Pert CPM
Pert CPM
Using
Microsoft Project 2010
ISO 9001:2008
Certified
Company
Critical path method for managing Bangladesh Bridge Authoritys (BBA)
Resettlement Project
Contents
BBA projects information according to the
network diagram introduced by director sir
Theoretical knowledge up to critical path
Practical knowledge
Advanced uses
We are
GROUP 3
CPM Planner : Md. Khairul Alam
1. Md. Moshiuir Rahman
2. Md. Mehedi Hasan
3. AKM Mahmud-ul-Hasan
4. Mst Mariam Akthar
5. Ms Johana Sharmin
6. Shaolin Ferdousi (New member)
BBA PROJECTS DATA
BBA PROJECTS DATA
Task Name Date
M 1 Contract Signing Sun 11/22/15
M 2 Letter to Proceed Thu 11/26/15
M 3 End Preliminary Activities Sat 11/28/15
M 4 Submission of Inception Report Thu 12/17/15
M 5Final Submission of Inception Report Thu 12/31/15
M 6 Submission of Preliminary Design Report Sun 2/28/16
M 7 Submission of Detailed Design Report Sat 5/28/16
M 08 End Building Permission Fri 8/26/16
M 9 Submission of PQ Document Mon 3/21/16
M 10 Submission of Tender Document and Review by Client Mon 6/27/16
M 11 Starts Construction Thu 8/18/16
M 12 Submission of Completion Report Mon 8/6/18
M 13 Project Completion Report Thu 8/1/19
Critical path of BBA Project:
Task Duration
T 1.1 Kickoff Meeting 1 Days
T 1.2Review of Resettlement Plan/Report 4 Days
T 2.1Engineering Survey 7 Days
T 2.5Action Area Plan 7 Days
T 2.6Conceptual Architectural Design 7 Days
T 2.8 Presentation of Inception Report & Discussion with Client 7 Days
T 2.9Incorporation of Comments 7 Days
T 3.1Preliminary Architectural Design Including Finish Schedule 30 Days
T 3.2Preliminary Structural Design 15 Days
T 3.10Preliminary Cost Estimate 7 Days
T 3.11Presentation and Discussion on Preliminary Design & Cost Estimate 2 Days
T 3.12Incorporation of Suggestion & Modification of Preliminary Design Report 5 Days
T5.1 Land use Clearance from RAJUK 90 Days?
T5.2 Special Project Permit for Large & Specialized Project from RAJUK 90 Days?
T5.3Preparation of RAJUK Drawing 90 Days?
T5.4Permission from Fire Services and Defense 90 Days?
T5.5Permission from WASA 90 Days?
T5.6Permission from Electric Authority 90 Days?
T5.7Permission from Gas Authority 90 Days?
T5.8Permission from DMP 90 Days?
T5.9Permission from Local Ward Commissioner 90 Days?
T5.10Permission from Dhaka City Corporation 90 Days?
T5.11Permission from DTCA 90 Days?
T5.12Permission from KPIDC 90 Days?
T5.13Permission from Civil Aviation 90 Days?
T5.14Permission from Department of Environment 90 Days?
T 5.15Permission from RAJUK 90 Days?
T 7.1Supervision for Quality Control 710 Days
T 7.2Supervision for Time Control 710 Days
T 7.5Defect Liability 360 Days
What is Project management ?
Project management is a methodical approach to planning and guiding project
processes from start to finish. According to the Project Management Institute, the
processes are guided through five stages: initiation, planning, executing,
controlling, and closing. Project management can be applied to almost any type of
project and is widely used to control the complex processes of software
development projects.
Why Project Management?
Why Project Management?
Why Project Management?
What is a Project?
A project is a (temporary) sequence of unique,
complex, and connected activities that have one goal or
purpose and that must be completed by a specific time
within budget, and according to specification.