Bridge Design Manual - July09
Bridge Design Manual - July09
JULY 2009
Added Commentary.
Added TS&L Report requirements in Structure Concept Review. Added requirement for Virtis load rating. Added Check Calculations & QA/QC check lists submittal at Final Design.
July 2009
Added paragraph for Design Calculations. Added preparation of design criteria in Designers Responsibilities. Added paragraph for duties of Bridge Engineer. Added load rating responsibility for Designer Added requirement for microfilming check calculations.
Commentary
The FHWA November 13, 1998 Memorandum is available at http://www.fhwa.dot.gov/bridge/unusual.htm
Permits: Review overweight permits in a timely manner. Design: Minimize traffic interference during construction. Access for inspection and maintenance shall be considered as part of the design, with emphasis on utilization and safety of personnel. All facilities shall be designed to prevent unauthorized access to the structure. Bridges replacements should enhance commercial routes. .
Article 0.7 Page 1 of 2 4/2008 TYPE, SIZE & LOCATION REPORT for CONSULTANT PROJECTS
GENERAL The purpose of the TS&L Report is to provide enough background information so that reviewers can effectively evaluate the proposed final design and the concepts it is based on. The report should describe the project, the proposed structure, and give reasons why the bridge type, size, and location were selected. The report should concisely summarize the information in 2-3 pages. A separate TS&L Report shall be prepared for each structure except minor projects such as deck joint rehabilitations or rail retrofits. The intent of the TS&L Report is the collection of pertinent data required for the design of the structure, in addition to documentation of design decisions. Pertinent data shall be extracted from other discipline reports and summarized in this Report for use by the structure designers. Even though the Hydraulics Report or Foundation Report may not be available at the time the TS&L Report is prepared, always include comments about assumptions made in consultation with the Hydraulics or Foundation Engineer. The TS&L Report will include the following sections, where applicable. Not all sections will apply to all structures. REPORT OUTLINE General Background Project description Structure location (may include roadway plan & profile and aerial photography) Right-of-way restrictions Permits and restrictions Utility conflicts or restrictions Railroad clearances or restrictions Design Specifications Environmental Wetlands Historical Sites Contaminated areas Recreation areas Threatened Species areas Environmental commitments listed in the environmental docu,emtation Design Concepts Rationale for: Building new bridge versus widening existing one Use of bridge versus culvert Foundation support assumptions Assumed pile or bearing capacity loads Assumed lateral soil pressure against abutment Seismic load assumptions Geometry and Layout Roadway width Traffic volumes Profile grade Horizontal alignment Design exceptions Sidewalks Railing Hydraulics Waterway opening High water elevation Clearance Bank protection Floodway information Deck drains
Many bridge replacement projects require a Biological Assessment. To aid in the process, try to address as many of the following subjects as practical. Project timing and chronology Alignment and span configurations of the new bridge in relation to the existing bridge Proposed treatment of the runoff and comparison of the number of drains on the existing bridge to the number of drains on the new bridge. Discuss the sizes, numbers, and removal methods of the existing bents, footings and piles within the Ordinary High Water Mark. Discuss the sizes, numbers, and construction methods of the new bents, footings and piles within the Ordinary High Water Mark. Method of dewatering Method of removal and disposal of existing bridge members with lead based paint Discuss the construction and removal methods for detour bridges, work bridges, or falsework within the Ordinary High Water Mark Extent and duration of heavy machinery work in the wetted channel Amount or extent of fill and/or riprap Possible staging area and access Amount and type of vegetation to be removed outside and within the Ordinary High Water Mark Amount of wetland impacted Any planned mitigation
Quality Control
Preliminary Design: Review major features of the project; structure type, constructability, environmental mitigation, cost. Check of the girder capacity, clearances, geometry. Final Design: Review structure type and major features to verify that changes in the overall project have not invalidated previous project decisions; presentation and thoroughness of the plans. Check of design calculations, details of the design, and plans. Design Check A complete check of the structural design calculations shall be carried out by a Professional Engineer other than the Professional Engineer responsible for the design. This design check shall be carried out by another Consultant when the design Consultant does not have adequate in-house capabilities to provide this check. The design check notes shall be stamped and submitted with the original design calculations.
1.2 DEFINITIONS
DESIGNATION OF CULVERTS AND BRIDGES ON DRAWINGS To determine whether a structure should be designated as a Culvert or a Bridge, the structure shall be measured along the centerline of roadway from the inside face of wall or abutment. If the measured length is 20 feet or less it shall be designated a culvert, if greater than 20 feet it shall be designated a bridge. In drawings that are designated as "Culverts" the length shown in the title block shall be the clear span measured perpendicular to the walls. In drawings that are designated as "Bridges" the length shown in the title block shall be the out to out distance of the abutments or walls measured along the centerline of roadway.
Commentary
The definition of bridge is in accordance with the Federal-Aid Policy Guide Title 23 CFR Section 650.403.
7.5.4 Resistance Factors 12.5.5 Resistance Factors 5.5.4.2 Resistance Factors.doc 11.5.6 10.5.5 Resistance Factors 6.5.4.2 Resistance Factors 8.5.2.2 Resistance Factors
Only articles in the ITD Bridge LRFD Manual use the .doc extension.
If the above criteria apply, consult your Group Leader. The minimum factor shall be 1.0. All bridges that are classified as critical under section 3.10.5 shall be considered Important.
Changed reference to 3.10.3 to 3.10.5 to agree with the 2008 Interims and deleted ADT & Detour Length Table. Added minimum value.
Commentary
The LRFD Bridge Design Specifications require walkways to be separated from the roadway with the use of a traffic or combination rail on high-speed urban expressways. The Definition for Speed-Low/High is in Article 13.2.
Revised the low/high design speed to 45mph to conform to the 2006 Interims.
2.3.3.1 NAVIGATIONAL
Bridges over navigable waters shall meet the vertical clearances required by the Coast Guard.
Added Coast Guard clearance requirement for bridges. Modified waterway clearance requirements with the concurrence of the Hydraulics Engineer. Added references to highway horizontal sketches in A2.6. Changes culvert width for concrete porta-rail to roadway width + 10-8. Changed minimum railroad vertical clearance to 23-4 to comply with BNSF/UPRR Guidelines for Railroad Grade Separation Projects, January 2007. Added references to railroad drawings in A2.3.
Figure 1 DEPRESSED ROADWAY TUNNEL EFFECT Low Level Water Crossings - Sufficient clearance over bodies of water must be maintained so that spray or condensation or water vapor does not result in prolonged periods of wetness of the steel. Clearance to bottom flange of at least 10 feet over sheltered, stagnant water and at least 8 feet over running water is recommended. Method of Selection The Bridge Engineer, in cooperation with the Group Leaders, will make the selection. The selection will be based on stress, economics, environmental considerations, and aesthetics. The selection will be made at the preliminary design stage.
3.
e.
MAINTENANCE Effective inspection and maintenance programs are essential to ensure that all bridges reach their intended service life. This is especially true in the case of uncoated weathering steel bridges. The following maintenance actions should be done routinely: Inspection Implement inspection procedures that recognize the unique nature of uncoated weathering steel and the conditions resulting from excessive corrosion damage. Develop inspection guidelines that highlight the structural features to be inspected and also illustrate the difference between the desired oxide coating and excessive rust scaling. Measurements of the oxide coating thickness should be taken during each bridge inspection and recorded in the bridge inspection reports. Controlling Roadway Drainage To the extent feasible the following should be done: Divert approach roadway drainage away from the bridge structure. Clean troughs of open (finger) joints and reseal "watertight" deck joints. Maintain deck drainage systems (scuppers, troughs, etc.) in order to divert deck drainage away from the superstructure steel and substructure units. Periodically clean and repaint all steel within a minimum distance of 1 1/2 times the depth of the girder from bridge joints. Other Maintenance Remove dirt, debris and other deposits that hold moisture and maintain a wet surface condition on the steel. In some situations, hosing down a bridge to remove debris and contaminants may be practical and effective. Some agencies have a regularly scheduled program to hose down their bridges. Maintain screens over access holes in box sections to prevent entrance by animals and birds. Remove growth of nearby vegetation that prevents the natural drying of surfaces wet by rain, spray or other sources of moisture.
Commentary
FHWA Technical Advisory T5140.22 can be found at http://www.fhwa.dot.gov/legsregs/directives/techadvs/t514022.htm HEC-21 can be found at http://www.fhwa.dot.gov/bridge/hec21.pdf
Article 2.5.2.6.3 Page 1 of 1 5/2004 2.5.2.6.3 CRITERIA FOR SPAN -TO-DEPTH RATIOS
Flexural members of bridge structures shall be designed to have adequate stiffness to limit deflections or any deformations that may adversely affect the strength or serviceability of the structure at service load plus impact. The minimum span to depth ratios are recommended unless computation of deflection indicates that lesser depths may be used without adverse effects. The span length of members that are not built integrally with their supports shall be considered the clear span plus the depth of the member but need not exceed the distance between centers of supports. The span length of continuous members shall be considered at the faces of support. When fillets making an angle of 45 degrees or more with the axis of the member are built monolithic with the member and support, the face of support shall be considered at a section where the combined depth of the member and fillet is at least 1.5 times the thickness of the member.
Commentary
HEC-21 can be found at http://www.fhwa.dot.gov/bridge/hec21.pdf Refer to NCHRP 67 for designing drainage piping systems.
W = 1 1 T
2 . 67
G1 = Incoming tangent grade on a vertical curve. Ft/ft G2 = Outging tangent grade on a vertical curve. Ft/ft i = design rainfall intensity (in/hr) Use the value from the Rational Method and compare to the Avoidance of Hydroplaning and Driver Vision Impairment. Rational Method 1. Select the rainfall intensity zone from the map. 2. Make a trial selection of duration and compute the trial intensity.
tc = t0 + t g
t 0 = 0.93
(C i )0.4 S 0.3
(W p n)0.6
t g = 484
S x T 2 C i W p
3. 4.
Using the trial intensity value, compute the total time of concentration The design intensity is the value when the trial duration equals the calculated total time of concentration.
Driver Vision Impairment i = 4.0 in/hr IDF = intensity-duration-frequency curve. See Figure 1 for the Rainfall Intensity Zone. The inlet design is based upon a 25-year frequency. The intensity for a given duration can be computed from the following equations: Zone 1 duration < 60 minutes duration > 60 minutes
i = 10 0 . 894094
i = 10 1 . 132115
Zone 2
S K = 1 (1 E ) u S
43560 Q f E C i W p
0.5
Lc = distance between deck drains after the first inlet (ft) Drains on tangent grade
Lc =
(n C i W p )0.67
LD = length of deck drain parallel to gutter flow (ft) Type 1 Drain = 0.78 ft. Type 2 Drain = 0.79 ft. Lvc = length of vertical curve (ft) n = Manning's friction coefficient (0.016) P = total inlet perimeter for flat grade bridges (ft) (C i W p )0.33 T 0.61 P= 102.5 S 0.06 n0.67 x Qf = full gutter flow at design spread (cfs)
Qf = 0.56 S 1.67 S 0.5 T 2.67 x n
S = grade of bridge deck at a given drain (ft/ft) Drains on vertical curve (G 2 G1) X S = G1 + L vc Su = longitudinal grade for upstream inlet on vertical curve bridge Sx = cross slope of deck (ft/ft) T = design spread (ft) The design spread is calculated assuming that the gutter flow can spread across the full shoulder width on bridges with not more than 2 traffic lanes. For bridges with more than 2 traffic lanes, the gutter flow can spread across the full shoulder width and half of the adjacent traffic lane width. V = gutter flow velocity (ft/sec)
V = 1.12 S 0.67 S 0.5 T 0.67 x n
Vo = Velocity of flow at which splash-over first occurs over a grate (ft/s.) Type 1 Drain
Type 2 Drain
Wp = width of pavement contributing to runoff (ft) equals the width of deck from the face of curb to high point of crown. WD = width of deck drain at right angle to gutter flow (ft) Type 1 Drain = 0.448 ft Type 2 Drain = varies X = distance from the PC of a vertical curve to the inlet (ft) XT = distance from PC of a vertical curve to the turning point (ft) G1 L Xt = (G 2 G1)
Figure 1
ZONE 2 INSET 1
ZONE 2 INSET 2
5. 6. 7.
(C i )0.4 S 0.3
(W p n )0.6
= 0.93
t g = 484
b.
c. d.
t c = t 0 + t g = 1.15 + 42.95 = 44.10 min The assumed time of 44 minutes is approx. equal to the computed time of 44.10 minutes. Therefore, use i = 1.39 in/hr. Avoidance of Hydroplaning d 1.67 64904.4 0.02 64904.4 Sx 0.0061.67 = 11.56 in / hr i= = 2 0.25 0.25 (18 10) C n Sx+ S2 (W p - T ) 0.9 0.016 0.022 + 0.032 Avoidance of Vision Impairment i = 4.00 in/hr Design rainfall intensity = 1.39 in/hr
Step 2. Compute full gutter flow based on the design spread of 10.
Qf = 0.56 0.56 S 1.67 S 0.5 T 2.67 = 0.021.67 0.030.5 10 2.67 = 4.12 cfs x n 0.016
= 43560 4.12 = 7969.94 ft 0.9 1.39 18
Step 3. Starting at the upslope end of the bridge, compute the distance to the first inlet.
L0 = 43560 Q f C i W p
Step 4. Since L0 is greater than the total bridge length (500 ft), no inlets are required. Step 5. Design the bridge end treatment. Since no drains are required, the assumed blockage = 0% Assumed duration = 4.5 minutes Assumed spread = 6 feet
(W p n)0.6
(C i )0.4 S 0.3
= 0.93
t g = 484
4.59 minutes are approx. equal to the assumed value of 4.5 minutes. Compute the design flow with the percent blockage
Q = C i A [(blockage) E (number of drains ) V ]
A= W p (length of bridge ) 18 500 = = 0.207 acres 43560 43560
Qf n 2.67 1.02 0.016 2.67 = T = = 5.93 ft 1.67 0.5 0.56 S1.67 S 0.5 0.56 0.02 0.03 X
This is approximately equal to the assumed value of 6 feet. Select an inlet that will handle 1.02 cfs and provide a pipe or paved ditch to convey the design flow from the drain to the toe of the embankment. Provide energy dissipation, if necessary, at the toe to achieve nonerosive velocities.
EXAMPLE 2 - TANGENT GRADE BRIDGE WITH INLETS REQUIRED EXCEL or MATHCAD programs can be used to complete the design process. Drains on tangent grade(.xls or .mcd) is on the X: drive in the LRFD Design Aids, Section 2 folder. Given: 2000 ft bridge S = 0.01 Sx = 0.02 Wp = 34 ft T = 10 ft n = 0.016 C = 0.9 Zone 2 d = 0.006 ft WD = 1.0 ft LD = 1.50 ft Step 1. Calculate the Design Rainfall Intensity Rational Method Assume duration of 12.25 minutes
i = 101.132076 0.60121 log (duration ) = 101.132076 0.60121 log (12 .25 ) = 3.00 in / hr
t 0 = 0.93
(C i )0.4 S 0.3
(W p n)0.6
= 0.93
t g = 484
t c = t 0 + t g = 1.73 + 10.53 = 12.25 min The assumed time of 12.25 minutes is equal to the computed time of 12.25 minutes. Therefore, use i = 3.00 in/hr.
Avoidance of Hydroplaning d 1.67 64904.4 0.02 64904.4 0.0061.67 Sx = 4.89 in / hr i= = 2 0.25 0.25 ( (34 10) C n (S x + S 2 ) W p - T ) 0.9 0.016 (0.022 + 0.012 ) Avoidance of Vision Impairment i = 4.00 in/hr Design rainfall intensity = 3.00 in/hr
Step 2. Compute full gutter flow based on the design spread of 10.
Qf = 0.56 1.67 0.5 2.67 0.56 Sx S T = 0.021.67 0.010.5 102.67 = 2.38 cfs n 0.016
43560 Q f C i W p 43560 2.38 = 1127.92 ft 0.9 3.00 34
Step 3. Starting at the upslope end of the bridge, compute the distance to the first inlet.
L0 = =
Step 4. Since L0 is less than the total bridge length (2000 ft), inlets are required. Step 5. Space inlets at Lc until the end of the bridge is reached. Compute the frontal flow ratio, E0.
Wd E 0 = 1 1 T
V =
2 . 67
1 .0 = 1 1 10
2 . 67
= 0 . 245
(L d )+ 0 . 474699
= 10
0 . 654078
log
(1 . 50 )+
0 . 474699
= 3 . 89
fps
Compute the inlet efficiency E = R f E 0 = 1 . 0 0 . 245 = 0 . 245 Compute the constant spacing between the remainder of the inlets.
Lc = 43560 Q f E C i W p = 43560 2.38 0.245 = 276.57 ft 0.9 3.00 34
Maximum Rf = 1.0
Step 6. Design the bridge end treatment. Since drains are required, assume blockage = 50% Assumed spread = 10.6 feet Assumed duration = 15.5 minutes
(C i )
(W p n )0.6
0 .4
S 0 .3
= 0.93
t g = 484
t c = t 0 + t g = 1.83 + 13.62 = 15.45 min 15.45 minutes are approx. equal to the assumed value of 15.5 minutes. Compute the design flow with the percent blockage Q = C i A [(blockage) E (number of drains ) V ] A= W p (length of bridge ) 34 2000 = = 1.56 acres 43560 43560
Check the design spread with the new computed flow. Compute the spread by solving the gutter flow equation for T.
Qf = 0.56 S 1.67 S 0.5 T 2.67 x n
1 1
Qf n 2.67 2.79 0.016 2.67 = T = = 10.61 ft 0.56 1.67 0.5 0.56 S1.67 S 0.5 0.02 0.01 X
This is equal to the assumed value of 10.6 feet. Select an inlet that will handle 2.79 cfs and provide a pipe or paved ditch to convey the design flow from the drain to the toe of the embankment. Provide energy dissipation, if necessary, at the toe to achieve nonerosive velocities.
Avoidance of Hydroplaning d 1.67 64904.4 0.02 64904.4 Sx i= = 2 C n S + S 2 0.25 (W p - T ) 0.9 0.016 0.022 + 0 x Driver Vision Impairment i = 4.00 in/hr Design intensity = 5.15 in/hr Step 2. Compute the inlet spacing 1312 S1.44 T 2.11 1312 0.021.44 102.11 x = = 325.32 ft Lc = (n C i W p )0.67 (0.016 0.9 5.15 34)0.67
)0.25
Step 3. Since Lc is less than the bridge length (4000 ft), inlets are needed. Step 4. Compute the total inlet perimeter
102.5 S 0.06 n0.67 x 102.5 0.020.06 0.0160.67
If the inlet is adjacent to the curb, then the sum of the other 3 sides should equal the computed inlet perimeter. A curb opening should equal the computed inlet perimeter. Solutions. Number of inlets required on each side of the deck. Number of drains = Lb Lc = 11.3 Use ND = 12 Lc Drain Spacing = Lb = 307.69 ft N D +1
Type 2 Drain 12 drains spaced at 307.69 feet along the length of bridge. 4.26 0.79 Width of drain = = 1.74 ft 2 Type 1 Drain 12 locations spaced at 307.69 feet along the length of bridge. P1 = 2*0.448 + 0.78 = 1.676 Number of drains required at each location = 4.26 / 1.676 = 2.6
Use 3
i = 10 1 . 132076
t g = 484
t 0 = 0.93
)=
10 1 . 132076
) = 3 . 01 in / hr
(W p n)0.6
(C i )0.4 S 0.3
= 0.93
t c = t 0 + t g = 1.73 + 10.53 = 12.25 min The assumed time of 12.25 minutes is equal to the computed time. Therefore, use i = 3.01 in/hr. Avoidance of Hydroplaning
d 1.67 64904.4 0.02 64904.4 Sx i= = 2 0.25 ( C n S + S2 - T ) 0.9 0.016 0.022 + 0.012 Wp x Avoidance of Vision Impairment i = 4.00 in/hr Design rainfall intensity = 3.01 in/hr Step 3. Assume the distance to the first inlet from the turning point to the end of bridge = 848 ft Distance from PC to first inlet, X = 848 + 1500 = 2348 ft. Compute the slope at the assumed first inlet location
0.25
S = G1 +
(G 2 G1) X
= 0.01 +
Step 5. Compute the distance to the first inlet and compare to the assumed value. K = 1.0 for the first inlet
43560 1.79 1.0 = = 848.07 ft C i W p 0.9 3.01 34 Assumed value of 848 ft equals computed value of 848.07 ft. Inlets are required since the distance to the first inlet, 848 ft, is less than the distance from the turning point to the end of bridge, 1500 ft. Lc = 43560 Q f K
( 0.01 0.01) 2729 = 0.00819 = 0.01 + 3000 Lvc Use the absolute value of S. Therefore, S = 0.00819. Compute the gutter flow at the design spread
S = G1 +
Qf = 0.56 1.67 0.5 2.67 0.56 Sx S T = 0.021.67 0.008190.5 102.67 = 2.16 cfs n 0.016
2 . 67
(G 2 G1) X
1 .0 = 1 1 10
1 .67
= 0 . 245
1.12 0.67 0.5 0.67 1.12 S x S T = 0.020.67 0.008190.5 100.67 = 2.155 fps n 0.016
Maximum Rf = 1.0
E = R f E 0 = 1 .0 0 .245 = 0 .245
Compute the interception coefficient, K. Su = 0.00565 S = 0.00819 0.5 0.5 0.00565 S K = 1 (1 E ) u = 1 (1 0.245) = 0.373 0.00819 S Compute the inlet spacing and compare to the assumed value.
Li =
43560 Q f K C i W p
The computed length of 380.72 ft equals the assumed value of 381 ft. Step 7. Repeat step 6 for each inlet until the end of the bridge is reached. Since the bridge is this example is symmetrical, the drain configuration will be the same from the turning point to both the begin/end of bridge. The following table summarizes the inlet spacing. Spacing of inlets from the turning point to begin/end bridge Inlet Spacing, Li Slope, S Gutter flow, Q Station Feet Ft/ft cfs 848.07 1 3348.07 0.00565 1.79 380.72 2 3728.79 0.00819 2.16 357.40 Only 2 drains are required on the bridge. The 357.40 ft to the third drain puts it at station 4086.19, which is beyond the end of the bridge. Step 8. Design bridge end treatment Since drains are required, assume blockage = 50% Assumed spread = 11.75 feet Assumed duration = 23.5 minutes
(W p n)0.6
(C i )0.4 S 0.3
= 0.93
t g = 484
23.5 minutes are equal to the assumed value. Compute the design flow with the percent blockage
Q = C i A [(blockage) E (number of drains ) V ] A= W p (length of bridge ) 34 3000 = = 2.34 acres 43560 43560
1.12 0.67 0.5 0.67 1.12 S x S T = 0.020.67 0.010.5 11.750.67 = 2.653 fps 0.016 n
V =
Check the design spread with the new computed flow. Compute the spread by solving the gutter flow equation for T.
Qf = 0.56 S 1.67 S 0.5 T 2.67 x n
1 1
Qf n 2.67 3.63 0.016 2.67 T = = 11.71 ft = 0.56 1.67 0.5 0.56 S1.67 S 0.5 0.02 0.01 X This is equal to the assumed value of 11.75 feet.
Select an inlet that will handle 3.63 cfs and provide a pipe or paved ditch to convey the design flow from the drain to the toe of the embankment. Provide energy dissipation, if necessary, at the toe to achieve nonerosive velocities.
SLOPE PAVING
Slope protection under bridges shall generally be provided under the end spans of grade separations and interchange structures and at railroad overpasses. Slope protection shall be concrete or crushed rock. Consult with the District to determine which one shall be used. Concrete slope paving shall be used in urban and suburban areas where vandalism could be a problem. Vandalism may be anticipated even if pedestrian traffic is prohibited under the bridge. Concrete slope paving may also be required by a duly constituted authority such as a railroad company. The maximum recommended slope for concrete slope paving is 2:1. Crushed rock of approximately 4 maximum dimension may be used at locations where vandalism is not likely to be a problem. The District should verify that a materials source for the rock is readily available. Avoid unpaved areas between slope paving and sidewalks. Avoid conducting water drained from slope paving across the top of a sidewalk. For dual structures over 15 skew, the end flared section shall be the same as for single structures over 15 skew. The center section shown on the standard drawing is typical for all dual structures at any skew angle with medians not more than 76 edge to edge of traveled lanes. For median strips greater than 76 use two single structures. Welded wire fabric may be deleted if fiber reinforced concrete is used. Modify the Standard Drawing details accordingly and add the following note to the Standard Drawing: Polypropylene fibrillated fibers, Fiber Mesh MD or equal, shall meet the material specifications of ASTM C-1116, Type 111 Section 4.1.3 (Synthetic Fiber Reinforced Concrete or Shotcrete). The weight of the fibers shall be 0.056 pcf. Calculate the data shown in the following sketch and show on the drawing to make the field layout easier.
Article A2.5 Page 1 of 2 6/2006 Properties & Support Spacing for PVC Pipe
Where PVC conduit is to be supported by hangers or pedestals at intervals, the distance between supports shall be small enough to avoid excessive sag of the conduit. Recommended support spacing and tabulated properties of PVC pipe are shown in the following Table.
Nominal size 1 1 1 2 2 3 4 5 6 8 10 12
O.D. inches 1.050 1.315 1.660 1.9 2.375 2.875 3.5 4.5 5.563 6.625 8.625 10.75 12.75
Average I.D. inches 0.804 1.029 1.367 1.590 2.047 2.445 3.042 3.998 5.016 6.031 7.942 9.976 11.889
SCHEDULE 40 PVC Minimum Wall Thickness inches 0.113 0.133 0.140 0.145 0.154 0.203 0.216 0.237 0.258 0.280 0.322 0.365 0.406
Pounds per 100 ft 22.6 33.3 45.0 53.7 72.0 113.6 148.8 211.8 287.4 373.3 561.9 796.6 1053.4
Nominal size 1 1 1 2 2 3 4 5 6 8
O.D. inches 0.840 1.050 1.315 1.660 1.900 2.375 2.875 3.500 4.500 5.563 6.625 8.625
Average I.D. inches 0.526 0.722 0.936 1.255 1.476 1.913 2.290 2.864 3.786 4.768 5.709 7.565
SCHEDULE 80 PVC Minimum Wall Thickness inches 0.147 0.154 0.179 0.191 0.200 0.218 0.276 0.300 0.337 0.375 0.432 0.500
Pounds per 100 ft 21.3 28.9 42.4 58.6 71.1 98.4 150.0 201.0 293.8 407.8 561.0 852.2
Spacing-
Spacing shown is set for a 100 maximum temperature. The physical properties of PVC material are: E = 410,000 psi Tensile Strength = 7300 psi at 78F Working Stress in Bending = 4.0 ksi Temperature coefficient = 0.035 per 100/ft
Commentary
The Table was taken from the July 2005 WSDOT Bridge Design Manual. The values were obtained from ASTM D1785 and Harvel Plastics. Revisions:
STRUCTURE WIDTH
BRIDGES NO SIDEWALK
Concrete Parapet
BRIDGES RAISED SIDEWALK WITH SPEEDS 45mph AND LOWER Combination Rail
B2.4A Utility Hangars for Prestressed Girders June 2006 Added new standard drawing for attaching water, sewer, and gas lines to new bridges. B2.4B Utility Hangars for Prestressed Girders June 2006 Added new standard drawing for attaching power, and communication lines to new bridges
EQ shall be assumed as 0.0 for Extreme Event I Load Combination. SE & TG shall be taken as follows:
0.0 for strength and extreme event limit states 1.0 for service limit states if live load is not considered 0.5 for service limit states with live load
MPF for design year ADTT>1000 in one direction 1.20 1.00 0.85 0.65
Adjusted MPF for design year (0.95) 100ADTT1000 in one direction 1.14 0.95 0.81 0.62
Adjusted MPF for design year (0.90) ADTT<100 in one direction 1.08 0.90 0.77 0.59
Commentary:
The multiple presence factor adjustment is described in C3.6.1.1.2.
Deleted 17th Edition Design for Local and Off System bridges. Added Commentary.
3.6.1.3.2 Loading for Optional Live Load Deflection The live load deflection should be based on the provisions of this article.
Lane Load
Fill Depth
CMP
Article 3.6.5.2 Page 1 of 1 4/2001 3.6.5.2 VEHICLE AND RAILWAY COLLISION WITH STRUCTURES
The provisions of this article shall also apply to columns of spill-through abutments contained within MSE wall fills. The 400-KIP collision force shall be assumed to act perpendicular to the face of the MSE wall at a distance of 4.0 FT above ground. Furthermore, the collision force shall be distributed over a MSE wall area not greater than 5.0 FT wide by 2.0 FT high and distributed through the fill in accordance with Article 3.6.1.2.6, where the fill depth shall be taken as the cover distance measured from the back face of the MSE wall panel to the face of the CMP pipe. The resulting pressure shall be assumed to act on the full diameter of the CMP and applied as a line load acting along the longitudinal axis of the column. 5 400 kips
Fill depth
CMP
5 + 1.15*fill depth
PLAN
MSE Wall Fill depth CMP
400 kips
2 + 1.15*fill depth
Finished grade
ELEVATION
=100
=180
Revised article to agree with 2008 Interims. Revised map to only show active fault locations.
Changed reference from 3.10.3 to 3.10.5 to agree with the 2008 Interims.
April 46 49 44
Mean Daily Temperatures from NWS historic climate summaries May June July August September 55 62 69 68 59 58 66 74 73 63 53 61 68 67 57
October 49 52 46
effective span
Schedule Number 1 concrete is intended for placement in the substructure. Typical placement is below the beam seats at abutment and piers and at wing walls. Schedule Number 2 concrete is intended for placement in the superstructure. Typical placement is above the beam seats.
CLASS OF CONCRETE The class of concrete is specified in 100 psi 28-day strength. Refer to Bridge LRFD Manual Article 5.12 for additional requirements on classes of deck concrete. Class Strength-psi Seal NA Use for underwater placement for sealing cofferdams 15 30 40 40A 1500 Use for a leveling course 3000 Not recommended for structural applications. 4000 Recommended for most structural members. Intended for use when high entrained air and low slump are necessary for extreme exposure and wear. Typical applications are deck slabs, curbs, and parapets. Intended for use when air entrained concrete is desirable for substructure elements. Typical applications are abutments, piers, pier caps, columns, and wing walls.
40B
The properties for structural concrete placed underwater shall be specified by a Special Provision. ALKALI SILICA REACTIVITY All coarse and fine aggregate for concrete shall be tested for ASR according to the Standard Specifications subsection 703.02 & 703.03. Aggregates found to be potentially reactive shall require mitigating measures. The mitigative additives may be fly ash, lithium or other additives in any combination. The proposed mix design shall be tested with the mitigative additives. BID ITEMS Concrete should be specified as follows:
Class 40A, Class 40B, and Seal Concrete bid items should be used. Do not specify concrete classes with fly ash.
Commentary Fly ash can not be produced that conforms to ITD Specifications and specifying fly ash on the contract plans will require the Resident Engineer to write a change order deleting it. The contractor may add fly ash to enhance the mix design at his option.
Fly ash concrete paragraph deleted and replaced with ASR paragraph to conform to the 2004 ITD Standard Specifications. Added Seal, Class 15, and Underwater structural concrete to Class of Concrete
April 2008
Article 5.4.3 Page 1 of 1 10/2000 5.4.3 REINFORCING STEEL 5.4.3.3 Special Applications
The maximum length of #3 and #4 bars shall be 40. The maximum length of #5 through #18 bars shall be 60.
For Service and Extreme Event Limit States see 1.3.2 Limit States (Resistance Factors) See article 5.10.11.4.1b for concrete columns in Seismic Zones 3 & 4.
Article 5.7.1 Page 1 of 1 3/2003 5.7.1 ASSUMPTIONS FOR SERVICE & FATIGUE LIMIT STATES
The following are ITDs preferred assumptions that differ from the LRFD Code: The modular ratio, n, should be equal to Es/Ec and not rounded. An effective modular ratio of n should be used for permanent loads and prestress.
Commentary
The computations require more effort to differentiate n and 2n, and the use of 2n for creep effects appears to increase fs only 1-2%.
e = 1.0 kips/inch
Components exposed only to the effects of weather such as pier caps and columns.
Class 2 Exposure
e = 0.75 kips/inch
Components exposed to earth fill or submerged in water such as abutments, wings, and footings. Also Deck slabs not designed in accordance with Article 9.7.2.
Ag
Ac
Commentary: From Oregon DOT Bridge Engineering Section Office Practice Manual 2003, Section 5.1.7.5
Commentary: At sections other than at the end, the values of Mu, Nu, Vu, Vs, Vp, and are assumed to apply over a bandwidth that is centered on the section under consideration. At the end, the bandwidth is taken as the distance from the inside edge of the bearing area to the section of critical shear. The code is not clear regarding what values of Mu, Nu, Vu, Vs, Vp, and apply over the bandwidth at the end. The commentary allows using Vu, Vs, Vp, and calculated at the section of critical shear over this bandwidth (Refer to C5.8.3.5.). Mu is taken as 0.0 ft-kips over this bandwidth. For uniformity within the Bridge Section, we have chosen to use the method in the commentary.
Method 1 is an approximate method that gives reasonably good results (as compared to Method 3) for conventional prestressed girders with a composite cast-in-place deck; however this method can be unconservative for girders without a cast-in-place deck. Method 2 is the least accurate method and should not be used for final design. Method 3, the refined method, presumably results in the most accurate estimate of long-term losses for all prestressed girder types with or without a cast-in-place deck, however it requires significantly more effort than either Method 1 or 2. For typical bridge construction with a conventional prestressed girder and a cast-in-place deck, Method 3 will not yield significantly different or better results as compared to Method 1. It is the Bridge Sections opinion that for conventional prestressed girders with cast-in-place deck the presumed level of accuracy achieved by using Method 3 is seldom warranted or even possible because the material properties that effect creep and shrinkage and the times for various load application are either unknown or beyond the control of the bridge designer. In general, Method 1 may be used for typical ITD bridge construction that involves precast, pretensioned members with a composite cast-in-place slab. Method 3 may be used for all prestressed girder types but must be used for precast, pretensioned members without a composite slab (such as deck bulb tees, side-by-side voided slab sections, etc) the use of Method 1 in this case would be unconservative. Method 2, if used at all, should be limited to preliminary designs only, not for final design. The term construction staging as used in C5.9.5.3 is understood to refer to a member that is constructed in stages rather than a bridge that is constructed in stages. Examples of members that are constructed in stages are segmental construction and post-tensioned spliced precast girders.
Design Assumptions for Method 3 (refined estimate of losses) It is ITD policy to use 55% humidity for all locations in Idaho. When using the refined estimate of losses (Method 3) there are some assumptions that need to be made concerning the age of the girder concrete (ageing starts at the end of the cure period) at transfer, at deck placement and at final time. Also the age of the deck concrete is also required for the determination of losses or gains due to loads applied to the composite section (such as rail loads and wearing surfaces). Because these ages are not usually known during the design process some conservative assumptions should be made.
Commentary:
The total loss of prestress, fpT, is defined as the difference in the stress in prestressing strands immediately before transfer (the jacking stress) and the effective stress in the prestressing strands after all losses, fpe. The total loss of prestress, fpT, is further defined as the sum of elastic losses and long-term (also called time-dependent) losses. For typical pretensioned, precast members with low-relaxation strand, the above definitions can be re-stated as the following equations: fpe = (0.75 * 270 ksi) fpT fpT = fpES + fpLT Where 0.75 * 270 ksi is the jacking stress. Where fpES is the elastic loss and fpLT is the long-term loss.
(Eqn. 5.9.5.1-1)
fpES , elastic losses or gains, occur instantaneously at the time of load application. While fpES consists of many different components, one for each load, there are two general categories. The first category is the elastic loss that occurs immediately after transfer of the prestress force to the girder (loss due to prestress combined with gain due to the member self weight). The second category is the loss or gain due to additional loads, such as non-composite dead loads, composite dead loads and live loads that are applied after transfer. It is ITDs policy to ignore the effects of this second category for simplicity and the fact that it is conservative to due so because in most cases this effect would result in a gain or increase in prestressing force. fpLT , long term losses, occur due to long-term shrinkage and creep of concrete, and relaxation of the prestressing steel. Sign Convention When loads or prestressing forces cause a member to shorten or the strands are allowed to relax, the tension stress in the strands decreases and the strands undergo a loss. A loss is considered to be a positive quantity. When loads cause the strands to elongate, the tension stress in the strand increases and the strands undergo a gain. A gain is considered to be a negative quantity. For typical construction, the losses will be greater than the gains, and the sum of losses and gains will result in an overall loss. fpT will typically be a positive quantity that is subtracted from the jacking stress.
Article 5.10.10.1 Page 1 of 1 8/1999 5.10.10.1 FACTORED BURSTING RESISTANCE - PRETENSIONED ANCHORAGE ZONES
In this section, the prestressing force at transfer is to be taken as the prestressing force just after transfer. This means that the loss due to elastic shortening should be subtracted out. For example, for low-lax strands the stress in the strand equals 0.75*fpu fpES where fpES is computed per section 5.9.5.2.3.
Article 5.10.11.4.1d Page 1 of 1 9/2004 5.10.11.4.1d TRANSVERSE REINFORCEMENT FOR CONFINEMENT AT PLASTIC HINGES
The commentary for this article specifies a maximum spacing of 8 center-center of longitudinal bars.
8 maximum
Interlocking spirals shall be used for non-circular columns. Reinforcement details are shown in the following sketch.
0.75D max
All State and Locally sponsored projects shall be required to provide a deck protection system in the design and construction on all new concrete bridge decks, regardless of the winter roadway maintenance salt policy. Both mats of reinforcing steel should be considered for epoxy coating in deck slabs that will be carrying high volumes of traffic and will be subjected to frequent winter salting applications. Since both high traffic and frequent salting will occur primarily in urban areas, all structures located in urban areas shall be evaluated for a dual protection system. A Single Deck Protection System is the minimum acceptable deck protection for decks exposed to traffic on all interstate, state, or county highways unless additional deck protection is required. The single deck protection system shall meet the requirements listed below. The type of deck protection system shall be shown or noted on the Situation and Layout Drawing. EXPOSED DECK SLAB The deck slab is considered exposed to traffic when the distance between the finished grade and the top of the concrete deck is less than 4 inches between the paved roadway shoulders. SINGLE DECK PROTECTION SYSTEM The concrete deck shall have an 8-inch minimum thickness of Class 40A concrete, which includes a inch expendable wearing surface that is considered as added dead load and not having structural capabilities. The top mat of reinforcement shall have 2 inches of cover. All reinforcement within 4 inches of surfaces exposed to traffic shall be epoxy coated, including concrete parapets. DUAL DECK PROTECTION SYSTEM A dual deck protection system shall be utilized for all structures requiring special construction techniques or that have been classified as major or unusual bridges. Any structure that will require shoring for removal and repair of the deck (e.g. CIP box girders, CIP tee beams, CIP slab bridges) shall have a dual protection system. Deck slabs on box girder bridges are difficult and costly to repair unless the deck is designed so a portion of the deck can be removed without requiring shoring, such as the Type 1 dual deck protection system. The dual deck protection system shall meet the requirements listed for one of the 3 following types. The type selected will require the approval of the Bridge Design Engineer prior to incorporating that system in the design. TYPE 1 The concrete deck shall have a 7 inch minimum thickness of Class 40A concrete, which does not include the 1 inch of replaceable wearing surface that is considered as added dead load and not having structural capabilities. The top mat of reinforcement shall have 1 inches initial cover (before scarification of inches). The deck shall be designed so that the top 1 inches can be removed without requiring shoring while maintaining traffic on a portion of the deck. The replaceable wearing surface of 1 inches shall be latex modified concrete or micro silica modified concrete. All reinforcement within 4 inches of surfaces exposed to traffic shall be epoxy coated, including concrete parapets. TYPE 2 The concrete deck shall have an 8-inch minimum thickness of Class 40A concrete, which includes a 1-inch expendable wearing surface that is considered as added dead load and not having structural capabilities. The top mat of reinforcement shall have 3 inches of cover. All reinforcement within 4 inches of surfaces exposed to traffic shall be epoxy coated, including concrete parapets. TYPE 3 Bridges using precast prestressed boxes or slabs as the deck to support traffic shall use the Type 3 Dual Deck Protection System. The concrete class and member sizes for precast, prestressed deck members shall be determined by design. The top mat of reinforcement shall have 2 inches of cover. The top surface of precast beams that act as the bridge deck shall have an asphalt overlay of 1 inches with an interlayer waterproofing membrane. Prior to placement of the membrane, all joints between precast units that exceed inch difference in elevation shall be over grouted to accommodate hand finishing. The grouted slopes
BURIED DECK SLABS The deck slab is considered buried when the distance between the finished grade and the top of the concrete deck is greater than 4 inches between the paved roadway shoulders. This generally applies to box culverts and stifflegs where roadway ballast is carried over the top slab. UNDER ROADWAY WITH LESS THAN 2 FEET FILL The deck slab shall be Class 40A concrete with a waterproof membrane applied as specified in Section 511 of the Standard Specifications. The top mat of reinforcement shall have 2 inches of cover. Both mats of reinforcement in the deck slab shall be non-epoxy coated bars. OUTSIDE ROADWAY OR FILL EXCEEDS 2 FEET The deck slab shall be Class 40B concrete. The top mat of reinforcement shall have 2 inches of cover. Both mats of reinforcement in the deck slab shall be non-epoxy coated bars.
ELECTRICAL CONNECTION TO BRIDGE DECK REINFORCEMENT The following is standard practice for locating electrical test connection points on the edges of new concrete bridge decks. CADDS cell on B5.7 is available for use on the plans. PLAIN & EPOXY COATED REINFORCEMENT Each deck section shorter than 250 should have two connection points. These connections should be located at the extreme ends of the deck section, within 3 of the ends of the deck section. The connections should be located on opposite sides of the deck. On decks greater than 250, electrical connection points should be evenly spaced, but no more than 250 apart. Locations should alternate between opposite edges of the deck. Spacing should be adjusted so that there is a connection point within 3 of each end of the deck section. A deck section is defined as a portion of deck where the longitudinal reinforcement is continuous throughout. The section ends at any point where there is a transverse joint if the longitudinal reinforcement does not pass through the joint. At a construction joint, where longitudinal steel is carried through the joint, the deck on both sides of the joint is part of a single, continuous deck section for electrical testing purposes.
CATHODIC PROTECTION On decks designed for cathodic protection, connection points shall be installed in the same locations as for ordinary reinforcement. In addition, some means must be provided to break the cathodic protection circuit so that readings can be taken with the protective current shut off.
PRECAST PRESTRESSED SLABS Electrical connection points are not required for precast, prestressed slab bridges and deck bulb-tee bridges.
Added paragraph for Electrical Connections to Bridge Decks that was in the ITD Bridge Metric/English Manuals.
Article 5.12 Page 3 of 3 6/2006 DECK PROTECTION SYSTEM DETAILS FOR NEW CONCRETE BRIDGE DECKS
Transverse Rebar
1 1/2" Micro Silica Modified Concrete or 1 1/2" Latex Modified Concrete Overlay
Cove
8"
7 1/2"
1 Cove
1"
Longitudinal Rebar
Cove
3"
Transverse Rebar
1" Wearing
8 1/2"
Slab By
1" Cove
Longitudinal Rebar
1" Cove
Longitudinal Rebar
Deep Bulb Tee Girders 66 inch and deeper bulb tee girders shall have temporary diaphragms installed between the exterior and first interior girder. These diaphragms shall be placed midway between all permanent diaphragms as well as the end beams before pouring the permanent diaphragms and end beams. Temporary diaphragms shall be removed after the deck overhang brackets have been removed. Expansion Ends To facilitate jacking for future repairs at simply-supported ends of precast, prestressed girder bridges, the end diaphragms shall be designed for a minimum clearance of 10 inches above the level of the beam seats on piers and abutments. No extra reinforcement is required beyond that provided for normal dead, live and impact loads. Continuous Ends The end of girders in bridges designed without expansion joints shall be cast into full-depth end diaphragms.
Commentary
Since most of the precast elements that are used are steam cured and the mix designs given in the ITD Standard Construction Specifications has replaced cement with fly-ash at a greater rate than one to one, the values as listed in this specification will not be correct.
Article 5.14.1.2.7 Page 1 of 1 12/2001 5.14.1.2.7 SIMPLE SPAN PRESTRESSED GIRDERS MADE CONTINUOUS
Negative Moments The following design criteria shall apply for the design of the negative moment steel in the deck. Case 1 Girders Designed As Simple Spans & Reinforcement Added To Control Cracking. (This is the typical design case for new bridges) The top longitudinal deck reinforcement over the piers, in addition to the standard empirical design reinforcement, shall be #6 bars at 12 spaced between the standard top deck bars. The full area of the additional reinforcement shall extend either direction from the bearing centerlines a distance of at least 10 feet or 15% of the longer span whichever is greater. At least half the area of the additional reinforcement shall extend to a distance from the pier of at least 15 ft or 20% of the longer span whichever is greater. The bottom longitudinal deck reinforcement shall be per the empirical design method, Article 9.7.2. Case 2 Girders Designed Fully Continuous For Live Load (This case may be used for new bridges where Case 1 is not feasible) The weight of the parapet may be distributed evenly to all the girders. The maximum negative moment may be taken at the face of the support. Longitudinal reinforcement shall be anchored in accordance with Article 5.14.1.2.7b. The section shall meet Strength 1 limit state requirements as follows: 1.25*DCnoncomposite, acting as simply supported and 1.25*DCcomposite + 1.5*DW + 1.75*LL, acting as a continuous beam. Both layers of steel in the deck may be used in resisting the negative moments. Only structures with fully effective construction joints at the piers, per Article 5.14.1.2.7c, shall be designed as continuous for the Service III limit state. This may be accomplished by placing the pier diaphragm concrete and the negative moment regions of the deck first and the positive moment regions only after the pier diaphragm concrete has reached 100% of its design strength. Case 3 Girders Designed As Simple Spans And The Deck Is Replaced To Eliminate Joints. (This case is used for existing bridges that are retrofitted) No design is required. Use #5 bars in the top mat at approximately 12 spacing over the piers and carry them at least a development length past the face of the support but not beyond the 1/4 pt.
Commentary
Case 1 The additional reinforcement is based on providing enough steel in the deck over the piers to limit the top deck steel stress to 36 ksi, the maximum allowed for serviceability. This is based on the assumption that all girders act together as a single unit, as in deflection calculations, and that the distance between the centerlines of bearings for each of the spans on a bent is at least 24 inches. The 24 inches between bearings is assumed to act as a short span between the main spans with a moment of inertia of a cracked section. The additional deck steel along with the steel provided in the empirical design method may not supply enough negative moment capacity to resist the full negative moments that would be realized in continuous girder design, however it will provide enough restraint to limit the steel stress to 36 ksi under service loads for all prestressed girder depths up to 72. Case 2 If the negative moment areas of the deck are placed first it may be assumed that the provisions of Article 5.14.1.2.7c are met. However, the deck reinforcement over the piers will then need to be designed for the negative moments at the piers generated by the concrete placed in the positive moment areas of the spans in addition to the composite loads. Otherwise the calculations of Article 5.14.1.2.7c will need to be provided in order to utilize continuity for Service III.
Article 5.14.1.4 Page 1 of 2 6/2006 5.14.1.4 SIMPLE SPAN PRESTRESSED GIRDERS MADE CONTINUOUS
The following design criteria shall apply for the design of simple span prestressed girder bridges constructed with a continuous concrete deck (no expansion joints at the piers). Case 1 Girders Designed As Simple Spans & Top Deck Reinforcement Added To Control Cracking. (This is the typical design case for new bridges) The top longitudinal deck reinforcement over the piers, in addition to the standard empirical design reinforcement, shall be #6 bars at 12 spaced between the standard top deck bars. The full area of the additional reinforcement shall extend either direction from the bearing centerlines a distance of at least 10 feet or 15% of the longer span whichever is greater. At least half the area of the additional reinforcement shall extend to a distance from the pier of at least 15 ft or 20% of the longer span whichever is greater. The bottom longitudinal deck reinforcement shall be per the empirical design method, Article 9.7.2. A positive moment connection at the piers shall be provided. This shall entail extending the required number of prestressing strand beyond the end of each girder 8 horizontally then bent vertical and anchored in the pier diaphragm. See details on standard drawing for Prestressed AASHTO Girder Details B5.2D or Prestressed Bulb Tee Girder Details B5.3O.
Varies
Case 2 Girders Designed Fully Continuous For Live Load (This case may be used for new bridges where Case 1 is not feasible and approved by the Bridge Engineer) The weight of the parapet may be distributed evenly to all the girders. The negative moment reinforcement shall be determined based on the maximum negative moment taken at the face of the support. Longitudinal reinforcement shall be anchored in accordance with Article 5.14.1.2.7b. The section shall meet Strength 1 limit state requirements as follows: 1.25*DCnoncomposite, acting as simply supported and 1.25*DCcomposite + 1.5*DW + 1.75*LL, acting as a continuous beam. Both layers of steel in the deck may be used in resisting the negative moments. Only structures with fully effective construction joints at the piers, per Article 5.14.1.4.3, shall be designed as continuous for the Service III limit state. The requirements of Article 5.14.1.4.3, may be considered satisfied if the girder age is at least 90 days at the time the continuity diaphragm is placed. A positive moment connection at the piers shall be provided with a minimum capacity, Mn, of 1.2Mcr in accordance with NCHRP Report 519. Case 3 Girders Designed As Simple Spans And The Deck Is Replaced To Eliminate Joints. (This case is used for existing bridges that are retrofitted) No design is required. Use #5 bars in the top mat at approximately 12 spacing over the piers and carry them at least a development length beyond the centerline of bearing of the girders but not beyond the 1/4 pt. of the span.
Commentary
Case 1 The additional reinforcement in the top of the deck is based on providing enough steel over the piers to meet the requirements for control of cracking in the deck per Article 5.7.3.4 assuming the total Service 1 live load is distributed equally to all girders. This additional deck steel may not supply enough negative moment capacity to resist the full negative moments that would be required in a continuous girder design for Strength 1 loading, however it will provide enough reinforcement to limit the steel stress requirements for crack control for spans up to 130 and girder depths up to 73.5. Girders not specifically designed for continuous action should still be provided with a positive moment connection in order to prevent possible cracking in the diaphragm and also to securely anchor the girders in the diaphragm. The number of prestressing strands that are extended into the pier diaphragm is based on the area of steel required to provide a moment capacity, Mn, sufficient to resist 0.6Mcr for the composite girder section in positive bending based on Mcr = Sfr where S is the composite section modulus and fr is the modulus of rupture equal to 0.24f`c where f`c is the strength of the diaphragm concrete. ITDs maximum slab thickness and the maximum effective composite slab width per Article 4.6.2.6.1 were used to establish the number of strands required for the various girder depths as well as development length. However, the number of strand and the development length shown on the standard drawing may be considered adequate. Case 2 Since the effects due to creep and shrinkage are highly dependent on conditions beyond the control or knowledge of the designer, it is more practical to allow the girders to age for 90 days before continuity is established in order to negate the effects of creep and shrinkage rather than attempting to calculate these effects based on assumed conditions and material properties that can vary significantly.
Article A5.2 Page 1 of 4 12/2004 TENSION DEVELOPMENT LENGTH Grade 60 reinforcement; 4000 psi concrete 5.11.2.1.1 TENSION DEVELOPMENT LENGTH MODIFICATION FACTORS FOR OTHER PLAIN BARS Lateral c-c spacing >= 6" & cover along spacing >= 3" (1) (2) Enclosed by spiral with diam > 0.25" & pitch <= 4"
0.80 0.75
MODIFICATION FACTORS FOR TOP PLAIN BARS (1) Lateral c-c spacing >= 6" & cover along spacing >= 3" (2) Enclosed by spiral with diam > 0.25" & pitch <= 4"
Top Bar
Article A5.2 Page 2 of 4 12/2004 TENSION DEVELOPMENT LENGTH Grade 60 reinforcement; 4000 psi concrete MODIFICATION FACTORS - OTHER EPOXY BARS (1) Cover <= 3*Db (2) Cover > 3*Db (3) Clear spacing <= 6*Db (4) Clear spacing > 6*Db (5) Lateral c-c spacing >= 6" & cover along spacing >= 3" (6) Enclosed by spiral with diam > 0.25" & pitch <= 4" EPOXY BARS - OTHER
3 4 1.500 3.000 18 15 18 15 15 12 14 12 14 12 12 12 5 1.875 3.750 23 18 23 18 18 15 17 14 17 14 14 12 6 2.250 4.500 27 22 27 22 22 18 21 17 21 17 17 13 7 2.625 5.250 34 27 34 27 27 22 26 21 26 21 21 17 8 3.000 6.000 45 36 45 36 36 29 34 27 34 27 27 22 9 3.384 6.768 57 45 57 45 45 36 43 34 43 34 34 27 10 3.810 7.620 72 58 72 58 58 46 54 43 54 43 43 35 11 4.230 8.460 88 71 88 71 71 57 66 53 66 53 53 43 14 5.079 10.158 122 98 122 98 98 78 92 73 92 73 73 59 18 6.771 13.542 158 126 158 126 126 101 119 95 119 95 95 76
3*Db 6*Db (1) (2) (3) (4) (1) & (5) (2) & (5) (1) & (6) (2) & (6) (3) & (6) (4) & (6) (1) & (5) & (6) (2) & (5) & (6)
1.125 2.250 14 12 14 12 12 12 12 12 12 12 12 12
MODIFICATION FACTORS - TOP EPOXY BARS Cover <= 3*Db (1) (2) Cover > 3*Db (3) Clear spacing <= 6*Db (4) Clear spacing > 6*Db (5) Lateral c-c spacing >= 6" & cover along spacing >= 3" (6) Enclosed by spiral with diam > 0.25" & pitch <= 4"
Top Bars
3*Db 6*Db (1) (2) (3) (4) (1) & (5) (2) & (5) (1) & (6) (2) & (6) (3) & (6) (4) & (6) (1) & (5) & (6) (2) & (5) & (6)
1.125 2.250 16 16 16 16 16 13 15 12 15 12 12 12
Article A5.2 Page 3 of 4 12/2004 COMPRESSION DEVELOPMENT LENGTH Grade 60 reinforcement; 4000 psi concrete MODIFICATION FACTORS (1) Basic development length (2) Enclosed by spiral with diam > 0.25" & pitch <= 4"
1.00 0.75
4 10 8
5 12 9
6 15 11
7 17 13
8 19 15
9 22 16
10 25 19
11 27 20
14 32 24
18 43 32
(1) (2)
8 8
Article A5.2 Page 4 of 4 12/2004 HOOKED TENSION DEVELOPMENT LENGTH Grade 60 reinforcement; 4000 psi concrete MODIFICATION FACTORS FOR PLAIN BARS (1) Basic hooked development length (2) Side cover for <#14 bar normal to plane of hook >=2.5" (3) (4)
90 hook: Side cover for <#14 bar normal to plane of hook >=2.5" & cover on extension beyond hook >=2" Hooks for <#14 enclosed in stirrups/ties along full development length at a spacing <=3*Db
PLAIN BARS
3 4 1.5 10 7 7 8 6 6 5 1.875 12 9 9 10 7 7 6 2.25 15 10 10 12 8 8 7 2.625 17 12 12 14 10 10 8 3 19 14 14 16 11 11 9 3.384 22 16 16 18 13 13 10 3.81 25 17 17 20 14 14 11 4.23 27 19 19 22 16 16 14 5.079 33 18 6.771 43
3*Db (1) (2) (3) (4) (2) & (4) (3) & (4)
1.125 8 6 6 6 6 6
MODIFICATION FACTORS FOR EPOXY BARS Basic hooked development length (1) Side cover for <#14 bar normal to plane of hook >=2.5" (2) (3) (4)
90 hook: Side cover for <#14 bar normal to plane of hook >=2.5" & cover on extension beyond hook >=2" Hooks for <#14 enclosed in stirrups/ties along full development length at a spacing <=3*Db Epoxy Bar
EPOXY BARS
3 4 1.500 12 8 8 10 7 7 5 1.875 15 10 10 12 8 8 6 2.250 18 12 12 14 10 10 7 2.625 20 14 14 16 12 12 8 3.000 23 16 16 19 13 13 9 3.384 26 19 19 21 15 15 10 3.810 29 21 21 24 17 17 11 4.230 33 23 23 26 19 19 14 5.079 39 18 6.771 52
3*Db (1) (2) (3) (4) (2) & (4) (3) & (4)
1.125 9 6 6 7 6 6
5.11.5.3.1 LAP SPLICES IN TENSION Grade 60 reinforcement; 4000 psi concrete (1) (2)
Lateral c-c spacing >= 6" & cover along spacing >= 3" Enclosed by spiral with diam > 0.25" & pitch <= 4"
148 194 147 118 155 118 112 146 111 90 117 89
Cover <= 3*Db Cover > 3*Db Clear spacing <= 6*Db Clear spacing > 6*Db Lateral c-c spacing >= 6" & cover along spacing >= 3" Enclosed by spiral with diam > 0.25" & pitch <= 4"
3*Db
A
1.125
(1) (2) (3) (4) (1) & (5) (2) & (5) (1) & (6) (2) & (6) (3) & (6) (4) & (6) (1) & (5) & (6) (2) & (5) & (6)
14 12 14 12 12 12 12 12 12 12 12 12
114 150 122 92 92 92 74 86 69 86 69 69 56 121 121 121 97 112 90 112 90 90 73 98 98 98 78 92 73 92 73 73 59 114 150 122
159 207 158 127 167 126 159 207 158 127 167 126 127 167 126 101 133 101 120 156 119 95 95 95 77 124 124 124 100 95 95 95 76 120 156 119
205 269 164 214 205 269 164 214 164 214 131 172 155 202 124 162 155 202 124 162 124 162 99 129
3*Db
A
1.125
(1) (2) (3) (4) (1) & (5) (2) & (5) (1) & (6) (2) & (6) (3) & (6) (4) & (6) (1) & (5) & (6)
16 16 16 16 16 13 15 12 15 12 12
105 138 100 105 138 105 138 105 138 85 99 79 99 79 79 111 129 104 129 104 104 99 99 99 79 93 74 93 74 74 105 138 100
130 170 138 129 168 137 130 170 138 129 168 137 129 168 137 103 134 109 121 158 128 96 96 96 126 103 126 103 126 103 121 158 128
179 235 179 178 233 177 179 235 179 178 233 177 178 233 177 142 185 142 166 218 166 134 175 133 166 218 166 134 175 133 134 175 133
233 304 230 301 233 304 230 301 230 301 185 241 216 282 173 226 216 282 173 226 173 226
Article A5.3 Page 3 of 3 12/2004 COMPRESSION DEVELOPMENT LENGTH Grade 60 reinforcement; 4000 psi concrete MODIFICATION FACTORS Basic development length (1) (2) Ties along splice with effective area >= 15% of (compression component thickness)*(tie spacing) With spirals (3)
4 15 13 12
5 19 16 15
6 23 19 17
7 27 22 20
8 30 25 23
9 34 29 26
10 39 32 29
11 43 36 32
14 51 43 39
18 68 57 51
12 12 12
Article A5.4 Page 6 of 15 7/2009 37 TOP FLANGE BULB TEE GIRDER SECTION PROPERTIES
CENTER OF GRAVITY DEPTH 30" 36" 42" 48" 54" 60" 66" 72" 84" AREA 449.9375 491.9375 533.9375 575.9375 617.9375 659.9375 701.9375 743.9375 827.9375 TOP 15.644 18.857 22.036 25.190 28.322 31.438 34.539 37.630 43.783 BOTTOM 14.356 17.143 19.964 22.810 25.678 28.562 31.461 34.370 40.217 MOMENT OF INERTIA 51,361 82,126 121,708 170,872 230,379 300,990 383,465 478,562 709,652
3-1
SECTION MODULUS WEIGHT LB/FT TOP 3,283 4,355 5,523 6,783 8,134 9,574 11,102 12,718 16,208 BOTTOM 3,578 4,791 6,096 7,491 8,972 10,538 12,189 13,924 17,645 469 512 556 600 644 687 731 775 862
2 Fillet
1-1
Article A5.4 Page 9 of 15 7/2009 48 TOP FLANGE BULB TEE GIRDER SECTION PROPERTIES
CENTER OF GRAVITY DEPTH 49" 55" 61" 67" 73" 85" AREA 641.284 683.284 725.284 767.284 809.284 893.284 TOP 23.607 26.600 29.591 32.585 35.579 41.569 BOTTOM 25.393 28.400 31.409 34.415 37.421 43.431 MOMENT OF INERTIA 208,593 278,326 360,358 455,445 564,342 826,595 SECTION MODULUS WEIGHT LB/FT TOP 8,836 10,464 12,178 13,977 15,862 19,885 BOTTOM 8,215 9,800 11,473 13,234 15,081 19,032 668 712 756 799 843 931
4-0
2 Fillet
1-6
2-5/32
4-1
3 Fillet
15
12
21
15
15
18
10
26
Article A5.5 Page 2 of 3 7/2009 MAXIMUM SPAN LENGTH PRECAST PRESTRESSED SLABS
Span 12 Solid Slab 15 Solid Slab 15 Voided Slab 18 Voided Slab 21 Voided Slab 26 Voided Slab 20 30 30 40 50 55 # of strand 16 22 22 26 30 32 Center of gravity 3.75 4.18 4.18 4.31 4.80 6.38
DESIGN CRITERIA AASHTO LRFD Beams are parallel Minimum 4 girders 28 psf asphalt pavement 44'-0" out - out bridge width with a concrete parapet HL93 Live Load " 270k low relaxation strand Girder fc = 6000 psi maximum
Article A5.5 Page 3 of 3 7/2009 NOTES TO DESIGNER FOR PRECAST PRESTRESSED SLAB
The Standard Drawings for precast prestressed slabs are shown in Appendix B for Section 5. The following criteria shall be used in developing details for projects utilizing precast prestressed slabs: PRESTRESSING STEEL Prestressing steel shall be designed as straight strand. TIE RODS Tie rods spacing shall be as follows: SPAN 40' at centerline span SPAN > 40' at 1/3 points Tie rods shall be oriented as follows: skew angle < 20 parallel to centerline bearing skew angle > 20 perpendicular to slab centerline When tie rod lengths greater than 20' are required, specify heavy-duty sleeve nuts to obtain the required length. BEARING PADS Bearing pads should be designed in accordance with Article 14.7.5 of the Bridge Design Manual. The beam seat shall be parallel to the bottom of the beams. MEMBRANE SEAL A waterproof membrane seal shall be applied to the top surface of the slabs when an asphalt wearing surface is used. The membrane seal shall conform to Section 511, Concrete Waterproofing System, Type A or Type D.
ci
= 57.619
' ci
(ksi)
fci = girder concrete strength at release (psi) Ig = Moment of Inertia of girder (in4) L = span length (ft) Wbeam = beam dead load (kips/ft) Non-composite Dead Loads 5 w SDL L 4 1728 SDL = 384 E c I g Composite Dead Loads
Ec =
E ci 0.85
CDL
5 wCDL L 1728
4
384 E c I c
P e L *144 = 8 E I
i p g
Pi = P0 fES*Aps fu = strand ultimate strength (ksi) Aps = total area of strand (in2) P0 = 0.75*fu*Aps a = distance from end of girder to harp point (ft) eend = Yb - cgend emid = Yb cgmid Yb = centroid of girder from bottom (in) cg = strand center of gravity (in)
At Release: release = g + p
C1
C2
C3
C1 = Camber strip thickness at ends of girder C2 = Camber strip thickness at point of girder C3 = Camber strip thickness at mid-span of girder D and G must be first calculated to determine C1, C2, and C3. A positive value for D or G indicates the profile is above its respective base line.
HC =
1.5 s L 2 R S = super-elevation rate (ft/ft) R = radius of horizontal curve (ft) L = girder span length (ft)
C2
s W f 2
Girder Stirrups The 4 standard projection of the girder stirrup into the deck slab should be checked. The variable depth of the camber strip may require the stirrup projection to be increased so the hook is above the bottom mat of slab reinforcement or decreased so the hook is below the top mat of slab reinforcement.
Revisions: April 2008 July 2009 Revised fci to psi Added ksi units to definition of Eci Added 144 units conversion to straight strand p equation. Added paragraph on girder stirrups.
B5.2A AASHTO Type 2 Prestressed Girder July 2009 Modified the end block reinforcement to comply with AASHTO Article 5.10.10. B5.2B AASHTO Type 3 Prestressed Girder June 2006 Extended the 6 stirrup spacing in the end block to comply with AASHTO Article 5.10.10.2. July 2009 Modified the end block reinforcement to comply with AASHTO Article 5.10.10. B5.2C AASHTO Type 4 Prestressed Girder June 2006 Extended the 6 stirrup spacing in the end block to comply with AASHTO Article 5.10.10.2. July 2009 Modified the end block reinforcement to comply with AASHTO Article 5.10.10. B5.2D Prestressed AASHTO Girder Details June 2006 Extended strand for the positive moment connection in the Type C Diaphragm to comply with Article 5.14.1.4 of the LRFD Manual. Changed Abutment Diaphragm Dowel Details to Girder End Details and labeled Type C Positive Moment Connection. July 2009 Added Note 9 for size of strand used in the design. Revised Note 5 for lateral restraint until deck is cured. B5.2E Pier Diaphragm for AASHTO Girders June 2006 Extended strand for the positive moment connection and widened the gap between girder ends to 10. B5.3A 36 Bulb Tee Prestressed Girder July 2009 Modified the end block reinforcement to comply with AASHTO Article 5.10.10. B5.3B 42 Bulb Tee Prestressed Girder July 2009 Modified the end block reinforcement to comply with AASHTO Article 5.10.10. B5.3C 48 Bulb Tee Prestressed Girder June 2006 Extended the 6 stirrup spacing in the end block to comply with AASHTO Article 5.10.10.2. July 2009 Modified the end block reinforcement to comply with AASHTO Article 5.10.10. B5.3D 54 Bulb Tee Prestressed Girder June 2006 Extended the 6 stirrup spacing in the end block to comply with AASHTO Article 5.10.10.2. July 2009 Modified the end block reinforcement to comply with AASHTO Article 5.10.10. B5.3E 60 Bulb Tee Prestressed Girder June 2006 Extended the 6 stirrup spacing in the end block to comply with AASHTO Article 5.10.10.2. July 2009 Modified the end block reinforcement to comply with AASHTO Article 5.10.10. B5.3F 66 Bulb Tee Prestressed Girder June 2006 Extended the 6 stirrup spacing in the end block to comply with AASHTO Article 5.10.10.2. July 2009 Modified the end block reinforcement to comply with AASHTO Article 5.10.10. B5.3G 72 Bulb Tee Prestressed Girder June 2006 Extended the 6 stirrup spacing in the end block to comply with AASHTO Article 5.10.10.2. July 2009 Modified the end block reinforcement to comply with AASHTO Article 5.10.10. B5.3H 84 Bulb Tee Prestressed Girder June 2006 Added new standard drawing. July 2009 Modified the end block reinforcement to comply with AASHTO Article 5.10.10.
B5.3I 49 Bulb Tee Prestressed Girder June 2006 Added new standard drawing for bulb tee with 48 top flange. July 2009 Modified the end block reinforcement to comply with AASHTO Article 5.10.10. B5.3J 55 Bulb Tee Prestressed Girder June 2006 Added new standard drawing for bulb tee with 48 top flange. July 2009 Modified the end block reinforcement to comply with AASHTO Article 5.10.10. B5.3K 61 Bulb Tee Prestressed Girder June 2006 Added new standard drawing for bulb tee with 48 top flange. July 2009 Modified the end block reinforcement to comply with AASHTO Article 5.10.10. B5.3L 67 Bulb Tee Prestressed Girder June 2006 Added new standard drawing for bulb tee with 48 top flange. July 2009 Modified the end block reinforcement to comply with AASHTO Article 5.10.10. B5.3M 73 Bulb Tee Prestressed Girder June 2006 Added new standard drawing for bulb tee with 48 top flange. July 2009 Modified the end block reinforcement to comply with AASHTO Article 5.10.10. B5.3N 85 Bulb Tee Prestressed Girder June 2006 Added new standard drawing for bulb tee with 48 top flange. July 2009 Modified the end block reinforcement to comply with AASHTO Article 5.10.10. B5.3O WF42G Prestressed Girder July 2009 Added new standard drawing. B5.3P WF50G Prestressed Girder July 2009 Added new standard drawing. B5.3Q WF58G Prestressed Girder July 2009 Added new standard drawing. B5.3R WF66G Prestressed Girder July 2009 Added new standard drawing. B5.3S WF74G Prestressed Girder July 2009 Added new standard drawing. B5.3T WF83G Prestressed Girder July 2009 Added new standard drawing. B5.3U Prestressed Bulb Tee Girder Details June 2006 Renumbered the sheet and extended strand for the positive moment connection in the Type C Diaphragm to comply with Article 5.14.1.4 of the LRFD Manual. Changed Abutment Diaphragm Dowel Details to Girder End Details and labeled Type C Positive Moment Connection. July 2008 Added Note 12 for size of strand used in the design. July 2009 Renumbered the sheet from B5.3O to B5.3U. Added Note 9 for size of strand used in the design. Revised Note 5 for lateral restraint until deck is cured.
B5.3V Temporary Diaphragm Details June 2006 Renumbered the sheet. July 2009 Renumbered the sheet from B5.3P to B5.3V. B5.3W Pier Diaphragm for Bulb Tee Girders June 2006 Renumbered the sheet, extended the strand for the positive moment connection, and widened the gap between girder ends to 10. July 2009 Renumbered the sheet from B5.3Q to B5.3W. B5.4A Typical Deck Bulb Tee Section & Details June 2006 Added new standard drawing. July 2009 Corrected spelling of Bulb Tee in title block Corrected wording in Note 6(one to when) Added Note 14 placing girders perpendicular to the cross-slope. Changed intermediate diaphragm reinforcement G9, G9A, D1, &D2 to #4 Specified G9 & G9A bars @ maximum 12 spacing B5.4B Prestressed Deck Bulb Tee Girder June 2006 Added new standard drawing. April 2008 Defined W Changed G14 to #4 Computed max. spacing for G11 & G12 flange reinforcement Modified Reinforcement Diagram Sketch for G1, G5, G5A, G11, G13, & G14. July 2009 Modified Reinforcement Diagram Sketch for G6 & G8 Added G9 & G9A bars to Reinforcement Diagram Added spacing of intermediate diaphragm bars in the Elevation view Added confinement length Y and Bursting Reinforcement length Z to End Reinforcement Detail B5.4C Prestressed Deck Bulb Tee Girder Details June 2006 Added new standard drawing. July 2009 Added Note 11 for size of strand used in the design. Added Notes 12 & 13 for deflection data Modified Deflection Data Table for D B5.5F 2-2 Prestressed Voided Slab June 2006 Extended the 6 stirrup spacing in the end block to comply with AASHTO Article 5.10.10.2.
B5.5G Typical Prestressed Slab Details June 2006 Corrected the reference in Note 10 to paragraph H to conform to the 2004 Standard Specifications. July 2009 Added Note 19 for size of strand used in the design. B5.7A Box Girder Details June 2006 Renumbered the sheet. B5.7B Post-tensioning Standard Details June 2006 Renumbered the sheet. B5.8 Electrical Connection to Top Reinforcing Steel June 2006 Added new standard drawing.
In those cases where the bridge geometry does not meet the above conditions the baseline may be defined, at the discretion of the engineer, as something other than what is described above. In such cases a separate camber table may be required for each girder. Curved girders will always require a separate camber table for each girder. In all cases the definition of the baseline shall be clearly indicated on the bridge plans. It should be noted here that interior and exterior girders on straight bridges should be cambered the same even if the design dead loads are different. For camber purposes all dead loads should be distributed equally to all girders in a cross-section. If the exterior girders are cambered different from the interior it will not only be difficult to attach the cross-frames but it will be impossible to control the finished grade across the width of the deck with a screed machine supported on the exterior girders. If the screed rails are set for finishing to the exterior girders they will not be correct for finishing over the interior girders. The exterior and interior girders essentially deflect the same during deck placement due to the load distribution effects of the diaphragms. The second part of developing the camber diagram is determining the amount of offset from the baseline to the finished position of the girder after all permanent loads have been applied. For bridges with no vertical curvature or abrupt changes in cross-section this offset will be zero the full length of the girder. Bridges fully or partially on vertical curves will have camber values varying from zero at the ends to a maximum value near the center of the girder (with positive values for crest and negative values for sag vertical curves). These values should be labeled in the camber table as vertical curve. The third part of developing the camber diagram is determining the amount of deflection dead loads and deck shrinkage cause in the girder. There are four types of deflections to consider: the self-weight of the steel (non-composite load), the weight of the deck concrete (partial-composite load), the weight of all other dead loads such as parapet & future wearing surface (fullycomposite load) and the effect of deck shrinkage over time (fully-composite load). Each one of these deflection types are calculated separately and shown in the camber table, a downward deflection is shown as positive camber and vice versa. The camber diagram shall only show the total of all camber values added together for a given point. The calculation of the deflections for girder self-weight and the parapet & FWS are relatively straight forward, however the calculation of the deflections due to the deck concrete and shrinkage are more complex. It is ITD policy to determine deflections due to the deck concrete based on the pour sequence. The deflections of the first pour are based on the whole girder acting non-composite, then the deflections of the second pour are based on the area of the first pour acting compositely with the rest of the girder non-composite and so on until the last pour. The deflections due to each pour sequence are added together and only the total is shown in the camber table. For deck shrinkage deflections a method based on classical structure analysis is presented below. Other methods that utilize structural analysis software (such as LARSA) may also be used provided they are based on the same concrete shrinkage strain.
The shrinkage deflection of composite beams can be determined by substituting an equivalent compression force for the shrinkage strain, this force is applied to the ends of each girder segment at mid depth of the deck. For deflection purposes this eccentric compression load has the same effect as applying a positive moment to the ends of each girder segment (a segment being a length of girder with the same section properties). The magnitude of the applied moments is equal to the compression force times the distance from the mid depth of the deck to the c.g. of the composite section for that segment. Where two segments join the applied moment is the difference between the calculated moments for each segment. The equivalent force and moments are determined as follows: Fsh = (1 )sh AE/3 Mi = Fsh(cgi T/2) where: Fsh = compression force required to produce a strain equal to sh Mi = moment applied to each end of a particular segment to model the shrinkage effect A = tributary area of the deck per girder (use total area of deck divided by number of girders) E = modulus of elasticity of the concrete cgi = center of gravity as measured from the top of a particular composite section T = thickness of the deck = average ratio of longitudinal deck steel to deck area for a given girder segment Example of a two span bridge with two different girder sections:
Span 1 Span 2
M1
M2 - M1
M2 - M1
M1
Segment 1
Segment 2
Segment 3
The composite I for the girder sections in this analysis should be based on 3n to account for the long-term creep effect and, at the engineers option, the transformed deck section to take advantage of the deck reinforcement. The resulting deflections for this load case are equivalent to the shrinkage deflections. These deflections can then be added to the dead load deflections and combined with the vertical curvature corrections to determine the total camber. This method is appropriate for both single and multiple spans.
Revised the shrinkage strain calculations to comply with the 2005 Interims.
Inches
4 3 2 1
Baseline 0 Abut 1 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.75 0.9 Pier 0.1
0.4
0.5
0.6
0.7
0.8
0.9
Abut 2
Span 1 Field Splice 0.75 0.22 0.99 0.12 0.20 1.52 Field Splice 0.25 0.22 0.71 0.12 0.20 1.24
Span 2
Span Point Abut 1 Girder D.L. 0 * Deck D.L. 0 Shrinkage 0 All Other D.L. 0 Total Deflection Camber 0 Vertical Curve Total Camber 0 0
0.76 1.44 2.04 2.56 3.00 3.36 3.64 3.75 3.84 3.96 2.06 3.79 5.08 5.88 6.20 6.07 5.60 5.27 4.93 4.31 * The deck dead load deflections are not symmetrical because they are based on a three part deck placement sequence.
3.96 3.84 3.75 3.64 3.36 3.00 2.56 2.04 1.44 0.76 4.20 4.71 4.99 5.27 5.69 5.81 5.53 4.78 3.58 1.95
Article 6.10.3 Page 1 of 3 4/2008 6.10.3 Constructibility Considerations for Steel Plate Girder Bridges
There are several constructibility issues that are unique to steel plate girder bridges that designers should account for in the design, plan preparation, and shop drawing review stages of a project. Diaphragm Installation for Skewed Bridges: On straight non-skewed bridges all girders across the width of the bridge rotate at their bearings about a single axis line which is perpendicular to the girders, therefore as each girder is loaded all the girders rotate about a common line and the end diaphragms that connect the girders are unaffected. On skewed bridges each girder rotates about its own axis offset from adjacent girders, consequently as the girders are loaded and the girder ends rotate a distorting force is induced in the end diaphragms that connect the girders, since the diaphragms are very stiff diagonally and the girders are relatively flexible torsionally the diaphragms will twist the girders, pulling the web out of plumb. The angle that the girder web is twisted out of plumb can be calculated as follows: = tan() where: = the out-of-plumb angle = the bridge skew angle = the angle of the end of the girder due to the dead load camber (other than girder self weight)
Girder Line
Plan View
Span
While there is no way to prevent girder twisting without the complete removal of diaphragms, when and how the girders twist can be controlled by the way the girders are detailed and fabricated. If the girders and diaphragms are detailed and fabricated for the diaphragms to fit the initial position of the girders, before the bridge deck is placed, then the girders will be plumb when the erection is complete. However, after the deck is placed, the girders will be twisted permanently in their final position, the girders will not sit level on the bearings and high distortional stresses will be locked into the diaphragms and girders. The only advantage to this method is that the girders and diaphragms fit initially, making it easier for the contractor to assemble.
Screed Rail
Overhang Bracket
Girder Rotation
Downward Deflection
The magnitude of the deflection at the edge of the deck in relation to the exterior girder is dependent on several factors; rotational stiffness of the girder, diaphragm spacing, amount of deck overhang and screed weight and location. The calculation of actual rotational stiffness of a welded I-girder is complex, and is made more difficult by the use of diaphragms, the change in flange sizes and the use of unsymmetrical sections. However the problem can be simplified by assuming that any applied torsion acts as a couple with one component of the couple applied to the top flange and the other opposing component applied to the bottom flange. The flanges can then be assumed to carry their respective loads as independent beams in the lateral direction (neglecting the effect of the web). The sum of the two resulting deflections divided by the depth of the girder is the amount of rotation at any given location. This method is conservative and results in rotations approximately 10% greater than would be calculated from a more precise torsional stiffness analysis. The flanges can be assumed to be continuous beams along the length of the structure with the diaphragms acting as supports. As a result the diaphragm spacing becomes the effective span when calculating the lateral deflections in each flange. The diaphragms should also be checked to be sure they are structurally adequate to carry the resulting reactions.
e P
P equals Pe equals
P Pe/d
The couple that is applied to the flanges can be calculated from the net eccentric vertical loading applied to the exterior girders. A typical construction detail involves an overhang bracket on the exterior side of the girder and a beam hanger on the interior side. The loads from this arrangement are multiplied by their respective moment arms as measured from the centerline of the girder and algebraically added together resulting in the applied torsional moment. This moment is then divided by the girder depth and the resulting load applied to both the top and bottom flange to form a couple. The flanges are then checked for the greatest deflection case and the resulting deflections for the top and bottom flange are added together and divided by the girder depth, which will give the rotation in radians. This value is then multiplied by the overhang dimension giving the amount of deflection that will occur at the end of the overhang. The deflection at the overhang should not be greater than 0.20 inches.
Screed Rail
Overhang Bracket
Girder Rotation
Downward Deflection
The magnitude of the deflection at the edge of the deck in relation to the exterior girder is dependent on several factors; rotational stiffness of the girder, diaphragm spacing, amount of deck overhang and screed weight and location. The calculation of actual rotational stiffness of a welded I-girder is complex, and is made more difficult by the use of diaphragms, the change in flange sizes and the use of unsymmetrical sections. However the problem can be simplified by assuming that any applied torsion acts as a couple with one component of the couple applied to the top flange and the other opposing component applied to the bottom flange. The flanges can then be assumed to carry their respective loads as independent beams in the lateral direction (neglecting the effect of the web). The sum of the two resulting deflections divided by the depth of the girder is the amount of rotation at any given location. This method is conservative and results in rotations approximately 10% greater than would be calculated from a more precise torsional stiffness analysis. The flanges can be assumed to be continuous beams along the length of the structure with the diaphragms acting as supports. As a result the diaphragm spacing becomes the effective span when calculating the lateral deflections in each flange. The diaphragms should also be checked to be sure they are structurally adequate to carry the resulting reactions.
e P
P equals Pe equals
P Pe/d
The couple that is applied to the flanges can be calculated from the net eccentric vertical loading applied to the exterior girders. A typical construction detail involves an overhang bracket on the exterior side of the girder and a beam hanger on the interior side. The loads from this arrangement are multiplied by their respective moment arms as measured from the centerline of the girder and algebraically added together resulting in the applied torsional moment. This moment is then divided by the girder depth and the resulting load applied to both the top and bottom flange to form a couple. The flanges are then checked for the greatest deflection case and the resulting deflections for the top and bottom flange are added together and divided by the girder depth, which will give the rotation in radians. This value is then multiplied by the overhang dimension giving the amount of deflection that will occur at the end of the overhang. The deflection at the overhang should not be greater than 0.20 inches.
20 ft
20 ft
1" by 14"
25 ft
1" by 14 "
60 ft
40 ft
60 ft
3 ft
1.375" by 14"
1.625" by 14"
1.375" by 14"
Span 1 80 ft
Span 2 100 ft
Span 3 80 ft
The top and bottom flanges actually act as twelve continuous sections for lateral load, however the remote sections have very little effect on deflections. Only two sections behind and one section in front of the section being checked need to be considered in the structural model, this limits the analysis to no more than four sections (see case 1 and 2 in this example). There are four vertical loads that should to be considered for the rotational effects: 1. The deck overhang concrete load. 2. The deck interior bay concrete load reaction on the exterior girder. 3. The screed load on the overhang. 4. The construction live load and walkway load in the work zone. (The work zone is considered to be a 20 ft. long zone centered on the screed) It is not necessary to consider the weight of the falsework because it is already in place when the form grades and screed rail settings are made. In this example the deck weighs 100 lbs/ft2, however an assumption must be made for the screed load. In this example the screed is assumed to weigh 4500 lbs per side spread out over 10 ft. The construction live load is 30 lbs/ft2 and the walkway load is 75 lbs/ft. The load per foot of length with associated moment arms, the resulting torsion and the equivalent lateral load applied to the flanges are as follows:
Interior Deck
Total Lateral Concrete Loads = 171 81 = 90 lbs/ft Screed Load Load = 4500/10 = 450 lbs/ft MomArm = 3.25 ft Torsion = 450(3.25) = 1463 lbs*ft/ft Screed Lateral Load = 1463/3 = 488 lbs/ft Uniform L.L.
(applied to all sections behind and including the one being checked)
Load = 30(3.25) = 98 lbs/ft (only applied to overhang area, a conservative assumption) MomArm = (3.25)/2 = 1.63 ft Torsion = 98(1.63) = 160 lbs*ft/ft Lateral Load = 160/3 = 53 lbs/ft Load = 75 lbs/ft MomArm = 3.25+1 = 4.25 Torsion = 75(4.25) = 319 lbs/ft Lateral Load = 319/3 = 106 lbs/ft
Walkway L.L.
The top flange has a moment of inertia of 229 in4 or 314 in4, depending on flange thickness. The bottom flange has a moment of inertia of 314 in4 or 372 in4. The deflection in this example is checked at two places, halfway between the abutment and first diaphragm (Case 1) and halfway between the fifth and sixth diaphragm, which is near the center of the second span (Case 2). The girder is assumed to be progressively loaded as the deck is placed with the screed located at the center of the last section to be loaded. For analysis purposes only one unloaded section and at most two loaded sections, other than the section being checked, need to be included when calculating the deflections. This is a conservative simplification; actual deflections will be slightly less.
Screed Load (450 lbs/ft) Live Load (159 lbs/ft) Concrete Load (90 lbs/ft)
Case 1
20 ft 20 ft
Screed Load (450 lbs/ft) Live Load (159 lbs/ft) Concrete Load (90 lbs/ft)
Case 2
20 ft 25 ft 25 ft 25 ft
Rotation = (0.035 + 0.124 + 0.061 + 0.025 +0.090 + 0.044)/36 = 0.0105 radians Deflection at end of overhang = 0.0105(3.25)(12) = 0.41 in > 0.20 Deflection is too great. Case 2: Deflection at midspan of the third section of the case 2 model: Concrete Load Deflection Top Flange = 0.043 in Screed Load Deflection Top Flange = 0.182 in Live Load Deflection Top Flange = 0.100 in Concrete Load Deflection Bottom Flange = 0.031 in Screed Load Deflection Bottom Flange = 0.134 in Live Load Deflection Bottom Flange = 0.074 in
Rotation = (0.043 + 0.182 + 0.100 + 0.031 + 0.134 + 0.074)/36 = 0.0157 radians Deflection at end of overhang = 0.0157(3.25)(12) = 0.61 in > 0.20 Deflection is also too great, either the diaphragm spacing will need to be reduced or a smaller overhang used.
Once the deflections are satisfactory the diaphragm and its connection to the girder should be checked: The greatest reaction at a diaphragm is in Case 2 just to the left of the section that has the screed load applied to it. The reaction loads at this diaphragm are as follows: Top Flange Reaction Concrete Load = 2400 lbs Screed Load = 2790 lbs Live Load = 1900 lbs Concrete Load = 2410 lbs Screed Load = 2760 lbs Live Load = 1890 lbs
Assuming the diaphragm is centered on the girder web the net LRFD Service II slip critical moment and force on the bolt pattern is, Net factored moment = (3/2){1.0(2400 + 2410) + 1.3(2790 + 1900 + 2760 + 1890)} = 25,428 lbs*ft Net factored force = 1.0(2400 2410) + 1.3(2790 + 1900 2760 1890) = 42 lbs
3"
42 lbs
24"
3/ " 8
Thick
The diaphragm has a section modulus of 63 in3 and therefore the factored bending moment in the diaphragm and the associated stress for Strength I: Factored moment = (3/2){1.25(2400 + 2410) + 1.75(2790 + 1900 + 2760 + 1890)} = 33,536 lb*ft Factored stress = 33,536(12)/63 = 6388 lbs/in2 The factored resistance is based on a stress equal to the yield stress of 50 ksi. 6.388 ksi < 50 ksi OK
* Revision of 11/2003 added uniform live load and walkway live load to overhang.
B6.1 Standard Steel Details June 2006 Corrected weld symbol for bearing stiffener bottom flange/web weld. Added Jacking Stiffeners to title for Bearing Stiffeners. Made drip control bar gap around bottom flange equal to 1/16. Added reference for locating shop splices to Assembly and Fabrication Details. Deleted the faying surfaces from Note 1 to conform to the requirements of 627.03 paragraph C of the Supplemental Specifications. Changed field splices to bolted connections in Note 3. Added Note 8 requiring girder web to be vertical under full dead load and deck shrinkage. Added Note 9 limiting shop splices. April 2008 Note 2 revised to match SSP for painting structural steel. Note 3 added AASHTO M164 Type 3 and defined design assumption for threads in the shear plane. Revised Note 3 for threads in the shear plane.
July 2009
Article 9.7.2.5 Page 1 of 1 4/2001 9.7.2.5 REINFORCEMENT REQUIREMENTS FOR SKEWED END ZONES
For skews exceeding 25, the specified reinforcement in both directions shall be doubled in the end zones. The following diagram shall define the end zone.
End Zone
>25
End Zone
AASHTO TYPE 3 Min Overhang to center of Girder Spacing ITD Slab Depth girder w/continuous barrier Feet Inches Feet 5.0 8.00 2.00 5.5 8.00 2.00 6.0 8.00 2.00 6.5 8.00 2.00 7.0 8.00 2.00 7.5 8.00 2.00 8.0 8.00 2.00 8.5 8.00 2.00 9.0 8.00 2.00 9.5 8.00 2.00 10.0 8.50 2.13 10.5 8.50 2.13 11.0 9.00 2.25 11.5 9.00 2.25 12.0 9.00 2.25 12.5 9.50 2.38 13.0 9.50 2.38 13.5 10.00 2.50 Min Overhang to center of girder w/o continuous barrier Feet 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.54 3.54 3.75 3.75 3.75 3.96 3.96 4.17
MODIFIED BULB TEE Min Overhang to center of Min Overhang to center of Girder Spacing ITD Slab Depth girder w/continuous barrier girder w/o continuous barrier Feet Inches Feet Feet Deck can not be designed by the Empirical Design method 5.0 5.5 Deck can not be designed by the Empirical Design method 6.0 8.00 2.00 1.74 6.5 8.00 2.00 1.94 7.0 8.00 2.00 2.15 7.5 8.00 2.00 2.36 8.0 8.00 2.00 2.57 8.5 8.00 2.00 2.78 9.0 8.00 2.00 2.99 9.5 8.00 2.00 3.19 10.0 8.00 2.00 3.40 10.5 8.00 2.00 3.61 11.0 8.50 2.13 3.82 11.5 8.50 2.13 4.03 12.0 9.00 2.25 4.24 12.5 9.00 2.25 4.44 13.0 9.00 2.25 4.65 13.5 10.00 2.50 4.86
Min Overhang to center of girder w/o continuous barrier Feet 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.54 3.54 3.75 3.75 3.75 3.96 3.96 4.17 4.17
STEEL GIRDER W/15" TOP FLANGE Min Overhang to center of Girder Spacing ITD Slab Depth girder w/continuous barrier Feet Inches Feet 5.00 8.00 2.00 5.50 8.00 2.00 6.00 8.00 2.00 6.50 8.00 2.00 7.00 8.00 2.00 7.50 8.00 2.00 8.00 8.00 2.00 8.50 8.00 2.00 8.00 2.00 9.00 9.50 8.50 2.13 10.00 8.50 2.13 10.50 8.50 2.13 11.00 9.00 2.25 11.50 9.00 2.25 12.00 9.50 2.38 12.50 9.50 2.38 13.00 9.50 2.38 13.50 10.00 2.50
Min Overhang to center of girder w/o continuous barrier Feet 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.54 3.54 3.54 3.75 3.75 3.96 3.96 3.96 4.17
Min Overhang to center of girder w/o continuous barrier Feet 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.54 3.54 3.54 3.75 3.75 3.96 3.96 3.96 4.17
STEEL GIRDER W/24" TOP FLANGE Min Overhang to center of Girder Spacing ITD Slab Depth girder w/continuous barrier Feet Inches Feet 5.00 8.00 2.00 5.50 8.00 2.00 6.00 8.00 2.00 6.50 8.00 2.00 7.00 8.00 2.00 7.50 8.00 2.00 8.00 8.00 2.00 8.50 8.00 2.00 8.00 2.00 9.00 9.50 8.00 2.00 10.00 8.50 2.13 10.50 8.50 2.13 11.00 9.00 2.25 11.50 9.00 2.25 12.00 9.00 2.25 12.50 9.50 2.38 13.00 9.50 2.38 13.50 10.00 2.50
Min Overhang to center of girder w/o continuous barrier Feet 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.33 3.54 3.54 3.75 3.75 3.75 3.96 3.96 4.17
Section 9.7.2.4 Design Condition The ratio of effective length to design depth shall not exceed 18 Section 9.7.2.4 Design Condition The ratio of effective length to design depth shall not be less than 6 Section 4.6.2.2.2b Interior Beams with Concrete Decks Table 4.6.2.2.2b-1 limits the maximum deck thickness to 12 inches Deck can not be designed by the Emperical Design method
B9.1A Permanent Metal Deck Forms Steel Girders June 2006 Revised Note 1 to conform to the 2004 Standard Specifications.. Added new Note 4 requiring submittal of shop drawings & design calculations for the deck overhang brackets with the metal forms submittal.. Added new Note 5 requiring mylars of approved shop drawings. Renumbered Notes. Added Styrofoam shall not be placed in the flutes to new Note 6. ASTM A-525 has been deleted and the reference to ASTM A-525 in Note 2 was removed. Deleted Note 10 for not adding chlorides to the concrete because it is covered in the Standard Specifications. B9.1B Permanent Metal Deck Forms Concrete Girders June 2006 Revised Note 1 to conform to the 2004 Standard Specifications.. Added new Note 4 requiring submittal of shop drawings & design calculations for the deck overhang brackets with the metal forms submittal.. Added new Note 5 requiring mylars of approved shop drawings. Renumbered Notes. Added Styrofoam shall not be placed in the flutes to new Note 6. ASTM A-525 has been deleted and the reference to ASTM A-525 in Note 2 was removed. Deleted Note 10 for not adding chlorides to the concrete because it is covered in the Standard Specifications.
Article 10.6 Page 1 of 1 6/2006 DESIGN GUIDELINES FOR SPREAD FOOTINGS ON ROCK
The design of spread footing on rock shall be in accordance with the AASHTO LRFD Bridge Design Specifications as summarized in the following procedure. General On rock, a linear pressure distribution is used for all limit states. This is because the rock will not be able to yield to form a more rectangular pressure distribution. The deformation of the rock will basically stay linear. The flexibility of the footing will affect this, but the linear distribution is the closest distribution to use. Service Limit State In the design of the footing reinforcement, the service limit state must be checked for crack control. Settlement does not need to be checked for footings on competent rock. As per Article 10.6.2.2.3d, elastic settlement on rock may generally be assumed to be less than . If settlements of this magnitude are unacceptable and a settlement analysis is required, there are no eccentricity requirements. There are no sliding requirements. The resistance factor is 1.0.
Strength Limit State The eccentricity requirements should be in accordance with Article 10.6.3.2.5. The resistance factors should be provided by the Geotechnical Engineer based upon his method of estimating the capacity of the rock. Sliding should be checked in accordance with Article 10.6.3.3. For equation 10.6.3.3-2, the friction angle shall be in accordance with Table 3.11.5.3-1.
Extreme Limit State The eccentricity requirements should be in accordance with Article 10.6.3.2.5 which limits the length of the pressure distribution under the footing is at least the footing length or width. This is to keep the footing from rocking too much. Sliding should be checked in accordance with Article 10.6.3.3. For equation 10.6.3.3-2, the friction angle shall be in accordance with Table 3.11.5.3-1.
Seismic Design of Abutments Article 11.6.5 allows the location of resultant of the reaction forces to within the middle to middle 0.8 of the footing base.
Commentary
Spread Footings on Rock Design Guidelines established based on LRFD specifications and correspondence from Monte Smith of Sargent Engineers.
Article 10.7.1.2 Page 1 of 1 4/2008 10.7.1.2 PILE SPACING, CLEARANCES, AND EMBEDMENT
Spacing, clearances, and embedment of piles shall be in accordance with AASHTO Article 10.7.1.2, except as follows: 1. If there is calculated uplift on a pile, positive means of anchorage and 12" of embedment shall be provided. 2. If there is a possibility of scour under footings, use 12" of embedment. 3. Use 24" embedment in the case of stubby abutments where the superstructure is integral with the pile cap and rotation is accomplished by bending in the piles. 4. For encased pile bents, the cut-off elevation should be a minimum of 1' above normal water elevation to avoid cutting off piles under water. 5. The concrete cover at the sides of piles in encased pile bents shall be a minimum of 9". Pile spacing greater than 10' should be avoided. Consult your Group Leader on designs with proposed pile spacing exceeding 10'.
Revisions: November 2006 Corrected the article number to agree with the 2006 Interims. April 2008 Revised the concrete cover in note 5 from 8 to 9.
Commentary
For the purpose of determining the structural capacity of the pile per Article 6.9.4.1the appropriate unsupported pile length for exposed pile bents should be based on the initial unsupported length plus the anticipated scour depth. For pile caps that are initially buried the appropriate unsupported pile length should be based on the anticipated scour depth below the bottom of the pile cap or seal concrete. A limit of 75% of the yield strength of the pile is imposed to avoid potential pile damage during driving. For economy 36 ksi steel should be specified in most cases because the large ultimate loads that are possible with 50 ksi steel are very difficult to achieve and verify with standard pile driving equipment.
Split Footing Layout & Pile Notes and Approved Points, Shoes, Boots, & Splicers into separate articles.
Article A10.2 Page 1 of 3 7/2009 APPROVED POINTS, SHOES, BOOTS, AND SPLICERS
Approved points, shoes, boots, and splicers for pipe and H piles prepared by the Materials Section are listed in the Tables on the following pages. Manufacturers' names, addresses, and telephone numbers used in the tables are listed below.
MANUFACTURERS' NAMES, ADDRESSES, AND TELEPHONE NUMBERS APF Associated Pile & Fitting Corp. Tel # 800-526-9047 DFP Dougherty Foundation Products, Inc. Tel # 201-337-5748 ICE International Construction Equipment, Inc. Products Manufactured by: Mid-America Foundation Supply Inc. Tel # 888-893-7453 PAI Piling Accessories Inc Part of APF VERSABITE Versabite Foundation Accessories Part of APF VERSA STEEL Versa Steel, Inc. Pile Accessories Division Tel # 800-678-0814 CONSTRUCTION SUPPLY COMPANY Tel # 503-620-2971
75500 VB-300 Series 77750-B PAR Series 77600-B VB-300P Series PAR Series 77750-B PAR Series H-777 H-776 HPH Series HPH-RB Series VS-300 Series HT-3300
H-777
HPR-RB Series
SPLICERS APF HP-30000 DFP HP-300 ICE HSA Series VERSA STEEL VS 400 CONSTR SUPPLY HS-1000
DFP 0140
OPEN-END CUTTING SHOE VERSA STEEL ICE ICE Inside Cutting Shoe VS-700 Series
CLOSURE BOOT APF PB-20000 DFP PB-170 ICE ICE Round Tite Boot
SPLICERS APF S-18000 S-20000 VB 800 Series DFP S-1800 ICE Round Bite Coupler CONSTRUCTION SUPPLY PS 8800 VERSA STEEL VS800
Split Footing Layout & Pile Notes and Approved Points, Shoes, Boots, & Splicers into separate articles Revised data based on Materials list of February 2009.
Article 11.6.1.3 Page 1 of 5 4/2008 11.6.1.3 DESIGN GUIDELINES FOR INTEGRAL ABUTMENTS
Integral abutments, where appropriate, should be considered for most bridge projects in order to eliminate joints and bearings thereby simplifying construction and reducing maintenance problems. Integral abutments are defined as those abutments that are rigidly attached to both the superstructure and the supporting piles so that all thermal movements and girder end rotations are transferred from the superstructure through the abutment to the piles.
Skew: Foundations:
Abutment Thickness: The minimum thickness of the abutment wall should be 3 feet in order to provide enough width to encase the piles and girders. Wing Walls: The wing walls should be cantilevered off of the abutments and shall be constructed parallel with the girders in order to minimize the soil pressure against the wings.
R=
P Pex + N I
where: R = single pile live load reaction (KIPS) P = total live load reaction at the abutment, without impact (KIPS) N = number of piles in the abutment e = the eccentricity of the total live load relative to the center of the pile group (FT) x = the distance from a given pile to the center of the pile group (FT) I = the moment of inertia of the pile group (FT2) For vertical loads piles shall be designed in accordance with Article 10.7 of the AASHTO LRFD Bridge Design Specifications for Strength I. Lateral loads on the piles may need to be considered on bridges skewed more than 25 when required to resist the soil pressure forces tending to rotate the structure. Piles must be ductile enough to accommodate both thermal movements and dead load and live load rotations of the superstructure. The ductility of the piles may be checked using the following equations: For Steel H-pile:
Ci =
19 fy bf 5.68 , 6 E 2 tf
0 < C i < 1 .0
Ci = 3.5 1.25
fy D , E t
one half the factored thermal movement range at the abutment (IN) twice the length from the bottom of the abutment to the first point of zero moment in the pile determined taking into account the effect of the soil on pile behavior and assuming a lateral deflection of (IN) Mp = plastic moment of the H-pile about the axis of bending or the plastic moment of the steel pipe pile without considering the concrete filling (KIP-IN) E = modulus of elasticity of the steel (KSI) I= H-pile moment of inertia about axis of bending, the moment of inertia of the hollow pipe, or moment of inertia of the concrete-filled pipe considering both the concrete and steel (IN4) w = maximum range of the factored angle of rotation of the superstructure at the abutment calculated assuming the structure is simply supported on the abutment (continuity of the superstructure over piers may be considered on multi-span bridges). This rotation is the sum of the rotations due to live loads plus all dead loads applied after making the rigid connection between the superstructure and the abutment assuming the loads are equally distributed to all girders (RAD) Ci = a ductility reduction factor for piles bf = width of H-pile flange (IN) tf = thickness of H-pile flange (IN) D = outer diameter of pipe pile (IN) t= thickness of pipe pile (IN)
Pile Reactions
Cantilever Bending Design Location Fill Face Reinforcment Pile Lateral Force Pile Moment
Design Location Stream Face Reinforcement Pile Lateral Force Pile Moment
2 = koH
Bending of the abutment acting as a continuous beam spanning between the girders under a soil pressure load. The full section of abutment (both pile cap and end diaphragm) may be used. For all design elements the soil pressure distribution may be assumed as the passive pressure for the top third of the abutment with the pressure varying linearly down to the at-rest pressure at the base of the abutment (strength I load factor for soil pressure of 1.00, 3rd Edition Article C10.5.5). This distribution is appropriate for concrete bridges up to 320 feet in length and steel bridges up to 120 feet in length. A more in-depth analysis of soil pressure distribution should be made for longer structures. The abutment need not be designed by the strut and tie model if the longitudinal reinforcement is determined by conventional beam analysis for each of the above cases and a minimum orthogonal grid of reinforcing bars is provided in accordance with Article 5.6.3.6.
Skew Affects
On structures with skews greater than 25 degrees, the tendency for the structure as a whole to rotate due to the non-concentric soil pressure forces acting against the abutments must be checked. A rotational moment about the center of the structure is induced by the soil pressure (strength I load factor of 1.00) acting on the abutment backwall at an angle normal to the backwall minus the soil-concrete interface friction angle;
(Article 10.6.3.4)
M RS = FRS (e RS )
FRS =
FNS cos
e RS = L sin( )
where: MRS = the soil pressure induced rotational moment FRS = resultant soil force eRS = the eccentricity of the opposing soil forces FNS = normal soil force based on the assumed soil pressure distribution = the soil-concrete friction angle L = bridge length = the bridge skew angle The resulting rotational moment must be resisted by a combination of the lateral pile resistance (strength I resistance factor of 0.55, ITD policy), and the soil force acting against the inside face of the wings at the acute corners (strength I resistance factor of 0.50, Table 10.5.5.2.2-1), as indicated in the sketch below. It can be assumed for simplicity that the resisting forces in the piles as well as the soil force against the wing walls is applied at right angles to the bridge centerline and their respective eccentricities calculated accordingly.
Bridge Length Lateral Pile Resistance Forces Soil Force Eccentricity
Approach Slabs
Approach slabs shall be used on all integral abutment bridges with a total thermal movement of more than inch. This will result in approach slabs on all concrete girder bridges over 130 feet long and on all steel girder bridges over 65 feet long. The expansion joints at the ends of the approach slabs need only be sized to accommodate thermal expansion assuming the joints are constructed at 60 F with a maximum temperature of 80 F for concrete and 100 F for steel.
Where interference between the piles and soil reinforcement occurs, the reinforcements must be designed around the piles, and the piles treated as backfill obstructions. A clear distance of no less than 1.5 feet from the back of the wall facing to the edge of the nearest pile or pile casing shall be provided. ITDs Special Provision further stipulates that 15 is the maximum angle that reinforcement can be skewed from a line perpendicular to the wall. The layout of the abutment in relation to the MSE wall should take the above into account.
Distance
15 1.5 min
Casing Diameter -ft 1.0 1.5 2.0 2.5 3.0 3.5 4.0
Distance from casing to fill face of MSE panel - ft 1.50 2.15 2.86 3.58 4.30 5.01 5.77
Stiffleg
Design Height
Design Height
Box Culvert
When the maximum span for the structure type is exceeded, a different structure type or multiple cells should be evaluated. Class 40 concrete and Grade 60 reinforcement should be used on all designs. Class 40B should be used for the footings or floors, barrel walls and wing walls. Class 40A should be used for deck slabs with less than 2 of fill and Class 40B when the fill is 2 or greater. When the distance between the finished grade and the top of deck is less than 4 between the paved shoulders the concrete cover over the top layer of reinforcement should be 2 and all reinforcement within 4 of the surface should be epoxy coated. When the fill is greater than 4 but less than 2 the cover over the top layer of reinforcement should be 2 however no epoxy steel is required. When the fill is 2 or greater the cover should be 2 with no epoxy steel. Main reinforcement for skews greater than 25 (Article 9.7.1.3) should be placed perpendicular to the centerline of the culvert. For skews 25 or less, the main reinforcement should be placed on the skew and the design span measured along the skew. Fillets should have a minimum leg of 6. Walls should be double reinforced and have a minimum thickness of 10. Slab thickness should be a minimum of 8 or (S +10)/30 whichever is greater (Table 2.5.2.6.3-1). The span length to determine the minimum thickness is the clear span between walls. Construction joints with keyways should be placed transverse to the barrel and should be located in the walls, top slab, and bottom slab. Joint spacing should not exceed 40. In lieu of a construction joint in the walls, the contractor may substitute an approved contraction joint. The minimum footing width for stifflegs should be 2 on rock and 3 on other materials. The design of culverts should meet the criteria for Strength - 1 and Service - 1 limit states.
Strength 1 Max. Factor Min. Factor 1.25 0.9 1.50 0.0 1.30 0.9 1.35 0.5 (Art. 3.11.7) 1.50 0.9 1.50 0.5 (Art. 3.11.7) 1.50 0.75 1.75 0.0 1.75 0.0 1.00 0.0
Service 1 Factor 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0 1.0
Concrete D.L. Assume 150 lbs/ft3 for the concrete and reinforcement (Table 3.5.1-1 & C3.5.1). Wearing Surface Assume a future overlay of 6 with a weight of 140 lbs/ft3 (Table 3.5.1-1). Earth Fill D.L. Use the density given in the Phase IV report. When not given assume 140 lbs/ft3 (rolled gravel from table 3.5.1-1). The earth loads should be modified to account for soil-structure interaction. The soil-structure interaction factor is as follows (Art. 12.11.2.2): For embankment installations (the typical case), Fe = 1 + 0.2(H/Bc) Fe shall not exceed 1.15 for installations with compacted fill along the sides of the box section, or 1.40 otherwise. Where, H = fill height above the deck surface Bc = out-to-out dimension of the culvert span For trench installations, Ft = CbBd2/HBc Fe Where, Cb = coefficient from figure 12.11.2.2.1-3 Bd = horizontal width of trench
Earth Pressure Shall be assumed to be linearly proportional to the depth of the soil based on the at rest pressure coefficient taken as k o = 1- sin f where f is the internal friction angle of the soil (Art. 3.11.5.2). Earth Surcharge When the structure is buried the fill above the deck is considered an earth surcharge and a constant uniform horizontal earth pressure shall be applied in addition to the basic earth pressure. The uniform horizontal pressure due to earth surcharge should be based on the at rest coefficient ko (Art. 3.11.6.1). Live Load Surcharge At the barrel wall live load surcharge shall be determined as follows (based on table 3.11.6.4-1): Up to 5 H: heq = 4.0 From 5 to 10 H: heq = 4- 0.2(H-5) From 10 to 20 H: heq = 3- 0.1(H-10) Higher than 20 H: heq = 2.0 Where heq is the equivalent height of soil in feet and H is the distance between the surface and the bottom of the footing in feet. Live Loads Where the span exceeds 15 feet (Art. 3.6.1.3.3) the live loads shall be either a design truck in combination with a lane load or the design tandem in combination with a lane load (Art. 3.6.1.2). Where the span does not exceed 15 feet, only the axle loads of the design truck or design tandem shall be applied (Art. 3.6.1.3.3). The live load applied shall be a single loaded lane with the single lane multiple presence factor applied to the load (Art. 12.11.2.1). Impact shall be 0.33(1.0 0.125DE) but shall not be less than 0.0 where DE is the minimum depth of earth cover over the structure (Art. 3.6.2.2). Impact shall only be applied to the truck or tandem (Art. 3.6.2.1).
Fill less than 2 (Article 4.6.2.10): Case 1. Traffic Travels Parallel to the Span (normal case) Analysis shall be based on a single loaded lane with the single lane multiple presence factor. The axle load shall be distributed to the top slab for moment, thrust, and shear as follows: E = 96 + 1.44(S) Espan = Lt + LLDF(H) Where E = lateral distribution width perpendicular to the span (inches) Espan = longitudnal distribution length parallel to the span (inches) S = the clear span length (ft) Lt = length of the tire contact area parallel to the span, 10 inches (Art. 3.6.1.2.5) H = depth of fill from top of culvert to top of pavement (inches) LLDF = fill distribution factor of 1.15 or 1.00 (Art. 3.6.1.2.6) The equivalent strip width used for the top slab should also be used for the walls and floor (Art. 12.11.2.3). Shear strength may be considered adequate when the slab is designed by the above procedure (see commentary). Case 2. Traffic Travels Perpendicular to the Span Live load shall be distributed according to Article 4.6.2.1 for concrete decks with primary strips perpendicular to the direction of traffic. Fill greater than 2: Wheel loads may be considered to be uniformly distributed over a rectangular area with sides equal to the dimension of the tire contact area increased by 1.15 times the depth of fill in granular backfill, or the depth of fill in all other cases. The lane load may be distributed over 12 feet in all cases. The tire contact area is 20 inches wide and 10 inches long. Where such areas overlap the total load shall be uniformly distributed over the area within the resultant perimeter. Multiple presence factors shall be used where applicable. Live load may be neglected where the depth of fill is over 8 feet and exceeds the total length of the structure. Where the live load moment based on distribution through fill depths more than 2 exceeds the moment calculated by Art. 4.6.2.10, the moment calculated by Art. 4.6.2.10 should be used. (Art. 3.6.1.2.6) Shear design when fill is greater than 2 (Art. 5.14.5.3): Vc = [0.0676(fc`)0.5 + 4.6(As/bde)(Vude/Mu)]bde But Vc shall not exceed 0.126(fc`)0.5(bde) where: As = area of tension steel (in2) de = effective depth from extreme compression to tension centroid (in) Vu = shear from factored loads (kips) Mu = moment from factored loads occurring simultaneously with Vu (kip-in) b = design width (in) For single span stifflegs and single cell boxes only, Vc need not be less than 0.0948(fc`)0.5(bde) Vu may be calculated at either the distance dv (Art. 5.8.3.2) from the face of the wall or at the end of the fillet. dv = center of compression force to center of tension force but not less than 0.9de or 0.72h. (in kips) Vc > Vu = 0.85
Min As shall be sufficient to resist 1.2Mcr or 1.33Mu whichever is less Adist= As/(L)0.5 but no more than 0.5As
where As is the required positive moment reinforcement and L is the span length in feet For crack control (Art. 5.7.3.4); e = 0.75 to be used in equation 5.7.3.4-1
Note: When calculating the Service-1 limit state stresses in the reinforcement for the purpose of satisfying crack control requirements the compression thrust forces in the culvert members may be considered in order to take advantage of the resulting reduction in tensile stresses. The equations presented in the commentary for Article 12.11.3 may be used for this purpose. Edge Beam Design The Live Load on edge beams shall be one line of wheels (either truck or tandem) plus a tributary portion of the lane load (Art. 4.6.2.1.4b). The tributary portion of the lane load shall be considered to be a uniform load of 64 lbs/ft2 on either the effective edge beam width, or in the case where the edge beam is skewed relative to the main slab reinforcement, on the same tributary area as defined for dead load. The effective edge beam width for culverts with main slab reinforcement parallel with the edge beam shall be the distance between the edge of deck and the inside face of the barrier or curb, plus 12, plus one-quarter of the strip width, E, determined above. The effective width shall not exceed either one-half the full strip width or 72 (Art. 4.6.2.1.4b). The dead load should be the weight of all structure components and the fill on the effective width. When the end of the culvert is skewed relative to the main slab reinforcement the dead load applied to the edge beam shall also include the weight of all loads on the tributary area at the end of the culvert as shown below. These loads may be applied to the edge beam as a uniform load. The edge beam should be designed as a simple span with a span length based on center-of-wall to center-of-wall along the skew.
an
Be
am
Ed
ge
Sp
Footing Pressures The dead load footing pressures on the footings of stifflegs and the floor of box culverts may be uniformly distributed to the total footing area. The live load footing pressures may be assumed to act on a length of footing equal to the width of the design lane plus 1.15 times the distance from the surface to the bottom of the footing (this is the same
Wing Wall Design Live load surcharge shall be applied where vehicular load is expected to act on the surface of the backfill within a distance equal to one-half the wall height behind the back face of the wall. Heq, the equivalent height of soil in feet, should be based on Table 3.11.6.4-2. The typical wing wall on a spread footing is free to deflect at the top under soil pressure and may therefore be designed using soil pressures based on the active state. The soil pressure coefficient, ka, may be determined by the Coulomb method from the information in the Phase IV report. Overturning: For foundations on soil, the location of the resultant of the factored strength-1 and extreme event-2 (vehicle collision at rail, if present) forces shall be within the middle one-half of the base. On rock the resultant shall be within the middle three-fourths (Art. 11.6.3.3). Sliding: For footings on cohesionless soils the factored resistance against failure by sliding may be taken as (Art. 10.6.3.4): RR = T(V tan f ) where: RR = factored resistance T = 0.8 for strength-1 (from table 10.5.5.2.2-1) T = 1.0 for extreme event-2 (Art. 10.5.5.3) V = total factored vertical load (minimum factors) f = internal friction angle of soil
The factored (strength-1 and extreme event-2) lateral loads shall not exceed RR . Wing Wall Footings: Foundation design shall be in accordance with Section 10 of the LRFD Code.
Commentary:
The LRFD design requirements for shear in slabs with less than 2 feet of fill are not consistent. Article 5.14.5.2 states that the provisions of Article 5.13.3.6 shall apply which indicates shear design is required. However if the live load distribution of Article 4.6.2.3 is used, which is a less conservative distribution than Article 4.6.2.10 for spans over about 9 feet, slabs may be considered satisfactory for shear (Art. 5.14.4.1). In addition it has been ITD practice for many years, in accordance with the Standard Specifications, to consider slabs designed with less than 2 feet of fill to be adequate for shear. Because ITD has had a good history of performance with this design procedure it will remain ITD policy. For fills over 2 feet the provisions of 5.14.5.3 shall also apply to stifflegs as well as box culverts. AASHTO is silent for the most part on cast-in-place concrete three sided frames however structurally they behave and are designed more like a four sided box culvert than a simply supported slab bridge. The culvert test results for shear shown in the commentary indicate that frame structures with the walls integral with the slab behave differently than simple slabs.
The crack control requirements where revised to reflect the 2005/2006 Interim changes in AASHTO Article 5.7.3.4. The effective edge beam width was revised to reflect the 2005 Interim changes in AASHTO Article 4.6.2.1.4b.
NEW CONSTRUCTION Concrete parapet is the preferred rail type for safety reasons. When an overlay is placed on the structure during original construction, the height of the parapet should be 2'-8" from the top of the overlay. Other rail types should be considered to meet Context Sensitive Design criteria. Concrete parapets and median barriers shall be constructed perpendicular to the roadway cross slope for superelevation rates up to 6%. Bridges with superelevation rates greater than 6% shall be evaluated on a case-by-case basis. For superelevation rates greater than 6%, revise the Notes on the Standard Drawing as follows: Concrete parapet shall be constructed so that the outside face is in a vertical plane. Height control shall be at the inside (traffic) face. End faces that fit up to precast concrete end sections shall be constructed perpendicular to the roadway grade. Concrete median barrier shall be constructed vertically. Combination railings shall be used on a raised sidewalk when there is no barrier between the roadway and sidewalk. Pedestrian/Bicycle Railing shall be used when a traffic barrier separates the roadway from the sidewalk. W-Beam railing may be used if the site meets TL-3 criteria and the span length is less than 40. REHABILITATION The following options should be considered on a deck rehab project: DO NOTHING When no major work is being done on the bridge and the existing rail is continuous and designed for a 10k rail load, then the existing rail is acceptable. The railing does not require a successful crash test, but the connection to the roadway railing should be modified to meet current standards. RETROFIT When no major work is being done on the bridge and the existing rail was not designed for a 10k rail load, the existing rail should be retrofit using the metal rail details shown on G-2-F in the Roadway Standard Plans, the Delaware Retrofit, or the Iowa rail retrofit. See Rail Standard drawings B13.7A, B13.7B, B13.7C, B13.7D, and B13.7E. No design calculations are needed to check the deck slab, but the exterior girder should be checked for the rail dead load and truck wheel load.
UP-GRADE Up-grading the existing rail should be considered when the work will be cost effective; e.g., when the deck slab is replaced. One of the standard rail types shown in the Bridge Design Manual should be used. The deck slab and exterior girder shall meet the requirements of the current AASHTO code.
The Combination Rail Test Level was changed to TL-3 to comply with Article 13.7.3.2. Corrected the w-beam railing reference from PL-1 to TL-3. Added the Delaware Retrofit to the Retrofit options. Added reference for Context Sensitive Design rail options. Added reference to new rail retrofit standard drawings B13.7A B13.7E.
TEST HIGHWAY LEVEL TYPE Local Street 1 Collector 2 Arterial 3 Freeway, Expressway, 4 Interstate 5 6 Freeway, Expressway, Interstate Freeways
DESIGN SPEED TRAFFIC TYPE <30 mph Low Volume <45 mph Small Number of Heavy Vehicles >50 mph Very Low Mixture of Heavy Vehicles >50 mph Mixture of Trucks & Heavy Vehicles
CRASH TEST VEHICLE Small Automobile, Pickup Truck Small Automobile, Pickup Truck Small Automobile, Pickup Truck Small Automobile, Pickup Truck, Single-Unit Van Truck Small Automobile, Pickup Truck, Van-Type Tractor-Trailer Small Automobile, Pickup Truck, Tractor-Tanker Trailer
>50 mph Higher Ratio of Heavy Vehicles >50 mph Higher Ratio of Tanker-Type Trucks
Test Level 5 & 6 railings should be considered when a high accident rate is expected because of unfavorable site conditions and when severe consequences from rollover or penetration beyond the barrier are expected. Unfavorable site conditions include but are not limited to the following: Reduced radius of curvature (Degree of curvature > 3) Steep downgrades on curvature (Grade > 3%) Variable cross slopes Adverse weather conditions. Test Levels 1-4 in the Table assume favorable site conditions. Increase one test level when site conditions are unfavorable.
Deleted Combination Bicycle Rail Deleted Bicycle Rail Deleted G-2-F Type 3 Changed weight of Pedestrian Rail from 96 plf to 102 plf Changed weight of G-2-F Type 4 from 13 plf to 20 plf Added Delaware Retrofit weight Added Iowa Retrofit weight Added Old Bridge Rail Table
STANDARD CONCRETE RAIL MOUNTED ON WALLS, CURBS OR EDGE BEAMS For the design of retaining walls and curbs or edge beams supporting standard concrete parapet the following design procedure may be used (also applicable for decks supporting curbs or edge beams where parapets are constructed on the curb or edge beam, i.e. buried decks): For walls and curbs only design Case 1 of Article A13.4.1, extreme event limit state, need be considered. The design loads are specified in Table A13.2-1. Design Case 3 need only be considered for the design of decks that support curb or edge beams with parapets. The loads for Design Case 3 shall be in accordance with Article 3.6.1, strength limit state. Design Case 1 Loads for Traffic Railings. Ft = 54 kips (from table A13.2-1 for TL-4)
For the general case, at least 8 feet from parapet joints or discontinuities, the design loads may be distributed over a length of wall, curb or deck as follows: Em = 11 + 2.67x Et = 6 + 2.67x
For the ends of parapet sections within 8 feet of joints or discontinuities the design loads may be distributed over a length of wall, curb or deck as follows: Em = 7.5 + 0.5x Et = 10 + 4x
where: Em = the length of wall, curb or deck the design moment is distributed over in feet. Et = the length of deck the design tension force is distributed over in feet. x = the distance from the base of rail to the design location in feet, either vertical or horizontal or both. In any case the load distribution length shall not exceed the actual member length. In lieu of the above method the provisions of Article A13.4.2 may be used where applicable.
Commentary
The above distribution equations where derived from the results of an elastic finite element analysis using the LARSA structural analysis program. These equations are based on the resulting tension and bending moment in the most severely stressed 6 width of the supporting member. If these equations are directly applied to the case of a parapet supported on a standard 8 thick deck overhang the calculated area of reinforcement at the face of rail would be 0.76 in2/ft, while a #4 and #6 bar at 12 inch spacings equals 0.64 in2/ft which is 84% of the calculated value. This is considered acceptable, however, because the LARSA model conservatively assumes an elastic distribution while the extreme event limit state relies on the ultimate strength of the supporting deck, which cannot be realized without significant yielding of the reinforcement (the strain at ultimate in this case is 580% of the yield strain), thereby resulting in a greater width of load distribution.
B13.4A 4-6 Standard Bicycle Rail June 2006 Deleted the 4-6 height rail standard drawing. B13.4B Standard Pedestrian/Bicycle Railing June 2006 Combined the Bicycle and Pedestrian rail drawings using a 3-6 height to conform to the approved 2006 Ballot Item. Deleted epoxy reinforcement from the Drilled Concrete Post Base. Widened the curb to 10 to provide cover for reinforcement around the anchor bolts. Modified the title block to include Bicycle. July 2009 Added V Groove detail 3 from edge of deck. Changed tube wall thickness to 3/16. B13.4C Pedestrian/Bicycle Railing Details June 2006 Revised Note 6 to require epoxy reinforcement only in the curb. Added Note 7 specifying Concrete Class 40A. Added Notes 16, 17, & 19 for tube ends, vent holes, and alternate splice details. Increased the top width of bar R2. Modified the title block to include Bicycle. July 2009 Renumbered the Notes Added additional requirements for powder coating Changed tube wall thickness to 3/16. Modified splice tube detail. Modified note 21 to read, Each rail section B13.6A W-Beam Railing Details June 2006 Added a note in the title block for using roadway standard drawing G-1-L on retrofit projects.
B13.7A G-2-F Type 1 Rail Retrofit Details June 2006 Added a new drawing. July 2009 Added details from Roadway Standard Drawing G-2-F to allow G-2-F to be deleted. Revised paint system in Note 3. B13.7B G-2-F Type 2 Rail Retrofit Details June 2006 Added a new drawing. July 2009 Added details from Roadway Standard Drawing G-2-F to allow G-2-F to be deleted. Revised paint system in Note 3. B13.7C G-2-F Type 4 Rail Retrofit Details June 2006 Added a new drawing. April 2008 Changed size of attachment angle to 6x4x5/16 and added Detail A. July 2009 Added details from Roadway Standard Drawing G-2-F to allow G-2-F to be deleted. Revised paint system in Note 1. B13.7D Delawatre Rail Retrofit Details June 2006 Added a new drawing. July 2009 Added details from Roadway Standard Drawing G-2-F to allow G-2-F to be deleted. Added Note 11 for painting field drilled holes. B13.7E Iowa Rail Retrofit Details June 2006 Added a new drawing.
Silicone sealants are poured in place directly over a foam backer rod placed in the expansion gap. The cured silicone sealant joint can accommodate tensile movements of up to 100% and compressive movements of up to 50% of the sealant width at installation. A minimum recess is required from the top of the pavement to the top of the silicone sealant in order to prevent tire traffic from contacting and debonding the sealant from the substrate. The following is a list of approved joints: MANUFACTURER DOW CORNING
Asphaltic plug joints consist of polymer modified asphalt (PMA) installed within a blockout over a steel plate. The steel plate spans across the expansion gap to retain the PMA during its installation. Application guidelines must be carefully followed to assure successful performance. They should not be used for joints having large skew angles, joints subjected to large rotations, joints subjected to differential vertical movements (for example, longitudinal separation joints), or in situations where the total height of the PMA above the steel plate is less than 2. Asphaltic plug joints should not be used in situations where the adjacent pavement is subjected to significant acceleration or deceleration (off ramps, traffic signals) because the PMA has a tendency to creep out of the blockout and this tendency is amplified by any horizontal loading. The following is a list of approved joints: MANUFACTURER LINEAR DYNAMICS D.S. BROWN WATSON BOWMAN ACME DEERY AMERICAN CORP
STYLE BRIDGE JOINT SYSTEM (BJS) MATRIX 502 ASPHALTIC EXPANSION JOINT WABO EXPANDEX JOINT SYSTEM DEERY FLEXIBLE JOINT SYSTEM
Polymer concrete headers are recommended at compression seal and silicone sealant joints. Polymer concrete provides tensile strength and toughness to resist traffic impact. Proprietary elastomeric concretes can also be used to further enhance impact resistance. Patent infringement issues may result when generic polymer concrete is used in combination with a Dow Corning silicone sealant.
LARGE MOVEMENT JOINTS Modular Expansion devices are the preferred system for movements in excess of 4". The skew angle should be less than 30and the movement per sealing element should not exceed 3. The same criteria for Medium Movement Joints apply to modular joints, in addition to the following. All large expansion devices should be designed for the movements required plus a safety factor of 15%. This excess allowance is intended to prevent destruction of the joint due to unpredictable movements at a given location. Consideration should be given to accommodating some earthquake movement. All elastomeric sealing components shall be continuous full width of each roadway, including curb treatment. The entire joint device should be shipped completely assembled to the jobsite. For large expansion joints specify all accepted name brands that provide good performance. Do not specify "OR APPROVED EQUAL".
The following is a list of approved joints: MANUFACTURER WATSON BOWMAN & ACME D.S. BROWN
As a guideline, bridges with the following lengths may be designed continuous without expansion joints at end abutments if the skew is less than 30. STRUCTURE TYPE Steel Structures Post-tensioned Concrete Cast-In-Place Concrete Prestressed Girder LENGTH 300' 400' 400' 400'
Compression seals should not be used when the skew exceeds 30. Joints with skews greater than 30 require special consideration - see "Selection Criteria for Strip Seals". To prevent snowplow blades from dropping into a joint, left-forward skews of 25-38 should be avoided.
Commentary As of October 2006, only two manufacturers of compression and strip seal joints could be found D.S.Brown & WatsonBowmanAcme. Listing only two products on the plans in acceptable to FHWA Idaho Division Office.
Added Commentary.
Article 14.7.5 & 14.7.6 Page 1 of 3 7/2009 DESIGN GUIDELINES FOR ELASTOMERIC BEARINGS
Elastomeric bearings shall consist of either plain elastomeric pads or steel-reinforced laminated pads. The bearings may be designed by either Method A (Article 14.7.6) or Method B (Article 14.7.5) of the AASHTO LRFD Bridge Design Specifications. Method A is the required design procedure for plain elastomeric pads. Method B is the preferred method of design for steel-reinforced laminated pads. Design Method B and/or the use of Grade 4 elastomer requires that a long term load test be preformed on at least 10% of the completed bearings per ITD Standard Specifications, Subsection 711.02 (5e). When Method B or Grade 4 elastomer is used it should be clearly noted in the plans to ensure that the correct testing is performed. The elastomeric material shall be specified by its hardness and grade when designing by Method A. Most bearing designs for Method A should be based on 60 durometer elastomer, Grade 3. The shear modulus for 60 durometer elastomer shall be assumed to range from 130 psi to 200 psi, with the least favorable value being used for the particular design parameter being considered. When designing by Method B the elastomeric material shall be specified by shear modulus and grade. The shear modulus should be specified as 130 psi with the design value increased or decreased by 15% whichever is the least favorable value for the particular parameter being considered. Grade 4 elastomer should be specified when the bridge is located in low temperature Zone D, if Grade 3 is used in Zone D the other components of the bridge must be designed to resist 1.5 times the shear force determined by Article 14.6.3.1 when a low friction sliding surface is used or 4 times this shear force for a nonsliding surface (see Article 14.7.5.2). Zone D for Idaho shall be defined as any area above an elevation of 3800 feet or any location in Bonner or Boundary County. Live Load reactions for bearing design shall be based on the girder distribution factor for shear, Article 4.6.2.2.3. In calculating the live load rotations the whole structure cross-section, acting as a unit, may be used. All loads and rotations used in bearing design shall be determined using the Service I limit state including dynamic load allowance (IM).
Bearing Details
Steel reinforced elastomeric bearings shall consist of alternating layers of a minimum of 14 gage A36 steel and neoprene bonded together. All internal layers of neoprene shall be of equal thickness, there is no limit on the maximum thickness of internal layers as there was in previous specifications provided all design criteria are met. However, the minimum thickness of internal layers should be 3/16 so that a minimum external layer does not violate the requirement to be no more than 70% of the thickness of an internal layer (Article 14.7.5.1). Exterior layers shall have a minimum thickness of 1/8 to provide enough cover to protect the reinforcement. Sole plates for steel girders shall be welded to the bottom flange to provide a level surface for the elastomeric pads to bear against. Sole plates shall be beveled to compensate for the longitudinal grade of the bridge. Sole plates shall be detailed with enough length (in the direction of the span) to accommodate construction tolerances.
Article 14.7.5 & 14.7.6 Page 3 of 3 7/2009 Information for Required Testing
All steel reinforced elastomeric bearings are to be tested for the Short-Duration Compression Test (subsection 711.02 {5d}). In order to perform this test the maximum design load for each bearing size and type is required. Therefore the method (A or B) that was used in design, along with the maximum design load for each size and type of bearing, must be called out on the bearing detail sheet so that all the information for fabrication and testing is available in one place.
Commentary In most cases Method B will result in significantly smaller and thinner bearing pads and although it requires more rigorous testing it will result in a more practical sized bearing.
Revisions July 2009 Revision to specify material by shear modulus for Method B and the definition of thermal movement to comply with 2008 interims.
A14.2 Page 1 of 1 6/2006 The following equations closely approximate the AASHTO curves shown in Figure C14.7.5.3.3-1 in the AASHTO LRFD Bridge Design Specifications. To evaluate the equations, stress should be in psi. The value for strain is in percent. 70 DUROMETER COMPRESSIVE STRAIN EQUATIONS Shape Factor(SF) 6.0
= C x
C = 0.05 600
0.15
1.0 0.0004 SF 0.65 6
x=
C = 0.5 1000
0.5
x=
SF 0.25 12
0.4
C = 0.065 600
0.15
x=
x=
SF 0.25 12
0.15
C = 0.10 600
0.15
x=
C = 0.6 1000
0.5
x=
SF 0.275 12
0.15
Revisions:
June 2006 Added explanatory notes defining the intent of the equations and the units for stress & strain.
0.7 1.2
15
COMPRESSIVE STRAIN - %
10
Translation
Strength Limit State Reversible Rotation (RAD) Service Limit State Irreversible Reversible Maximum bearing dimensions (in) Upper Surface Lower Surface Overall height Tolerable movement of bearing under transient loads (in)
Serviceability Strength Serviceability Strength Vertical max perm min Transverse Longitudinal Vertical Transverse Longitudinal Transverse Longitudinal Transverse Longitudinal Transverse Longitudinal Transverse Longitudinal Transverse Longitudinal Transverse Longitudinal Transverse Longitudinal Transverse Longitudinal Vertical Transverse Longitudinal Transverse Longitudinal Transverse Longitudinal Transverse
Allowable resistance to translation under service limit state (kips) Allowable resistance to rotation under service limit state (k/ft) Type of attachment to structure
KEEPER ANGLE (NOT FOR SEISMIC RESTRAINT) The length of the cope can be reduced if the sole plate is designed with a shear tab. This will reduce the required length of the keeper angle. HORIZONTAL LEG dH = Length of horizontal leg of the restraint angle (inches) t = Thickness of the restraint angle (inches) PL = Max. Longitudinal force (kips) FT = Allowable tensile stress (ksi) FS = Factor of Safety CW = Width of cope in the horizontal leg = 1 1/2". = Diameter of the anchor bolts (inches) PL + CW + d H min FS FT t Minimum edge distance for anchor bolts must be checked. VERTICAL LEG (Recommended angle size of 6"x 6" x 3/4" to start design) dV = Length of vertical leg of the restraint angle (inches) t = Thickness of the restraint angle (inches) PT = Max. Transverse force (kips) FS = Factor of Safety CH = Height of cope in the vertical leg = Sole PL + Steel PL + Stainless steel + PTFE + Pad + 1/4". CL = Length of the cope = Soleplate + T + 1". T = Total temperature movement (inches) FB = Allowable bending stress (ksi) PT CL d V min C H + F B FS t
B
C.
D.
III. Design Example Existing 25 year old concrete bridge with 1 expansion gaps at each abutment at 60F 160 total length Skew angle = 15 Value of constants = 15 = 0.0000060 L = 160/2 = 80 Tmin = 0 Tmax = 80 Tnormal = 60 Gexist = 1 Installmin = 40 Installmax = 80 A. Movement Calculations 1. Mt = (12)(80)(0.0000060)(80-0) = 0.461 2. Ms = 0
C.
D.
Expansion gaps at assumed extreme installation temperatures 1. Gmin = 1 + (60-40)/10(0.0556) = 1.111 2. Gmax = 1 - (80-60)/10(0.0556) = 0.89 Check Sealant Capacity at minimum installation temperature 1. Mc = (80-40)/10(0.0556) = 0.224 2. 0.224/1.111 = 0.20 < 0.50 OK 3. Mo = (40-0)/10(0.0556) = 0.224 4. 0.224/1.111 = 0.20 < 1.00 OK Check Sealant Capacity at maximum installation temperature 1. Mc = (80-80)/10(0.0556) = 0.0 2. 0.0/0.89 = 0. 0 < 0.50 OK 3. Mo = (80-0)/10(0.0556) = 0.445 4. 0.445/0.89 = 0.50 < 1.00 OK
D.
C. Joint width at 60 (1.5)/cos 35 = 1.831" (0.5)/cos 35 = 0.610" Total = 2.441" D. Adjustment in joint opening for a 10F change in temperature: = (12)(300)(0.000006)(10)(cos 35) = 0.177
A14.6 Page 9 of 10 7/2009 SELECTION CRITERIA FOR MODULAR JOINTS I. Design Limitations
A. B. C. D. Maximum movement of 3 per each seal element. Maximum gap between adjacent center beams should be limited to 3. Movements should be increased 15% to provide a factor of safety. Temperature Range Concrete structures....... 0 to 80F Steel structures......... -30 to 120F
II.
Design Procedure A. Movement Calculations 1. Calculate the joint opening movement due to temperature drop from the installation temperature and shrinkage. 2. Calculate the joint closing movement due to temperature rise from the installation temperature. 3. Total movement (Mt) along centerline of bridge is the sum of (1) & (2) times 1.15. 4. Total movement normal to joint is Mt(cos). B. Joint Size 1. Total movement range (MR) should be a multiple of 3 based upon A3, C. Installation Gaps 1. Compute the minimum distance face-face of edge beams (Gmin).
Number of seals (n) = MR/3 Number of center beams = (n-1) w = Center beam top flange width g = Minimum gap per seal at full closure Gmin = (n-1)(w) + (n-1)(g)
2. D.
3. Compute gaps at different temperatures. Center Beam Spacing 1. Check spacing between center beams at minimum temperature.
G0F = G60F + total opening movement Spacing = [G0F (n-1)(w)]/n
2. III.
Design Example
Structure type - box girder Total length 1200 Skew Angle - 15 Expansion joints at both abutments Point of no movement for temperature and shrinkage is at the center of the bridge Value of Constants: = 0 = 0.0000060 = 0.0002 = 0.8 L = 1200/2 = 600
A.
2. 3. 4. B.
Closing Movement
Mtemp = (12)(6300)(0.0000060)(80-60) = 0.864
Joint Size 1. MR = 5.118 Use a 6 movement rating joint. Installation Gaps 1. Assume center beam top flange width =2
Number of seals = 6/3 = 2 Number of center beams = (2-1) = 1 Minimum gap per seal at full closure = 0 Gmin = (1)(2.50) + (1)(0) = 2.50
C.
2. 3.
Gmax = 2.5 + 6 = 8.5 G60F = Gmin + total closing movement = 2.5 + (0.864)(1.15)(cos15) = 3.46
Adjustment in opening for a 10F change in temperature = (12)(600)(0.0000060)(10)(cos15)= 0.417 G40F = 3.46 + (60-40)/10(0.417) = 4.29 G80F = 3.46 (80-60)/10(0.417) = 2.63
D.
2.
Spacing at 60F
Spacing = [3.46 (1)(2.50)]/2 = 0.48 Minimum recommended installation width = 1.5. Center beam must be mechanically separated in order to replace strip seal elements.
Added definition of on Page 1 and revised 0.8 factor to include c-i-p box girders & t-beams Added Selection Criteria for modular Joints Added Selection Criteria for silicone sealant joints
Article 15.1 Page 1 of 2 5/2004 CHECKING PROCEDURE FOR PRESTRESSED GIRDER SHOP DRAWINGS
The following is a list of items that should be checked to insure a complete and thorough review of prestressed girder shop drawings. Submittal Data Strand Certification Strand type (stress relieved or low relaxation) Ultimate strength Strand Area Modulus of elasticity Jacking Force/Gauge Pressure Data from the calibration test and a graph or equation representing the relationship between jacking force and gauge pressure shall be included. Bed Layout Total length of strand being tensioned Hold-down point locations with horizontal and vertical dimensions Hold-up point locations with horizontal and vertical dimensions Elongation Calculations Elongation of each strand to be measured and the corresponding gauge pressure Checking Procedure The tensioning method varies with each fabricator and the method of calculating the elongations varies accordingly. Jack Data
Jacking data shall fit the graph or equation submitted and the jack used in the test shall be the jack used for tensioning.
Strand Data Strand data shall match the certification sheet. The prestressing manufacturer must be reminded in the review letter that if the actual strand properties being used vary by more than 5% from the assumed values in the calculations then new elongation calculations will have to be made. Initial Prestress Force An initial force and initial gauge pressure shall be given. This is the force in the strand before any elongation measurements are made. Final Prestress Force This is the desired force in the strand after all the elongation losses have occurred. Low relaxation strand Pf = 0.75x270xstrand area Stress relieved strand Pf = 0.70x270xstrand area Calculated Elongations i = initial elongation = Pi L/AE f = final elongation = Pf L/AE Elongation Losses Elongation losses are treated differently depending on when they occur. There are three different times an elongation loss can occur: a. Before the strand is seated, B (dead-end seating or abutment deflection due to the jacking in progress). b. When the strand is seated, S (strand slipping in the chuck when released). c. After the strand is seated, A (abutment deflection due to subsequent jacking of other strands).
Gauge Pressure for Straight Strands Use the gauge pressure vs. jacking force graph or equation and solve for the gauge pressure. Fj = jacking force = (f + S + A) AE/L Elongation for Straight Strands Measured before seating Measured after seating M = f - i + B + A + S M = f - i + B + A
Elongation for Harped Strand Use the geometry for the hold-down and hold-up points to calculate the increase in the strand length due to harping. H = elongation due to increase in length of harped strand MH = elongation of harped strand = M - H Gauge Pressure of Harped Strand Use the gauge pressure vs. jacking force graph or equation and solve for the gauge pressure. Fj = jacking force = (f - H + S + A) AE/L The above calculations should be made for each strand and a table prepared listing the measured elongation and corresponding gauge pressure for each strand. Refer to Appendix H of the PCI Manual for Quality Control for Plants and Production of Structural Precast Concrete Products, 4th Edition, for sample tensioning calculations.
Article 16.1 Sheet 1 of 3 2/2008 PRELIMINARY STRUCTURE COST ESTIMATE The charts on the following sheets provide cost per square foot data for the preliminary estimate of total structure cost. The costs apply to ordinary structure types. The data is based upon the low bid from projects awarded from 2000 thru December 2007. The total cost per square foot includes all the bid items necessary to construct the structure except for the following: Preliminary Engineering E&C Traffic Control The costs for Repair and Rehabilitation projects require an individual estimate of cost for each project because of the wide diversity of work. Consult with the Group Leader/Bridge Engineer to obtain costs from similar projects. Cost data is available for the following types of structures: NEW CONSTRUCTION CULVERTS PRESTRESSED GIRDERS STEEL GIRDERS MISCELLANEOUS CONCRETE RETAINING WALLS PEDESTRIAN BRIDGES WIDEN CULVERTS
NEW CONSTRUCTION
STRUCTURE TYPE CULVERTS CAST-IN-PLACE PRECAST $165 $165 COST/SQ. FOOT OF DECK PLAN AREA 2000 thru 2007
PRESTRESS GIRDERS AASHTO, BULB TEE, DECK TEE VOIDED SLAB, TRIDECK $165 $215
MISCELLANEOUS STRUCTURES
STRUCTURE TYPE CONCRETE RETAINING WALLS PEDESTRIAN UNDERPASS PEDESTRIAN OVERPASS PRESTRESSED GIRDER, STEEL TRUSS WIDEN CULVERT COST/SQUARE FOOT 2000 thru 2007 $50 $135
$155 $90
Commentary
The unit prices are based upon trend lines of the weighted average of the 3 low bidders for each year and trend lines of all the unit costs of all the bidders based upon the bid opening date. The data is taken from the abstract of bids from January 2005 through June 2009.
Article 16.2 Page 2 of 6 7/2009 AVERAGE UNIT PRICES FOR STANDARD BID ITEMS (Based Upon 3 Low Bids from Jan 2005 thru June 2009) SECTION 203 - REMOVAL OF OBSTRUCTIONS
ITEM NO. 203-020A 203-020A 203-020A 203-035A ITEM Removal of Single Span Bridges Removal of Multi-span Bridges Removal of Truss Bridges Removal of Culverts UNIT SF SF SF SF ALL DISTRICT S $17 $20 $15 $15
NOTE : Use square foot cost for estimating purposes but show as cost per EACH on the Cost Estimate.
NOTE : Multiply Str. Exc. unit cost by 2.0 if underwater excavation involved, and by 2.5 if rock excavation involved.
NOTE : Reduce deck concrete costs by $20/CY when girder type makes slab forms unnecessary. Use LF/in2 of area for estimating, but show as FT on Cost Estimate.
Article 16.2 Page 3 of 6 7/2009 AVERAGE UNIT PRICES FOR STANDARD BID ITEMS (Based Upon 3 Low Bids from Jan 2005 thru June 2009)
NOTE : Steel Bridge - Use Cost/lb for estimating purposes but show as lump sum on the Cost Estimate. Reduce costs by $0.10/lb for rolled girders. Increase costs by $0.05/lb for haunched girders. Increase costs by $0.10/lb for curved girders.
NOTE : For HP12 Test Piles add $0 to the cost of the Furnish & Drive item. For HP14 Test Piles add $25 to the cost of the Furnish & Drive item. For 12 Shell Test Piles add $5 to the cost of the Furnish & Drive item. For 16 Shell Test Piles add $60 to the cost of the Furnish & Drive item
NOTE : Use Cost/lb for estimating purposes but show as lump sum on the Cost Estimate.
Article 16.2 Page 4 of 6 7/2009 AVERAGE UNIT PRICES FOR STANDARD BID ITEMS (Based Upon 3 Low Bids from Jan 2005 thru June 2009) SECTION 510 - CONCRETE OVERLAY
ITEM NO. 510-005A ITEM Concrete Overlay UNIT CY ALL DISTRICTS $1100
NOTE : Use 10% of total of all other bid items for small projects and 7.5% for large projects for estimating purposes but show as lump sum on Cost Estimate.
Article 16.2 Page 5 of 6 7/2009 AVERAGE UNIT PRICES FOR SPECIAL PROVISION BID ITEMS (Based Upon 3 Low Bids from Jan 2005 thru June 2009) EXPANSION JOINTS
ITEM NO. S501-06A S501-06A S501-06A S501-06A S501-05A S501-06A S501-40A ITEM Compression Seal Joints w/armor angles Compression Seal only Strip Seal Joints Modular Joints Asphaltic Plug Joints Silicone Sealant Elastomeric Concrete Header UNIT LF/inch LF/inch LF/inch LF/inch CF FT CY ALL DISTRICTS $65 $20 $60 $110 $700 $30 $14,000
SURFACE TREATMENT
ITEM NO. S501-60A S501-51A ITEM Textured Concrete Surface Anti-Graffiti Coating UNIT SY SF ALL DISTRICTS $50 $0.80
NOTE: Use LF/inch of diameter for estimating, but show as FT on Cost Estimate.
DEWATER FOUNDATION
ITEM NO. S500-11A S500-11A ITEM Cofferdam Other UNIT SF LS ALL DISTRICTS $40 $35,000
NOTE : Use Cost/sf of cofferdam form area for estimating purposes but show as lump sum on the Cost Estimate. Cofferdam form area is equal to the perimeter of the seal concrete times the difference in elevation of the bottom of the seal concrete and the cofferdam vent elevation.
RAIL RETROFIT
ITEM NO. S501-30A S501-30A S501-30A S501-20A ITEM Std Drawing G-2-F Type 1 Std Drawing G-2-F Type 2 Delaware Thrie Beam Remove End Block UNIT FT FT FT EA ALL DISTRICTS $120 $130 $130 $1600
RETAINING WALL
ITEM NO. S501-17A S501-18A S501-17A S501-17A S501-17A ITEM MSE Wall Coping Segmental Block Wall Welded Wire Wall Welded Wire Wall w/Concrete facing UNIT SF FT SF SF SF ALL DISTRICTS $45 $95 $30 $40 $45
Article 16.2 Page 6 of 6 7/2009 AVERAGE UNIT PRICES FOR SPECIAL PROVISION BID ITEMS (Based Upon 3 Low Bids from Jan 2005 thru June 2009) TEMPORARY SHORING
ITEM NO. S501-90A S501-90A ITEM Bridge Culvert UNIT LS LS ALL DISTRICTS $70,000 $45,000
CRACK REPAIR
ITEM NO. S501-30A S501-50A ITEM Preparation Injection UNIT FT GAL ALL DISTRICTS $75 $2000
UTILITY CONDUITS
ITEM NO. S501-30A S501-30A ITEM Complete across bridge At Abutments with diaph sleeves & deck inserts UNIT FT/conduit FT/conduit ALL DISTRICTS $20 $10
Article 16.3 Sheet 1 of 1 02/2003 BRIDGE IMPROVEMENT TYPE CODE The bridge improvement type code is a two digit number that is needed on the ITD-2101form, Project Authorization and Agreement, by the FHWA for their approval process. The following codes should be used: 08 Bridge New Construction Construction of a new bridge that does not replace or relocate an existing bridge. 10 Bridge Replacement Added Capacity Total replacement of a structurally inadequate or functionally obsolete bridge with a new structure constructed with additional lanes in the same general traffic corridor to current geometric construction standards. Incidental roadway approach work is included. The use of this code requires a National Bridge Inventory structure number (Bridge Inspection Master Key Number). Bridge Replacement No Added Capacity Total replacement of a structurally inadequate or functionally obsolete bridge with a new structure constructed without adding lanes in the same general traffic corridor to current geometric construction standards, or widening the lanes and/or shoulders of an existing structure without adding through lanes. A bridge removed and not replaced or replaced with a lesser facility is considered a bridge replacement. Incidental roadway approach work is included. The use of this code requires a National Bridge Inventory structure number (Bridge Inspection Master Key Number). Bridge Rehabilitation Added Capacity The major work required to restore structural integrity of a bridge as well as work necessary to correct major safety defects. Bridge deck replacement (both partial and complete) and widening of bridges including addition of through lanes to specified standards are included. Construction of a dual structure to alleviate a capacity deficiency is also included. Work required to correct minor structure and safety defects or deficiencies, such as deck patching, resurfacing, protective systems, upgrading railings, curbs and gutters, and other minor bridge work. If HBRRP funds are involved, the use of this code requires a National Bridge Inventory structure number (Bridge Inspection Master Key Number).
11
13
14
Bridge Rehabilitation No Added Capacity The major work required to restore structural integrity of a bridge as well as work necessary to correct major safety defects. Bridge deck replacement (both partial and complete) and widening of bridges without adding through lanes to specified standards are included. Work required to correct minor structure and safety defects or deficiencies, such as deck patching, resurfacing, protective systems, upgrading railings, curbs and gutters, and other minor bridge work. If HBRRP funds are involved, the use of this code requires a National Bridge Inventory structure number (Bridge Inspection Master Key Number). Facilities for Pedestrians and Bicycles An independent project (not part of any other Federal-Aid Highway project) to construct a facility to accommodate bicycle transportation and pedestrians.
28
Compacting backfill will be measured by the cubic yard of backfill material placed. The volume will be determined as follows: 1. Conduit: As shown on the plans. 2. Other Structures: a. Below the original ground surface: A volume equal to the volume of structure excavation less the volume of the permanent structure including opening, contained within the limits of measurement for structure excavation. b. Above the original ground surface: The volume contained between the outside walls of the structure and vertical planes 4 ft. outside thereof; the original ground surface; and a horizontal plane 1 ft. above the top of the structure or of the subgrade, whichever is the lesser. c. Volumes of backfill placed through water around abutments, wing walls and piers, will not be included in the measurement of quantities for compacting backfill.
2'-0" EXCAVATION
2'-0"
2'-0" BACKFILL
2'-0"
Natural ground
2'-0" EXCAVATION
2'-0"
Natural ground
2'-0" BACKFILL
2'-0"
2'-0"
2'-0"
4'-0"
Subgrade
2'-0"
BACKFILL
Article A16.1 Page 1 of 1 4/2008 ELIGIBLE & EXEMPT ITEMS FOR COST ESTIMATE
GENERAL The bridge construction unit costs are submitted yearly to FHWA. This cost data is used in the apportionment process as described in Title 23, U.S.C. Section 144(e). The unit cost report is for new and replaced highway bridges constructed with Federal funds on Federal-aid highways (highway bridges on the NHS and other Federal-aid highways) and on non Federalaid highways (highway bridges on local roads and rural minor collectors; off-system highway bridges). Unit costs shall be based on bridge costs only. To make this data as accurate as possible and uniform nationwide, the following guidelines for eligible costs should be followed when coding the Bridge Cost Estimate database. EXEMPT ITEMS (Items not to be included in the Unit Cost Calculations) Mobilization Demolition of existing bridge Stream channel work Riprap Slope paving Earthwork (exclusive of structural excavation and structural backfill) Clearing and grubbing Retaining walls not attached to the abutment Guardrail transitions to bridges Maintenance and protection of traffic Detour costs Signing and marking Lighting Electrical conduit Inlet frames and grates Field office Construction engineering items Training Right-of-way Utility Relocation Contingencies Painting steel or concrete members for aesthetic purposes Textured concrete surface ELIGIBLE ITEMS (Items to be included in the Unit Cost Calculations) As a general rule, if the item is necessary to construct the bridge, it is eligible. The following items have been ruled eligible by FHWA HQ. Temporary shoring for bridge construction (formwork, falsework, and retention of roadway fill) Work bridges or platforms Deck treatments or wearing surface overlays Deicing systems used for deicing decks for traffic safety Approach slabs (when paid for as a bridge item, e.g. on integral abutment bridges) Painting steel members to prevent corrosion
Commentary
The above information is based on FHWA Memorandum for Bridge Construction Unit Costs Attachment C and on information from Greg Kolle, FWWA Nebraska Division Bridge Engineer.
NOTES
PLAN ORGANIZATION Plan sheets shall be assembled in the normal order of construction as follows: Situation and Layout Sheet Index, Quantities, & Vicinity Map Design and General Notes Foundation Investigation Stage Construction Details Footing Layout and Pile Details Abutment Details Wingwall Details Bent or Pier Details Framing Plan Girder Details Deck Typical Section Deck Details and Pour Sequence Bearing Details Expansion Joint Details Railing/Parapet Details Approach Slab Details Reinforcement Details
A
If the section can not be placed on the same sheet where it is taken, the following note should be added next to the section symbol; For Section A-A see sheet #_. Details are noted by using a bubble with a letter and a leader line to a bubble around the specific detail or view to be expanded for clarity as follows:
See Detail A
or
The letter designation for views and details shall begin with A on each sheet; e.g., Detail A, View A-A. Each structural component (abutment, pier, etc.) shall be detailed separately as a general rule. If similar components are the same except for height, then the details can be shown on a single sheet using a table for the variable dimensions. REVISIONS The revision block shall be used to record revisions made after the plans have been signed by the Bridge Engineer. Minor revisions shall be done using plastic lead or ink and erasing or crossing out the items to be changed. Major revisions may require the changes be done using the CADD and resigning the drawing. Revisions shall be noted by a number in a triangle next to the change. A number corresponding to the change shall be placed in the triangle in the revision block, followed by the date, the initials of the person making the change, and a brief description of the changes made on the drawing. FINAL PLANS The completed drawings shall be stored in the vertical plan file and the index filled out to indicate which packet contains the drawings. Both the full size stamped mylars and half size plans for bidding with electronic signature shall be stored in the vertical file.
Article 17.2 Page 1 of 4 7/2009 SITUATION AND LAYOUT FOR HIGHWAY & WATERWAY CROSSINGS
PURPOSE The purpose of the Situation and Layout sheet is to provide an accurate overview and orientation of the project. The Engineer, checker, and detailer are responsible to ensure this data is correct. Once the Situation and Layout is approved, it should not be changed and final design should begin. SITUATION AND LAYOUT Refer to the Bridge Design Manual page B17.4 for plan sheet format data. An engineering scale should be used for the sheet. The Situation and Layout data shall be the first sheet of the structure plans and shall consist of the following plan sheets. Sheet 1 of the final plans shall contain the following items: PLAN ELEVATION PROFILE DATA HORIZONTAL ALIGNMENT DATA HYDRAULIC DATA Sheet 2 of the final plans shall contain the following items: VICINITY MAP SHEET INDEX QUANTITIES Sheet 3 of the final plans shall contain the following items: DESIGN NOTES GENERAL NOTES The PRELIMINARY Situation and Layout data should include a fourth sheet if necessary showing the following data: Typical section (Could be put on sheet 3 and then removed on final plan preparation) Curb-curb and out-out widths Sidewalk and curb widths Type of railing Slab thickness Slab reinforcement cover for both mats Girder type and spacing Centerline and profile grade point Crown slope Design features Show enough details of design features to clarify the concept. This should include abutment and pier/bent elevations and/or sections. The Title Block shall be completed as follows: Sheet Title: SITUATION AND LAYOUT Project Description: The project description shall include the following: Total length of a bridge to the nearest foot and clear span length of a culvert to a tenth of a foot. Type of main supporting member Names of features involved in the crossing Examples: 262 STEEL GIRDER UNDERPASS ROBERTS I.C. I-15 STA 300+77.51 SH-48 STA 29+46.79 256 PRESTRESSED CONCRETE BRIDGE E. BRIDGE ST. OVER WEISER RIVER STA 8+24.78
PROFILE DATA Title the view PROFILE DATA. The view can be drawn "Not to Scale". Show the profile grade across the structure. Show the location of the structure on the alignment. Show the begin/end of bridge station and elevation. Show the profile grades for all highways involved in the crossing. Show the following vertical curve data: Stations and elevations at point of curvature, point of intersection, and point of tangency. Length of vertical curve Incoming and outgoing grades in percent HORIZONTAL ALIGNMENT DATA Title: HORIZONTAL ALIGNMENT DATA. Show the stations at point of curvature, point of intersection, and point of tangency on the PLAN view if possible. If not possible, list the stations in the curve data. Show the following horizontal curve data: , T, L, R, S, RL, and Z. Horizontal curves shall be described by the degree of curve. Show the superelevation transition data if applicable. Cross-sections at the control points are recommended. If the structure is on a tangent alignment, show the bearing in the PLAN view. HYDRAULIC DATA Title: HYDRAULIC DATA Show the following hydraulic data for streams and rivers: FLOOD DISCHARGE H.W. ELEVATION VELOCITY Design (Q50) cfs ft fps cfs ft fps Base (Q100) cfs ft fps Scour (Qsc) Show the following hydraulic data for canals: Canal Flow cfs H.W. Elevation ft Velocity fps Flow controlled by __________________ Canal Company. Hydraulic data is not required for minor structure rehabilitation or extension projects. VICINITY MAP A map of the State of Idaho showing location of the project. A vicinity map showing the location of the bridge site. INDEX OF SHEETS Title: INDEX OF SHEETS The bridge plans shall be numbered independently from the roadway plans and shall start with sheet 1.
DESIGN & GENERAL NOTES The Design Notes shown on page B17.1A B17.2D of the Bridge LRFD Manual are intended to be used as a checklist for the usual situation and should be modified to fit each individual case. Multi-span prestressed girder bridges should include one of the following notes as specified on page 5.14.1.2.7: a. Girders designed as simple spans and reinforcement added to resist negative moment. b. Girders designed fully continuous for live load. c. Girders designed as simple spans; slab reinforcement added to limit cracking. The computed and ultimate values for the Pile/Footing Design Loads should be shown on the final Situation and Layout submittal. Projects involving rehabilitation or repair should add the following note under CONSTRUCTION: The contractor shall verify dimensions in the field before ordering material. The estimated ADT data 20 years after the projected year of construction should be used to compute the single lane ADTT. The 20 year projected single lane ADTT shall be shown on the plan sheet with its corresponding year.
Article was renumbered to 17.2 to allow for addition of new Article 17.1. Deleted Traffic Data from Situation Layout requirements. Single lane ADTT was added to the Transient Loads on the Design & General Notes sheet.
Added paragraph for Vicinity Map, Index, & Quantities Sheet. Revised Index of Sheets to Sheet Index on page 1.
Article 17.3 Page 1 of 1 4/2008 SITUATION AND LAYOUT FOR RAILROAD CROSSINGS
GENERAL The Situation and Layout for Railroad crossings shall be the same as for Highways & Waterways with the addition of the following data. PLAN VIEW Show the railroad milepost at the intersection with the highway and direction of increasing railroad milepost. Show the limits of the railroad Right of Way. Show the Township, Range, and Section data. Identify each track as mainline, siding, spur, etc. and show track spacing dimensions. Show all access roadways. Show the point of minimum horizontal and vertical clearance and the distance from the nearest track. Show any utilities crossing the structure and show the location of any deck drains. No deck drains will be installed over the railroad right of way. Show all utilities in the vicinity of the railroad (if none, a note should state No known utilities). ELEVATION VIEW Show the minimum vertical clearance taken from the top of rail. Distance between the top of pier footings and top of rail. Show the abutment slope protection and call out the slope perpendicular to the railroad. Show Railroad drainage ditches. (Make sure they are unobstructed by the construction) Show existing and future track locations. Show limits of fencing and protective railing or splashboards. TYPICAL SECTION Identify superstructure structural members. Show type of railing/fencing and height. RAILROAD CONSTRUCTION CLEARANCES Show an Elevation view that has minimum horizontal and vertical construction clearances. PROFILE DATA Show the railroad profile grades at top of rail for 1000 each side of the structure.
DESIGN NOTES & GENERAL NOTES The Notes shown on pages B17.1A thru B17.1D of the Bridge LRFD Manual are intended to be used as a checklist for the usual situation and should be modified to fit each individual case.
Article was renumbered to 17.3 to allow for new article 17.1. Referenced new Design & General Notes drawings B17.1A B17.1D.
Font = 24 #7 ft in 21 10.5 13 1 10 11.25 8 2 6 6.75 4 4.5 2 2.25 1 1.125 0 0.875 0 1.75 0 2.625 0 3.5 0 5.25 0 7.0 0 10.5 1 2 1 9 2 4 3 6
DESCRIPTION Continuous Dot Dash Medium Dash Long Dash Centerline (Long Dash/Short Dash) Short Dash Phantom Line (Long Dash/2 Short Dash) Centerline (Long Dash/Medium Dash
PLOT LINE THICKNESS-inches WEIGHT 22x 34 11x 17 0 0.0075 0.0035 1 0.0125 0.0060 2 0.0175 0.0075 3 0.0225 0.0110 4 0.0375 0.0180
BRIDGES DESIGNED CONTINUOUS FOR LIVE LOAD WHEN GIRDERS ARE LESS THAN 90 DAYS OLD When the deck is placed on girders that are less than 90 days old from the time they are cast, any rational deck placement sequence (other than continuous placement) may be used provided the girders are designed in accordance with Article 5.14.1.4.3 for the loading, creep and shrinkage that result from the sequence that is chosen.
Commentary
Refer to Article 5.14.1.4 -Simple Span Precast Girders Made Continuous In order to mitigate the development of positive moments at the piers due to girder creep, the girders are required to mature for 90 days to prevent excessive creep after the deck is placed. In accordance with the AASHTO Specifications this allows the same placing sequence as girders designed as simple spans without the need to calculate the effects of creep as is required for girders less than 90 days old.
Revisions:
June 2006 August 2006 Article was renumbered to 17.5 to allow for new article 17.1. The deck placement sequence for bridges designed continuous for live load was revised to reflect changes that were adopted by AASHTO 2006 ballot item #13.
A17.1 Page 1 of 2 8/2004 SITUATION AND LAYOUT CHECKLIST FOR HIGHWAY / WATERWAY CROSSINGS PROJECT NAME: PROJECT KEY NUMBER: BRIDGE DRAWING NUMBER:
CHECKED BY:
Use pencil to mark items. Use an X or to indicate completion. Use INC to indicate items which are incomplete and N/A to indicate items which do not apply. For additional information on the design requirements refer to Chapter 17 of the LRFD Manual.
BORDER
Designed and Detailed Names Design Checked and DWG Checked Names (required when work has been checked) Corrections Name (need only be completed when corrections have been made) Engineers Stamp (For Full and Half sized Sheets) Project Number Sheet Title Project Description (Length, Type of Support, Crossing, Station) Bridge Inspection Master Key (Only required on sheet 1) Bridge Drawing Number (required but may not be available during preliminary design) Project County and Key Number Sheet Numbering (required for final design and PS&E submittals)
PLAN VIEW
View Title with scale factor Length of Structure (out to out) along survey line Station and Finished Grade Elevation at the Beginning and End of structure along Centerline. Abutment / Pier number, Station, and Finished Grade Elevation shown at the Intersection of the Abutment / Pier Centerline and Survey line at the following locations: Centerline of bearing of Abutments Center of Piers / Bents Span lengths along survey line shown as follows: Single Spans or End Spans: abutment centerline bearing - centerline pier/bent Interior Spans: centerline pier/bent - centerline pier/bent Bridge Width shown (out - out). Width should include the parapet, curb and sidewalk as applicable. Curb-to-Curb Width shown Roadway Lane and Shoulder Widths shown Lane Direction and Name of Closest Town/Geographical Feature in that Direction indicated North arrow shown Intersection Angle shown if not a 90 crossing horizontal and vertical clearances shown as follows: Highway Crossings: Show the point of minimum vert. and horiz. clearance for the highway Stream Crossings: Show the point of minimum clearance above Q50 high water elevation Identification of Survey and Profile lines Existing Bridge Details shown (as needed) Existing Bridge Drawing Number given (Needed only if existing bridge is to be removed) Plan View Oriented so Elevation View can be placed below Plan View Bridge Stationing at Centerline of Structure shown and runs Left to Right of sheet Culvert Stationing at Centerline of Structure shown and runs Bottom to Top of sheet Rip Rap Limits shown with pay note (as applicable) Contour lines shown and gray shaded Utilities Crossing the structure shown (as applicable) Deck drains shown (as applicable) Survey Cap shown with installation note Horizontal Alignment Data should be included in this view if possible. See Horizontal Alignment Data Checklist for items to be included.
PROFILE DATA
View Title with scale factor Profile Grade Across Structure Shown Structure Location Shown on Profile Station and Elevation for the Beginning and End of Structure Shown Profile Grades for all Highways involved in Crossing Shown The following Vertical Curve Data Shown: Stations and Elevations at Point of Curvature, Point of Intersection, and Point of Tangency Length of Vertical Curve Incoming and Outgoing Grades as a percent
HYDRAULIC DATA
TRAFFIC DATA
View Title Traffic Data for Construction Year and 20 years past Construction year Shown (Current ADT, Future ADT, Current ADT % Trucks, Future ADT % Trucks, Design Speed)
INDEX OF SHEETS
View Title Sheet number and Sheet Title Shown for all Sheets
QUANTITIES
View Title Bid Item Number, Description, and Unit Shown for all applicable items Bid Item Quantity Shown (Not Required until Final Design)
The notes shown on B17.1- B17.2 are intended as a design and detailing aid. Only those notes required should be shown on the plans. Notes should be modified or added to match the requirements of each structure. The values required for the Footing & Pile Design Loads are to be furnished as follows: X xx Geotechnical Engineer Bridge Designer
B17.1A Design and General Notes concrete girder railroad bridge April 2008 Added new sheet. July 2009 Deleted IC from Extreme Event loads B17.1B Design and General Notes concrete girder railroad bridge April 2008 Added new sheet July 2009 Added Method B for Elastomeric Bearings Deleted MSE Wall note Designed in accordance. B17.1C Design and General Notes steel girder railroad bridge April 2008 Added new sheet July 2009 Deleted IC from Extreme Event loads B17.1D Design and General Notes steel girder railroad bridge April 2008 Added new sheet July 2009 Added Method B for Elastomeric Bearings Deleted MSE Wall note Designed in accordance. B17.2A Design and General Notes concrete girder highway bridge June 2006 Revised Construction Specification note to Project plans & specifications. Revised Design Procedures notes to list only proprietary software programs and added Design Speed. Added Single Lane ADTT to Transient Loads because traffic data was deleted from the Situation Layout sheet. Revised Footing Design Loads format to show nominal bearing resistance value and the effective footing area/width. April 2008 Denoted drawing for use on a highway bridge. Added reference to 2008 Interims Changed Seismic data to agree with 2008 Interims Modified Footing & Pile Design loads July 2009 Added Method B for Elastomeric Bearings Deleted MSE Wall note Designed in accordance. B17.2B Design and General Notes steel girder highway bridge June 2006 Revised Construction Specification note to Project plans & specifications. Revised Design Procedures notes to list only proprietary software programs and added Design Speed. Added Single Lane ADTT to Transient Loads because traffic data was deleted from the Situation Layout sheet. Revised Footing Design Loads format to show nominal bearing resistance value and the effective footing area/width. April 2008 Denoted drawing for use on a highway bridge. Added reference to 2008 Interims Changed Seismic data to agree with 2008 Interms Modified Footing & Pile Design loads July 2009 Added Method B for Elastomeric Bearings Deleted MSE Wall note Designed in accordance. B17.2C Design and General Notes concrete culverts June 2006 Revised Construction Specification note to Project plans & specifications. Revised Design Procedures notes to list only proprietary software programs and added Design Speed. Added Fill Depth and Live Load Surcharge to Permanent Loads. Revised Footing Design Loads format to show nominal bearing resistance value and the effective footing area/width. April 2008 Added reference to 2008 Interims Modified Footing Design loads
B17.2D Design and General Notes metal pipes June 2006 Revised Construction Specification note to Project plans & specifications. Revised Footing Design Loads format to show nominal bearing resistance value and the effective footing area/width. April 2008 Added reference to 2008 Interims Modified Footing Design loads B17.3 Sheet Index, Quantities, & Vicinity Map April 2008 Added new sheet. B17.4 Consultant Plan Sheet June 2006 Renumbered sheet from B17.1 to B17.3. Added Note 7 for electronic stamp note levels. April 2008 Renumbered sheet from B17.3 to B17.4.