Project Selection Models: Nadeem Kureshi
Project Selection Models: Nadeem Kureshi
Nadeem Kureshi
Project Selection
Decision Models
Realism
Capability
Flexibility
Ease of use
Cost
Easy computerization
Nonnumeric Models
Q-Sort Method
Numeric Models:
Profit/Profitability
Models
Present Value
The Present value or present worth method of evaluating
projects is a widely used technique. The Present Value
represents an amount of money at time zero
representing the discounted cash flows for the project.
PV
T=0
In this context, the discount rate equals the minimum rate of return for
the investment
Where:
NPV = Present Value (Cash Benefits) - Present Value (Cash Costs)
Present Value
Example
Initial Investment:
$100,000
Project Life:
10 years
Salvage Value:
$ 20,000
Annual Receipts:
$ 40,000
Annual Disbursements:
$ 22,000
Annual Discount Rate:
12%, 18%
What is the net present value for this project?
Is the project an acceptable investment?
Annual Receipts
$ 226,000
Salvage Value
6,440
Annual Disbursements
-$124,000
-$100,000
$ 8,140
Future Value
The future value method evaluates a project
based upon the basis of how much money will be
accumulated at some future point in time. This
is just the reverse of the present value concept.
FV
T=0
Annual Receipts
Salvage Value
$ 20,000
Initial Investment
$20,000(year 10)
Annual Disbursements
-$310,600
PV/FV
No theoretical difference if project
is evaluated in present or future
value
PV of $ 25,282
$25,282(P/F, 12%, 10)
$ 8,140
FV of $ 8,140
$8,140(F/P, 12%, 10)$ 25,280
Annual Value
Benefits:
125
Investment:
Costs:
$10,000
Salvage
-$ 6,508
-$1,383
Since this is less than zero, the project is expected to earn less than the
acceptable rate of 10%, therefore the project should be rejected.
Benefit/Cost Ratio
Project A
Project B
Present value cash inflows
$500,000
$100,000
Present value cash outflows
$300,000
$ 50,000
Net Present Value
$200,000
$ 50,000
Benefit/Cost Ratio
1.67
2.0
Payback Period
One of the most common evaluation criteria used.
Simply the number of years required for the cash income from
a project to return the initial cash investment.
The investment decision criteria for this technique suggests
that if the calculated payback period is less than some
maximum value acceptable to the company, the proposal is
accepted.
Example illustrates five investment proposals having identical
capital investment requirements but differing expected annual
cash flows and lives.
Payback Period
Example
Calculation of the payback period for a given investment proposal.
a) Prepare End of Year Cumulative Net Cash Flows
b) Find the First Non-Negative Year
c) Calculate How Much of that year is required to cover the previous
period negative balance
d) Add up Previous Negative Cash Flow Years
Initial
Investment
Alternative A
(45,000) 10,500
11,500
10
c)
0.78 = 10,500/13,500
d)
3 + 0.78
Example:
Calculate the payback period for the following investment proposal
Initial
Investment
Alternative A
(120)
10
10
50
10
50
50
50
50
50
50
100
150
200
250
300
50
1.00
4.00
Example:
Calculate the payback period for the following investment proposal
Initial
Investment
Alternative A
(120)
10
10
50
10
50
50
50
50
50
50
100
150
200
250
300
50
1.00
4.00
Example:
Calculate the payback period for the following investment proposal
Initial
Investment
Alternative A
(120)
10
10
50
10
50
50
50
50
50
50
100
150
200
250
300
50
1.00
4.00
Example:
Calculate the payback period for the following investment proposal
Initial
Investment
Alternative A
(250)
86
50
77
10
41
70
127
24
40
124
252
276
282
322
52
0.73
3.73
Example:
Calculate the payback period for the following investment proposal
Initial
Investment
Alternative A
(250)
86
50
77
10
41
70
127
24
40
124
252
276
282
322
52
0.73
3.73
Example:
Calculate the payback period for the following investment proposal
Initial
Investment
Alternative A
(250)
86
50
77
10
41
70
127
24
40
124
252
276
282
322
52
0.73
3.73
Example
Given an investment project having the following annual cash flows; find the
IRR.
Year
Cash Flow
0
(30.0)
1
(1.0)
2
5.0
3
5.5
4
4.0
17.0
20.0
20.0
(2.0)
10.0
Solution:
Step 1. Pick an interest rate and solve for the NPV. Try r =15%
NPV = -30(1.0) -1(P/F,1,15%) + 5(P/F,2,15) + 5.5(P/F,3,15) + 4(P/F,4,15)
+ 17(P/F,5,15) + 20(P/F,6,15) + 20(P/F,7,15) - 2(P/F,8,15) + 10(P/F,9,15)
= + $5.62
Since the NPV>0, 15% is not the IRR. It now becomes necessary to select a
higher interest rate in order to reduce the NPV value.
Step 2. If r =20% is used, the NPV = - $ 1.66 and therefore this rate is too high.
Step 3. By interpolation the correct value for the IRR is determined to be r
=18.7%
Analysis
The acceptance or rejection of a project based on the IRR
criterion is made by comparing the calculated rate with
the required rate of return, or cutoff rate established by
the firm. If the IRR exceeds the required rate the project
should be accepted; if not, it should be rejected.
If the required rate of return is the return investors
expect the organization to earn on new projects, then
accepting a project with an IRR greater than the required
rate should result in an increase of the firms value.
Analysis
There are several reasons for the widespread popularity
of the IRR as an evaluation criterion:
Analysis
Selecting a Discount
Rate
There is nothing so disastrous as a rational investment
policy in an irrational world John Maynard Keynes
We have discussed the time value of money and
illustrated several examples of its use. In all cases an
interest rate or discount rate is used to bring the
future cash flows to the present (NPV - Net Present
Value)
The selection of the appropriate discount rate has been
the source of considerable debate and much
disagreement. In most companies, the selection of the
discount rate is determined by the accounting
department or the board of directors and the engineer
just uses the number provided to him, but short of just
being provided with a rate, what is the correct or
appropriate rate to use?
Example
What is the impact of the discount rate on the investment?
Cash
Flow Yr
0
Cash
Flow Yr
1
Cash
Flow Yr
2
Cash
Flow Yr
3
Cash
Flow Yr
4
Cash
Flow Yr
5
-500
-500
+750
+600
+800
+1000
IRR
ROR
NPV
2%
1,941
6%
1,581
10%
1,283
15%
981
20%
739
47.82%
If the value of the project drops, it may fail the selection process.
If the value increases, the investor gets a higher payoff.
Unweighted 01 Factor
Model
X marks in 0-1
scoring model are
replaced by
numbers, from a 5
point scale.
Si SijWj
j 1
where
Si the total score of the ith project,
Sij the score of the ith project on the jth criterion, and
Wj the weight of the jth criterion.
j 1
k 1
Si SijWj Cik
Final Thought
ACTIVITY