A Presentation On: By: Abhay Avhad (121520001) Komal Thabaj (121520013)
A Presentation On: By: Abhay Avhad (121520001) Komal Thabaj (121520013)
CPM
By:
Abhay Avhad (121520001)
Komal Thabaj (121520013)
Introduction
Any project involves planning, scheduling and controlling a
times for each activity are worked out by applying forward and
backward pass techniques, critical path is identified, along with
the float for the non-critical paths.
Controlling: Controlling refers to analyzing and evaluating the
Network?
A network is the diagrammatic representation of a work plan
Components of CPM
Network
Activity: An activity represents
an action and consumption
of resources (time, money, energy) required to complete a
portion of a project. Activity is represented by an arrow.
Dummy
Activity
Network Representation
Two systems of network representation
Activity-on-node (AON):
Nodes represent activities, and arrows show precedence
relationships.
Activity-on-arrow (AOA):
Activity-on-node (AON)
In this system activities are represented on the nodes, and
Activity-on-arrow (AOA)
In this system an activity is graphically represented by an
B
Procure aggregate
& sand
2
D
Concrete slab
4
1
Network Analysis
Earliest Event Time
(TE): It is the earliest possible
occurrence of an event i.e. the earliest possible time when all
activities leading to an event will be completed.
Latest Event Time (Tl):It is defined as the latest possible
occurrence of an event
without delaying the project
completion time i.e. it is the latest time when all activities
leading to an event may be completed without delaying the
project completion time.
Forward Pass
For calculating the earliest event times (TE), computations
are made in a forward direction (left to right). This process is
called the 'forward pass'.
2
1
1
3
Backward Pass
For calculating the latest event times (Tl), computations are
made in a backward direction (right to left). This process is
called the 'backward pass'.
2
3
1
1
3
2
15
8
0
15
8
13
15
Backward pass
6
15
8
0
13
0
3
15
15
8
0
13
0
3
15
Critical Path
Analysis
joining the
critical activities
The path
in a network is
called the Critical Path. It is the longest path in the
network and the time along this path determines the
completion time of the project.
The critical path is distinctly shown in the network by double or
bold lines or in red colour.
Further, any delay in completing the critical activities will
increase the project duration.
The activity, which does not lie on the critical path, is
called non-critical activity. These non-critical activities
may have some slack time.
Assignmen
t
THANK
YOU