Substation Construction Project. Project Schedule

This document outlines the Butwal-Kohalpur 132 kV Substation Project being undertaken by CWE-NHE Joint Venture. It provides an introduction to the project organization, work schedule and progress. The project involves upgrading substations in Butwal, Shivpur, Lamahi and Kohalpur, as well as constructing a new substation in Kusum. Major works completed include surveys, soil testing and equipment procurement, while civil works and finalizing equipment drawings are ongoing. The project is expected to be completed by January 2013.

Uploaded by

Bishnu Chapagai
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
50% found this document useful (2 votes)
4K views

Substation Construction Project. Project Schedule

This document outlines the Butwal-Kohalpur 132 kV Substation Project being undertaken by CWE-NHE Joint Venture. It provides an introduction to the project organization, work schedule and progress. The project involves upgrading substations in Butwal, Shivpur, Lamahi and Kohalpur, as well as constructing a new substation in Kusum. Major works completed include surveys, soil testing and equipment procurement, while civil works and finalizing equipment drawings are ongoing. The project is expected to be completed by January 2013.

Uploaded by

Bishnu Chapagai
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPTX, PDF, TXT or read online on Scribd
You are on page 1/ 12

Bishnu Chapagai

January 2, 2012
CWE NHE Joint Venture

Butwal Kohalpur 132 kV Substation Project
Outlines
Introduction
Proposed Project Organization Chart
Work Schedule
Work Progress
Summary and Future works

2
Introduction Salient Features
3
Butwal
(Existing)
Number of 132
kV Line bays -
One
RTU & OLTE
Shivpur
(Existing)
Number of 132
kV Line bays -
Two
RTU & OLTE
Lamahi
(Existing)
Number of 132
kV Line bays -
Two
Shifting of
Reactor and
accessories
RTU & OLTE
Kusum (New)
Number of 132
kV Line bays -
Five
Power
Transformer
132/11, 30 MVA
11 kV One
incoming and
two outgoing
Distribution
Line Materials
RTU & OLTE
Kohalpur
(Existing)
Number of 132
kV Line bays -
One
Capacitor Bay
One
Power
Transformer
132/33 kV, 30
MVA
RTU & OLTE
Introduction Contract Agreement
4
Employer Nepal Electricity Authority, Grid Development, TLSCD
Contractor CWE NHE Joint Venture
Signing Date December 27, 2010
Contract Effective

LC effective in favor of CWE NHE JV (Expected date:
January 9, 2012)
Completion Period 18 months from Contract effective date
Contract Amount

USD 3.7 million + NPR 158 million
Approved Manufacturers
JSB, HEAG and NISSIN (China), AREVA T&D, ABB,
STATCON (India), COMMTEL (Finland)
December 27, 2010
Proposed Project Organization Chart Core Team
5
Project
Manager
Site Manager
(Kusum &
Kohalpur)
Electrical
Supervisor
Civil Supervisor
Assistant/Store
Electrical
Supervisor
Electrical
Overseer
Civil Overseer
Testing/Com.
Team
Accountant
Work Schedule - Highlights
6
ACTIVITIES COMPLETION
Expected date of Contract Effective January 9, 2012
Civil works of existing S/S May, 2012
Civil works of Kusum S/S September, 2012
Equipment Procurement and Delivery July, 2012
Erection and Installation works December, 2012
Testing & Commissioning January, 2013
Request letter for Taking Over Certificate February, 2013
Microsoft Project Based on Contract Effective date
Work Progress - Major
7
Electrical Design/Drawings
SLD and Layout of existing S/S approved . SLD
and Layout of Kusum to be submitted.
Civil Design/Drawings
Foundations and Steel of existing S/S Submitted to
NEA. Control Building for Kusum undergoing
Civil Works
Contractors for four existing S/S selected. Anchor
bolts for foundations ordered
Major Equipment from foreign origin
Transformers and Battery/Charger under
manufacturing. GCB inspection on Jan 3, 2012. PA
with ABB, COMMTEL and AREVA (11 kV VCB
and Panel) in process
Local Materials Distribution Line materials for Kusum ordered
Topographical Survey in Kusum Completed
Soil Exploration works at Kusum Completed
Soil Resistivity Test in all five S/S Completed
Gantry Structures Verification Completed
Equipments Status
Instrument Transformers, DS and LA
HEAG, China
Revised Drawings received after a long
follow up. Still lots of comments
Capacitor Bank NISSIN, China
Clarification on Drawings to be
accepted by NEA
RTU ABB, India
BOM finalized and Price Schedule to be
revised
OLTE COMMTEL, Finland BOM finalized and PA sent to the party
11 kV VCB and CRP SCHNEIDER,
India
Signed/Sealed PA to be received from
manufacturer
Work Progress - Snapshots
8
TOPOGRAPHACALSURVEY AT KUSUM
Work Progress - Snapshots
9
SOIL EXPLORATION WORKS AT KUSUM
Work Progress - Snapshots
10
SOIL RESISTIVITY TEST
Summary and Future works
11
Work Plan/Schedule
Contract Effective date
Progress upto date
Delay in Civil Works in Existing S/S
Site Clearance in Kusum
Civil Contractor Selection for Kusum



Questions and Recommendations..!



THANK YOU


12
CWE NHE Joint Venture
Butwal Kohalpur 132 kV Substation Project