0% found this document useful (0 votes)
845 views

Modeling Drop Structures in HEC-RAS

The document discusses two methods for modeling drop structures in HEC-RAS version 3.1: 1) modeling as an inline weir structure, using the standard weir equation, or 2) modeling using cross-sections placed where the water surface and velocity change rapidly through the drop structure. It provides examples comparing the results of each method using data from a physical model study. Key aspects of properly placing cross-sections and accounting for submergence, baffles, and other features are also covered.

Uploaded by

relu
Copyright
© © All Rights Reserved
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
845 views

Modeling Drop Structures in HEC-RAS

The document discusses two methods for modeling drop structures in HEC-RAS version 3.1: 1) modeling as an inline weir structure, using the standard weir equation, or 2) modeling using cross-sections placed where the water surface and velocity change rapidly through the drop structure. It provides examples comparing the results of each method using data from a physical model study. Key aspects of properly placing cross-sections and accounting for submergence, baffles, and other features are also covered.

Uploaded by

relu
Copyright
© © All Rights Reserved
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 29

Modeling

Drop
Structures in
HEC-RAS
Version 3.1

Modeling Drop Structures


Overview
Modeling a Drop Structure as an
Inline Structure (Weir).
Modeling a drop structure with
cross-sections through the drop.
Example using Lab Data.

March 2003

HEC-RAS Version 3.1

Slide 2 of 27

Overview

What is a Drop Structure?

March 2003

HEC-RAS Version 3.1

Slide 3 of 27

Overview

Why do we use Drop Structures ?

March 2003

HEC-RAS Version 3.1

Slide 4 of 27

Overview

March 2003

HEC-RAS Version 3.1

Slide 5 of 27

Overview

March 2003

HEC-RAS Version 3.1

Slide 6 of 27

Overview

March 2003

HEC-RAS Version 3.1

Slide 7 of 27

Overview

March 2003

HEC-RAS Version 3.1

Slide 8 of 27

Overview

March 2003

HEC-RAS Version 3.1

Slide 9 of 27

Overview

March 2003

HEC-RAS Version 3.1

Slide 10 of 27

Components of Drop Structure


Control Section
Energy Dissipation Section
Adjacent Protection

3 or
4
subcritical

yb
yc

yb = 0.715 yc

yb

Rectangular
channel

subcritical

stilling basin:used
to dissipate energy

March 2003

HEC-RAS Version 3.1

Slide 11 of 27

Overview

How can we Model a Drop Structure


with HEC-RAS ?
Inline

Weir Option

Using

Cross Sections

March 2003

HEC-RAS Version 3.1

Slide 12 of 27

Overview

Which is more appropriate?


Inline

Weir Option - probably better if


just interested in elevations upstream
and downstream of structure.

Using

Cross Sections - better if interested


in profile through the structure.

March 2003

HEC-RAS Version 3.1

Slide 13 of 27

Cross-Section Locations
When placing cross-sections near
and through a drop structure, they
need to be placed where the water
surface and velocity are changing
rapidly (this applies when using an
inline weir also).

March 2003

HEC-RAS Version 3.1

Slide 14 of 27

Modeling a Drop Structure


as an Inline Weir

The standard weir equation is used:


Q = CLH3/2
where:

C = 2.6 - 4.0 (dependent on

shape)
L = Length of weir
H = Upstream Energy Head
March 2003

HEC-RAS Version 3.1

Slide 15 of 27

Inline Weir - Submergence


Submergenc
e is defined
as H2/H1

March 2003

HEC-RAS Version 3.1

Slide 16 of 27

Inline Weir - Submergence

March 2003

HEC-RAS Version 3.1

Slide 17 of 27

Inline Weir - Cross Section


Layout
6

Inline Weir
Structure
5
4

Cross Sections
1

3
2

Model the
floor blocks
as blocked
obstructions.
March 2003

HEC-RAS Version 3.1

Slide 18 of 27

Modeling a Drop Structure


as an Inline Structure
Under the
Geometric
Dataclick on
Inline
Structure

March 2003

HEC-RAS Version 3.1

Slide 19 of 27

Modeling a Drop Structure


as an Inline Structure
A series of windows allow for entry of weir characteristics

March 2003

HEC-RAS Version 3.1

Slide 20 of 27

Modeling a Drop Structure


with Cross Sections
Cross Sections

Model the
floor blocks
as blocked
obstructions.
March 2003

HEC-RAS Version 3.1

Slide 21 of 27

Cross Section Layout for Ogee


Shapes Drop Structure
Cross Sections

March 2003

HEC-RAS Version 3.1

Slide 22 of 27

Modeling Baffles in the


Stilling Basin
Increase
n values
at baffle
blocks to
account
for
increased
roughnes
s

March 2003

HEC-RAS Version 3.1

Slide 23 of 27

Example Using Lab Data

WES Physical Model Study (WES,


1994)

March 2003

HEC-RAS Version 3.1

Slide 24 of 27

Example - Modeled as a
Weir

Cross Sections
Inline Weir
March 2003

HEC-RAS Version 3.1

Slide 25 of 27

Example - Modeled with Cross


Sections Only

Cross Sections
March 2003

HEC-RAS Version 3.1

Slide 26 of 27

Example - Comparison of
Two Methods

March 2003

HEC-RAS Version 3.1

Slide 27 of 27

Example - Comparison
Zoomed In

March 2003

HEC-RAS Version 3.1

Slide 28 of 27

The End

You might also like