Operations Scheduling
Operations Scheduling
Operations Scheduling
OBJECTIVES
Work Center Defined Typical Scheduling and Control Functions Job-shop Scheduling Examples of Scheduling Rules Shop-floor Control Principles of Work Center Scheduling
What is Scheduling?
Last stage of planning before production occurs
Specifies when labor, equipment, and facilities are
Objectives in Scheduling
Meet customer due dates
Minimize job lateness Minimize response time
Minimize overtime
Maximize machine or labor
system
Components of Scheduling
Scheduling in job shops involves:
Assigning tasks to different machines (or work centers) Deciding about the sequence of processing of the job on different
machines on the basis of some priority rule (called sequencing or prioritization) the other during processing (called routing)
Planning the route of movement of the material from one department to Issuing dispatch lists to the various work centers (called dispatching) Tracking the progress of various jobs scheduled and in case of delays in the
implementation of schedules, revising the schedules and expediting the completion of certain jobs (called expediting)
Work Center
A work center is an area in a business in which
Loading
Loading means assigning tasks to work centers or
machines.
When loading of jobs on machines or work centers is done keeping in view their maximum capacity, it is called finite loading. Infinite loading means while assigning tasks to a
Finite loading
Actually schedules in detail each resource using the setup and run
time required for each order. Forward scheduling Backward scheduling (Example: MRP)
10
system takes an order and then schedules each operation that must be completed forward in time. It can tell the earliest date that an order can be completed.
Backward scheduling starts from some date in future
(possible a due date) and schedules the required operation in reverse sequence. This system tell when an order must be started in order to be done by a specific date.
10
11
High-volume manufacturing
Med-volume manufacturing Low-volume manufacturing
12
13
14
15
16
Do all the jobs get done on time? No, Jobs B, C, and D are going to be late
17
18
20
21
scheduling n jobs to 2 m/c. Objective of Johnsons rule is to minimize the flow time from the beginning of the first job until the finish of the last.
22
23
Jobs A B C D
24
Drop D out, select the next smallest time (Job A), and place it 4th in the job sequence.
Drop A out, select the next smallest time. There is a tie in two stages for two different jobs. In this case, place the job with the smallest time in the first stage as early as possible in the unfilled job sequence. Then place the job with the smallest time in the second stage as late as possible in the unfilled sequence. Job Sequence 1 Job Assigned D 2 B 3 C 4 A
25
26
27
Input/Output Control
Input Work Center Output
planned output
28
29
7. Obtain feedback each day on jobs that are not completed at each work center
8. Match work center input information to what the worker can actually do
30
31
32
Question Bowl
A Work Center may be which of the following? A single machine A group of machines An area where a particular type of work is performed All of the above None of the above
a. b. c. d. e.
33
Question Bowl
When work is assigned to a work center simply based on what is needed over time, we would refer to this as which of the following scheduling systems?
a. c. e.
34
Question Bowl
Typical scheduling and controlling of operations include which of the following functions?
a.
c.
35
Question Bowl
Typical scheduling and controlling of operations include which of the following functions? Determining the job sequences Dispatching Expediting late and critical orders All of the above None of the above
a. b.
c.
d. e.
36
Question Bowl
Which of the following are standard measures of schedule performance used to evaluate priority rules? Meeting due dates Maximizing job flow time Maximizing work-in-process inventory All of the above None of the above
a. b. c.
d.
e.
Answer: a. Meeting due dates (Correct answer can also include minimizing WIP inventory, idle time, and job flow time.)
37
Question Bowl
Which priority rule uses the calculation of the difference between the due date and the current date divided by the number of work days remaining?
a. c. e.
b. SOT d. FCFS
38
Question Bowl
The major functions of a shop-floor control are which of the following?
a.
b. Measuring efficiency c.
Answer: e. All of the above (Correct answer can also include providing quantity by location and actual output data.)
39
Question Bowl
Which of the following are Tools of ShopFloor Control? Daily dispatch lists Scrap reports Rework reports All of the above None of the above
a.
b. c.
d.
e.
Answer: d. All of the above (Correct answer can also include all status and exception reports and input/output control reports.)
40
Question Bowl
Which of the following is a Principle of WorkCenter Scheduling?
a.
Answer: a. There is a direct equivalence between work flow and cash flow (There are nine other principles.)
41