two tasks, "Add wiring" and "Inspect electrical," the "Inspect electrical" task cannot be completed until the "Add wiring" task is completed. The dependent task (B) cannot be completed until the task that it depends on (A) begins. The dependent task can be completed at any time after the task that it depends on begins. The SF link type does not require that the dependent task be completed concurrent with the beginning of the task on which it depends. For example, the roof trusses for your construction project are built off-site. Two of the tasks in your project are "Truss delivery" and "Assemble roof." The "Assemble roof" task cannot be completed until the "Truss delivery" task begins.
Start-tofinish (SF)
TOP OF PAGE
Print
Show All
Once you've finished your initial planning or if you haven't even started! use Microsoft Project 2010 to create and set up your project plan. You can then use Project's powerful features to more effectively manage your project. This overview shows you the big picture of setting up a project. Follow the links in each step for detailed information about each process.
Step 1: Create a project Step 2: Add tasks to your project Step 3: Outline your project Step 4: Create calendars Step 5: Save and publish
TOP OF PAGE
TOP OF PAGE
TOP OF PAGE
TOP OF PAGE
New to Microsoft Project? Maybe you're responsible for a long, complex project and you have never used this program before. What now? Follow the links in this document for detailed information about the advantages of using Project over other programs, and then start to use it to perform basic project management tasks. You can also learn how to get more help from other Project users who have been in the same boat.
Use Microsoft Project to manage your project Create and schedule your project Connect with other Project users
TOP OF PAGE
Print
Show All What happened to the menus and toolbars? In Microsoft Project 2010, they have been replaced with the Ribbon, which helps you quickly find the commands that you need to complete a task. Commands are organized in logical groups that are collected together under tabs. This document provides a broad overview of what you can find in each tab of the Ribbon, followed by a short example of how to use the Ribbon to perform a basic project management task. It also directs you to more detailed information on that task.
In this article
The Task tab Sample use: Top-down scheduling Sample use: User-controlled scheduling The Resource tab Sample use: Team planner The Project tab Sample use: Set a baseline The View tab Sample use: Add a timeline to a view The Format tab Sample use: Change the color of Gantt bars
For a detailed description of top-down scheduling, see Top-down planning with summary tasks (or phases).
3.
Project 2010 incorporates those tasks into the existing schedule. For a full description of the manual and automatic scheduling options in Project 2010, see How scheduling works in Project.
TOP OF PAGE
3.
Now that the team planner is here, you probably want to know how to use it. Check out View your team's work with the Team Planner.
TOP OF PAGE
3.
In the Set Baseline dialog box, select the baseline and its parameters that you want to set. For a detailed discussion about baselines, see Create or update a baseline or an interim plan.
TOP OF PAGE
3.
4.
Click the Format tab to access options for customizing the timeline.
NOTE
You cannot select the Timeline and Details check boxes at the same time. You must choose one view or the other.
TOP OF PAGE
2.
On the Format tab, in the Gantt Chart Style group, click a style in the Gantt Chart Style list.
3.
The colors of the Gantt bars for your entire project are instantly updated. That's fairly easy! But there are many more ways that you can customize Gantt bars in addition to applying predefined styles. See Format the bar chart of a Gantt Chart view.