Project Cost Management: Chapter 7 of PMBOK®
Project Cost Management: Chapter 7 of PMBOK®
Management
Chapter 7 of PMBOK
budget
Concerned with cost of resources needed to
complete activities; consider effect of project
decisions on cost of using product life-cycle
costing
Most prospective financial impact of using the
product is outside the project scope
Consider information needs of stakeholders,
controllable and uncontrollable costs (budget
separately for reward and recognition systems)
work
Having historical records is key to improving estimates
Costs (schedule, scope, resources) should be managed to
estimates
A cost (schedule, scope, baseline) should be kept and not
changed
Plans should be revised as necessary during completion
of work
Corrective action should be taken when cost problems
(schedule, scope and resources) occur.
project.
How to manage project to the cost baseline
and cost variances.
Part of project management plan.
How the estimate should be stated.
Reporting format.
dollars
project.
How to manage project to the cost baseline
and cost variances.
Part of project management plan.
How the estimate should be stated.
Reporting format.
Cost Estimating
Cost Estimating Inputs:
Enterprise Environmental Factors
1) Marketplace Conditions
2) Commercial Database
. Organizational Process Assets.
Policies and Procedures
Cost Estimating Templates
Historical Information
Lessons Learned
Cost Estimating
Cost Estimating Inputs:
Enterprise Environmental Factors
1) Marketplace Conditions
2) Commercial Database
. Organizational Process Assets.
Policies and Procedures
Cost Estimating Templates
Historical Information
Lessons Learned
Cost Estimating(Inputs)
Project Scope Statement
WBS
WBS Dictionary
Project Management Plan.
Reliable when previous projects are similar and individuals have expertise form of expert
judgment
Parametric
Reliable when historical information is accurate, parameters are quantifiable, and model is
scalable
For example, a model might provide an estimate of $50 per line of code for a s/w
1)
2)
3)
4)
unknowns).
Can be aggregated across several activities.
Buffer activity in CCM.
Supporting Detail
Description of scope (reference to the WBS)
Documentation how estimate was developed
Indication of range of possible results
Assumptions
Cost Management Plan how cost variances will be managed
Cost Risk: associated to seller for Fixed Price; associated to
Supporting Detail
Description of scope (reference to the WBS)
Documentation how estimate was developed
Indication of range of possible results
Assumptions
Cost Management Plan how cost variances will be managed
Cost Risk: associated to seller for Fixed Price; associated to
Cost Baseline
Performance Reports meet, exceed budget
50/50 Rule task is considered 50% complete when it begins and gets credit
for remainder 50% only when completed
20/80 Rule - task is considered 20% complete when it begins and gets credit
for remainder 80% only when completed
0/100 Rule task only credited when fully completed
Change Requests
Cost Management Plan
Cost Change Control System defines the procedures by which the cost
Rate of Performance
Rate of performance (RP) is the ratio of actual work
EVM
PV = FV
(1 + r) N
FV = Future Value
R = Interest Rate
N = Number of time periods