Front-End Loading (FEL) refers to including robust planning and design early in capital-intensive processing industry projects, such as petrochemical and refining projects, to influence design changes when costs are relatively low. It typically divides work into three stages - FEL1 produces initial planning documents, FEL2 preliminary design documents, and FEL3 produces project definition documents ready for purchasing equipment.

Uploaded by

국무성
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
2K views

Front-End Engineering Design Feed

Front-End Loading (FEL) refers to including robust planning and design early in capital-intensive processing industry projects, such as petrochemical and refining projects, to influence design changes when costs are relatively low. It typically divides work into three stages - FEL1 produces initial planning documents, FEL2 preliminary design documents, and FEL3 produces project definition documents ready for purchasing equipment.

Uploaded by

국무성
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Definition

Front-End Loading (FEL) is the process for conceptual development of processing industry projects. Example of processing industry are petrochemical, refining, pharmaceutical. FrontEnd Loading is also referred to as Pre-Project Planning (PPP) or Front-End Engineering Design (FEED).

Overview
Expanding on the above definition, Front-End Loading refers to including robust planning and design early in a project's lifecycle (i.e., the "Front End" of a project), at a time when the ability to influence changes in design is relatively high and the cost to make those changes is relatively low. It typically applies to industries with highly capital intensive, long lifecycle projects (i.e., hundreds of millions or billions of dollars over several years before any revenue is produced). Though it often adds a small amount of time and cost to the early portion of a project, these costs are minor compared to the alternative of the costs and effort required to make changes at a later stage in the project. It also typically uses a Stage-Gate process, whereby a project must pass through formal Gates at well defined milestones within the project's lifecycle before receiving funding to proceed to the next Stage of work.

FEL Stages
It is common industry practice to divide Front-End Loading activities into three stages: FEL1, FEL-2, and FEL-3. For each stage, typical deliverables are listed below.

FEL-1

FEL-2

FEL-3
Purchase Ready Major Equipment Specifications Definitive Estimate Project Execution Plan Preliminary 3D Model Electrical Equipment List Line List Instrument Index

Material Balance Energy Balance Project Charter

Preliminary Preliminary Preliminary Preliminary

Equipment Design Layout Schedule Estimate