PMP 15min Guide
PMP 15min Guide
com
1-800-418-6789
www.preplogic.com
1-800-418-6789
A product life cycle describes the phases through which a product progresses from inception (idea) to end-of-life (obsolescence). The project life cycle will intersect with the product life cycle at various points in the ongoing life of a product Stakeholders are many and various. Their wants, needs, and desires shape project requirements and influence project performance. The culture and structure of a performing organization influences (constrains) the ways in which work on a project can be performed.
PrepLogic
15-Minute Guide
TM
identifies the business needs that will be met by the project; documents the product requirements and characteristics of the product or service that the project will deliver; and demonstrates how the product or service supports the performing
1-800-418-6789 www.preplogic.com
=
PrepLogic
www.preplogic.com
1-800-418-6789
organizations strategic plan. Enterprise Environmental Factors Any or all external environmental factors and internal organizational factors that surround or influence the projects success. Organizational Process Assets Any or all process-related assets, from any or all of the organizations involved in the project that are or can be used to influence the projects success.
WBS
Work Breakdown Structure (WBS) A deliverable-oriented hierarchical decomposition of the work to be executed by the project team to accomplish the project objectives and create the required deliverables. It organizes and defines the total scope of the project.
identify that a change has occurred or needs to occur; ensure that only approved changes are implemented by influencing those elements that may circumvent integrated change control; and coordinate all approved changes across the project as they affect interdependent, interconnected or related components of the project.
Activity Sequencing
The Precedence Diagramming Method (PDM), also known as activity-on-node (AON), uses a node and arrow convention to model the relationships between schedule activities. The nodes are depicted using boxes or rectangles that represent activities. Activities are connected with arrows that represent dependencies between the activities. The PDM can be used to model four different types of dependency relationships in which one activity cannot commence or finish until the preceding activity has either started or ended. These relationships are defined as: Finish-to-Start The predecessor activity must finish before the successor activity can commence; Finish-to- Finish The predecessor activity must finish before the successor activity can finish; Start-to-Start The predecessor activity must start before the successor activity can start; and
Configuration Identification provides the basis by which product configuration is defined and verified, products and documents are labeled (i.e. version, series, etc.), changes are managed and accountability is identified and maintained; Configuration Status Accounting assures the capture, storage and retrieval of configuration management information required to effectively manage both the product and information about the product; and Configuration Verification and Auditing establishes that the performance and functional requirements defined in the configuration documen-
1-800-418-6789 www.preplogic.com
=
PrepLogic
www.preplogic.com
1-800-418-6789
Start-to-Finish - The predecessor activity must start before the successor activity can finish. A lag applies a delay to the successor activity A lead accelerates the successor activity. The Arrow Diagramming Method (ADM), also known as activity-on-arrow (AOA), uses an arrow and node convention to model the relationship between schedule activities. Arrows represent the schedule activities. The connection of arrows to nodes represents dependencies. Note that this is the opposite of the PDM convention. ADM is less commonly used than PDM diagramming and is characterized by the following features:
g
Schedule Development
Forward pass involves calculating the early start (ES) and early finish (EF) dates by moving forward, from left (start) to right (finish), through the network diagram. Formula: EF = ES + duration The early finish date is calculated by adding the duration of the activity to the early start date. Backward pass involves calculating the late start (LS) and late finish (LF) dates by moving backward, from right (finish) to left (start) through the network diagram. Formula: LS = LF duration The late start date is calculated by subtracting the duration of the activity from the late finish date. Flexibility in the project schedule is represented by float (or slack) in the network paths. Float is defined by the amount of time that a schedule activity can be delayed without delaying the project. Float can be calculated using either late start and early start dates or late finish and early finish dates. Remember these for the exam: Formula: Float = LS ES or Formula: Float = LF EF There are two kinds of float. Memorize these. Do not confuse the two: Free float represents the amount of time that a predecessor schedule activity can be delayed without delaying the early start of the successor schedule activity; Total float represents the amount of time that a schedule activity can be delayed from its early start date without delaying the project completion date. Where a project needs to meet imposed dates or other schedule constraints, schedule compression techniques can be used to shorten the project schedule while maintaining the scope of the project. Two compression methods are commonly used: Crashing in which additional resources are applied to shorten the duration of critical path tasks. This usually implies an increase in cost to pay for additional staff, buy additional work hours (overtime) or purchase technology. Fast Tracking in which tasks that are normally performed serially are performed in parallel. This can result in tasks being removed from the critical path.
ADM diagrams incorporate dummy relationships (using dummy activities); and only finish-to-start dependencies are used in ADM diagrams.
A dummy activity is a schedule activity of zero duration with no actual work content. Project Schedule Network Templates based on previous projects may be used by the project team to create the schedule network diagram. There are three types of logical relationships or dependencies: Mandatory (hard logic) dependencies that are defined by the inherent or physical characteristics of the work to be performed. Discretionary (soft logic) also referred to as preferred or preferential logic, are dependencies established by best practices generally followed in a specific application area or may be preferred according to the circumstances of the project. External dependencies that arise from the relationship between project schedule activities and non- or external project activities.
1-800-418-6789 www.preplogic.com
=
PrepLogic
www.preplogic.com
1-800-418-6789
The output from the schedule development process is the Project Schedule, which can be presented in one or more of the following formats:
g
The Cost Management Plan defines how the following criteria will be applied to the project:
g
Milestone chart presents the start and end dates for the projects major deliverables (milestones) in a bar chart format; Bar (or GANTT) chart presents both the start and end dates for project schedule activities and their durations in a bar char format. Project schedule network diagram presents both the critical path and the network logic relationships using an AON diagram format.
Units of measurement identifies the base units that will be used for measuring resource utilization; for example, hours, days, weeks, etc. for staff; dollars, euros, etc. for costs; Level of precision prescribes the precision to which schedule activity cost estimates will be recorded; for example, to within the nearest $100, $1,000, etc. Control thresholds prescribes the agreed variances in costs or time (schedule) that are tolerated when measurements are taken; Earned value rules describes the basis on which earned value techniques (EVT) will be applied to monitor project performance; Control account (CA) prescribes how work packages in the WBS will be linked to and tracked through the performing organizations accounting system. Report format defines the formats for the projects cost reports; Estimation, Budget & Control processes describes how the cost estimation, budget and control processes will be applied to the project.
Cost Estimating
Rough Order of Magnitude (ROM) is in a range of -50% to +100% from the expected or actual value; Order of Magnitude is in a range of -25% to +75% from the expected or actual value; Budget estimate is in a range of -10% to +25% from the expected or actual value; and Definitive estimate is in a range of -5% to +10% from the expected or actual value. The PMBOK identifies a number of inputs that are used in the estimating process, of which the following are the most important:
g
Present value the discounted value (i.e. the current value) of a future sum or stream of cash flows. This value is expressed by the formula PV = FV divided by 1 + r multiplied by n, where PV = Present Value, FV = Future Value, r = the interest rate and n = the number of time periods; Net Present Value (NPV) equal to the present value of the total benefits (which can be expressed as either revenue or income) of the project, minus the costs. Internal Rate of Return (IRR) the rate (expressed as an interest or discount rate) at which the value of the project inflows (revenues) and the project ou flows (costs) are exactly equal, or the rate at which the net present value = 0. Payback Period the length of time (usually expressed as time periods or number of years/months) required of a company to recover its initial investment in the project before it starts generating a profit, i.e. the time it takes to pay back the cost of the project. Benefit Cost Ratio (BCR) compares benefits to costs. Benefits can be expressed as either revenue or payback (not profit). If the BCR value is greater than 1, then the benefits of the project outweigh the costs; if the BCR value is less than 1, then the costs outweigh the benefits.
Project Scope Statement covers the totality of those elements that determine what the project will deliver and how it will deliver the projects products and services. Work Breakdown Structure (WBS) defines the scope and interrelationship of the projects component work packages. Risk register considers information on risk responses. The response to each risk identified in the projects Risk register will have a cost associated with it that needs to be taken into account when estimating costs. Schedule Management Plan Uses schedule activity resources
1-800-418-6789 www.preplogic.com
=
PrepLogic
www.preplogic.com
1-800-418-6789
and their respective durations as key inputs. Lessons Learned provides input to estimates based on the performance of previous, comparable projects. Project team knowledge Project team members can provide input to estimates based on their own experience and knowledge of similar projects.
Variances in both project cost and schedule are measured using the following formulae: Cost Variance (CV) measures the difference between the estimated value of the budgeted work accomplished and the actual cost of the work accomplished. It answers the question Are we on budget? Formula: EV minus AC = CV A negative CV value (-) indicates that the project is over budget, while a positive value (+) indicates that the project is under budget; and Schedule Variance (SV) - measures the difference between the estimated value of the budgeted work accomplished and the estimated value of the scheduled work that is to be accomplished. It answers the question Are we on schedule? Formula: EV minus PV = SV A negative SV value (-) indicates that the project is behind schedule, while a positive value (+) indicates that the project is ahead of schedule. The following indices are used to measure the projects cost and schedule performance: Cost Performance Index (CPI) indicates the rate of return that the project spend is yielding. It answers the question For every project dollar we spend, what is the project returning? Formula: EV divided by AC = CPI A CPI value greater than 1 indicates that for every dollar spent, the project is earning more than the project spend (that is, costs are running below estimated levels). A CPI value of less than 1 indicates that the project is spending more than it is earning (that is, costs are running ahead of the estimated levels). The CPI value indicates how efficiently the project is being run with respect to costs; and Schedule Performance Index (SPI) indicates the rate of project progress compared to the scheduled or planned progress. It answers the question If we continue at this rate, will we achieve our project end date as planned? Formula: EV divided by PV = SPI EV is also used to forecast performance, to help assess the cost, or amount, of the work remaining to complete the project. Budget at Completion (BAC) represents the total planned value of the project work, and it is therefore the sum of all of the budgeted work. Formula: total cumulative PV at completion (PVc) = BAC
Various estimating methods are used to develop the projects costs estimates. You should familiarize yourself with the following methods. Note how and when it is most appropriate to use each of the following methods: Analogous (or Top-Down) estimating uses the actual costs of similar, previous projects as the basis for estimating the cost of the current project. Parametric (or unit cost) estimating uses mathematical models to derive a scaled cost for the project, based on the parameters of the work to be performed. Bottom-Up estimating involves estimating the cost of individual work packages or individual schedule activities with the lowest level of detail.
Cost Control
g
Variance analysis in which the actual performance of project work is compared to planned or expected performance, and any variations are assessed as to their impact on the project. Variance analysis is most often performed on cost and schedule data, but can also include scope, quality, resource and risk assessment; Trend analysis in which project performance is assessed over time to determine if the projects performance is improving or deteriorating, or is within an acceptable range of variation; Earned value in which planned performance (the baseline) is compared to actual performance.
There are three main concepts in EV analysis. The purpose of these is to measure whether the value of project work performed at a given moment in time (when measurements are taken) is as planned. Earned Value (EV) the estimated value of the budgeted amount of the work actually accomplished or performed when performance is measured. This is alternatively known as the Budgeted Cost of Work Performed (BCWP); Planned Value (PV) the estimated value of the scheduled work that is to be accomplished or completed during the next reporting period. This is alternatively known as the Budgeted Cost of Work Scheduled (BCWS) ; and Actual Cost (AC) the total cost of the work actually accomplished in performing the project work when performance is measured. This is alternatively known as the Actual Cost of Work Performed (ACWP).
10
1-800-418-6789 www.preplogic.com
=
PrepLogic
www.preplogic.com
1-800-418-6789
Estimate at Completion (EAC) represents the currently expected total cost of the project when performance is measured and applies the current spend rate (expressed in the CPI value) to the total budget, to derive an estimate of what the project will cost at this rate. Formula: BAC divided by CPI = EAC Estimate to Complete (ETC) represents an estimate of how much it will cost to complete the project from this point (when performance is measured) forward. The cost of the work actually accomplished is subtracted from the expected total cost of the project, to derive an estimate of how much more it is now expected to cost to complete the project. Formula: EAC minus AC = ETC
Precision and accuracy are not equivalent the principle that precision is defined by observed consistency that the value of repeated measurements are closely clustered and exhibit minimal scatter or dispersion when plotted. The Cost of Quality (COQ) includes all of the costs related to quality the principle, formulated by Joseph M. Juran, that the cost of quality includes both the cost of conformance and the cost of nonconformance. Conformance costs include all prevention and appraisal costs associated with investing in proactive measures designed to assure delivery of quality requirements (validated by customer acceptance). ISO 9000 provides for the establishment of quality systems within organizations, and it is administered by the International Organization for Standardization (ISO). Total Quality Management (TQM) based on the principle that if quality requirements are met, then customer requirements are met, TQM provides the primary focus for the ways in which a performing organization will strive to meet those requirements. Six Sigma an approach to quality management that emphasizes continuous process improvement using statistical measurement to guide improvements and focuses on identifying and solving the root causes of problems.
Plan the task or activity, specifying the desired outcome; Do the task or activity, as defined in the plan; Check the results of the task or activity against the desired outcome; and Act to correct or amend the task or activity if the results did not meet the desired outcome.
Quality means satisfying customer requirements the principle that customer requirements define the scope of the quality attributes that need to be met by the project. Because customer satisfaction is based on subjective needs, the PMBOK considers them to be unquantifiable expectations (page 110), which are difficult to successfully satisfy. Quality is a management responsibility the principle that management is ultimately responsible for quality within the performing organization delivering the project. Once again, W. Edwards Deming is influential in defining the standards associated with this principle. Quality is not the same as grade the principle that grade is a category or rank that is used to distinguish items that have the same functional use but\ do not share the same requirements for quality (as defined by ISO standard 8402).
Attribute a defining characteristic of a process or product. The attribute is measured to determine if the item or component sampled is acceptable. Variable the characteristic of the process or product that is measured, such as size, shape, weight, etc.; Sample size the number of items, or representatives, selected in the sample set; Range the limits of a population, defined by the difference between the largest measurement or value and the smallest in the population distrib tion; Variance a measurement of how far the variable being measured is from the expected value typically associated with that variable (the norm); Standard deviation a statistical measure of dispersion of a sample, represented by the square root of the average of the squares of deviations about the mean of a set of measurements or data. Standard deviation is used to identify the range of accuracy that is applied to the results of a defined measurement. It is commonly represented by the sigma (or standard deviation) scale in ascending order of magnitude, as follows:
4 4 4 4
+/- 1 sigma = 68.26%, +/- 2 sigma = 95.46%, +/- 3 sigma = 99.73% (representing 27 in 10,000 occurrences), +/- 6 sigma = 99.99% (representing 1 in 10,000 occurrences);
11
12
1-800-418-6789 www.preplogic.com
=
PrepLogic
www.preplogic.com
1-800-418-6789
Normal distribution across a statistical sample is depicted by a bell curve distribution, in which 50% of the curve occurs above the mean (to the right hand side of the mean point, usually a line dividing the bell curve), and 50% occurs below the mean (the left-hand side of the mean point); Mean the arithmetic average expressed by the sum of the measurements in a sample set, divided by the number of measurements (the sample size); Median the value in a range of data points representing the midpoint in the range, and having as many data points above the midpoint as it does below; Mode the value in a range of data points that represents the most frequently observed value in that range; Statistical sampling involves selecting a sub-set of the total population for inspection (the sample set). Attribute sampling an audit technique in which representatives of a population are selected (the sample set) and assessed for absolute conformance (yes or no); Variables sampling an audit technique in which the degree of conformity of a sample representative is measured and rated on a continuous scale; Special causes unusual events or results observed in a process indicating that it is not in control; Common causes also known as random causes, these are events or results that are attributable to a known variation within the normal working of the process. Assignable cause a single data point, or a pattern of data points, that indicates investigation is required to determine the cause of variation in the process (see Control charts below); Tolerances specify the acceptable variations in the attributes of a process, and provide measurement of the degree of accuracy within the tolerable range of variation (acceptable margin of error); Control limits define the variable limits (upper and lower) within which a process is observed to be in control. Control limits are dynamic and should be adjusted when required, to reflect the normal range of operation of the process; Prevention includes all of the actions taken to keep errors out of the\ process; and Inspection includes all of the actions taken to keep errors out of the hands of the customer.
g g g g g g g g g g g g g g
points gathered in a control chart are used to identify special cause variation, that is, evidence that the process is inconsistent or unpredictable in its behavior (it is not in control). Flowcharting is used to analyze how problems occur through the depiction of the interrelation of elements within a process. Cause and Effect Diagrams also known as fishbone or Ishikawa diagrams, cause and effect diagrams are used to depict and aid analysis of how various factors may contribute to, or be linked to, potential problems or effects. Histograms are bar charts that show the distribution of variables where each bar (or column) represents an attribute or characteristic of a problem or event. Pareto Chart is a specific kind of histogram in which the causes of a problem or event are ordered by frequency of occurrence, and displayed by category or type of cause. Pareto charts are used to identify and evaluate nonconformities in processes. Run Chart is used to track and analyze trends in performance over time. Data points are plotted in the order in which they occur on a line graph so that patterns of variation in the process or results (including both improvement and deterioration) are captured over time. Scatter Diagram depicts the pattern of relationships between two variables, and is used to analyze the possible relationships between changes observed in the two variables. Dependent versus independent variables are plotted.
Project staff alternatively referred to as project team members, they include all staff performing project work as a regular part of their assigned duties. Project staff report directly or indirectly to the project manager; Project team includes the project manager, the project management team and, on some projects, the sponsor, too; Project management team - a sub-set of the project team, alternatively known as the core, executive or leadership team, who are responsible for project management activities. On small scale projects the project management team may be comprised of most of the project staff; and Project manager the person assigned by the performing organization to achieve the project objectives.
Rule of Seven Control Charts are used to determine whether or not a process is stable or exhibits predictable performance (is in control). The chart depicts the behavior of a process observed over time. It is a tool for detecting trends. The data
13
14
1-800-418-6789 www.preplogic.com
=
PrepLogic
www.preplogic.com
1-800-418-6789
functional managers for directing and assigning staff to project work, as well as sharing in control over the project budget. Strong Matrix control and influence over resources and budget assigned to projects is shared with functional managers, though the project manager exerts the stronger authority over these. Projectized Performing projects is the business of the organization, and functions and departments are primarily aligned to support the execution of projects. Roles and responsibilities are typically described and depicted in the following formats:
g
Hierarchical-type chart in which project activities and deliverables are mapped to the functional group or department responsible for executing those activities and delivering artifacts in accordance with the project management plan. Matrix-based chart in which the level of responsibility for a project task or deliverable is explicitly identified with a team member or group. Text format in which much more detailed descriptions of roles, responsibilities, levels of authority, qualifications, competencies, etc., can be provided than in a hierarchical or matrix chart format.
RACI chart Responsible the team member who has ultimate authority for executing the task or activity meeting the needs of the project; Accountable the team member who has ultimate responsibility for ensuring that a task or activity has been completed as required by the needs of the project; Consult the team member who must be consulted about the performance of the task or expected outcome, as it may impinge or directly affect the performance of activities or tasks for which they are responsible; and Inform the team member who must be made aware of the performance of a task or outcome so that they can respond, if appropriate, from an informed perspective. All roles and responsibilities required by the project must be identified and defined as a result of the human resource planning process. At the very least, the following must be documented:
g
Collective bargaining agreements union and other employee agreements with the performing organization may limit the project management teams ability to flex roles and working arrangements to meet project needs; Economic conditions may impact the kind of human resources that can be secured and utilized effectively. Organizational structure the performing organizational structure directly impacts how the project is performed with respect to the amount of influence and authority that the project manger and project management team can exert in securing and directing the necessary resource and priority to successfully complete project activities.
Five Types of Organizational Structures Functional in a functional organization, each specialist department or group has ultimate authority over any project work performed by its staff, and will defer to other departments for work outside of its specialization. Projects are performed in accordance with the hierarchical structure of the company. Weak Matrix functional departments still exert strong control over resource allocations and budget, and the project managers authority is limited. Balanced Matrix the project manager begins to share authority with
Role the part that the team member will play in the project. Each team member is ultimately accountable for the role assigned to them; Authority confers rights to make decisions, apply resource and sign approvals. The level of authority exercised by each team member derives
15
16
1-800-418-6789 www.preplogic.com
=
PrepLogic
www.preplogic.com
1-800-418-6789
from their designated and agreed upon project responsibilities; Responsibility is defined by those accountabilities which the team member must perform or execute to meet project needs; and Competency is defined by a team members skills and capacity to perform tasks assigned to them to meet project requirements. Team member competency impacts, both positively and negatively, project perfo mance.
The Staffing Management Plan is the formal planning document that describes how and when the projects human resource requirements will be met and is comprised of the following components: Staff acquisition addressing how and where project staff will be added to the project, including costs of acquisition (determined by the skills, know edge, and experience required to meet project needs); Timetable identifying when staff will be added to the project and how long they will be utilized on project activities. Release criteria defining when and how staff will be released from the project and returned to their functional department or transitioned to another project. Training needs identifying how required competencies will be acquired by staff to meet the projects needs; Recognition and Rewards (R&R) defining criteria and behaviors by which team members will be rewarded for their project efforts. The scope of an effective R&R scheme must be based on those activities that a team member can personally influence and control. Compliance identifying how the project will ensure that it meets the requirements of human resource policies, statutory regulations, union agreements, etc.; Safety identifying relevant health and safety policies and procedures that may affect staff in the performance of their project work.
g
Physiological needs representing the basic or fundamental needs of existence, such as shelter, food, clothing, etc. The primary objectives of these needs are self-preservation and comfort; Safety needs representing the avoidance of risk, pain or harm. These needs are met by anything that promotes and assures stability, order and security; Social needs representing companionship, family and social relationships; Esteem needs represented by our sense of status, derived from achievements and responsibilities that are recognized, acknowledged and rewarded; and Self Actualization representing the cognitive level at which the individual realizes their full potential, attaining self-fulfillment.
Empathy the ability to step into another team members shoes, not just to see their perspective on an issue or problem, but to understand with feeling what the issue or problem really means to that team member. Influence the ability to achieve a desired outcome or state in the mind of a project participant, without having to give explicit direction or exert overt pressure to achieve that result. Creativity the ability to find solutions to problems using available resources in imaginative or ingenious ways. Group facilitation comprises various interpersonal techniques that are used to mediate the contributions of individuals to ensure balanced and full participation in team activities by each individual.
17
18
1-800-418-6789 www.preplogic.com
=
PrepLogic
www.preplogic.com
1-800-418-6789
limits of their influence and the level of their authority. There are five commonly recognized sources for this power. These are: Reward in which bonus, promotion and other incentives are used to encourage positive behaviors that enhance project performance; Expert in which knowledge and expertise (technical or specialist) are used to establish credibility and build confidence among team members in the leadership abilities of the project manager. Referent in which reference to the authority of someone in a higher position or via association is used to establish leadership. Such reference may also be based on personality or knowledge; Penalty (or Coercive) in which rewards are withheld or actions are penalized on the basis of non-performance, usually via formal disciplinary procedures. In all cases, the objective of these actions is to correct negative behaviors that impair or disrupt project performance; and Legitimate (or Formal) in which the leadership of the project manager is officially recognized by the performing organization. The level of authority exerted is based on a hierarchical position. Conflict can arise in many areas of the project. The main sources of conflict are:
g
The source of the conflict is only partially addressed, and may re-surface, but in a different form; Collaboration (or consensus) similar to compromise but more effective, because the multiple viewpoints of the protagonists are acknowledged and accommodated within the solution. Collaborative solutions emphasize working together, and this is a very effective way of resolving conflict; and Confrontation (or problem solving) in which the sources of the conflict are discussed and examined by the protagonists in an open-minded dialogue. The root causes are identified and acknowledged, and alternative solutions to the conflict are accepted. Confronting directly the root causes of the problem is the most effective way of resolving conflict.
Schedule created by the tension between the desire to complete project tasks according to an idealized timetable, and the performance of those tasks according to the constraints of the actual project environment; Priority divergent or conflicting views on the order of accomplishment of the project activities, or between one project assuming (or being assigned) precedence over another; Resource lack of availability or access to the right kind of resources to perform project tasks; and Technical viewpoint divergent opinions regarding the best way to perform project activities, especially those involving alternative choices over technology decisions.
Approaches to Conflict Avoidance (or withdrawing) in which management ignores the conflict, and the problem continues unresolved; Accommodation (or smoothing) in which common ground between the protagonists is identified by emphasizing those areas on which there is agreement, but does not address areas of disagreement. The source of the conflict is deemphasized but is not resolved; Compromise (or bargaining) in which the protagonists negotiate over the issues causing conflict, and jointly arrive at a win-win position by giving som thing up in return for gaining something. Forcing (or dictating) in which a specific solution to the conflict is imposed on the protagonists. One party usually gains more than the other (win-lose).
19
20
1-800-418-6789 www.preplogic.com
=
PrepLogic
www.preplogic.com
1-800-418-6789
4. Noise anything that may impede or distort the transmission of the message or the interpretation (understanding) of the message by the receiver (for example, using excessive technical terminology when communicating with a non-technical audience); and 5. Decode the process by which encoding is reversed and the received message is translated back into thoughts and ideas. External interfaces to identify how the project will meet the communication needs of stakeholder groups external to the performing project organization. For example, keeping local communities appraised of construction work that may impact their environment; Company and departmental organization charts to identify how and where potential project resources are organized by the performing project organization, including understanding the interactions between departments and groups (as documented in methods of working or operational procedures); Roles & responsibilities to understand the functions and activities for which individuals and groups are accountable for within the performing project organization; Internal communications to identify mandatory or other regularly required communications requirements within the performing project organization, for example, monthly project status reports for the Project Management Office; Formula: n(n-1)/2 where n = number of stakeholders
risk management approach, accounted for in the cost baseline; Stakeholder tolerances identifying the risk tolerance profile of each stak holder, as revised by the risk management planning process; Methodologies describing the tools, techniques and processes that will be used to manage risk; Definition of Risk Probability and Impact defining how probability and impact will be applied during the Qualitative Risk Analysis process Probability and Impact matrix defining how risks will be prioritized according to their probability and impact on the projects objectives; Tracking describing how risk activities such as outputs and artifacts will be recorded and documented, including lessons learned. Also included is reference to how risk management activities will be audited; and Reports describing the content and format of the Risk Register and project risk reports.
Risk Identification
Delphi technique in which ideas and opinions about potential risks are collected from experts, and a consensus view on the risks is developed. The steps involved in this process are:
g
If there are 10 project stakeholders, then the potential number of communications channels is 45. If you double the number of stakeholders to 20, does the number of channels double? Increasing the number of stakeholders not only increases the complexity of the communications channels numerically, but also increases how the communications requirements of those additional stakeholders will be met. Identifying all of the projects stakeholders is critical to ensuring successful project communications.
a questionnaire is circulated to the experts to solicit risk ideas; responses are summarized and then circulated to the experts for review and comment; and updated responses which are re-circulated for further review and comment.
Brainstorming in which idea-generation is facilitated with the project team and relevant subject matter experts to explore, uncover and identify areas of potential project risk. Interviews in which project participants, subject matter experts and stak holders are interviewed to identify project risks based on their experience. SWOT (Strengths, Weaknesses, Opportunities, and Threats) analysis in which potential risks are identified by looking at each of the SWOT characteristics as they apply to the project. Root Cause analysis in which the underlying causes of risks are identified and analyzed. Causation characteristics can be used to categorize similar risks and formulate responses.
21
22
1-800-418-6789 www.preplogic.com
=
PrepLogic
www.preplogic.com
1-800-418-6789
Ranking providing a relative ordering of the significance of the risks evaluated on the project. This should include sufficient information about the risk event, and how it has been evaluated to enable decisions about how to respond; Categorization identifying root causes or patterns of risk for further evaluation; Trend analysis noting any observed trends in risks events; Low priority risk watchlist identifying low probability and/or low impact risks that do not require immediate attention but should be monitored by the project team; Near term risk responses identifying those risk events that require urgent attention by the project management team; and Additional analysis and response identifying those risks that do not pose an immediate threat to the project but require further evaluation.
23
24
1-800-418-6789 www.preplogic.com
=
PrepLogic
www.preplogic.com
1-800-418-6789
Notes
25
26
1-800-418-6789 www.preplogic.com
=