1-1 Mcgraw-Hill/Irwin ©2009 The Mcgraw-Hill Companies, All Rights Reserved
1-1 Mcgraw-Hill/Irwin ©2009 The Mcgraw-Hill Companies, All Rights Reserved
Chapter 3
Project Management
1-2
3
OBJECTIVES
1-3
4
Project Management
Defined
Gantt Chart
Vertical
VerticalAxis:
Axis:
Always Horizontal
Horizontalbars
barsused
usedtotodenote
denotelength
length
AlwaysActivities
Activities
or ofoftime
timefor
foreach
eachactivity
activityor
orjob.
job.
or Jobs
Jobs
Activity 1
Activity 2
Activity 3
Activity 4
Activity 5
Activity 6
Time Horizontal
HorizontalAxis:
Axis:Always
AlwaysTime
Time
1-5
6
Pure Project
A pure project is where a self-contained team
works full-time on the project
Structuring Projects
Pure Project: Advantages
1-6
7
Structuring Projects
Pure Project: Disadvantages
Duplication of resources
Organizational goals and policies
are ignored
Lack of technology transfer
Team members have no functional
area "home"
1-7
8
Functional Project
Research and
Engineering Manufacturing
Development
Example,
Example, Project
Project B
B is
is in
in the
the functional
functional
area
area of
of Research
Research and
and Development.
Development.
1-8
9
Structuring Projects
Functional Project: Advantages
1-9
10
Structuring Projects
Functional Project: Disadvantages
1-10
11
President
Research and
Engineering Manufacturing Marketing
Development
Manager
Project A
Manager
Project B
Manager
Project C
1-11
12
Structuring Projects
Matrix: Advantages
Pinpointed responsibility
1-12
13
Structuring Projects
Matrix: Disadvantages
1-13
14
1 Project 1 Project 2
1-14
15
Network-Planning Models
1-15
16
1-16
17
1-17
18
1. Activity Identification
2. Activity Sequencing and
Network Construction
3. Determine the critical path
From the critical path all of the
project and activity timing
information can be obtained
1-18
19
A None 2
B A 1
C B 1
D C 2
E C 5
F D,E 5
D(2)
G F 1
E(5)
1-20
21
ES=4
EF=6
1-21
22
LS=4
LF=9
1-22
23
ES=4
Slack=(7-4)=(9-6)= 3 Wks
EF=6
1-23
24
Immediate
Task Predecesors Optimistic Most Likely Pessimistic
A None 3 6 15
B None 2 4 14
C A 6 12 30
D A 2 5 8
E C 5 11 17
F D 3 6 15
G B 3 9 27
H E,F 1 4 7
I G,H 4 19 28
1-24
25
ET(A)=
ET(A)=3+4(6)+15
3+4(6)+15
Immediate Expected 66
Task Predecesors Time
A None 7 ET(A)=42/6=7
ET(A)=42/6=7
B None 5.333
C A 14 Immediate
Task Predecesors Optimistic Most Likely Pessimistic
D A 5 A None 3 6 15
E C 11 B
C
None
A
2
6
4
12
14
30
F D 7 D A 2 5 8
E C 5 11 17
G B 11 F D 3 6 15
H E,F 4 G B 3 9 27
H E,F 1 4 7
I G,H 18 I G,H 4 19 28
Opt.
Opt. Time
Time ++ 4(Most
4(MostLikely
LikelyTime)
Time) ++ Pess.
Pess. Time
Time
Expected
ExpectedTime
Time == 66
1-25
26
Opt.
Opt. Time
Time ++ 4(Most
4(MostLikely
LikelyTime)
Time) ++ Pess.
Pess. Time
Time
Expected
ExpectedTime
Time == 66
1-26
27
Opt.
Opt. Time
Time ++ 4(Most
4(MostLikely
LikelyTime)
Time) ++ Pess.
Pess. Time
Time
Expected
ExpectedTime
Time == 66
1-27
28
Example 2. Network
Duration = 54 Days
C(14) E(11)
A(7) H(4)
D(5) F(7)
I(18)
B G(11)
(5.333)
1-28
29
What
What isis the
the probability
probability of
of finishing
finishing this
this project
project in
in
less
less than
than 53
53 days?
days?
p(t < D)
D=53
t
TE = 54
DD -- TTEE
ZZ ==
cpcp
22
1-29
30
Pessim.
Pessim. -- Optim.
Optim.)22
Activity variance, = 22
(
Activity variance, = ( )
66
p(t < D)
t
D=53 TE = 54
D
D -- TTEE 53- 53-54
54
ZZ == == == -.156
-.156
cpcp
22 41
41
p(Z
p(Z <<-.156)
-.156) ==.438,
.438, or
or 43.8
43.8 %
% (NORMSDIST(-.156)
(NORMSDIST(-.156)
There
There isis aa 43.8%
43.8% probability
probability that
that this
this project
project will
will be
be
completed
completed in in less
less than
than 53
53 weeks.
weeks.
1-31
32
What
What is
is the
the probability
probability that
that
the
the project
project duration
duration will
will
exceed
exceed 5656 weeks?
weeks?
1-32
33
p(t < D)
t
TE = 54
D=56
D
D -- TTEE 56 56--54
54
ZZ == =
22 =
== .312
.312
cp
cp
41
41
p(Z
p(Z>>.312)
.312) == .378,
.378, or
or 37.8
37.8 %
%(1-NORMSDIST(.312))
(1-NORMSDIST(.312))
1-33
34
Time-Cost Models
1-34
35
CPM Assumptions/Limitations
End of Chapter 3
1-36