General Procedure of Shipbuilding
General Procedure of Shipbuilding
SUMMARY
1 2 3 FROM CONTRACT TO DELIVERY CLASSIFICATION SOCIETY LARGE CONTAINER VESSEL
1
> From Contract to
Delivery
CONCEPT
Owner Project
Shipyard
CONTRACT
DESIGN
Basic/ Production Purchasing of Material Owner/ Class Approval Hull Hull Outfitting Machinery Outfitting Electric Outfitting Painting Quality Assurance Production Control
Purchasing Dept.
PRODUCTION
DELIVERY
A/S
4
CONCEPT
SHIPBUILDING PROCESS
INITIAL STAGE
Broker
* Owner * Shipyard
Shipyard
Letter of Intent
CONTRACT
INITIAL STAGE
ROLES in SHIPBUILDING
INITIAL STAGE
GENERAL ARRANGEMENT
INITIAL STAGE
75K MIDSHIP
INITIAL STAGE
75K MIDSHIP
10
INITIAL STAGE
DIAGRAM OUTFIT
11
INITIAL STAGE
DIAGRAM OUTFIT
12
INITIAL STAGE
DIAGRAM OUTFIT
13
INITIAL STAGE
DIAGRAM-MACHINERY
14
INITIAL STAGE
DIAGRAM-MACHINERY
15
INITIAL STAGE
DIAGRAM-MACHINERY
16
INITIAL STAGE
ACCOMMODATION PLAN
17
INITIAL STAGE
ACCOMMODATION PLAN
18
INITIAL STAGE
ACCOMMODATION PLAN
19
DESIGN STAGE
20
DESIGN STAGE
SPIRAL DESIGN
21
DESIGN STAGE
SPIRAL DESIGN
Definition of Requirements
Definition of Requirements
Empirical Calculations
Constraints (Design)
Form
Form Selection
Seakeeping
Preliminary Manouvrability Control
Power
Ship Type Type Ship Area/ Weight
Range
Area
Next Design Step
General Arrangement
Weight
Displacement
22
DESIGN STAGE
SPIRAL DESIGN
GENERAL PROCEDURE OF SHIPBUILDING 23
DESIGN STAGE
DESIGN STAGE
Basic Design
Lines, Propeller General Arrangement Trim & Stability Loading, etc. Hull Key Plan : Midship Section Construction Profile & Deck Plan Shell Expansion : Cargo Hold Engine Room/ Fore Body/ Aft Body Stern Frame/ Accommodation
Structure Drawing
Production Drawing : Shop Drawing/ Cutting Plan Hull Design Structural Analysis : Static Analysis Coarse Mesh/ Fine Mesh Fatigue Analysis Sloshing Analysis Bow Impact & Slamming Analysis Vibration Analysis
DESIGN STAGE
Key Design : Piping Diagram, Ventilation Mooring, Anchoring, Steering Life Saving, Fire Fighting Traffic Arrangement : Pipe Piece, Traffic Piece, etc Small Equipment
Production Design
Accommodation Design : Interior, Piping, Outfitting Purchasing Order : Pipe, Valve, Equipment
Key Design
: E/R Piping Diagram, Machinery Arrangement, M/E, Generator, Boiler, Compressor : Pipe Piece, Vent Piece, etc. Small Equipment : Equipment, Valve, etc.
Machinery Outfitting
Production Design
Purchasing Order
25
DESIGN STAGE
Key Design : Automation Electrical System Navigation Equipment : Cable Piece Light Equipment : Switch Board Equipment, Cable, Sensor
Electric Outfitting
Production Design
Purchasing Order
26
PRODUCTION STAGE
Production Control Production Hull, Hull Outfitting, Machinery Outfitting, Paint Quality Assurance
CONDITION
HULL PRODUCTION
Cutting
Sub-Assembly
Assembly
Each Block
P.E
Block Painting
Pre-Outfitting
Grand P.E
Dock Erection
27
PRODUCTION STAGE
OUTFITTING PRODUCTION
Pre-Outfitting In Block
Outfitting In Dock
Outfitting In Quay
PAINTING
Block Painting
Dock Painting
Cosmetic Painting
28
PRODUCTION STAGE
29
PRODUCTION STAGE
30
PRODUCTION STAGE
31
PRODUCTION STAGE
32
PRODUCTION STAGE
33
PRODUCTION STAGE
34
PRODUCTION STAGE
35
PRODUCTION STAGE
36
PRODUCTION STAGE
37
PRODUCTION STAGE
38
PRODUCTION STAGE
39
PRODUCTION STAGE
40
PRODUCTION STAGE
41
Speed Endurance Tank Test Anchoring/ Mooring Rudder, Steering Vibration, Noise Equipment Operation Navigation
Correction If Any
Delivery Sign
Departure
A/S (1 YEAR)
42
43
44
2
> Classification
45
Classification
MAJOR WORK
DRAWING APPROVAL
CERTIFICATION
Intermediate
46
Commercial
Design review
Follow-up in service
T0 Contract
T0 + C Delivery to Owner
RFC Signed
RFC : Request For Certificate
CLASS PROCESS
LPO
CLASS PROCESS
Design review
T0
Contract
LPO core activity : Design review Design review can start before RFC signed ( TAKE CARE - CONTRACT DEFINITION ) Completed when Ad 523 + annexes are examined and signed ( technical green light given to Condition Monitoring CM for Class certificate )
T0 + C
Delivery to Owner
RFC Signed
49
CLASS PROCESS
Design review
LPO core business : Design review against Referential
T0
Contract
Referential : BV Rules / IMO Reg. LPO Interpretations : - allowed with BV Rules ( within general conditions) - not allowed for IMO Reg. Rules : technical interpretations / protect interest of Owner ( final CLIENT )
T0 + C
Delivery to Owner
RFC Signed
High technical knowledge frequently requested as Clients may be less educated / powerfull than BV
Great risk of uncontrolled move from design review activity to Consultancy activity
50
CLASS PROCESS
Follow-up in service
T0 + C
LPO activity : Design review at any time in case of conversion Rules : technical interpretations / protect interest of Owner Technical support of CMs / Station surveys Several LPOs may be concerned Technical documentation processing ( drawings + calculation sheets )
Scrap
Delivery to Owner
or
Change of Class
51
TECHNICAL ASSISTANCE
52
2
MEMBER
Classification
IACS MEMBERS
ABS : American Bureau of Shipping BV : Bureau Veritas CCS : China Classification Society DNV : Det Norske Veritas GL KR LR NK : Germanischer Lloyd : Korean Register of Shipping : Lloyd Register : Nippon Kaiji Kyokai
Classification
IACS MEMBERS
ASSOCIATES
IRS : Indian Register of Shipping
REQUIREMENTS
- Procedural Requirement
Web Site
www.iacs.org.uk
GENERAL PROCEDURE OF SHIPBUILDING 54
3
> Large Container Vessel
55
SUMMARY
1 2
General : Large Container Vessels Bureau Veritas References in Large Container Vessels - Steps of review process - Torsion analysis - Fatigue analysis - Bow flare analysis
3 BV Hull Expertise
BV Lashing Expertise
56
GENERAL
57
GENERAL
58
GENERAL
59
GENERAL
Torsion/Warping stress Fatigue Acceleration forces on lashing Engine power Shaft alignment Parametric roll Slamming/Bow impact
60
BV REFERENCES
HHI
1x5,500 TEU containerships for YANG MING LINE 1x7,800 TEU containership for CMA CGM
DSME
1x6,500 TEU containership for CGM CMA
61
BV REFERENCES
SHI
8 x 5,770 TEU containerships for CMA CGM
CSBC
18x2,200 TEU containerships for WAN HAI LINES, DELMAS, CMA CGM, YANG MING LINE
IMABARI
3x5,500 TEU containerships for COSCO
GENERAL PROCEDURE OF SHIPBUILDING 62
BV REFERENCES
PROJECT MANAGEMENT
333,44 m
42,8 m 27,3 m 14,5 m 24,25 kn 68656 kW
Key elements: Between half December and the end of March the complete structure has been
reviewed. This was only possible in close cooperation with the Shipyard. Several meetings at the shipyard site, exchanging information and calculation results and discussing the findings, have taken place. Two offices of Bureau Veritas, Korea and Paris, have been working around the clock in order to make the deadlines of the shipyard.
63
BV HULL EXPERTISE
Hatch coamings / Superstructures connection Longitudinal Hatch Coamings Bow Flare impact
Cross-deck structures
64
BV HULL EXPERTISE
65
BV HULL EXPERTISE
TORSION ANALYSIS
TORCIS calculation
2 calculations:
wave 60 degree
wave 120 degree
Estimation of warping stress in side shell , upper-deck all along the vessel N/mm2
66
BV HULL EXPERTISE
TORSION ANALYSIS
Fatigue due to warping (L27) 16 years (L28) 17 years (L29) 13 years (L30) 15 years (L31) 17 years
67
BV HULL EXPERTISE
TORSION ANALYSIS
68
BV HULL EXPERTISE
TORSION ANALYSIS
X1 =
s1
s1 + w1(Cfvwv1+Cfhwh1 + Cf )
Quartering sea: Maximize static , vertical bending (50%), horizontal bending (100%) and torsion (100%)
69
BV HULL EXPERTISE
71
BV HULL EXPERTISE
TORSION ANALYSIS
Stress Girders
72
BV HULL EXPERTISE
TORSION ANALYSIS
- Transverse Bulkhead
- Support Bulkhead - Transverse Frame - Bottom Girders
73
BV HULL EXPERTISE
TORSION ANALYSIS
HATCH CORNERS
74
BV HULL EXPERTISE
TORSION ANALYSIS
Support Bulkhead
75
BV HULL EXPERTISE
TORSION ANALYSIS
Stress concentrations
GENERAL PROCEDURE OF SHIPBUILDING 76
BV HULL EXPERTISE
FATIGUE ANALYSIS
BV HULL EXPERTISE
FATIGUE ANALYSIS
78
BV HULL EXPERTISE
FATIGUE ANALYSIS
Hatch Corners
In order to increase fatigue life, compromise between: - sufficient reinforcement - smooth grinding
Hot spot edge of the corner Hatch corner in the midship and fore part
GENERAL PROCEDURE OF SHIPBUILDING 79
BV HULL EXPERTISE
FATIGUE ANALYSIS
Hatch Corners
In order to increase fatigue life, compromise between: - sufficient reinforcement - smooth grinding
80
BV HULL EXPERTISE
Slamming
Maximum impact in forward area: - Buckling in transverse frames - Buckling on side shell plate and stiffeners - Detail connections in forward area
81
BV HULL EXPERTISE
82
83