Inventory Control in PPC
Inventory Control in PPC
Inventory Control
Inventory Control objectives:
1.
2.
Inventory Control
Types of demands: 1.
Independent Demand
Demand or consumption for the item is un-related to demand for other items. Example: End products and spare parts
2.
Dependent Demand
Demand for the item is directly related to demand for something else, usually because the item is a component of an end product, subject to independent demand.
Example: An automobile is an end product having independent demand, while tyres and other components required to build the automobile falls in the dependent demand category as their demand depends on demands of automobiles to be manufactured.
Inventory Control
An automobile is an end product having independent demand, while tyres demand depends on demands of automobiles.
2.
Inventory Control
2.
Inventory Control
Used for control of inventories of independent demand items Addresses two important issues a. How much to order? Decided by means of using economic order quantity formulas.
b. When to order
Accomplished using reorder points.
Replenishment
Inventory Level
Time
Time
Inventory Control
Follow the reorder point system To be high enough level so as to minimize the probability of a stock out. - Implemented using computerized inventory control systems
Demand Rate
Inventory Level O
Reorder Point
Time
Time
Buffer Stock
Detail schedule indicates : Quantities of each item When it must be ordered When it must be delivered to achieve the master schedule Technique used for determining quantities of dependent demand items constituting the inventories of raw material, purchased parts, work in process etc.
Sales orders
Product Design
Capacity planning
Master production schedule Bill of material file Inventory Record file Capacity requirement planning
2.
3.
4.
Lists component parts and sub-assemblies that make up each product and used in computing the requirement of raw material and components used in the end products listed in the master schedule. Case: Simplified structure of an assembled product.
Product consists of two sub-assemblies
Identifies each item by part number and gives time-phased record of its inventory status. Data includes gross requirement for the item i.e. How many units will be needed to build products in the master schedule
For every unit of final product listed in MPS, the required number of components of each type must be ordered or fabricated. Its ordering or manufacturing lead time to be taken in to account. For each component, the raw material must be ordered, accounting for its ordering lead time. Assembly lead time to be considered in the scheduling of sub-assemblies and final products.
There are no scheduled requirements, receipts or order releases indicated in the inventory records for these items. Neither material M4 nor component C4 is used on any other product. Determine the time phased requirement for M4, C4 and S2 to meet the master schedule for product P1. Orders for P1 beyond period 9 to be ignored in this case.
Case Solution:
Deliver Requirements for P1 must be offset by 1 week to obtain the planned order releases. S2 must be exploded by 2 units per P1 unit and offset by 1 week to obtain its order release. C4 is exploded by 2 units per S2 units and offset by 2 weeks to obtain its requirements and M4 is offset by its 3 week ordering time to obtain its release date, taking in to account current stock of M4 on hand...\Material Requirement Case solution P1-C4.xls
To determine the labour and equipment requirement needed to meet the master Production Schedule. To identify companys long term future capacity needs To identify production resource limitations in order to plan a realistic Master Production Schedule.
The Master Production Schedule reduced to material and component requirement using MRP. This provides estimates of the required labour hours, machinery/equipments and other resources required to produce the components. The required resources compared to plant capacity over the planning horizon.
Compatibility of master production schedule with plant capacity is checked and adjustment made to the schedule or plant capacity.
2.
3.
Number of work shifts - per production period increased or decreased , authorizing evening and night shifts and or using week end shifts
Inventory stockpiling Used to maintain steady employment period during slow demand period
4.
5.
Order Backlogs deliveries delayed/prioritized during busy period when resources insufficient to keep up with demand.
Subcontracting- Contacting work (Out sourcing) during peak period or taking in extra work during slack period.
6.
Additional Machinery More productive machinery New Type of machines to match future changes in product design.
Construction of new plants Purchase of existing plants from other companies due to lack of demand or obsolescence.
The Ideal Batch size One Part. Practically more than parts are produced at a time but the batch size is kept small.
In JIT philosophy producing too many units is to be avoided as much producing too few units.
2. Small Batch sizes and setup reduction: Use of EOQ formula to compute batch
size. Efforts to be focused on finding ways to reduce set up time.
Use of quick acting clamping devices instead of nuts and bolts Perform as much of the setup work as possible while previous jobs still running. Eliminate or minimize adjustments in setups Use of group technology , cellular manufacturing: Similar part styles produced on the same equipments, i.e. Machining Centers etc..
Small lot size requires parts to be delivered before stock out occur at downstream stations (final Assembly).
Workers inspect their own output to make sure it is right before it moves o the next operation.
Low work in process requires reliable production machinery & equipment. Emphasis on reliable equipment design and preventive maintenance
Order to produce parts at a given work station comes from the downstream station (Assembly or Final Assembly) that uses those parts.
As the supply of parts becomes exhausted at a given station it places an order at the upstream station (parts manufacturing /feeding) to replenish the supply.
Procedure repeated at each workstation in the plant has the effect of pulling parts through the production system Push system of production operates by supplying parts to each station in the plant. Driving the work from upstream station to downstream station.
Types of Kanbans:
1. Production Kanban 2. Transport Kanban
Work station
Transport Kanban
When station C starts work on a full container, a worker removes the transport Kanban from that container and takes it back to station B. The worker finds a full container of parts at B that has just been produced, removes the production kanban from that container and places it on a rack at B. The worker then places the transport kanban in the full container, which authorises its movement to station C. The production kanaban on the rack at station B authorizes production of a new batch of parts.
The kanban pull system between stations A and B and between station C and D operates the same way as it does between station B and c
The work force to inspect the quality of their work and to deal with minor technical problems with the machinery so that major breakdown do not occur.
Suppliers to hold to the standards of on time delivery, zero defects and other JIT requisites as the company itself.
Reducing the total number of suppliers Selecting and developing vendors/suppliers with proven track records for meeting quality and delivery standards. Establishing long term partnership with suppliers
Selecting the suppliers that are located near the companys manufacturing facility/plant