Network Models Are The Control Technique of The Project. PERT and CPM Are The Network Models Used For Planning, Scheduling and Control of The Project
Network Models Are The Control Technique of The Project. PERT and CPM Are The Network Models Used For Planning, Scheduling and Control of The Project
PERT and CPM are the network models used for planning, scheduling and control of the project.
Objective
The main objectives of network models are to Define the activities to be done in the project. Integrate the activities in a logical time sequence. Dynamic control over the progress of the project plan.
PERT originally was an activity on arc network, in which the activities are represented on the lines . Over time, some people began to use PERT as an activity on node network. For this discussion, we will use the original form of activity on arc.
Identify the specific activities . Determine the proper sequence of the activities. Construct a network diagram. Estimate the time required for each activity. Determine the critical path. Update the PERT chart as the project progresses
Benefits of PERT
PERT is useful because it provides the following information: Expected project completion time. Probability of completion before a specified date. The critical path activities that directly impact the completion time. The activities that have slack time and that can lend resources to critical path activities. Activity start and end dates.
PERT Limitations
The following are some of PERT's weaknesses: The activity time estimates are somewhat subjective and depend on judgement. In cases where there is little experience in performing an activity, the numbers may be only a guess. In other cases, if the person or group performing the activity estimates the time there may be bias in the estimate. Even if the activity times are well-estimated, PERT assumes a beta distribution for these time estimates, but the actual distribution may be different. Even if the beta distribution assumption holds, PERT assumes that the probability distribution of the project completion time is the same as the that of the critical path. Because other paths can become the critical path if their associated activities are delayed, PERT consistently underestimates the expected project completion time. The underestimation of the project completion time due to alternate paths becoming critical is perhaps the most serious of these issues. To overcome this limitation, Monte Carlo simulations can beperformed on the network to eliminate this optimistic bias in the expected project completion time.
Benefit of CPM
CPM provides the following benefits: Provides a graphical view of the project. Predicts the time required to complete the project. Shows which activities are critical to maintaining the schedule and which are not.
CPM models the activities and events of a project as a network. Activities are depicted as nodes on the network and events that signify the beginning or ending of activities are depicted as arcs or lines between the nodes.
A,2
D,3
start
finish
B,4
C,2
Specify the individual activities. Determine the sequence of those activities. Draw a network diagram. Estimate the completion time for each activity. Identify the critical path (longest path through the network) Update the CPM diagram as the project progresses
CPM Limitations
CPM was developed for complex but fairly routine projects with minimal uncertainty in the project completion times. For less routine projects there is more uncertainty in the completion times, and this uncertainty limits the usefulness of the deterministic CPM model. An alternative to CPM is the PERT project planning model, which allows a range of durations to be specified for each activity.