Location of UPFC in Electrical Transmission System: Fuzzy Contingency Ranking and Optimal Power Flow
Location of UPFC in Electrical Transmission System: Fuzzy Contingency Ranking and Optimal Power Flow
com
Location of UPFC in Electrical Transmission System: Fuzzy Contingency Ranking and Optimal Power Flow
Ch. Chengaiah, Prof. R.V.S. Satyanarayana and Dr. G.V Mrutheswar
Department of Electrical and Electronics Engineering, Sri Venkateswara University College of Engineering, Sri Venkateswara University, Tirupati-517502- India. AbstractIncrease in electrical power demand due to modernization has led to the increase in the number of power
stations and their capacities and consequent increase in the power transmission lines which connect the generating stations to the load centers. So, the operation and planning of large interconnected power systems are becoming increasingly complex. The Fast-Decoupled Load Flow method is performed to estimate post contingencies of line flows and bus voltages for other contingency cases. Based on system operators past experience, each post-contingent quantity is assigned a degree of severity according to the potential damage that should be imposed on the power system. Hence human experts tend to use linguistic variables to describe the degree of severity, uncertainty exists in knowledge representation. The objective of contingency screening and ranking is to quickly and accurately select a shortlist of critical contingencies from a large list of potential contingencies and rank them according to their severity. This paper presents an approach for selection of suitable location for Unified Power Flow Controller (UPFC) considering normal and network contingencies. A new approach is considered using Fuzzy Logic Controller (FLC) to evaluate the degree of severity of the considered contingency and to eliminate the masking effect. The purpose of Optimal Power Flow (OPF) is to calculate the recommended set points for power system controls to trade-off between security and economy. The Newton Raphson (NR) method is considered to obtain Optimal Power Flow. It can be obtained either in a preventive or corrective mode. In this paper, a preventive mode of OPF is used to provide suggested improvements for selected contingency cases. The selection of suitable locations for UPFC, use the criteria on the basis of improved system security and Optimized Power flow. The proposed approach is tested on IEEE-14 bus system.
Keywords Power Flow Analysis (NRLF and FDLF), FLC, UPFC, OPF.
I.
INTRODUCTION
The most comprehensive and flexible device emanated from the Flexible AC Transmission Systems (FACTS) initiative is UPFC. It improves system performance under normal and network contingency conditions. Also UPFC is most expensive thus it is important to ascertain the location for placement of UPFC device suitable for various network contingencies. The UPFC is an advanced power system device capable of providing simultaneous control of voltage magnitude, active and reactive power flows in an adaptive fashion [1]. It has Instantaneous speed of response Extended functionality Capability to control voltage, line impedance and phase angle in the power system network Enhanced power transfer capability Ability to decrease generation cost Ability to improve security and stability Applicability for power flow control, loop flow control, load sharing among parallel corridors [2]. The location of UPFC device in the power system on the basis of static - dynamic performances. There are several methods for finding locations of UPFC in vertically integrated systems, but little attention has been devoted to interconnected power systems under network contingencies. Fuzzy set based reasoning approach has been developed for contingency ranking. The post contingent quantities like line flows and bus voltages are expressed in fuzzy notation and further processed through fuzzy reasoning rules to achieve desired contingency list [3] In this paper for selection of suitable locations of UPFC. The voltage stability index (L-index) of load buses is used as the basis for improved system performance after evaluating the degree of severity of the considered contingency [4]. By Fast-Decoupled Load Flow (FDLF) method, the value of L-index is calculated for various contingency cases. The proposed approach for selection of UPFC location has been tested on IEEE 14-bus system [5]. The purpose of Optimal Power Flow (OPF) is to calculate the recommended set points for power system control s that are trade-off between security and economy. The Newton Raphson (NR) method is considered to obtain optimal power flow. The primary task is to find a set of system states within a region defined by the operating constraints such as voltage limits and branch flow limits [11]. The secondary task is to optimize a cost function within this region. Typically, this cost function is defined to include economic dispatch of active power while recognizing the network-operating constraints. The OPF can be obtained either in a preventive or corrective mode [6]. In this paper, the preventive mode is considered to obtain the OPF which is used to provide suggested improvements for selected contingency cases.
10
Location of UPFC in Electrical Transmission System: Fuzzy Contingency Ranking II. VOLTAGE STABILITY INDEX (L -INDEX)
Consider a system where n is the total number of buses, with 1,2,.....g generator buses, and g+1,.n, (n-g) load buses. For a given system operating condition, using the load-flow results, the voltage-stability index [6-7] or L - index [7-8] is computed as,
.. (1) Where j = g +1,....,n and all the terms within the sigma on the right hand side are complex quantities. The values of F ji are complex and are obtained from the network Y-bus matrix. For a given operating condition,
(2) Where IG, IL, VG, and VL represent complex current and voltage vectors at the generator nodes and load nodes. [Y GG], [YGL], [YLL] and [YLG] are corresponding partitioned portions of the network Y-bus matrix. Rearranging, one can obtain
For stability, the index Lj must not be violated (maximum limit = 1) for any node j. Hence, the global indicator L describing the stability of the complete subsystem is given by L= maximum of Lj , for all j (load buses). An L-Index value away from 1 and close to 0 indicates improved system security. For an unloaded system with generator/load buses voltage 1.0+j0.0 the L indices for load buses are closest to zero, indicating that the system has maximum stability margin. For a given network, as the load/generation increases, the voltage magnitude and angles change near maximum power-transfer condition and the voltage-stability index Lj values for load buses tend to close to unity, indicating that the system is close to voltage collapse. While the different methods give a general picture of the proximity of the system voltage collapse, the L index gives a scalar number to each load bus. Among the various indices for voltage-stability and voltage collapse prediction, the L index gives fairly consistent results. The L indices for given load conditions are computed for all the load buses; and the maximum of the L-indices gives the proximity of the system to voltage collapse. Algorithm for obtaining voltage stability index: Form the network admittance matrix for the system. Obtain the elements of FLG by using equation (4). Obtain the value of L-index by using the formula specified in the equation (1) by substituting the values of FLG which are determined in step 2
III.
The proposed fuzzy approach uses L-index as post contingent quantity in addition to bus voltage profiles to evaluate contingency ranking [3]. The bus voltage profile and L-index values are expressed in fuzzy set notation. The severity indices are also divided into different categories. The fuzzy rules are used to evaluate the severity of each post contingent quantity. The Fuzzy inference structure is tested in MATLAB fuzzy toolbox.
11
Fig. 4. Membership functions for 4 linguistic variables of reactive power loading The fuzzy rules are used for evaluation of severity index of post contingent quantities like bus voltage profiles, Lindex, Real and Reactive power loadings are tabulated in table 1. Table 1: Fuzzy rules Post- contingent quantity. Severity Index LV,NV,OV MS, BS, MS VLI, LI, MI, HI,VHI VLS, LS,BS,AS,MS LL, NL,FL,OL LL,NL,FL,OL Where: VLS- very less severe; LS- less severe; BS- below severe,; AS above severe ; MS more severe. LS,BS,AS,MS LS,BS,AS,MS.
12
IV.
The network composite System Overall Severity Index is obtained by adding the four Overall Severity Indices as Shown in Fig.5 which is called Parallel Operated Fuzzy Inference System (FIS). When the Overall Severity Index for each Contingency in the contingency list is obtained, the overall Severity indices for those contingency cases with a severity Index exceeding a pre-specied value are listed, and ranked According to the network composite Overall Severity Index.
V.
In order to effectively investigate the impact of UPFC device on transmission systems, the implementation has been tested on IEEE 14-Bus system [12], which consists of Five Synchronous machines, three of which are Synchronous compensators used for reactive power Support and another two of which one is considered as generator bus and another one is considered as a slack bus, which is also called as reference bus and three Tap changing Transformers and one tertiary winding Transformer. There are shunt reactors also connected at various buses for transient-over voltage protection. In this
13
For finding the Severity Index, the heuristic rules are to be used. The system consists of 20 lines and each line is removed as a single line outage (contingency) to obtain contingency ranking based on the severity index. The System Overall Severity Index (SOSI) is obtained by adding the four overall Severity Indices as shown in Fig 4 and the Overall Severity Index for each contingency in the contingency list is obtained, the Overall Severity Indices for those contingency cases with a Severity Index exceeding the pre-specified value are listed out and ranked according to System Overall Severity Index. The top ten contingencies are arrived based on the System Overall Severity Index obtained by using Fuzzy Approach and corresponding results are tabulated in Table 2.
14
The proposed approach can provide the user that may cause immediate loss of load or islanding at certain bus. This kind of information in which is a very helpful to system operators, an Overall Severity Index is given for which outage case.
From the Table 3, it is observed that the possible locations of UPFC under this rank- 1 contingency are 2-5 and 34. When UPFC is placed between 2-5 gives minimum power loss as compared to the position of 3-4. Table 4: Rank2 Contingency (line outage 6-11) S.No 1 2 Line 6-5 11-10 Total power loss (p.u.) 0.1629 0.1869
15
From the Table 5, it can be observed that the possible locations of UPFC under this rank 3 contingency are 9-10 and 6-11.When UPFC is placed between 9-10 gives minimum power loss as compared to the position of 6-11. From the above results, for contingency 2-3, when UPFC is placed between buses 2-5 gives minimum power loss and significant improvement in Voltage profiles and Power profiles. So the line 2-5 is selected as best location of UPFC to achieve Optimal Power Flow (OPF). This is summarized in Table 10
VI.
The Optimal Power Flow (OPF) is to calculate the recommended set points for power system controls to trade-off between security and economy by using N-R method [8- 9-10]. It can be obtained either in a preventive or corrective mode. For contingencies found to cause over loads, voltage limit violations are the stability problems, hence preventive actions are required. In this paper, a preventive mode of OPF is considered, and test results are carried out with and without UPFC device which is presented in the following sections.
16
17
8.808441
18
Table 10: Summary of results with and without UPFC for Optimal Power Flow S.No Bus No. Parameter Without UPFC (p.u) With UPFC (p.u.)
Voltage Magnitude
0.954157
0.970344
Voltage Magnitude
0.832320
1.005439
2-5
Power loss
0.016416
0.003736
0.3507
0.1393
19
VII.
CONCLUSIONS
In this paper, bus voltages and the voltage stability indices at the load buses are also used as the post-contingent quantities to evaluate the network composite contingency ranking. The fuzzy contingency ranking method eliminates the masking effect of other methods of contingency ranking effectively. The selection of UPFC location under contingencies is obtained in the order of system severity. A set of most severe contingencies, based on the severity, is identified which needs additional supporting devices. Based on the above set of network contingencies, a few transmission lines are considered for placement of UPFC devices. For each contingency, analyses are carried out with placement of UPFC in different transmission lines. From the results the most severe contingencies are selected based on severity by using fuzzy, and the voltage profile, power flow through the lines increases and power loss at those severe contingencies also reduces by placing the Unified Power Flow Controller (UPFC). The proposed approach for UPFC location and Optimal Power Flow (OPF) can be tested for any bus system.
REFERENCES
[1]. [2]. [3]. [4]. [5]. [6]. [7]. [8]. [9]. [10]. [11]. [12]. Narain G .Hingorani Laszlo Gyugyi Understanding FACTSIEEE Press, 2001. L.Gyugyi,Unified Power Flow Control concept for flexible AC transmission system, IEEE proc 139(4) (July 1992) 323-331. Yuan-Yih HSU and Han- Ching Kuo,Fuzzy set based contingency ranking IEEE Transaction on power system Vol 7,NO.3, August 1992. P. Kessel, H. Glavitsch, Estimating the Voltage Stability of a Power System, IEEE Transactions on Power Delivery, Vol. PWRD-1, No.3, July 1986. U.C Chukwu, C.O Ahiakwo and M.A Nanim Solving Power System Problem Using Fast- Decoupled Algorithm Vol.17 No.2 (2007), pp.160-172. European Journal of Scientific Research Volume 17, No 2 April 2007 pp. 160-172 Lof,P.A.et al: Fast Calculation of Voltage Stability index , IEEE trans,1992,ps-27,(1 ) pp.54-64. D.Thukaram, L.Jenkins and K.Visakha Improvement of system security with Unified Power Flow Controller at suitable locations under network contingencies of inter connected systems IEE Proc-Gener.Transm.Disrib.Vol.152,No.5.Sep-2005. C.R. Fuerte-Eaquivel, E.Acha, Unied power ow controller: a critical comparison of Newton-Raphson UPFC algorithms in power ow studies, IEEProc. Gener. Transm. Distrib. 144(5)(1997)437444. D.P. Kothari and J.S.Dhillon Power System Optimization PHI-2007. Z. Huang et al., Application of UPFC in interconnected power systems- modeling, interface, control strategy and case study, IEEE Trans. Power Syst., vol. 15, no. 2, pp. 817-824, May 2000. M.H Haque, C.M.Yam, A simple method of solving the controlled load flow problem of a power system in the presence of UPFC, electrical power system research 65(2003) pp. 55-62. Ch. Chengaiah and R V S Satyanarayana A Comparative Study of 5-Bus and 14-Bus Systems with UPFC: A Power Flow Perspective The IUP Journal of Electrical & Electronics Engineering, Vol. IV, No. 1, pp. 65-82, January 2011.
Biographies
Ch. Chengaiah, obtained his B.Tech.(1999) from Sri Venkatesawra Uiniversity College of Engineering, Tirupati, A.P,. India and M.E .(2000) from National Institute of Technology(NIT) formerly called as Regional Engineering College, Tiruchinapalli,Timilnadu,India. He is having a total teaching experience of 12 years. He has published 9 papers in National/ International journals. At present he is working as Associate professor in EEE of S.V.University College of Engg.., Tirupati, A.P., and India. His research interest is Power System Operation & Control and Control Systems. Prof. R.V.S Satyanrayana , obtained his B.Tech. (1985), M.Tech.(1987) and Ph.D (2003) from Sri Venkatesawra Uiniversity College of Engineering, Tirupati A.p. India He is having a total teaching experience of 24 years in teaching UG/PG courses. He has guided one Ph.D and ten more are working for Ph.D under his guidance . He has published more than 62 papers in National/ International jour nals. He is awarded Educational Excellence Award. At present he is working as professor in ECE and also Placement officer of S.V.University College of Engg..,Tirupati, A.p., India. Dr. Marutheswar, Obatined his B.Tech (1985),M.Tech (1987) and Ph.D (2008) from Sri Venkatesawra Uiniversity College of Engineering, Tirupati A.p. India He is having a total teaching experience of 21 years in teaching UG/PG courses. At present 6 are working for Ph.D under his guidance. At present he is working as Associate professor in EEE and also CCC director of S.V.University College of Engg..,Tirupati, A.p., India.
20