Week 4
Week 4
CPM
CPM: The critical path is that which has
zero slack, since delay on this activity will
mean a delay to the over all project.
Finding the critical path (step 5) is a major
in controlling a project. Activities on the
critical path represent tasks which, if
performed behind schedule, will delay the
whole project. Managers can derive
flexibility by identifying the non-critical
activities and replanning, rescheduling and
reallocating resources such as manpower
and finances within identified boundaries.
Critical Path
Analysis
Critical Path
Analysis
If ES and LS for any activity is
known, then one can calculate
values for the other three times as
follows:
EF = ES + t
LF = LS + t
S = LS - ES or S = LF - EF
Critical Path
Analysis
Critical Path
Analysis