06-Project Time Management
06-Project Time Management
ProjectManagementTraining
ProjectTimeManagement
Monitoring & Controlling Processes Planning Processes
Initiating Processes
Closing Processes
Executing Processes
Knowledge Area
Process Initiating Planning Activity Definition Activity Sequencing Activity Resource Estimating Activity Duration Estimating Schedule Development Executing Monitoring & Control Closing
Time
Schedule Control
ProjectTimeManagement
The process required to manage timely completion of the project Project time management start with planning by the project management team (not shown as a discrete process) In small project, defining & sequencing activities, estimating activity resource & duration, developing schedule are viewed as a single process process.
6.1DefineActivities
The process of identifying the specific actions to be performed produce the p j project deliverables. Work package decomposed into activities (schedule activities) Tools & Techniques
1. 1 2. 3. 4 4.
Decompositions Rolling wave planning Templates Expert judgment
Inputs
1. 1 Scope baseline 2. Enterprise
environmental factors 3. Organizational process assets
Outputs
1. 1 Activity list 2. Activity attributes 3. Milestone list
In the real word sometime we skip define activities since we take WBS down to the activity level. p y This is not a wrong practice but not a PMBOK practice.
DefineActivities(Tools&Techniques)
Rolling Wave Planning: progressive elaboration planning where you do not to plan
activities until you start the project management process for that phase is in the project life cycle
6.2SequenceActivities
Process of identifying and documenting relationship among the project activities
Inputs
1. 2. 3. 4. 5.
Activity list Activity attributes Milestone list Project scope statement Organizational process assets
Outputs
1. Project schedule
network diagram 2. Project document d t updates
PrecedenceDiagrammingMethod(PDM)
Precedence Diagramming Method (PDM) or Activity-on-Node (AON) Method used in Critical Path Methodology(CPM) No dummy activities Logical relationship:
Finish-to-Start (FS) Finish-to-Finish (FF) Start-to-Start (SS) Start-to-Finish (SF)
ApplyingLeads&Lags
Use leads and lags to support realistic and achievable project schedule. Each activity is connected at least to one predecessor and one successor except the start and the end.
A predecessor B C Successor
Leads.
May be added to start an activity before the predecessor activity is complete.
Lags g
Inserted waiting time between activities A A
PrecedenceDiagrammingMethod(PDM)
Example of PDM which showing logical relationship and leads or lags
Other method to draw network diagram: Arrow Diagramming Method (ADM) GERT: allows loops between activities
DependencyDetermination
To define sequence among activity, these type of dependency are used:
1. 1 Mandatory (hard logic) Inherent in the nature of work being done or required by the contract E.g. You must design before you can develop 2. Discretionary (preferred, preferential, or soft logic) Define base on knowledge Can be changed if needed g Important when how to shorten or re-sequence the project 3. External part o tside Based on the need t of the party outside the project
Network diagram
PERT chart Shows just dependencies (logical relationship) C Could show the critical path if activity duration estimates added f
PERT
PMD
EF = ES + D -1 LS = LF D +1 Float (F) = LS ES = LF EF
6.3EstimateActivityResources
Process of estimating the type and quantities of material, people, equipment or supplies required to p pp q perform each activity. y
Inputs
1. 2. 3. 4.
Activity list Activity attributes Resource Calendars Enterprise environmental factors 5. Organizational process assets
Outputs
1. Activity resource
requirements 2. Resource breakdown structure 3. Project d 3 P j t document t updates
EstimateActivityResource(Tools&Techniques)
Resource Calendar:
Information (skill location etc) in which resource (people equipment material (skill, location, (people, equipment, material, etc) are potentially available.
Bottom up estimating: p g
Activity is decomposed to be more confidence in estimating
6.4EstimateActivityDurations
Process of approximating the number of work periods to complete individual activities with estimated resources.
Schedule shall be as believable and realistic as possible (do not allow padding)
Inputs
1. Activity list 2. Activity attributes 3 Activity resource 3. 4. 5. 6. 7.
requirements Resource Calendars Project scope statement Enterprise environmental factors Organizational p g process assets
Outputs
1. Activity duration
estimates 2. Project document updates
EstimateActivityDurations(Tools&Techniques)
Analogous Estimating (Top down):
use actual duration of previous activity (historical) that has similarity
Parametric Estimating: g
use statistical relationship between historical data and other variables (e.g. learning curve) Th result can b The lt become h i ti ( heuristics (experience b d t h i / l of th b) i based technique/rule f thumb)
3PointsEstimate(PERT)
Also called Program Evaluation and Review technique (PERT) Use for time and cost estimation Expected calculated from Most-likely, Optimistic, Pessimistic Range of estimate = EAD (Expected Activity Duration) +/- SD (Standard Deviation)
Expected Standard Deviation Variance
P + 4 + 6
P 6
P 2 6
SD=
variance
Exercise:Treepointestimates(PERT)
Duration M 5 4 8 10 O 1 2 5 5
Variance range
Exercise:PERT Mosttrickyquestion
Together with your team, you applied three-point estimation on a Critical path which consists of two activities. hi h i f i ii The following duration uncertainties are all calculated assuming a 3 sigma Confidence interval. The duration uncertainty defined as pessimistic minus optimistic estimate of the uncertaintydefined estimateof first activity is 18 days; the second estimate has an uncertainty of 24 days. Applying the PERT formula for paths, what is the duration uncertainty of the entire th? path?
A. A B. C. D. 21 days 30 days 42 days No statement is possible from the information given.
Exercise:PERT Mosttrickyquestion(Answer)
See that the question says that Duration Uncertainty is Pessimistic minus Optimistic in other words P O W k d P-O. We know th t SD iis (P-O ) / 6 , thus SD is "duration Certainty " / 6 that (P O th i "d ti C t i t Thus For Path 1 : SD = 18/6 = 3 Variance = 3*3 = 9 For path 2 : SD = 24 /6 = 4 Variance = 4*4 = 16 Total Path Variance = 16 + 9 = 25 Sqrt (25) = 5 Meaning ( ) / 6 = 5 g (P-O) (p-O) = 5 * 6 DURATION UNCERTAINTY = 30
6.5DevelopSchedule
Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule. p j Inputs
1. Activity list 2. Activity attributes 3. 3 Project schedule 4. 5. 6. 7. 8. 9.
network diagram Activity resource requirements q Resource Calendars Activity duration estimates Project scope statement Enterprise environmental factors Organizational process assets
Outputs
1. 2. 3. 3 4.
Project schedule Schedule baseline Schedule data Project document updates
CriticalPath
Critical Path is the longest duration path Identify the shortest time needed to complete a project There can be more than one critical path We dont want critical path, it increase risk Dont l D t leave a project with a negative fl t you would compress th schedule j t ith ti float, ld the h d l Near-critical path is the path that has close in duration to critical path Float (Slack) Total float: the amount of time an activity can be delayed without delaying the project end date or intermediary milestone. Free float: the amount of time an activity can be delayed without delaying the early start date of its successor(s) successor(s). Project float: the amount of time an activity can be delayed without delaying the externally imposed project completion date required by customer/management.
CriticalPathMethodBasic
Activity A B C D E F G H A B B C D,F E Precedence Duration 2 3 1 4 2 1 5 2 2 0
Dummy activity = 0 resource & 0 duration I H J G,I Critical activities - all activities in the critical path - Delay in the completion of these activities will lengthen the project timescale - Has float = 0
CriticalPathusingPDM
Forward Pass
Calculation Forward Pass: ES + D = ES(successor) use highest value on join Backward Pass: LS D (predecessor) = LS (predecessor) U llowest value on jjoin Use t l i
Backward Pass
Exercise
Questions: What is the critical path? What is critical path duration? What is float (slack) duration of activity A30? Answers: -
CriticalChain(BufferManagement)Method
The longest duration path through the project considering both activity dependencies and resource constraints. Network diagram and critical path are identified first Type of buffers yp
Project buffer Feeding buffer Resource buffer
WhatifScenarioAnalysis
Analysis on effect of changes on a particular thing (assumption) on the project which make activity duration change. Monte Carlo Simulation Used when there is possibility that the critical path will be different for a given set of project conditions. Using probability distribution for each activity or group of activities Using computer software Using three-point estimates and network diagram Help deal with path convergence g
Multiple paths converge into one or more activities (but adding risk)
ScheduleCompression
Fast Tracking
Performing critical path activities in parallel. Usually increase risk and requires more attention to communication. May need a rework. y E.g. Design is half finished and start coding.
C hi Crashing
Analyze cost and schedule trade-offs. Determine most compression for least cost. Crash the tasks that cost the least first, focusing on minimizing project cost. Always results in increased cost.
ProjectSchedule
Schedule can be shown with or without dependencies (logical relationship). relationship) Presented as
Summary form e.g. Master Schedule, Milestone schedule Detailed form
Format:
Network diagram Milestone chart Bar chart (Gantt chart)
ScheduleData
Includes at least:
Schedule il t S h d l milestone Schedule activities Activity attributes Assumptions & Constraints
6.6ControlSchedule
Process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule. p j Inputs
1. Project Management
Plan 2. Project Schedule 3. Work performance information 4. Organizational p process g assets
Outputs
1. Work performance 2. 3. 4. 5.
measurements Organizational process assets updates Change requests Project management j g plan updates Project document updates
Nexttopic: p ProjectCostManagement
ThankYou