PEM - Types of Contract
PEM - Types of Contract
Types of Contract
Prof. Debopam Roy
What is a contract
Agreement between competent parties enforceable at law Formation of Contract:
Object Proposal / Offer Acceptance Consideration Reciprocal promise
Architect/Engineers (A/E) Prime/General Contractor Sub-contractors Suppliers Banks & Financial Institutions Specialized Service Agencies Labor Regulatory agencies General Public
Surety Bonds
Insurance Contracts
Subcontractor Agreements
Labour Agreements
Nature of Contracts
Owner Architect Contracts and Owner Engineer Contracts Owner Construction Manager Contracts Owner Contractor Contracts
ONE-OF-A-KIND CONTRACTS
Created for a particular project Little about them is standard or traditional
These Conditions of Contract are recommended for engineering and building work of relatively small capital value. However, depending on the type of work and the circumstances, the Conditions may be suitable for contracts of considerably greater value. They are considered most likely to be suitable for fairly simple or repetitive work or work of short duration without the need for specialist sub-contracts. This form may also be suitable for contracts which include, or wholly comprise, contractor-designed civil engineering, building, mechanical and/or electrical works.
Conditions of Contract for Construction, which are recommended for building or engineering works designed by the Employer or by his representative, the Engineer. Under the usual arrangements for this type of contract, the Contractor constructs the works in accordance with a design provided by the Employer. However, the works may include some elements of Contractor-designed civil, mechanical, electrical and/or construction works.
Conditions of Contract for Plant and Design-Build, which are recommended for the provision of electrical and/or mechanical plant, and for the design and execution of building or engineering works. Under the usual arrangements for this type of contract, the Contractor designs and provides, in accordance with the Employers requirements, plant and/or other works; which may include any combination of civil, mechanical, electrical and/or construction works
Conditions of Contract for EPC Turnkey Projects, which are recommended where one entity takes total responsibility for the design and execution of an engineering project. Under the usual arrangements for this type of contract, the entity carries out all the Engineering, Procurement and Construction: providing a fullyequipped facility, ready for operation (at the "turn of the key"). This type of contract is usually negotiated between the parties.
The purpose of these guidelines is to present the commonly used methods of consultant selection, to explain the respective procedures and to combine them all in one compact document, as well as to emphasize and explain FIDIC's policies on the subject of selection.
The terms of the Client Consultant Model Services agreement (The White Book) have been prepared by FIDIC and are recommended for general use for the purposes of pre-investment and feasibility studies, designs and administration of construction and project management, where proposals for such services are invited on an international basis: They are equally adaptable for domestic agreements.
BIDDING DOCUMENTS
Normally begins with an advertisement Identifies the project for which bids are desired The owner Time and place of bid opening Instructions to potential bidders on how to obtain a full set of contract documents Invitation for Bids (IFB) or Request for Proposals (RFP) IFB used when bidders must strictly confirm to drawing and specs. RFP when bidders may propose variations for the project
BIDDING DOCUMENTS
IFB or RFP typically include: A description of the contract work The identity of the owner The place, date, and precise time of the bid opening The penal sum of the required bonds (bid bond, performance bond etc.) A description of the drawings and specs, their cost, and where they may be obtained Rules regarding withdrawal, modifications, late bids etc.
BIDDING DOCUMENTS
Instructions to Bidders Bid Form Bidders complete this document, sign, seal and turn it in Constitutes the offer To constitute a responsive bid, the bid form must be completely filled, signed and sealed in accordance with the IFB or RFP and Instructions to Bidders
BIDDING DOCUMENTS
Bid Forms Contents A definitive statement of the general terms and conditions of the offer The format of the commercial terms applying to the offer Supplementary information that the owner may want to know about the bidder Requirement for public projects Bid security
Those that are either site specific or in some other way apply only to the specific contract
SPECIFICATIONS
The technical requirements for each division of work in the contract will be completely detailed in specifications Conforms to Uniform Construction Index or Masterspec format Should be carefully drafted so that both parties to the contract have a mutual understanding of the precise technical requirements
DRAWINGS
Complement the specifications Should be sufficiently clear to adequately show exactly what is to be built Certain features may be shown in fairly general terms, requiring the contractor to prepare the detailed drawings In fixed-priced bids should be adequately sufficient and clear
Fixed Price
Lump Sum EPC, Turnkey, Design Build
Cost Reimbursable
Cost plus percentage fee (CPPF) Cost plus fixed-fee (CPFF) Cost plus incentive fee (CPIF) (Also called as Target Estimate) Guaranteed Maximum Terms (GMP)
Concessions
Measurement Contract
Contract is Broken Down into a series of bid items, each for a discrete element of work of the project The two parties are not bound by the total value of work. They are bound by each individual rates Payment is based on actual measured quantity of work Most common type is Item Rate
used in preference to the item rate contract for the works where the estimated quantities are uncertain and likely to change considerably.
Mode of payment
Same as item rate
Illegal for Public Works : Where the owner happens to be a public body or government department this form of contract cannot be adopted except during emergencies.
Concession
The contractor undertakes to design, finance , construct , operate and maintain the works for a concession period The contractor recuperates his cost from the collection of charges levied on the beneficiaries who use the work and in some cases annuity payment each year. The facility is returned back to the government and all rights of concessionaire cease to exist Depending on the type of ownership, this may be further subdivided into different formats used in different countries at different times
Concession
BOT BOOT BTO DBFO BOLT ROT LOO Annuity FBOOT BOOST BRT BOO
Concession
Build Operate Transfer Build Own Operate Transfer Build Transfer Operate Design Build Finance Operate Build Operate Lease Transfer Rehabilitate Operate Transfer Lease Own Operate Annuity Finance Build Own Operate Transfer Build Own Operate Subsidies Transfer Build Rent Transfer Build Own Operate
Concession
The cost of construction of the project is ascertained in the manner of a lumpsum or item rate contract The bidder then works out the cost of financing the project and its recovery from the collection of toll or similar method till the cost of construction together with the cost of finance and expected profit is fully recovered The cost of maintenance of the project during the period in question has also to be added to the basic cost Each years income will recover the cumulative investment till the net becomes zero or negative
Concession
The concession period worked out by each bidder will depend upon the cost of construction worked out by each bidder and also the rate of interest considered for financing the project and expected profit. The bidder who submits the cash flow projections seeking the minimum period of concession is generally awarded the contract.
Concession
In some cases the total income predicted over any reasonable concession period does not adequately cover the total cost (EPC + O&M)+ interest + profit The authorities can provide some grants to bridge the gap Known as Viability Gap Funding The authority fixes the period of concession and seeks offers on the basis of grant expected from the employer The bidder expecting the least grant is generally awarded the contract The grant may be in the form of annuity payment or released in a phased manner as mutually agreed by the parties
Concession
In some cases, the bidders do not need grant, and the cumulative income from the years of concession fixed by the authority, far exceeds the total cost In these cases, the concessionaire may quote an upfront negative grant, or a share in revenues to the authority The bidder offering maximum negative grant or share in revenues will be awarded the contract
Concession
Documents
In addition to the usual contract documents cash flow projections giving details of how the contactor intends to generate finance and use it till the recovery of his capital, investment cost and profit during the concession period , forms an integral part of the contract
Concession
The main agreement contains several schedule describing
the project site project facilities site delivery schedule design requirements construction requirements operation and maintenance requirements cash flow projections annuity / grant payment schedule performance security state support agreement substitution agreement hand back requrements
Concession
Pros
public authority is not required to finance the project immediately project is made to generate the funds and be self financing to the extent possible greater autonomy for the contractor more scope for value engineering and innovation quality is assured since poor quality means increased maintenance cost for the contractor
Concession
Cons
greater risk on contractor Contractor needs expertise in not only construction but other areas like finance, O&M as well
Concession
Ideal type of contract for highways and expressways, bridge , tunnels , electricity power generation and supply etc that save the cost of operation or time of travel for which users will pay reasonable charges Not suitable for works that are not likely to generate capital for self financing eg. rural water supply projects, village roads , city roads, etc.
BID BONDS
The bid bonds protects the interests of the owner against the potential loss that it may incur upon the refusal of the lowest bidder to sign the contract Bid bond guarantee The surety guarantees to the obligee that the principal will enter into a contract in the event of an award The principal will furnish the performance bond and insurance policies required by the contract
BID BONDS
Bid bond penal sum: can be expressed in either of the two ways: As either a fixed amount of money or as a percentage of the bid total It can be stated in the form of actual damages suffered, up to a stated limit
PERFORMANCE BONDS
Invoking the performance bond: Requires proof of default Delay may be because of conditions of force majeure In most cases, proof of actual default leads to litigation
Ways to make good the guarantee: (once default is established) Assist principal to remedy default by providing financial assistance Take control of contract and complete project by hiring another contractor or by the principal itself Allow obligee to get it completed and pay the obligee
PERFORMANCE BONDS
How much does surety pay? Penal sum is 100% of the contract price Determination of suretys obligation can be reached in various ways: Surety and obligee agree on a fixed amount (upto the penal sum limit). If actual costs are higher, surety doesnt pay anything, if costs are lower, oblige keeps the difference Another way would be to pay: actual costs incurred any unpaid contract balance + liquidated damages (due under contract), subject to maximum (penal sum)
PERFORMANCE BONDS
Owners misconception about performance bonds Possessing the bond does not imply absolute power over contractor Surety wont act until they believe principal is truly in default. If surety pays up and later it is discovered that there really wasnt any default on part of the principal, the surety cant recover the paid up money from indemnitors To collect eventually on the performance bond guarantee, the obligee must be legally correct on the facts of the default
PERFORMANCE BONDS
Excess early contract payments In cases when the contract is heavily front loaded, the obligee may actually not recover all costs incurred Surety is not liable to pay for such losses and will contest excess early payment Contractor protection of bonding capacity Small contractors wont want the surety to receive complaints about their performance If surety takes control of project (after default), the contractor will have to pay up later for all expenses incurred by surety
Need to understand clearly the purpose and key features of each in order to decide which should be used for a particular business transaction
PURCHASE ORDERS
Intended for transactions that involve the sale of goods by a seller and delivery of those goods to a contractor buyer at the site of a construction project. Should be distinguished from the provision of services or the performance of work involving labour at or on the construction site
PURCHASE ORDERS
Goods or Provision of Services? Whether a particular transaction constitutes the sale of goods or the provision of services? Treat all transactions involving the provision of significant amounts of on-site construction labour as a construction operation requiring the use of a subcontract agreement Transactions that do not involve the provision of significant amounts of labour at the site should be treated as the sale of goods. It should be handled with a purchase order In India, Sale of Goods Act. 1930 applies
PURCHASE ORDERS
Use of purchase orders for certain jobsite services That involve minimal labor like provision and collection of trash containers Purchase order quantity limitations PO can be limited to a one-time transaction or may provide for a continuing supply of goods on an asrequired basis PO for continuing supply may be open ended or limited to stipulated maximum quantity.
PURCHASE ORDERS
Conflicts with sellers sales quotations The fine print on the back of the preprinted vendors sales quotation document conflicts with similar fine print on the back of preprinted purchase order document boilerplates Both vendors and contractors/purchasers try to obtain the most favorable terms Drafter of PO should ensure that the conflicts are avoided Flow-Down Language from Prime Contracts PO may contain explicit flow-down language intended to make all applicable provisions of the prime contract also apply to the PO
SUBCONTRACT AGREEMENTS
A prime contract between an owner and a prime contractor must exist before a construction subcontract can exist Prime contractor decides to lay off or subcontract, a portion of the work to another contractor called a subcontractor Prime contractor still retains the original liability to the owner for the performance of the work. Subcontract work can be directly spelled out in the prime contract or it may be work incidental to the contractor
INSURANCE CONTRACTS
Primary parties Construction Contractor the insured Insurance Company the carrier Additional Parties additional named insured Policies for the construction industry Workers compensation and employers liability policies Public (or third-party) liability policies Builders risk policies Equipment floater policies Miscellaneous policies for special situations and needs