Project Plan: Critical Path Method: STEP 1: Identify The Logic Network
Project Plan: Critical Path Method: STEP 1: Identify The Logic Network
QUESTION 1 For the project below, determine the critical path, calculate ES,EF, LS,LF, the total float and the free float. Draw Gantt Chart form the CPM
ACTIVITY A. B. C. D. E. F. G. H. DURATION (WEEK) 3 5 4 2 6 4 2 1 IPA A A B,C B,C D E F,G
B A C
F H
STEP 2: Draw the actual network based on Step 1: fill in the ID and duration
B 5 A 3 C 4
D 2
F 4 H 1
E 6
G 2
o o o o
ES LS
F EF G 2 LF
o o o
ff
STEP 3: Forward path calculation (+ve & max value) get Early Start and Late Start 03 26931722 625
0 A 3
3 B 5
8 D 2
10
10 F 4
14
0 A 3
16 H 1 3 C 4 7 8 E 6 14 14 G 2 16
17
(when there are option eg 8 or 7 for Forward path , choose maximum value ; for backward path choose minimum value)
ff
STEP 4: Backward path calculation (-ve & min value) 16 A 1 17 Early finish - duration = Early early start @ 17-1 =16
STEP 6: Culculate the FLOAT = the different between ES and LS or/and EF and LF
3 3
0 B 5
8 8
8 10
2 10 D 2 12
10 12
2 F 4
14 16 16 0 17 H 1 17
0 0
0 A 3
3 3 3 4 1 C 4 7 8 8 8 0 E 6 14 14 14 14 0 16 G 2 16 16
ff
STEP 7: Identify the critical path= A--> B-->E-->G-->H (The network from task with 0 float to the next task with 0 float)
3 3
0 B 5
8 8
8 10
2 10 D 2 12
10 12
2 F 4
14 16 16 16 0 17 H 1 17
0 0
0 A 3
3 3 3 4 1 C 4 7 8 8 8 0 E 6 14 14 14 14 0 16 G 2 16
eg free float activity C: EF(C)=7 ; ES (D) = 8 ; ES(E)=8 thus FF (C) = 1 D: EF(D) = 10 ; ES (F) = 10; thus FF(D) = 0