Generators and Generator System Design
Generators and Generator System Design
Learning Objectives:
1.The audience will understand the applicable code requirements
including NFPA 70: National Electrical Code and NFPA 110:
Standard for Emergency and Standby Power Systems
2.Attendees will learn the criteria for selecting the appropriate
generator or generators for the building type and/or application
3.Viewers will understand the criteria for designing the generator
system, and know the differences between prime rated versus
standby rated engines (U.S. EPA standards)
4.Viewers will learn the criteria for commissioning generators and
the electrical systems they support.
Presenters:
Robert R. Jones Jr., PE, LEED AP,
JBA Consulting Engineers,
Las Vegas, Nev.
EPSS
EPS
LOAD TERMINALS
Generator System
NEC Article 700.12(B)(2): 2-hour minimum, Class 2.
NFPA 20 Chapter 9.6.2.3: 8-hour minimum, Class 8.
AIA Guidelines for Design and Construction of Healthcare
Facilities (Joint Commission requirement): 24 hours
minimum, Class 24.
Level 2
Required where EPSS failure is less critical to human life
and safety.
NEC Article 701: Legally Required Standby.
Research Codes
System Capacity
and Use
2
1
Starting kVA
What is the biggest starting kVA block (i.e. a
chiller system)
Special considerations
High harmonic content
Intermittent starting
Generator Ratings
Standby Power:
Maximum output is available for non-programmed power
outages.
Average demand during outages should not exceed
continuous rating of generator.
Typical usage of 200 hrs/yr; max expected usage of 500
hrs/yr.
Prime Power:
De-rated capacity, typically 10% reduction from standby
power rating.
Maximum output available for varying loads for all outages.
Average demand should not exceed continuous rating.
Continuous Power
Maximum output available at all times.
De-rated capacity, typically a 15% reduction from prime
power ratings.
Generator De-Rating
A prime generator is essentially a standby generator de-rated plus
additional accessories. The same generator de-rated again is a
continuous duty.
2000 kW standby = 1825 kW prime = 1600 kW continuous
But with prime and continuous ratings, everything is bigger:
generators, space to accommodate, air intake requirements, fuel
consumption, but with less capacity.
Warranty Issues
What does all of this have to do with
my warranty?
Standard warranty for generators are
defined by run hours and length of time,
and typically include the rating of the
generator.
Warranties generally do not include:
Use of standby generators in prime
applications
Use of blended fuels such as a natural
gas/diesel mixture
Excessive overloading of the generator.
Tier 4
Researched
Codes
System
Capacity
and Use
Select a
System
Types of Generators
Portable
Stationary Standby
Diesel
Liquid Propane
Natural Gas
Dual Fuel.
Fuel Considerations
On-site fuel storage NEC 700.12(B)(3)
Dual Fuel (or Bi-fuel)
Can provide an extended runtime.
Usually an aftermarket retrofit to a diesel generator. Although,
some manufacturers do have a factory assembled and tested
bi-fuel systems.
Typically achieves a 40%/60% split.
Fuel Polisher
Diesel fuel will foul when stored more than 3 to 6 months
without conditioning or detergent additives.
This presents an issue for large on-site fuel storage systems.
Location
Indoor
EPS shall be located in a dedicated room with 2hour fire resistance rating (NFPA 110 Chapter 7.2.1)
EPSS equipment may be located in EPS room
(NFPA 110 Chapter 7.2.1.2)
Outdoor
Requires weatherproof enclosure (NFPA 110
Chapter 7.2.2.1)
EPSS equipment may be located within the EPS
enclosure (NFPA 110 Chapter 7.2.2.3)
Redundancy
Data centers, hospitals, large-scale
hospitality resorts, municipal command
centers, etc.
N+1, 2N
Multiple priorities
Real-time demand load management
Generator Ratings.
Examine the system voltage. Is the primary
distribution routed at low voltage (600 V or
less) or medium voltage (more than 600 V,
but less than 38 kV)?
208 V, 3-Phase System; 900 kW/1125 kVA
240 V, 1-Phase System; 600 kW/750 kVA
480 V, 3-Phase System; 2000 kW/2500 kVA
13 kV, 3-Phase System
Generator Accessories
Typical Package Generator
Jacket Heater
Battery Charger
Daytank Controls
Other Considerations
Remote Radiator
Radiator Fan
Aftercooler Water Pump
Motorized Dampers
Remote Fuel Pumps
Researched
Codes
System
Capacity and
Use
Select a
System
Installation and
Commissioning
EPSS Commissioning
Generator
Remote Alarm Annunciation
Fuel System Performance
Parallel Switchgear (if applicable)
Load Shedding
Switchgear Features
Generator Assembly
Sound Testing
Sound criteria requirements at certain locations
Air Performance
Sufficient air to the generator engines
Emissions too close to an intake
Air emissions testing
Generator Accessories
Battery charger goes back on with generator power
Jacket heater turns off when unit is running
Alarm Annunciation
Alarms annunciate at
Unit Mounted
Controller (CV)
Alarms Annunciate at
Remote Annunciator
(RA)
Doesnt address
parallel system
alarms!
Per NFPA 110 and
NFPA 99
Alarm
(a) Overcrank
CV
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
KEY:
CV Control panel-mtd. visual indication
RA Remote Audible
S Shutdown of EPS
X Required
S
X
RA
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
X
Alarm Annunciation
Most alarms can be simulated at the
generator, and verified at the annunciator.
Must include audible and visual annunciation
at remote location.
Recommend adding parallel switchgear
(EPSS) alarms where used.
Other codes supplement this too, such as
high-rise requirements in NFPA 101.
BRANCH
ATS-CHCEP
ATS-FP
ATS-CR1
ATS-CR2
ATS-LS1
ATS-EQ2
ATS-XRAY
ATS-EQ1
ATS-EQHCEPA
ATS-EQHCEPB
ATS-EQHCEPC
ATS-N1
Critical
Fire Pump
Critical
Critical
Life Safety
Equipment
Equipment
Equipment
Equipment
Equipment
Equipment
Non-Essential
480
480
480
480
480
480
480
480
480
480
480
480
Total (KVA)
26.7
75
283.5
129
220.6
119.2
854
3000
Priority 200
SUB
L.S.
T.I. LOAD
No.
201
Y
Y
202
Y
Y
203
Y
Y
204
Y
Y
213
205
Y
Y
1082
206
Y
Y
143.8
Total (KVA) 1439
Total (KW @ 0.9 P.F.) 1295
Mode: Bus Optimization Off / Generator Demand Off (with Amp Generator)
Operation: Generators will load each priority level as a block. The quantity of priority
Blocks connected is the same as the priority block connected. If a generator fails,
the block associated with that generator will shed.
Scenario 1: Startup. Turn off Normal power, system should call for start. Priority
1 loads will transfer within 10 seconds. Priority 2 will transfer after their associated
time delays.
Scenario 2: Second Generator Failure Priority two Block Loads shed. Turn
Second Gen back on and all Priority 2 loads add in one block.
Scenario 3: Gen 1,2 Operating. System Bus overload of 105 % over two
generators simulated by a 4-20ma generator. (3000 kW * 1.05 = 3150 kW); Priority
2 loads should shed in descending priority & sub priority order.
Bus under-frequency
(Sheds loads and locks out!)
Learning Summary
Researched
Codes
NEC
NFPA 110, 99
IBC
System
Capacity and
Use
Demand and
Calculated Loads
Tier Ratings
Select a System
Fuel Source
Location
Parallel?
Redundancy
Installation and
Commissioning
Load Bank
Annunciation
System Testing
Code References
Presenters:
Robert R. Jones Jr., PE, LEED AP,
JBA Consulting Engineers,
Las Vegas, Nev.