DEE Module 5.3 All
DEE Module 5.3 All
E-mail: [email protected]
AUSTRALIA
CANADA
IRELAND
NEW ZEALAND
SINGAPORE
SOUTH AFRICA
UNITED KINGDOM
UNITED STATES
6 Testing of Transformers
6.1
General
There are a number of regional standards that define the functional and testing requirements for power and distribution transformers. Universally the transformer principle is the same comprising two or three windings (Mostly 2) with magnetic core and enclosure tank. For example some of the main standards available for transformers under IEC are as below: IEC- 60076 Power Transformer IEC- 60296 Specification for unused mineral insulating oils for Transformer & Switchgear IEC- 60137 Insulating Bushing for alternating voltage above 1000V. IEC- 60354 Loading Guide for oil immersed power transformer. IEC- 60364 Specification for Gas operated relays IEC- 156 Method for the determination of the electric strength of insulating oils. Some of the British standards for transformers are as below. BS 7806:Dry-type power transformers BS 7821- 4 parts: Three phase oil-immersed distribution transformers, 50 Hz, from 50 to 2500 kVA with highest voltage for equipment not exceeding 36 kV. BS 7844- 2 parts: Three-phase dry-type distribution transformers 50 Hz, from 100 to 2500 kVA with highest voltage for equipment not exceeding 36 kV. In North America following IEEE/ ANSI standards are generally adopted. IEEE C57.12.00 - Standard General Requirements for Liquid-Immersed Distribution, Power, and Regulating Transformers
IEEE C57.12.01 - Standard General Requirements for Dry-Type Distribution and Power Transformers ANSI C57.12.22 - Requirements for Pad-Mounted, Compartmental-Type, Self-Cooled, ThreePhase Distribution Transformers with High Voltage Bushings; 2,500 kVA and Smaller: High Voltage, 34,500 GrdY/19,920 Volts and Below; Low Voltage, 480 Volts and Below Requirements. ANSI C57.12.26 - Standard for Transformers - Pad-Mounted, Compartmental-Type, Self-Cooled, Three-Phase Distribution Transformers for use with Separable Insulated High Voltage Connectors: High Voltage, 34,500 GrdY/19,920 Volts and Below; 2,500 kVA and Smaller. ANSI C57.12.28 - Switchgear and Transformers, Pad-Mounted Equipment - Enclosure Integrity ANSI C57.12.50 - Requirements for Ventilated Dry-Type Distribution Transformers, 1-500 kVA Single-Phase and 15-500 kVA Three-Phase, with High Voltage 601-34,500 Volts, Low Voltage 120-600 Volts. IEEE C57.12.51 - Requirements for Ventilated Dry-Type Power Transformers, 501 kVA and Larger Three-Phase, with High Voltage 601-34,500 Volts, Low Voltage 208Y/120-4,160 Volts IEEE C57.12.90 - Standard Test Code for Liquid-Immersed Distribution Power, and Regulating Transformers and Guide for Short-Circuit Testing of Distribution and Power Transformers (ANSI). IEEE C57.12.91 - Test Code for Dry-Type Distribution and Power Transformers ASTM D877 - Test Method for Dielectric Breakdown Voltage of Insulating Liquids Using Disk Electrodes. These standards not just define the standard construction requirements but mainly indicate the acceptance criterion for a transformer before putting a transformer for a particular service application, mainly relating to the testing of transformers at manufacturers works or in an approved laboratory. This is done to ensure that they meet the specific needs of an application. The tests are broadly classified as: Routine tests Type tests Special tests
Further, like any standard electrical equipment, transformers are tested on-site before commissioning, which may be classified as: Pre-commissioning tests. Periodical maintenance tests
This chapter briefly covers the requirements laid down by international standards and best practices followed in industry for transformers before accepting for an application (routine and type tests) and before putting into service (pre-commissioning tests). Maintenance related tests are covered in a separate chapter.
6.2
Routine tests
The quality of transformers depends on successfully verifying the performance of components that go into it. A manufacturer is expected to ensure that the following checks and tests are conducted before/during assembly:
Testing of Transformers 93
a) Quality checks and tests on all bought-out components/parts like laminations, conductors, protection devices, oil, insulation materials, bushings, etc. b) Tests on individual items like tanks, windings, control panels, etc. being built at the works The above test reports do not normally form a part of completed transformers. But in the interest of quality, it is necessary to ensure that the manufacturer is in possession of all pertinent records. The tests (on major parts of a transformer) are covered separately towards the end of this chapter. Once the transformer is fully assembled, the following routine tests are recommended. These tests are to be normally carried out in the presence of the customer at a manufacturers works. Hence it is expected that the manufacturers factory includes a well-equipped testing division. a) b) c) d) e) f) g) h) i) j) k) l) m) n) Visual inspection Measurement of winding resistance Measurement of voltage/turns ratio Verification of polarity and vector group Measurement of impedance voltage and load losses Measurement of no load losses and no load current Measurement of insulation resistance Power frequency voltage withstand test Induced voltage withstand test RIV Corona Voltage test (Above 132 kV) Partial Discharge measurements (300 kV and above) Lightning impulse test (For above 132 kV) Switching impulse voltage withstand test (For above 132 kV) Tests on OLTC
it is to be ensured that the windings are not unduly in hot condition when resistance measurements are taken. It shall be noted that three-phase transformers will have the terminals connected in Star or Delta and accordingly the measurements will give net parallel resistance values as per configurations. For example with A, B, C, N as terminals and with connection in Star, the resistance across A-B will give the total resistances of AN and BN. In Delta connections two windings will be in series and parallel to the third winding across which the measurement is taken. The main point is to ensure that the values are uniform and the copper losses are within the guaranteed figures. The readings are to be taken across all two terminals of the transformer to check the uniformity. In case there is some non-uniformity, it could be due to some open winding or loose connections, which are to be thoroughly checked and rectified.
Testing of Transformers 95
The connections basically require interconnecting the phase terminals of primary and secondary windings, applying voltage to one set of winding and measuring the voltage across the various terminals caused by the induction phenomenon. As is evident from the diagrams, if the voltage measured across A1-A2 is less than the voltage measured across A1-a2 then the polarity is said to be subtractive, and if it is greater, then the polarity is additive.
Figure 6.2 Test connections for determining single-phase transformer winding polarity
Figure 6.3 illustrates the test connections for a three-phase star-star connected transformer with subtractive polarity and the result verifies that the vector group matches with the requirement. The voltage measured across C2-A2 and C2-B2 must be equal and shall be more than the measurements between C2 -c2 and B2 - b2. Further the voltage across C2 -b2 must be more than C2c2 and similar result is to be checked between B2-c2 and B2-b2.
Figure 6.3 Test connections for determining three-phase transformer winding polarity
Rated Current Losses at rated current = Measured loss at test current Test Current
Percentage Impedance =
Test Voltage Rated Voltage
100
Since the power factor during these measurements could be very low (less than 0.1), watt meters suitable for such low power factor shall be considered. Further three watt meter method is preferred compared to two watt meter method to avoid large multiplication constant.
Testing of Transformers 97
No load test is conducted by feeding the voltage to the LV winding at rated frequency. The core loss consists of eddy current losses and hysteresis losses. The eddy current value is dependent on rms value of supply voltage while hysteresis loss depends on the average value of voltage. Two voltmeters are used with a bridge rectifier type to indicate the average value and a dynamometer type to indicate rms value. The actual loss, P, is given by:
P= P m P + KP 1 2
Where
Pm is the measured no load loss P1 being the fraction of hysteresis loss to the total iron loss (0.5 for grain oriented steel and 0.7 for non-grain oriented steel) P2 being the fraction of eddy current loss to the total iron loss (0.5 for grain oriented steel and 0.3 for non-grain oriented steel)
RMS voltage K= 1.11 Average Voltage 2
And
Safe IR values in Mega ohms at applicable ambient temperatures 30 C 40 C 50 C 60 C 600 300 150 75 500 250 125 65 400 200 100 50 200 100 50 25
These are called power frequency withstand voltage and have been covered earlier in this book (Table 4.2). The line terminals of the windings under test are connected together and test voltage is applied to these terminals with the other windings and tank connected to the ground. The application of test voltage is for one minute. The induced potential voltage test is basically to check the inter turn insulation and the main insulation between the windings and ground. The test voltage is twice the rated voltage of the winding with uniformly insulated windings. For graded insulation windings (Adopted for 66KV and above generally) the test voltage is about 1.5 times the nameplate voltage. For higher voltages it is usual to raise each V terminal in turn by applying single phase voltage to the LV winding. The neutral terminal may be raised to a higher potential to get at least twice the normal voltage per turn of the tested winding. The duration is 60 seconds for upto twice the rated frequency. However in order to avoid core saturation, the test frequency is chosen at higher value of around 150 to 240 Hz with the time of application reduced suitably as below.
Test Duration in seconds = K Rated frequency Test Frequency
The value of K may be 100 or 120 depending on whether it is a 50 Hz or 60 Hz rated transformer (with a minimum duration of 15 seconds).
This test requires special circuits to measure the partial discharges while applying a higher voltage for a considerable duration. Typically the transformer phase and neutral is applied 1.3 times the rated phase to neutral voltage value for 5 minutes and raised to 1.5 times the rated phase to neutral voltage value for 5 seconds and again continuing with 1.3 times the voltage for 30 minutes. During this entire sequence the partial discharge shall not exceed 300 pC at 1.3 times voltage and shall be within 500pC during the short 5 seconds while applying 1.5 times the voltage (Figure 6.4).
Testing of Transformers 99
The current AS (NZ) Standard 2374.3-1982 requires Pd testing only on 330 kV transformers and above. However, Pd testing has for many years been found to be an excellent quality control tool such that the tests were performed as early as 1982 even on some 33 kV transformers. Moreover, the permissible partial discharge levels were often reduced in purchasing specifications below that mandated by the standard so that relatively small irregularities can be detected. Many such irregularities were detected (see Figure 6.5), examples being: rust and copper slivers contamination of windings un-earthed steel bolts, etc. low oil in bushings copper cable cut-offs inadvertently dropped onto windings
In other cases again, Pd testing could have prevented a transformer failure in service due to welding rod remnants dropped onto the windings, had it only been performed on re-energizing after repair. The latest IEC standard 60076.3-2005 does recognize the value of the tests more and prescribes it for transformers > 72.5 kV. It combines the test with the induced voltage test and specifically calls for two different types, namely a short duration test (ACSD) lasting 20 min and a long duration test (ACLD) lasting 75 min according to a prescribed voltage profile. The critical period is always the one following extreme test voltage application at the induced voltage level, because if the discharge inception level has been exceeded, then it will be necessary that those discharges will also extinguish. Special attention is required with transformers having graded insulation because in such cases only single phase tests can normally be performed. The critical issues to be searched for are that the discharges will not exceed the limit value and further that they will not have a rising tendency during the test. State-of-the-art equipment enables all terminals to be tested and recorded simultaneously, which permit very good failure location by comparison the discharges at the various terminals (Figure 6.6). Where bushing condenser taps are not available, suitable blocking capacitors are used instead, refer to images.
The switching impulse test is similar to the lightning impulse test with one reduced full wave (75%) and two full waves of the rated impulse magnitude.
6.3
Type tests
Following are the type tests which are optional and carried out on units if the client specifies the same. Normally these are conducted at additional cost: a) b) c) d) Temperature rise test Lightning impulse test (for below 132 kV) Switching impulse test (for below 132 kV) Partial Discharge test (for below 300 kV)
The temperature rise test basically comprises of allowing a full current load to be passed through the windings until the thermometer readings reach steady state values. The source is normally a low voltage, high current one. After the steady state temperature is reached the transformer will start cooling thereby changing the winding resistance value. The change in resistance value is taken to find the thermal constant of the transformer windings and to interpolate the rise in winding temperature. The normal duration of a temperature rise test may be about 10 hours and increasing to one day for large capacity transformers. Though this is a type test, the temperature rise within the agreed limits will give a clear condition of the transformer under service conditions. Different cooling modes are normally to be tested separately. On large or important transformers a test at up to 1.5 times continuous maximum rating is often specified and is then carried out for a period of some 2-10 hours to prove compliance with AS/IEC. This is done subject to a maximum hot-spot temperature of 1201400C and the performance checked by analysing the oil for dissolved gases (DGA) afterwards
6.4
Special tests
Special tests are normally carried out only if required for performance checks. The following special tests are to be carried out if specified in the contract: a) b) c) d) e) Measurement of zero sequence impedance Short circuit test Sound level measurements Measurement of harmonics at no load Measurement of auxiliary power by fans and pumps
The three terminals of the star winding are connected and a voltage is applied between these terminals to neutral with the Delta winding left floating. Zero sequence impedance value in ohms is equal to three times V/I where V is the single phase voltage applied and I being the resultant current.
simply the product of the sound pressure measurements and the radiating surface area. A formula involving logarithms as for all evaluations relating to sound level is contained in the standards. Complications and refinements to this principle have arisen more frequently with more and more importance paid to this aspect of performance because of residential noise pollution. Firstly, a more sensitive test in the form of sound intensity measurements is thus possible and used sometimes, especially where the sound power levels are in the order of 70 dBA. Whilst its results are easily verifiable by simple arithmetic, the volume of data and the testing technique are such that only a computerized output is normally useful. Another aspect is that of sound under load. The conventional sound is the result of magnetostriction of the core plates and a direct function of flux density in the core. Windings also have a sound, which depends on the amount of current flowing through them. Indeed, windings move under load and that sound of winding vibration can be rather significant. It is ascertained during load loss testing or temperature rise testing. A formula is provided in the standards to adjust for the appropriate level of current and to permit combining the two sound levels of core and windings to produce just one figure as the guarantee. The noise level is an environmental issue and is necessary where transformer noise may become objectionable. The loss measurements for auxiliary pumps and fans depend upon the cooling method used for the transformers.
IEC does not categorize the transformers based on voltage. However as per ANSI, Class 1 power transformers are upto 69 kV while Class 2 power transformers are for voltages between 115 and 765 kV.
6.5.3
IEC Typical impedances Rated KVA %Z Upto 630 631-1250 1251-3150 3151-6300 6301-12500 12501-25000 250001200000 4.0% 5.0% 6.25% 7.15% 8.35% 10.0% 12.5%
HV BIL 60-110 150 200 250 350 450 550 650 750
ANSI C57 Values Without OLTC With OLTC LV LV LV >2400 V 420V >2400 V ---5.5 5.75 7.0 6.5 6.75 7.5 7.0 7.25 8.0 7.5 7.75 8.5 8.0 --9.0 8.5 --9.5 9.0 --10.0 9.5 --10.5 10.0 ---
6.5.4
Cooling classification
Liquid filled transformers are defined based on the cooling methods. Natural cooling is termed as ONAN. Adding Fans for forced air-cooling will make the transformer ONAN/ONAF. Where forced liquid cooling is employed the transformer capacity is specified for ONAN/ONAF/OFAF conditions. In case of ANSI/IEEE, these are termed as OA, OA/FA and OA/FA/FOA respectively. Aircooled transformers have similar classifications. AN in IEC refers to self-cooling while ANSI indicates it as AA. The forced air-cooling in the two standards is AF and AFA respectively. To AS/IEC, a further cooling mode variation to OFAF is frequently used, namely ODAF. With that cooling mode, oil is not just forced into the transformer but also through the windings. Where that cooling mode is employed and is proven by special oil guiding components, a winding temperature rise of 70C is permissible in lieu of 65C.
IEC Class A (105) E (120) B (130) F (155) H (185) C (220) Max temp rise in C 65 75 80 100 125 150 Class 130 150 185 200 220
6.5.6
Guaranteed figures
Manufacturers normally guarantee the losses and impedance values subject to some tolerance. In case of IEC, the tolerance levels specified are marginally higher compared to ANSI. In case of impedance values IEC specifies an acceptable tolerance of 7.5% for more than 10% Z and 10 % for less than 10% Z. ANSI specifies 7.5% tolerance for dry type. In case of liquidfilled type the tolerance is 7.5% if IZ > 2.5% and 10% for IZ < 2.5%. Referring to the losses, IEC specifies the tolerance of +10% for total losses. But IEC allows +15% tolerance on individual components like no-load and load loss provided the +10% overall loss tolerance is not exceeded. On the other hand, ANSI is stricter with a figure of +6% for total losses with a +10% tolerance for component losses. In regard to the voltage ratio, both the standards allow a tolerance of +0.5%. Specifications also contain almost always a method whereby the loss-performance is included in tender evaluations such that load and no-load losses multiplied by the specified rates ($/kW) are added to the tender price for the purpose of tender evaluation. If the guaranteed losses should be exceeded on test, corresponding liquidated damages are generally levied.
6.5.7
Test values
Because of the varying voltage levels, the respective standards identify the lightning impulse and power frequency based on the applicable ratings/categories in tabular form. Generally IEC levels are marginally (around 10%) lower compared to ANSI values for these figures. Routine tests and type tests are almost the same in both standards but their applicability differs. For example, Lightning impulse test, which is a type test per IEC is a routine test for ANSI class 2 power transformers. At the same time ANSI does not consider the resistance test, impedance and load loss measurement tests as routine tests for transformers rated 500 kVA and below.
6.5.8 General
Both standards identify specific details to be furnished in the respective transformers. The standards also list out the standard accessories, which are not so different.
In general it may be noted that the standards do not differ much and normally a transformer tested in one standard may be able to provide the same kind of service like the transformer manufactured and/or tested to the other standard.
6.6
Tests on parts
6.7
Viscosity at 40C Minimum flash point Maximum pour point Maximum Neutralisation value
Maximum acidity Maximum water content Min. Electric strength Dielectric dissipation Factor
11 Dielectric Strength (kV/mm) 10 9 8 7 6 5 4 3 0 5000 10000 15000 20000 25000 30000 Particles per 100 ml of Oil Dry Fibres Wet Fibres Metal Particles
Oil w ith 60 micron fibres, approx. 50 g/t Filtered Oil, approx. 20 g/t particles 40 60 80 100
6.7.4 Color
New oil is relatively clear and the change in oil color over a period of service is inspected. The lab test is conducted by comparing a sample of oil to some colour standards and applies to all types of oil including transformer oil. The color is expressed in a numeral value and a value about 3.5 is generally acceptable. If appreciable change in color is noticed (value exceeds 3.5 denoting darker oil), it may indicate the presence of contaminations.
6.7.9 Viscosity
Viscosity is a measure of resistance offered by oil to flow without any external forces. The transformer cooling is achieved by radiators, which in turn depend on the mobility of hot oil at
top and relatively cooler oil at bottom. Normally viscosity increases with decreasing temperature and hence the viscosity shall be as low as possible at low temperatures.
6.7.13
Furans are a family of chemical compounds that get released and dissolved in the oil when cellulose insulation decomposes due to overheating, oxidation, reactions with acid, moisture and oxygen. Furanic content in oil is a reliable method of estimating the remaining life of the paper insulation. When the furans become greater than 250 parts per billion, it can be judged that paper insulation is getting deteriorated and consequently the life of the transformer is getting reduced at a higher rate. The most important of Furan compounds is 2-furfuraldehyde. In healthy transformers, there are no detectable furans in oil, or they are in negligible quantities. In those cases where deterioration
of paper insulation has taken place, furan levels can be found to be in the range of 100 ppb to 70,000 ppb (ppb - parts per billion). Testing is performed for five different furans caused by different problems. The five furans and their most common causes are as follows. 5H2F (5-hydroxymethyl 1-2-furaldehyde) caused by oxidation (aging and heating of paper insulation 2FOL (2-furfurol) caused by high moisture content in paper 2FAL (2-furaldehyde) caused by overheating of paper 2ACF (2-acetylfuran) caused by lightning (rarely observed in DGA) 5M2F (5-methyl-2-furaldehyde) caused by local severe overheating (hot spots) Table 6.4 gives the relationships between Furans, DP (degree of polymerization) and the estimated percentage of remaining life. However for diagnosing the problem, judgment should not be based only on Furan test. To be on the safe side, dissolved gas analysis should also be performed over a period of time and trending should be done on the results of the DGA analysis.
Table 6.4
55C Rise transformer 2FAL (ppb) 58 130 292 654 1464 1720 2021 2374 2789 3277 3851 4524 5315 6245 7337
65C Rise Transformer Total Furans (ppb) 51 100 195 381 745 852 974 1113 1273 1455 1664 1902 2175 2487 2843
Estimated degree of Polymerization (DP) 800 700 600 500 400 380 360 340 320 300 280 260 240 220 200
Interpretation
Excessive aging rate High rate of failure End of expected life of paper insulation
Insulation paper is tested by taking sample of the paper insulation from the transformer windings. This necessitates opening up the transformer to perform the DP test. Hence it is advisable not to open the transformer only for the purpose of performing the DP test. DP test can be performed when the transformer is opened for some other reason. A sample of paper of approximately 1 cm2 size is removed from a convenient location at the top from the center phase winding with a pair of tweezers. Top of the center phase is chosen for sampling since the insulation at that location is subjected to the hottest condition and therefore is expected to be thermally aged more. The sample should be sent to a laboratory for performing the DP test. The results of the DP test can be analyzed using Table 6.5 which shows the remaining life of the insulation in relation to the DP values.
Table 6.5
DP and percent of remaining paper life (Courtesy EPRI's Guidelines for the Life extension of Substations)
New insulation material 60% to 66% remaining life 30% remaining life Zero remaining life
6.8
Table 6.5
Site Acceptance tests Oil Dielectric breakdown voltage test Insulation Resistance test between windings and windings to earth
Ratio check at normal tap and other taps Winding Resistance Pressure test if transformer is supplied with inert gas. Power factor (DDF) test for above 15KV windings rated above 10 MVA Oil sample test Accessories test
Test criteria and Acceptable values Normally with disc or spherical electrodes having 2.5mm spacing 30 KV minimum acceptable voltage With 1000V DC megger upto 600V, 2500V DC megger between 601 to 5000V and 5000V DC megger above 5001. For oil filled transformers the IR values shall be as below for these three categories. Oil filled: 100 Meg Ohm upto 600V, 1000 Meg Ohm 5000V and 5000 Mega Ohm beyond 5000V. Dry Type: Five times the above figures. Values shall be within 0.5% of the calculated values, same as the factory tests. Cross check for conformance with factory tests. At least 6 pounds pressure for 12 hours minimum and check for any leaks using soap solution around seals and gaskets. Ensure the values are below 0.5% In an approved laboratory and ensure the test values are within acceptable figures given earlier. Ensure proper operation of all accessories, relays, pressure relief device, gauges, etc.
b) Polarisation index value (10 minutes IR to 1 minute IR) shall be found which shall exceed 1.5 c) Turns ratio test on all tap positions to be found and shall not deviate more than 0.5% of the voltage ratio requirement. d) Power factor test values shall be found and shall not exceed 0.5% for oil filled transformers and shall be within 1.0% for dry transformers. e) Dielectric test results shall comply with the following. Dielectric breakdown voltage 35kV minimum below 69kV, and 30kV minimum for 69 kV upwards. Neutralisation number 0.025 mgKOH/gm maximum. Interfacial tension 35 dynes/cm minimum. Color 1.0 maximum. Winding resistance values shall not exceed 1.0% for adjacent windings and comparable overall. AC High voltage potential test not exceeding 75% of the factory test values.
Table 6.6
Nominal voltage
Insulation Class
10 15 19 26 34 40 50 70 95
7 Transformer Installation
7.1
Figure 7.1
The layout of the plant also depends on the size of the plot, layout of various process areas, load center importance, etc. The schemes shown in Figure 7.1 may be practically spread out over a small or vast area, generally in line with Figure 7.2.
Figure 7.2
7.2
Transformer layouts
In designing the layout and installations of transformers, the following are the main factors to be considered: whether Indoor or outdoor ventilation requirements possibilities of fire hazards noise considerations
7.3
Indoor locations
In locating a transformer indoors, decisions on the following are essential: Oil draining facilities Containment during oil drain Requirement of forced ventilation Approach Removal facilities, when required.
It is quite uncommon to have high capacity transformers mounted indoors mainly because of the space limitation, fire hazard conditions, maintainability, etc. Also the transformers with EHV bushings in the order of 66 kV and above are mounted outdoor because of the simplicity in bringing the conductors by overhead lines. The insulated cable connections at these voltages are uneconomical, non-feasible and also pose a lot of limitations in routing large sized cables. Hence it can be presumed that a transformer is normally mounted outdoor if it is having EHV bushings, unless special requirements demand otherwise.
There are many methods of avoiding or at the very least minimizing the risk of such hazards. Conventionally, it has been a general practice in many substations that employ oil filled transformers and switchgear, to provide surfaces of chipping and a drainage sump to transport away any oil spillage that could potentially fuel a fire. This method however is not foolproof. It has been found that over a period of time, these chipping collect dust and grime and this grime would provide the wick for sustained combustion. Alternatively, one could explore the possibility of providing a firewater sprinkler system around the transformer, which could be automatically triggered in the event of a fire. Note that water displaces oil and any old oil spillage would be washed up from the sump. Therefore, it is imperative that this large quantity of excess oil and water be carted away as quickly as possible to deluge water treatment centers before allowing the water to enter into storm water drains. Provision should be made to separate oil from water and for containment before this separation. Additional precautions, such as separation or segregation, may also be considered if the above solutions are not feasible. Separation involves locating the transformer well away from all other equipment, but this may not be convenient, as there may be space constraints. On the other hand, segregation calls for firewalls to be built around transformers such that fires, if any, would be contained within the walls. This firewall or barrier must be suitably reinforced to be capable of withstanding any explosion from the transformer. The main reason for such separation and segregation requirements is because in the event of transformer oil igniting (for whatever reason), the damage caused shall be restricted to the transformer alone and its immediate ancillary equipment, and shall not interfere with any other unit assemblies in its vicinity. It would be necessary that the layout shall have provisions to completely drain out the oil, which is normally done by providing oil soak pits with adequate capacity. Further the oil cannot be allowed to leak inside the room or other factory areas. In order to install transformers within buildings, it is a general practice that one uses dry type resin encapsulated units rather than using liquid-filled transformers to overcome most of the above issues in one shot. Again cost could play a role in such decisions.
7.3.2 Ventilation
Once it is decided to have transformers indoors, whether oil filled or dry type, then adequate ventilation and physical isolation is required. Physical isolation is mainly for oil-filled ones but ventilation is a main requirement for indoor transformers. The main issue with ventilation is insufficient or non-availability of free air to cool the transformer. Hence, transformer windings reach their maximum permissible temperatures with loads as low as 50%. It is recommended that the transformer room is provided with open doors and ventilation fans to enforce forced cooling, if the layout does not allow natural free flow of air across the transformer body. The room in which transformers are placed must have ventilation arrangements to ensure that heated air escapes readily and can be replaced by cool air. Inlet openings should be near the flow and distributed to be most effective. The outlet opening(s) should be as high above the apparatus as the construction of the building will permit. The number and size of outlets required will depend on their distance above the transformer and on the efficiency and load cycle of the apparatus. In general, about 60 square feet of outlet opening or openings should be provided for each 1000 kVA of transformer capacity. Air inlets should be provided with the same total area as the outlets. Self-cooled transformers should always be separated from one another and from adjacent walls, partitions, etc. in order to permit free circulation of air about the tanks. This separation should not be less than 750 mm and shall preferably be around 1 meter.
A typical transformer mounted indoors with such arrangements is given in Figure 7.3. It is to be noted that forced ventilation shall allow cross-flow of air from one end to other end of the transformer.
Figure 7.3
The dielectric must have a fire point above 300C to be classified as a fire resistant fluid The dielectric must not contribute to or increase the spread of an external fire nor must the products of combustion be toxic Normal operation, electrical discharges or severe arcing within the transformer must not generate fumes or other products that are toxic or corrosive This does not mean that liquid-filled transformers cannot be used within buildings. They would meet all of the above criteria and in addition are cheaper and smaller than cast-resin or other dry type units. However there must be a provision for total spillage of the dielectric with suitable sumps and/or bunded catchment areas, such that in the event that spillage occurs the building drains would not be flooded with the dielectric liquids. If the transformers are installed on higher levels, then suitable precautions must be taken to prevent leakages to lower floors. On the other hand the building must be made totally weatherproof and care taken to ensure that there should be no deluges due to pipe leaks on dry type of transformers, after installation. Needless to say, every installation should have proper ventilation. It is necessary to take samples of the insulating liquid from the top and bottom of the tank and test its dielectric strength. The dielectric strength should be 30 kV or higher. If it is lower, the transformer should not be placed in service until the dielectric strength has been restored by filtration. In the case of pressurized and sealed transformers, it is common that a pressure vacuum gauge if supplied along with transformer could read negative due to lower temperature at the site of installation, compared to the ambient temperature at which it is sealed. This is not an indication of an abnormality, but in fact an indication that the tank is properly sealed.
7.4
Outdoor installation
It is also common practice to have large size transformers located away from the center of the active plant area. This is due to overhead conductors associated with EHV connections, which cannot be taken inside the plant area. Hence proper fencing and access restrictions shall be necessary in these installations. It is also a recommended practice and some times statutory to have firewalls between transformers, when the installation includes multiple transformers adjoining each other. This is to ensure that an oil explosion in one transformer is not carried over to the other transformers. For outdoor installations, a level concrete plinth of correct size to accommodate the transformer in such a way that no person may step on the plinth should be provided for transformers. Further the access requirements are the same as per indoor transformers and should be adopted. i.e., the breather, oil level indicator, rating and diagram plate, dial thermometers etc, are to be accessible for safe examination with the transformer energized. It should also be possible to have safe access to the operating mechanisms of the on-load tap changer/off circuit tap switch, marshalling box etc. The sampling valve, drain valve, etc. should also be at convenient locations. It is generally approved to have a clearance of about 750 mm to 1000 mm all around transformers to allow access from any side and also to ensure proper cooling. These clearances do not normally increase with the increase in transformer capacities. Though it is not mandatory in some countries, it is practised to have 2 hour fire rated walls between transformers which are mounted side by side. These walls are called blast wall/ fire wall and the main purpose of the wall is to basically prevent oil splash over to the adjacent transformer in case of severe faults leading to transformer blasts and fires. Normally installations having multiple transformers have standby transformers and in such cases it is very important to ensure that these walls are provided to minimize breakdowns in power supply. Also it is very necessary to ensure that the oil drained out under emergency conditions are taken in bunds and are not disposed to storm water drains. This is mainly an environmental issue with many Governments introducing legislations for transformer bunding and safe oil disposals without polluting the surroundings. If any oil-filled transformers are used in the power plant, provisions are made to contain any oil leakage or spillage resulting from a ruptured tank or a broken drain valve. The volume of the containment should be sufficient to retain all of the oil in the transformer to prevent spillage into waterways or contamination of soil around the transformer foundations. Special provisions (oilwater separators, oil traps, etc.) must be made to allow for separation of oil spillage versus normal water runoff from storms, etc. IEEE 979 and 980 provide guidance on design considerations for oil containment systems.
In such installations, it will be very important to ensure that creepage distances are comparatively higher than those for standard installations. Table 7.1 gives the creepage distances of bushings recommended for non-polluted and polluted atmospheric surroundings. The creepage distance is about 1.5 times for polluted atmosphere (~ 15/16 inch/kV) compared to normal atmosphere (5/8 inch/kV). Some time outdoor bushings are provided with arcing horns.
Table 7.1
Highest System Voltage (kV) 3.6 7.2 12 24 36 72 123 145 245 420
Creepage distance for Normal atmosphere (mm) 95 130 230 380 580 1100 1850 2250 3800 6480
Creepage distance for polluted atmosphere (mm) 130 230 380 560 840 1700 2800 3400 5600 9660
7.5
Core-and-coil assembly
It is also preferable to check the condition of a transformer core and coil assembly, if the transformer had been kept in non-energized condition for long periods of time. In such cases, the insulating liquid shall be lowered to the top of the core-and-coil assembly and the interior shall be inspected for any possible damage. It is preferable that the coils and insulation are not exposed to the air during such inspections. Examine the top of the core-and-coil assembly, all horizontal surfaces and the underside of the cover for signs of moisture. If there are no signs of moisture or damage, proceed with the reassembly of the transformer. If there are signs of moisture inside the tanks, steps should be taken to determine the extent of it and the manner in which the moisture entered the transformer. Reassembly should be carried through and the manufacturer of the equipment should be requested to make recommendations concerning further checks and steps for drying out the transformer.
7.6
Noise considerations
Transformer noise is caused by a phenomenon called magnetostriction. When a piece of magnetic sheet steel is magnetized it undergoes extension and goes back to its original condition once the magnetic force is removed. All transformers operate on AC systems, which means that the magnetic circuit also undergoes the cyclic changes in line with the supply frequency. The extension and contraction of these sheets is not uniform throughout the length of the sheet due to the irregular concentration of impurities and hence the expansion/contraction varies along the length of the sheet. The extensions and contractions happening are not visible to the human eye but are sufficient enough to cause vibrations of the molecules forming the sheet steel. These vibrations are transferred in the form of noise, which we hear from the transformer. The level of this noise depends on the magnetic flux produced by the system voltage, which cannot be reduced beyond the minimum required values. The noise level is also due to the varying properties of steel over the length of the sheet, which is also unavoidable.
In every full AC cycle the magnetic core extends and contracts twice. That is for a 50 Hz system, the transformer core internal particles will be vibrating at twice the frequency of the supply i.e. at 100 Hz and this frequency of vibrations is called the fundamental noise frequency of the transformer. Further, due to the natural non-uniformity in the materials, the resultant noise also has harmonics similar to the supply system with odd multiples of frequency. So in a standard 50 Hz operation, we get noise frequencies of 100 (1st), 300 (3rd), 500 (5th), 700 (7th) cycles per second and so on. However, the major contributors of sound are the fundamental and third multiple noise frequencies while other frequencies are low. Further the noise level does not increase with the increase in load current and hence a transformer will have almost same noise irrespective of load conditions. The transformer sound levels are measured in terms of decibels (dB) and this measurement has to be done at various parts of the transformer since the sound emitted is not uniform. Normally the measurements are done at 3 feet or 1 meter from the body, by sound measuring devices along the periphery/contour of the transformer. It is to be remembered that an absolute value of outside ambient sound measurement taken with the transformer un-energized and the values measured after energizing are suitably adjusted to get the real sound contribution from the transformer. It is observed that the vibrations basically produce the noise and hence a transformer installation shall consider limiting these vibrations as well as limiting the transfer of these vibrations as much as possible. Hence transformer installation practices play an important role in limiting the transfer of vibration levels, thereby cutting down the noise level to the maximum possible extent. The main practice to be followed is to isolate the core and coils of the transformer from the ground so that the vibrations are not transferred through the foundation. In air- cooled dry types this means to isolate the core and coil of the transformers from its support on the ground. For an oil-filled transformer it is achieved by isolating the core and coil from its tank base, and isolating the transformer tank base from the supporting ground. Following guidelines could be helpful in containing these vibrations and the resultant sound. Use vibrating materials, which are guaranteed to eliminate transformer noise frequencies (at 100 Hz and above). The best practice is to use anti-vibration pads. Any solid connection from the vibrating transformer to a solid structure will transmit vibration. Hence ensure that all connections to solid terminations are not rigid but flexible. This includes incoming cables, bus bars, stand off insulators, etc. The shipping bolts shall be removed at the time of installation so that they do not short circuit anti-vibration pads. Where the transformers are installed indoors, adequate acoustic treatment would be required on the walls and ceilings to ensure that the noise levels are not transferred to outside areas. If steel plates are used for enclosures, ensure that they are properly gasketed. The fastening down bolts shall be isolated.
7.7
avoided. Connections must be made without placing mechanical tension or torques directly on the terminals. Minimum phase-to-phase and phase-to-ground clearances shall be maintained. Bolted connections shall be protected against corrosion. It is recommended to use torque wrenches to ensure proper tightening torques. A torque of 45~60 Nm for M12 bolts and 90~120 Nm for M16 bolts is recommended. Use of spring washers is to be ensured to compensate for thermal expansions and to maintain contact pressures. In corrosive areas like sulphurous atmosphere, the joints shall be treated with jointing compound.
7.8
7.9
Lifting of a transformer is to be done carefully and the use of cranes is recommended considering the weight and importance of the equipment. The recommended lifting arrangement is as per Figure 7.4.
Figure 7.4
Lifting of Transformer
Hydraulic jacks shall be employed at the jacking points provided in the transformer, when required for transferring from the truck and when fastening or turning transport rollers. During such times care must be taken to lift not more than 2 inches at every point so that no torsional strains are imposed. Earthing of transformer body is a must and it shall be ensured that proper earthing connections are provided at the transformer yard. Transformers received at site and not installed immediately are likely to absorb moisture. Hence it is desirable to erect and commission the transformer with minimum delay. However this may not always be the case. If an oil-filled, indoor-type transformer is stored outdoors for a considerable duration, it should be thoroughly covered to keep out rain. A transformer should not be stored or operated in the presence of corrosive vapors or gases, such as chlorine. Should it become necessary to store accessories for a long period of time, they should be stored in a clean, dry place or the manufacturer should be contacted for explicit instructions on the storage of individual pieces.
Voltage ratio test This is required to ensure that all the connections are intact and the windings and tap connections are not disturbed during transport. This test is to be carried out at all tap points. Vector Group test This is another test to check the integrity of connections and ensure that the vector group meets the specification requirements. Insulation resistance test The tests are to be carried out on all the winding terminals to ground. A typical test arrangement is shown in Figure 7.5
Figure 7.5
The values are to be obtained by applying the voltage continuously for 60 seconds. Normally 1kV megger is used upto 6.6 kV and 2.5 kV / 5 kV megger is used for higher voltage transformer windings. The test results at different ambient temperatures shall be corrected to base temperature say 20C. Table 7.2 gives the correction factors for the various temperatures.
Table 7.2
Correction factor 0.13 0.18 0.25 0.36 0.5 0.75 1.0 1.4 1.98 2.80 3.95 5.60 7.85
It can be seen that the IR values obtained vary inversely with respect to ambient temperature. The 60-second IR value corrected to 20C shall be a minimum of 100 Mega ohms. Further, the IR readings at 15 seconds shall also be taken. The value of IR at 60 seconds shall be 1.2 to 3 times the 15 second value. A value less than 1.2 indicates the possibility of moisture presence in transformer insulation.
Oil testing The oil sample shall be sent to an approved laboratory to verify its contents. At the same time it is also necessary to filter the transformer when the installation takes a long time (normally the case). The oil dielectric strength shall be tested and ensured that they meet minimum requirements.
7.12 Commissioning
If all the above pre-commissioning tests/checks are found satisfactory, allow settling time of at least 24 hours for oil and release air from all points. Ensure the following just at the time of commissioning, which may require repeating some of the pre-commissioning checks considered in the earlier clause. Are feeder cables/overhead lines connected to bushing terminals without stressing the porcelains? Are winding neutral terminals properly grounded or ungrounded as required by system operation? Is tank solidly grounded at grounding pads located near the bottom of the tank? Are all current transformers connected to a load or short-circuited at the secondaries? Open secondaries can produce voltages dangerous to humans and connected equipment. Is the tap changer/tap switch set in desired position to give desired voltage ratio and locked for off circuit switch? Have all tools and foreign objects been removed from the transformer? Are all openings and joints sealed? Is insulating liquid at proper level in tank? Also check the levels in other liquid-filled compartments (if applicable). Are all fans and control circuits (if supplied) operational? Is insulating dielectric strength of oil at least 30 kV? Are all personnel away from the transformer? Are fire protective devices in place? Once the above conditions are satisfied, the commissioning can take place in steps. Following are the recommended steps for commissioning. Energize the transformer at no-load with the tap changer at normal position, after setting the protective relays to the minimum extent possible. The voltage should be built up in steps wherever possible. Check whether the primary voltages and currents are balanced. Also check if there is any undue noise or vibration during commissioning and try to find the causes, whether internal or external. After a few hours of energizing at no load, the transformer should be switched off. The following checks and corrections shall be taken up. The Buchholz relay should be checked for collection of air/gas. Abnormalities noticed should be corrected. All protective relays should be reset to normal values. The transformer can now be permanently energized and loaded gradually checking and ensuring the following. Check whether the voltage and currents on the HV & LV sides are balanced. Increase the load to the rated value and check that the noise is not appreciable. A good transformer operates with a healthy hum.
Observe the operation for a few hours and ensure there is no appreciable increase in temperatures. If the operation is satisfactory, the transformer is kept on load and readings of voltage and currents on all the phases of both HV & LV sides are checked. Check and record the temperature of top oil at regular intervals.
Alarm 85 C 95 C
Trip 90 C 105 C
Fan setting 80 C
Protective and functional requirements are complied with under expected conditions Earth fault currents and earth leakage currents can be carried without danger including thermal, thermo-mechanical and electromechanical stresses Adequate strength or additional mechanical protection appropriate to the assessed external influences Value of earthing resistance is in accordance with the protective and functional requirements of the installation and is continuously effective Figure 7.6 shows a typical earthing system.
Figure 7.7
Earth electrodes of the following types shall be used Vertical driven rods or pipes not less than 1.8 m into the ground Horizontal grid, mesh or plates Electrodes embedded in foundations Metallic reinforcement of concrete The type of earth electrode and its embedded depth shall be such that, the earth resistance will not rise above the maximum limit value. Increase in resistance due to corrosion over a period of time should be taken into account in the design and material of construction of the electrodes. In locations where corrosion is expected to be severe, electrodes shall be made of hard drawn copper, copper clad or stainless steel or other material exhibiting equivalent properties. In places where corrosion is not severe, galvanized or plain steel electrodes may be used. Aluminum shall not be used as a buried electrode.
Touch voltage is the voltage which appears between any point of contact with uninsulated metal work located within 2.5 metres from the surface of the ground and any point on the surface of the ground within a horizontal distance of 1.25 metres from the vertical projection of the point of contact with the uninsulated metal work. Refer to figure 7.7. Where works are installed in a special location or a frequented location, the touch voltages shall be within the limits set as following
Special Locations
- Works installed in special locations and operating at voltages not exceeding 66kV shall comply with the requirements of curve A1 shown in figure 7.8. - Works installed in special locations and operating at voltages exceeding 66kV shall comply with the requirements of curve A2 shown in figure 7.8. These requirements shall not apply to any lines and associated fittings operating at or above a voltage of 66kV
Frequented Locations
- Works installed in frequented locations and operating at voltages not exceeding 66kV shall comply with the requirements of curve B1 shown in figure 7.8. - Works installed in frequented locations and operating at voltages exceeding 66kV shall comply with the requirements of curve B2 shown in figure 7.8. These requirements shall not apply to any lines and associated fittings operating at or above a voltage of 66kV.
The power system neutral earth is provided by the interconnection of the station earthing system with the power system neutral. Power system neutral earthing shall comprise one of the following connections A solid connection, usually to a transformer star point An impedance connection employing a resistance, a reactance or an earthing transformer The earthing of the power system neutral shall Provide an earth reference for the power system Prevent abnormal system over voltages during intermittent earth faults and Permit the selective operation of current operated earth fault protection
Reduce the probability of mechanical damage Minimize the impact of minor corrosion Have adequate current carrying capacity The earthing systems should be upgraded wherever the fault levels increase above the original design level Necessary allowances shall be made for current distribution in the earthing system
Figure 7.9 Fault Duration Levels for Standard Aluminium and Copper non tensioned Earthing Conductors
Figure 7.11 Recommended earthing arrangement for air break isolator with other apparatus
Figure 7.12 Recommended earthing arrangement for lightning arresters (surge diverters)
Figure 7.13