Inspection Of: Piping Systems (In-Service) 570
Inspection Of: Piping Systems (In-Service) 570
( In-Service)
API 570 Code
API
570 Code
Position Measurements
Piping System:
design
conditions .
Inspection of Piping
Systems
Proximity
Transducer
Piping Inspection
During Construction
(fabrication & Installation )
ASME B31.3
( Process Piping )
ASME B31.1
( Power Piping )
In-Service inspection
( On-Stream & Of-Stream )
Considering Risk
Ref. to API 580&581
Considering Consequenc
of failure only
Ref. to API 570 & 574
Limitations
Excluded & Optional
Piping systems
Raw, Intermediate
& finished products
Packages, Heaters,
Boilers, Heat exchangers
Objectives of Inspection
Inspection Objectives
Safe
Operating
Reliability
Efficiency
Saving Cost
Environment
Deadlegs
Types of deterioration
Corrosion Under
Insulation (CUI )
Soil-To-Air
Interfaces (S/A)
Creep cracking
Fatigue Cracking
Environmental
cracking
Areas of Deterioration
Injection Points
The greater of
12 upstream
or 3 times diameter
The lesser of
Second change
in direction
or 25 feet after
first change
Thickness
Measurement
Locations
(TML)
11
Deadlegs
Stagnant Flow
OR No Flow
Areas
High points
Low Points
Bypass
Vents
Drains
12
12 Under ground
13
Exposed to mist
From cooling
Towers / Exposed
To steam vents
14
Down streams of
Pumps,
Compressors
Discharge
Points of flow
Directional
Changes OR
of turbulent flow
15
When to Inspect ??
Inspection Intervals
Jurisdictional
Requirements
Remaining
Life (API 570)
Service
Classes
(API 570)
RBI
Piping Classes
Class I
Flammable/
Auto refrigerate
& Rapidly
Vaporized
Class II
Class III
Piping over or
adjacent to
water/public
17
On-site
Strong Acids
& caustics
On-site
Hydrocarbons
Slowly
vaporize
H2, FG & NG
Class III
Off-Site
Acids &
Caustics &
Remote Areas
Distillate product
Lines from & to
Storage & Loading
On-site
Hydrocarbons
Slowly
Vaporize & operating
Below Flash Point
Thickness
Measurements
Off-Stream
Inspection
Supplemental
Inspection
Vibration
Measurement
External VT
Thickness
Measurements
Material
Verification &
traceability
Supplemental
Inspection
Acoustic
Emission &
Leak Detection
Thermography &
Temp. Measurements
RT / UT for Weld / BM
Inspection
22
Notes
For more information about the detailed inspection for
piping systems components & deteriorations
mechanisms, Ref. to API RP 574 & API RP 579.
Pressure tests not normally conducted as part of a
routine inspection, But when conducted this will be
after completing a repair, alteration OR rerating.
23
Recommended Max.
Intervals For Inspection
Class I
Thickness Measurements
5 Years Max.
Visual Inspection
5 Years Max.
Recommended Max.
Intervals For
Inspection
Class II
Thickness Measurements
10 Years Max.
Visual Inspection
5 Years Max.
Recommended Max.
Intervals For
Inspection
Class III
Thickness Measurements
Visual Inspection
10 Years Max.
10 Years Max.
In-service Degradations .
API
Calculations For
Remaining Life
Calculation (RL)
Corrosion Rate (CR)
Determination
MAWP Determination
(mm) =
STCR
(mm) =
RL (years) =
- t
initial
actual
Time (years) between them
previous actual
Time (years) between them
actual required
Corrosion Rate (mm)
Repairs
Welding Repairs
( On-Stream)
Temporary Repairs
Non-welding Repairs
(On-Stream)
Permanent Repairs
Insert Patches
( Flush Patches )
Split coupling /
Plate patch
(Fillet Welded)
30
Non-welding Repairs
(On-Stream)
Bolted Leak Clamps
Leak Sealing
Leak Dissipating
Devices
Rerating
Rerating
Derating (Decrease Rating)
32
Soil Resistivity
(Corrosivity measurement each 5 Yrs)
Internal Inspection
External Inspection
(Excavation & Thickness Measurements)
Leak Testing
Excavation For
Thickness measurement
Without C.P
Frequency
Leak Test For C.P Lines
(as alternation)