Investment Appraisal: Methods of Capital Budgeting: Presented By: Shyam Kumar Mishra Sonia Gupta PGDM (Ib) 2008-2010
Investment Appraisal: Methods of Capital Budgeting: Presented By: Shyam Kumar Mishra Sonia Gupta PGDM (Ib) 2008-2010
Methods of Capital
Budgeting
1 10 -90 1 70 -30
2 60 -30 2 50 +20
3 80 +50 3 20
• Select those projects from the top of the list till the capital Budget is
exhausted.
B. Mutually Exclusive Projects
In the case of two mutually exclusive projects, the one with a lower
payback period is accepted, when the respective payback periods are
less than or equivalent to the stipulated payback period.
Discounted Payback
Discounted Payback - is almost the same as payback,
but here we have to first discount our cash flows i.e.
we reduce the future payments by your cost of capital.
Thus NPV of proj L= -100+ 9.09+ Thus NPV of proj S = -100 + 63.64 +
49.59 +60.11= 18.79 41.32 + 15.03 = 19.98
Therefore If both the proj are exclusive the proj S is selected as it has greater NPV
. If both the proj are independent then both the proj are selected since both has
+ve NPVs.
Decision Rule for NPV:
A. "Capital Rationing" situation
Select projects whose NPV is positive or equivalent to zero.
Arrange in the descending order of NPVs.
Select Projects starting from the list till the capital budget allows.
IRR =
If both the projects are mutually exclusive then proj S is selected because
it has a higher IRR.
If S and L are independent, accept both. IRRs > r = 10%.
Project S:
Decision rule for IRR:
A. "Capital Rationing" Situation :Select those
projects whose IRR (R) = r, where r is the cost of
capital. Arrange all the projects in the descending
order of their Internal Rate of Return. Select
projects from the top till the capital budget allows.
B. "No Capital Rationing" Situation: Accept every
project whose IRR (R) = r, where r is the cost of
capital.
C. Mutually Exclusive Projects: Select the one with
higher IRR
Normal Cash Flow Project:
0 1 2 3 4 5 N NN
- + + + + + N
- + + + + - NN
- - - + + + N
+ + + - - - N
- + + - + - NN
NPV ($) r NPVL NPVS
60
0 50 40
50 5 33 29
NPV L=33 at r=5
10 19 20
40 Crossover 15 7 12
Point = 8.7% (4) 5
20
30 18.1 0 -
- 0
23.6
20
S
NPV S=29
10 at r=5 IRRS = 23.6%
L
0
0 5 10 15 20 23.6
Discount Rate (R%)
-10
IRRL = 18.1%
NPV and IRR always lead to the same
accept/reject decision for independent
projects:
NPV ($)
r (%)
IRR
Mutually Exclusive Projects
S IRRS
r 8.7 r %
IRRL
Pavilion Project: NPV and IRR?
0 1 2
r = 10%
NPV = -386.78
NPV NPV Profile
IRR2 = 400%
450
0 r
100 400
IRR1 = 25%
-800
Modified Internal Rate of Return - MIRR -
Is basically the same as the IRR, except it assumes that the revenue (cash
flows) from the project are reinvested back into the company, and are
compounded by the company's cost of capital, but are not directly invested
back into the project from which they came.
The MIRR is similar to the IRR, but is theoretically superior in
that it overcomes two weaknesses of the IRR. The MIRR
correctly assumes reinvestment at the project’s cost of capital
and avoids the problem of multiple IRRs. However, please
note that the MIRR is not used as widely as the IRR in practice.
MIRR (=R at which)= TV/(1+R)n – CF0 =0
Where TV (Terminal Value of cash Inflows) = CF 1 (1+r)n-1 +
CF2(1+r)n-2 + CF3(1+r)n-3 + ………………. CFn
CF1, CF2….. are Cash Inflows at time period 1 year, 2 years…
etc.
N is total time of project
MIRR (=R at which)= TV/(1+R)n – CF0 =0
Considering Proj L:
CF0 =-100 , CF1= 10, CF2= 60, CF3= 80
MIRR= TV/(1+ R)n+CF0= 0
i.e. [10(1+r)2 + 60(1+r)1+ 80(1+r)0]/(1+R)3-100= 0
i.e. [10(1.1)2 + 60(1.1)1+ 80]/(1+R)3-100= 0
i.e. [12.10 + 66+ 80]/(1+R)3-100= 0
i.e. [158.10]/ (1+R)3 = 100
i.e. 58.10= (1+R)3
i.e. R=16.9 % which satisfy the above equation
Therefore MIRR= 16.9%
MIRR is better than IRR because:
Decision Rule for MIRR:
C. Mutually Exclusive Projects: Select the one with higher MIRR
PI(Profitability Index);
Profitability
ratio is otherwise referred to as Benefit/Cost ratio. This is an extension of the
Net Present Value Method.
definition of PI: Profitability index (PI) is the ratio of present value of Cash
Inflows to the present value of Cash outflows. The present values of cash flows are obtained
at a discount rate equivalent to the cost of capital.
i.e. PI= ( Present value of Cash Inflows)/ (Present value of Cash outflow)
i.e. PI = PVCF/ Initial Investment
i.e. PI= Present Value of Total BENEFIT/Present Value of Total Cost
i.e. PI = [ CF1/(1+r)1 + CF2/(1+r)2 + CF3/(1+r)3+…………CFn(1+r)n]/ CF0
Where CF1, CF2……….are Cash Inflows after 1 year, 2years respectively.
CF0 is Present value of Cash Outflow or Initial Investment
i.e. PI = NPV+1
Accounting rate of return is the rate
arrived at by expressing the average annual net
profit (after tax) as given in the income statement
as a percentage of the total investment or average
investment. The accounting rate of return is
based on accounting profits. Accounting profits
are different from the cash flows from a project
and hence, in many instances, accounting rate of
return might not be used as a project evaluation
decision. Accounting rate of return does find a
place in business decision making when the
returns expected are accounting profits and
not merely the cash flows.
AROR = Net Profit after Tax/Average Investment
Decision Rules for AROR:
A. Capital Rationing Situation :
• Select the projects whose rates of return are higher than the cut-off rate
• Arrange them in the declining order of their rate of return and Select
projects starting from the top of the list till the capital available is
exhausted.
B. No Capital Rationing Situation and Independent Projects:
Select all projects whose rate of return are higher than the cut-off rate.
C. Mutually Exclusive Projects :
• It Is Easy To Calculate.