Presentation About Lifting
Presentation About Lifting
Responsibilities of Lifting
Engineer and Safe Lifting
REGARDS:
ENGR SYED IMRAN
SHAH
Introduction
The role of the lifting team, which includes the lifting Engineer, crane operator, rigger and signalman, is
crucial to ensure safe lifting activities at workplaces. Many of past accidents had shown that proper
planning, co-ordination and supervision of the lifting work could have prevented the accidents and the
needless loss of lives. In particular,
the role of the lifting Engineer & supervisor is key especially given the collaborative nature of the
work and the importance of ensuring that The various parties are trained and competent, and that
they carry out their roles safely and effectively. this presentation will not only provides you the
roles and responsibilities of lifting Engineer & Supervisor but also information on common hazards
associated with lifting, Lifting Plans, Risk Assessment (RA), Permit-to-Work (PTW) System and
Safe Work Procedures (SWP),
Developing detailed lifting and load out plans: cranes selection and working circumstances, rigging study.
Lifting lugs and lifting beams design and other steel structure design.
Calculating GBP, C.O.G. and weight theoretically and physically using synchronous hydraulic jacks systems
Attending heavy lifting meetings both internally and externally with direct client interface.
Inspection of cranes and lifting equipment as they are delivered to site, including inspection of certificates,
maintenance records etc.
ensuring that the ground conditions are safe for any lifting operation to be performed by mobile cranes;
if unsafe conditions are reported to him, to take suitable measures to rectify the conditions so that the lifting
operation can be conducted safely.
defective or damaged lifting gears such as slings, hooks, inserts, eyes, shackles;
Hazard Identification
Risk Evaluation
Risk Control
Permit-to-Work (PTW) System is a system to manage and control certain types of hazardous work including
lifting operations. The contractors supervisor coordinating the lifting operation is to apply for the PTW to
carry out the lifting operation. In the application for PTW, he should state the scope and conditions in which
the lifting operation is to be carried out. An independent inspection is then conducted on-site to verify that
appropriate control measures have been taken to mitigate any foreseeable risks. After confirming that the
measures have indeed been taken, the application would then be approved by an authorized person.
etc
Lifting gears must also be inspected to ensure that they are free of any faults or defects before any lifting operation can
begin.
Lifting supervisor must not allow the lifting operation to be carried out if any defects are spotted during the pre-use
checks by the crane operator until all the faults of the cranes are fully rectified. Similarly, lifting gears must not be used
if defects are spotted and reported by the riggers.
When there is a change in equipment configuration, such as alteration of the boom length or tower
crane height; or
Mode of use
over a bridge.
ASME A120.1 Safety Requirements for Powered Platforms for Building Maintenance
ASME B30.2 Overhead and Gantry Cranes (Top Running Bridge, Single or Multiple Girder, Top