Lva1 App6892
Lva1 App6892
5 June 2014
By : Ernst de Villiers
Layout of Presentation
Problem Statement
Construction of the Voltage Regulator
Basic theory of Voltage Regulation
Implementation of Voltage Regulators
Voltage Regulators Vs. Load Tap Changers
Case Study Commissioning
Problem Statement
Problem Statement
To minimize the time and expense of serving the new load, the length
of the feeder is usually extended. Hence, in most cases, the feeder
develops an unacceptable voltage drop as shown in the figure below.
Operational Theory
Transformer Model
Ideal Transformer
Operation Theory
Step-down Trfr
Step-up Trfr
8
Step-down Trfr
Step-up Trfr
11
12/12/16
12
13
14
Bushing Construction
15
Bushings
The preferred bushing terminals are smooth, hot-dip tinned, copper cylindrical
stems provided with bimetallic clamps that are suitable for accepting aluminum
or copper conductors of 6 mm to 15 mm diameter.
16
17
22 kV Application
MCOV:
> 2.5 kV
>5 kV
<10.5 kV
<20 kV
10 kA
10 kA
Creepage
31mm/kV
31mm/kV
18
19
Reactors
Core type is designed that the two coils are interlaced resulting in minimal
impedance-to-load current flow and therefore minimal voltage drop.
20
21
22
Drag-Hand
The Yellow tap indicating needle drags minimum and maximum needles.
23
Type of Regulators
Two types of regulators:
Type A
Type B step-voltage regulators are predominately used for distribution
lines outside of the substation and lateral circuits.
How does a Voltage Regulator work?
24
Type A Regulator
The tapped series winding is located on the load side of the shunt
winding, and by adjusting those taps the output load voltage
changes.
25
Type B Regulator
The tapped series winding is located on the source side of the
shunt (excitation) winding, and by adjusting those taps the output
load voltage changes.
26
Regulator Ratio
Typical maximum boosts and bucks are 10%.
What will aR and nt=N2/N1 be in the maximum boost and buck positions?
27
Since % voltage is Per Unit voltage x 100, the Per Unit voltage
change per step is
28
The ratio (N2/N1)effective is then given by the pu voltage change per step
times the number of steps (Tap):
Note that if Tap is 0, then the effective turns ratio is 0. In this case,
there is no boost, and VL=VS.
29
30
12/12/16
31
How is it implemented?
Open-Delta
3 Voltage Regulators
2 Voltage Regulators
Cost effective
32
Connection Configuration
33
Configuration
Open-Delta connection
Closed-Delta connection
34
35
Regulator Tests
The AVR shall have been type tested in accordance with, and found to
comply with, the following requirements of ANSI/IEEE C57.15.
Impulse test;
Temperature rise;
Short-circuit tests KA rating-3 seconds amps;
Insulation testing Megger
36
Where to Apply
37
Where to Apply
38
Where to Apply
39
2.
3.
4.
5.
6.
7.
40
2.
3.
4.
5.
6.
7.
41
42
Transformer + LTC
43
44
45
Cost Comparison
46
11kV Pine conductor line that interconnects with Prospect - Gately line
via a normally open point situated at structure PRO-KBH-79.
Approximately 2078 number of customers 83km line.
This feeder is at its voltage limit due to the normal growth from supply
upgrades and new developments in the area.
The acceptable voltage limit for this feeder is 95% of nominal.
Currently, the minimum voltage is 95%, hence the initiation of this
project.
47
48
Regulator Characteristics
49
Thank you
Open for Discussion